Delivery date of PR in past

Hello,
We are having one PR which is created by MRP run. PR is created with the delivery date in the past.
PR requested date   :20.02.2014.
PR release date       :19.02.2014
PR delivery date       :19.02.2014.
Planned delivery time : 1.
GR processing time    : 1.
We are using APO  for planning.when i tried to create a PR manually for the same material, below dates are got picked.
PR requested date : 26.2.2014
PR release date     :26.02.2014
PR delivery date     : 27.02.2014
Can anyone explain this?
Thanks,
Sankar.

Hello Sankar,
PReq delivery date of the purchase requisition consider the WEBAZ. Fisrt check you have same GR posiing time in ECC and APO.During this process, the factory calendar is taken into account.Variances occur if WEBAZ and the calendar do not match in the both systems.
Also check when this PR was created by MRP. In your both the case PR requested date is different  20.02.2014 and 26.2.2014.
What is result when you create manaul PR in ECC?
Go to SPRO > Materials Management > Purchasing > Environment Data > Define Attributes of System Messages > System Messages - Here make message no. ME039 i.e. Delivery date is in the past as E= Error.
Best Regards,
R.Brahmankar

Similar Messages

  • Whether Shopping cart delivery date can be in past date!!

    Hello SRM Gurus,
    There is a requirement from my customer, it may be strange.
    The requirement is : Shopping cart (requestor) should be abe to save having delivery date as a past date  and  PO in SRM with same past date.
    Is there any BADI available or programming is required?
    Pls post your sugesstions.
    Regards
    Madhan

    i think you can do this config . 584 message ready made available for you as E . now you can turn to W
    and do lot of testing for entire procurement cycle.
    .. it may give some trouble approval time too. check it up
    IMG activity 'Influence Message Control' (Enterprise Buyer -> Cross-Application Basic Settings -> Message Control):
    Select the line with business object BUS2121 and double-clicking on 'Message Control'.
                        Message cl:   BBP_PD
                        No. :          584
                        Text:         W
    Save the new entry.

  • Purchase order-delivery date

    presently users are maintaining delivery date in po with back dates. we want to control as it should be on or after current calender date.
    plz suggest how can we configure this requirement

    Hello,
    Goto SPRO >> Materials Management >> Purchasing >>Environment data >> Define attributes for system messages >> system messages >>>> Here you configure for Application are = ME and message  - 039 - Delivery date is in the past from warning to error message.
    Regards,
    Shailesh

  • Delivery Date Format in PO !!!

    Hi Friends ,
    I am uploading the delivery date from an input file to create a PO using BAPI_PO_CREATE1 . Before the BAPI call i see in t_poschedule-delivery_date = 08012006.This is the correct date which needs to be uploaded in PO . 
    But after the BAPI call the t_poschedule-delivery_date = 06/23/2006.
    Can you please advise why this is happening ??
    Thank you

    Here you go Dude...!!!
    <b>FYI</b>
    <b><u>OSS Note # 858316</u></b>
    <b>BAPI_PO_CREATE1: Incorrect delivery date</b>
    Symptom
    You create a purchase order using the BAPI_PO_CREATE1 function module or the CreateFromData1 method of the PurchaseOrder business object (BUS2012). When you do this, you transfer the delivery date and/or the statistical delivery date in the schedule lines using the internal display YYYYMMDD, where Y stands for the year, M for the month and D for the day.
    The system may issue one of the following messages during the processing of the data
    ME 039
    Delivery date is in the past
    or error message ME 078
    Delivery date outside period covered by factory calendar
    Other terms
    BUS2012, POSCHEDULE, DELIVERY_DATE, STAT_DATE, EEIND, EKET, ME078, ME039, EME078, EME039
    Reason and Prerequisites
    The problem is caused by a program error.
    Solution
    Implement the program correction.
    The following logic applies for the conversion of the delivery date:
    1. If the delivery date is transferred in the internal display (YYYYMMDD), the BAPI converts the delivery date automatically.
    2. If the delivery date is transferred with . or - or / , then there is no conversion, since these are external date formatting characters.
    3. If the delivery date is transferred in the internal display and the date category is also transferred (for example W or 2 for the week date), then the date is not converted.
    Hope this’ll give you idea!!
    <b>Pl... award the points.</b>
    Good luck
    Thanks
    Saquib Khan
    "Some are wise and some are otherwise"

  • Delivery Date in PR/PO

    Hi, need help!
    How to config delivery date such that it cannot be earlier than request or PR/PO date? In what tcode to config it?
    Thanks in Advance!

    Hi,
    Go to SPRO > Materials Management > Purchasing > Environment Data > Define Attributes of System Messages > System Messages - Here make message no. ME039 i.e. Delivery date is in the past as ERROR.
    But this will check the System Date not PO Date.

  • Delivery date to be recalculated and get it updated in PO

    After the last approval step the delivery date shall be recalculated. The recalculation shall happen with the maintained lead time based on the PO creation date. The calculation uses the available factory calendar for the delivery date. Please help how to proceed and get the delivery date recalculated to update the delivery date in PO.
    regards
    AAA
    Edited by: Alex Abraham Anoop on Jan 2, 2009 8:24 AM

    Hi
    Please go through the below notes...
    Note 735220 - Requested delivery date from contract in shopping cart
    Note 735220 - Requested delivery date from contract in shopping cart
    Note Language: English Version: 3 Validity: Valid from 07.05.2004
    Summary
    Symptom
    During the creation of a shopping cart, a source determination occurs in
    the background and exactly one contract is determined which contains a
    delivery time in day. The system issues a message that the requested
    delivery date cannot be met. However, the user does not receive information
    on where the delivery time comes from: Catalog or contract.
    More Terms
    SRM, Supplier Relationship Management, Ecommerce, E-Commerce, BBP, EBP,
    Enterprise Buyer professional edition, E-Buyer, E-Procurement, SAP
    Business-to-Business Procurement, shopping cart, requested delivery date,
    delivery time, contract, catalog
    Cause and Prerequisites
    The problem is caused by a program error.
    Solution
    Implement the attached program corrections and then carry out the following
    steps: Call up Transaction SE80 and go to function group BBP_PDIGP in
    subroutine CHECK_DELIV_DATE (Include LBBP_PDIGPF2I).
    There, you must define text elements text-001 and text-002. To do this, go
    to 'Goto -> Text elements -> Text symbols' and enter 'Contract' for
    text-001 and 'Catalog' for text-002.
    Activate program SAPLBBP_PDIGP.
    In addition, adjust message #244 "Requested delivery date cannot be met".
    Call up message class BBP_PD in Transaction SE91 and go to message 244
    which must be enhanced as follows: "Requested delivery date cannot be met
    (&1 - delivery time = &2 day(s))".
    Note 814100 - The delivery date lies outside of the factory calendar
    Note 663619 - Delivery date is not checked
    Note 660962 - Warning message if delivery date is missing
    Note 752868 - SC desired del.date: Change error message to warning
    message
    Note Language: English Version: 3 Validity: Valid from 07.07.2004
    Summary
    Symptom
    You approve a shopping cart for which the desired delivery date is in the
    past. The system displays an error message stating that the delivery date
    cannot be met. This message is an error message by default. In your case it
    is not problematic if a shopping cart is approved that has a desired
    delivery date in the past. That is, this message should be set via the
    message control in such a way that it is either displayed as error or
    merely as warning message.
    However, the message is not provided as a customizable message.
    More Terms
    Customizeable message, Enterprise Buyer professional edition, E-Buyer, EBP,
    E-Procurement, SAP Business-to-Business Procurement, BBP, Ecommerce,
    E-Commerce, BBP_PDC_MSG, BBPC_PDMSG, BBPC_PDMSG_CUS, shopping cart,
    message, message control, customizable message, validity period
    Cause and Prerequisites
    Additional requirements.
    The quantity of the customizeable messages is predefined by SAP because the
    control of these messages affects the process flow.
    Solution
    Implement the attached program correction and proceed according to the
    following instruction. If you implement the changes manually, note that
    only a modification is possible.
    o Start Transaction SE91 to maintain message class BBP_PD and switch
    to change mode.
    o Create a new message with number 584 and specify the following
    text: 'In the shopping cart to be approved, the delivery date is in
    the past'.
    o Save the message.
    o Start Transaction SM30 to maintain database view BBPV_PDMSG.
    o In the maintenance screen, a list of already delivered messages is
    displayed. Add the following new entry:
    ApplicArea: BBP_PD
    MsgNo: 584
    Object Type: BUS2121
    Allowed: EW
    Standard: E
    Switch off: <leave empty>
    o Save the new entry.
    Afterwards you can set the message type of the corresponding message to
    'Warning Message' via IMG activity 'Influence Message Control' (Enterprise
    Buyer -> Cross-Application Basic Settings -> Message Control):
    o Select the line with business object BUS2121 and double-clicking on
    'Message Control'.
    o Adding a new entry:
    Message cl: BBP_PD
    No.: 584
    Text: W
    o Save the new entry.
    so do you have any plans to issue warning /error message during the approval/order time itself sice it is tightly linked with source of supply too right? or just you want to validate during creation of Purchase order after approving it?
    regards
    Muthu

  • Delivery date not getting recalculated while approving via outlook

    Hello,
    After creating a shopping cart and if we approve after say 3 days via SRM portal the delivery date gets recalculated and takes into reconsideration these days and this is the value that gets populated in the purchase order
    But if the approval is via "OUTLOOK", the delivery date is not recalculated and the old delivery date is sent into the PO.so sometimes the delivery date becomes in the past.
    Although BAdI takes into consideration delivery time+lead time calculation for SRM portal approved shopping carts it is not taking into consideration for OUTLOOK.
    Is there any solution for this
    Regards

    Hi JJ
    BADI BBP_DOC_CHANGE_BADI- BUS2201 . while creating PO try to validate them if you are in ecs mode
    i believe standard SAP dont recalculate delivery date while creation of PO.
    regards
    Muthu

  • Delivery date in MIRO - PO reference

    I would like to see the delivery date (posting date in the GR document) in the MIRO transaction under PO reference. There is a delivery date that appears in the All information layout, but that refers to the expected delivery date. Please advise.

    Hi,
    Go to SPRO > Materials Management > Purchasing > Environment Data > Define Attributes of System Messages > System Messages - Here make message no. ME039 i.e. Delivery date is in the past as ERROR.
    But this will check the System Date not PO Date.

  • PR Request Delivery Date

    Hi,
    How can I restrict users back-dating a Request Date of a Purchase Requisition? Change it from warning to error.

    Hi,
    The message ME 039 (Delivery date is in the past) is configurable as an Error message. However, the message 06 245 (Can delivery date be met?) is not. It can only be issued as a Warning message.
    SAP IMG (Trx. SPRO)
    -> Materials Management
       -> Purchasing (Trx. OLME)
        -> Environment
         ->Define attributes of system messages
          .- System messages
    Here, change the value in field 'Cat' (category) to 'E'
    Regards,
    Purnima.
    Edited by: Purnima Prem Priyan on Jan 17, 2012 12:15 PM

  • Delivery schedule dates are coming in Past dates

    Hi Friends,
    In the Scheduling Agreements the delivery schedule dates are coming in the past dates even tough the scheduling agreements are having new schedules. There is also open quantities there for the scheduling agreements.
    please kindly explain me what is the delivery schedule date in Scheduling Agreement.
    Thanks in advance.
    Regards,
    Kannan M

    Hi Khan,
    Just check this thease might be the reasons to get correct the delivery schedule.
    To access a delivery schedule, mark a scheduling agreement item and choose Goto ® Item ® .
    The following data is displayed in the delivery schedule tabstrip:
    ·        Delivery schedule number and date
    ·        A wide range of standard cumulative quantities
    ·        Delivery information
    To display deliveries for the delivery schedule, choose Deliveries on the delivery schedule tabstrip.
    In scheduling agreements involving external agents, the system displays deliveries made to the customer by external agents as consignment issues.
    ·        Correction delivery information
    To display or create correction deliveries, choose Corr. delivery on the delivery schedule tabstrip.
    ·        An analysis function
    ·        Information at a glance
    To display a summary of delivery schedule data, choose Short disp. on the delivery schedule tabstrip.
    ·        Schedule lines
    Choose DlvSch.Hdr on the delivery schedule tabstrip to access the delivery schedule header. The following data is displayed here:
    ·        Information on quantities received by the customer
    ·        Information on the customer fiscal year and cumulative quantities reset due to a year change
    ·        A wide range of cumulative go-ahead quantities
    ·        Notes on the delivery schedule
    Correcting Cumulative Delivered Quantities
    Prerequisites
    You correct cumulative quantities in scheduling agreements:
    ·        In case of returns
    ·        When there has been a processing error
    ·        When there has been a year change
    ·        When you are transferring initial quantities from a legacy system into the SAP System
    To do this, you create a correction delivery within the delivery schedule itself. This delivery is not relevant for requirements planning, shipping, goods issue, or billing.
    Correct cumulative quantities only when the customer has not posted goods receipt.
    Procedure
    To create a correction delivery (document type LFKO):
           1.      Choose Corr. delivery on the delivery scheduletabstrip.
    The system displays a dialog box in which you enter a:
    -         Correction delivery date
    For help on deciding where you want to position the correction delivery, choose Display. The system lists delivery dates in chronological order.
    -         Correction quantity
    Enter a negative correction quantity by placing a minus sign after the quantity.
           2.      Choose Enter and save the scheduling agreement.
    Result
    When you save the correction delivery, the system updates the cumulative quantities in the delivery schedule.
    To display correction deliveries, choose Deliveries on the delivery schedule tabstrip, or  Environment ®  Display document flow.
    Example
    Your customer returns 200 pieces of material from a delivery made on 7/10 because of damage during transport. Several other deliveries have been made before you prepare the correction delivery, so you view a list and choose an appropriate date. In this case you decide on 7/14 because it occurs after the delivery on 7/10 and before the delivery on 7/15.
    Regards,
    Murthy V.N

  • Delivery date in past in scheduling agreement

    Hi
    In ME38 , when I try to  change delivery schedule for a line item   from 05/07/2008 to 02/08/2008 , system is  giving below error .
    *Delivery date is in past *
    I am ignored this message  and pressed enter  and saved the scheduling agreement .
    Just I need to know , does this error has any ramification  in any way .?
    Thanks in Advance

    Hi,
    In SAP the delivery date is not taken in Past,so it is showing you warning/error message.
    It is not advisable to have delivery date in past.This is inturn cause problem when you going forward & want to evaluate  vendor on delivery performance.
    Thanks,
    AMIT

  • Load a sales order with delivery date in the past

    Hi,
    We want to load in the system a sales order with delivery date in the past, and maintain the schedule delivery date in the past. To do that, in the customizing Sales And Distribution / Basic Functions / Delivery Scheduling and Transportation Scheduling / Define Scheduling By Sales Document Type, I selected the flag Blackwards. But the problem is that the rest of the dates in the scredule line: goods issue date, loading date, material avail.date and transportation Plan Date, are in blank and you cannot enter any data because the system deletes it.
    How can I have these dates informed with dates in the past?
    Thanks in advance,

    You can control this using the "Message Control" in the SAP IMG.
    Supplier Relationship Management>SRM Server>Cross-Application Basic Settings>Message Control>Influence Message Control
    Using this you convert Error to Warning or even swith off this message.
    Please refer this thread for complete steps:
    Re: How to change an error message to a warning message in SRM
    Note: you need to suppress the messages relevant to your case here.
    Regards
    Kathirvel

  • Order confirmation with delivery date in past

    Hello everybody,
    In the SNC portal, we have a lot of old Purchase order which are not confirmed, and when we try to confirmed them, we have the error below :
    Order XXXXXXXX, item 00010, schd. line 0000000002: delivery date lies in past
    My client wish create a super user (admin ?) who can confirmed a Purchase Order item with a delivery date in past (for example 06/08/2011).
    Is it possible to create such profiles? If so how to configure it in SNC.
    Are there other solutions ?
    Thank you very much for your help.
    Stéphane.

    Hi Stéphane,
    Normally in a standard SAP settings Purchase order confirmation in past gives warning message but you can have PO confirmation in past from warning to error or Information.
    Go to SPRO>Supply Network Collaboration>Basic Settings>Validation>Own Settings-->Maintain Settings in Validation Profiles
    Maintained below setting if you want message as information (No error or warning message)
    Profile:POC2
    Validation check:PO_DELVRY_DATETIME_IN_PAST
    Msg.Type:I
    Save Mode:Save Message as Valid
    Continuation Mode:Continue checks
    Profile:POC3
    Validation check:PO_DELVRY_DATETIME_IN_PAST
    Msg.Type:I
    Save Mode:Save Message as Valid
    Continuation Mode:Continue checks
    Maintained below setting if you want message as error
    Profile:POC2
    Validation check:PO_DELVRY_DATETIME_IN_PAST
    Msg.Type:E
    Save Mode:DO not Save Message
    Continuation Mode:Discontinue checks
    Profile:POC3
    Validation check:PO_DELVRY_DATETIME_IN_PAST
    Msg.Type:E
    Save Mode:DO not Save Message
    Continuation Mode:Discontinue checks
    Maintained below setting if you want message as warning
    Profile:POC2
    Validation check:PO_DELVRY_DATETIME_IN_PAST
    Msg.Type:W
    Save Mode:Save Message as Valid
    Continuation Mode:Continue checks
    Profile:POC3
    Validation check:PO_DELVRY_DATETIME_IN_PAST
    Msg.Type:W
    Save Mode:Save Message as Valid
    Continuation Mode:Continue checks
    Above setting is a generic setting for all user and If you need User specific setting then it is a customization required.
    Regards,
    Nikhil

  • Delivery Date in the past

    Hi Guys,
    Question:
    I have one item order with a Customer requested date of 6/23/2008 entered against plant 2000.
    quantity 400 units.
    Because we ware moving to a new warehouse we had to create a new sales document against plant 2019 with a creation date of 7/10/2008 but we left the same customer requested date ( in the past )
    stock just became available recentily in october and the material availability date was for October 24th, at plant 2019.
    so the system split the line into 2, line one with a delivery date in the past (6/23/2008) and
    the other with a delivery date in Novemeber.
    Does anyone know why this would happend? the MAD is in octoboer, so why would the system force
    the first line to be delivered on 6/23/2008?
    is the issue caused by creating the new order and leaving the Customer Requested date in the past?
    there were some other items in this Order that did not behave this way.
    any feedback would be appreciated.
    Cheers
    JD Loera

    While entering the sales, if you maintain the customer's requested date as in the past then system would give you a warning message and you can proceed. When you enter the material it would not be possible to deliver the goods as per the customer's requested date and hence system would carry out the forward scheduling and propose the next possible date when the delivery can be made to the customer.  This would ensure you have more than one schedules line for the line item.
    Regards
    Nadarajah Pratheb

  • Prevent past date entry on the delivery date field

    Hi Guys,
    I was wondering whether it is possible within standard SAP Business one 8.8 to prevent users from entering past date in the delivery date field on the Sales order screen.   I have people making mistakes by entering 10/10/2010 instead of 10/10/2011.  This caused problems with reports etc..
    Is there a formatted search query i can create to warn/alert users with a message stating incorrect date entered? Please advice best course of action?
    Regards
    nick

    Deepak,
    The following code is already in this section?  Can i just add Gordon query below the last "END" statement?
    --    ADD   YOUR  CODE  HERE
    declare @islocked int
    select @islocked = 0
    if(@object_type = '17' and @transaction_type <> 'A')
    select @islocked = U_LockedForEdit from [@A1WMS_Staging] where U_objType = '17' and U_docEntry = @list_of_cols_val_tab_del
    if(@object_type = '22' and @transaction_type <> 'A')
    select @islocked = U_LockedForEdit from [@A1WMS_Staging] where U_objType = '22' and U_docEntry = @list_of_cols_val_tab_del
    if(@object_type = '202' and @transaction_type <> 'A')
    select @islocked = U_LockedForEdit from [@A1WMS_Staging] where U_objType = '202' and U_docEntry = @list_of_cols_val_tab_del
    if(@islocked <> 0)
    begin
    select @error = 999
    select @error_message = 'Order Cannot be Updated/Canceled/Deleted as it is Locked in WMS'
    end

Maybe you are looking for