Different strategy Group

Dear PP Gurus ,
       I m created a Material No with Strategy group 50 .
Then i m created Plan Number  For This Material using MD61 Tcode .
Then i m created Planned Order also for This material.
Both the Values, Plan Number And Planned Order number Are Stored in Plaf Table .
But i m created Another Material Number with strategy group 10 Means , In Plaf table Only Stored Planned Order Number .
Plan Number is not Updated .
Why Plan Number is Not Updated in Plaf Table ?
Anythink Mistakes From ABAPer Or Functional .
Explain Me.....
Warm Regards ,
GJ

Hi
This is standard functionality and not an error.
Strategy 50 is related to MTO type of production.
Planned independent requirements that are planned using this particular strategy 50 are listed in a separate segment in the MRP list. The planned orders are created with the order type VP and are unconvertible. The sales orders for this strategy are entered as individual customer requirements and are maintained in a separate segment in the planning run.
Strategy 10 is related to MTS type of production and Planned orders can be used interchangebly for any requirement. For this reason plan number is not updated in PLAF table.
Regards,
Krishna Mohan

Similar Messages

  • Independent requiement is not comsumed in strategy group 10

    HI Gurus,
    My material is maintained as :
    Strategy group :      10      Make-to-stock production
    Consumption mode     2    backward anf forward
    Indenpendent requirement is created as LSF.
    in MD04, it shows like below:
    stock                            5
    IndReq   LSF     20-       15-
    CusOrd  xxx      1-         16-   
    Reqtype of Cusord is KSL.
    after i finish PGI, it shows like below:
    stock                            4
    IndReq   LSF     20-       16-
    So i have two questions:
    1:why the indReq is not consumed.
    2:how to control when to cosume inreq , when sales order is created or when PGI is done?
    BR,
    Dragsky

    Hi
    In strategy 10 PIR is consumed when delivery is done against sales order.
    This is controlled at the time of definition of MRP strategy IMG->PP->Demand Mgmt->PIR->Planning strategy. by assigning requirement class to the strategy. 
    For st 10 requirement class is 100. for consumption following options are available
    No consumption with customer requirements
    Consume planning with assembly
    Consume planning w/o assembly
    Consume planning material (w/o assembly)
    for 100 option 0 is maintained which is standard sap setting not recommended to change. If you need a different behaviour you can create a new rer class and strategy as per your need.
    Regards
    Abhishek

  • Strategy group / Availability check

    Hi Gurus,
    When availability check is assign during material creation in MRP3 view, by defaul SAP assign the same one in Sales: General/Plant view. I understand that this is the same field on plant level (MARC-MTVFP)
    In my mind, the first one (in MRP3) will be used to determine MTO, MTS and so one.
    The second one (in Sales) will be used during sales order creation for availability check.
    Is there a relation between both?
    Moreover which is the link between availability check and the strategy group?
    I'm quick lost to know which I need to use on sales side, on production side because for a same availability check you can have more than one checking rules (one for SD order, one for PP...). Each one can be different.
    A best practise could not be to have similar criteria for all checking rules of the availability check?
    Thanks.
    Stéphane

    Hi,
    Availability check in the MRP3 View of the Material master is nothing but checking Group.
    ( 01- Daily requirements ,02- Individual requirements and so on )
    You allocate the checking group to the material in the material master under the availabilty check field in the MRP data screen.
    If you have not maintained a checking group for a material, the material will not be checked for availability.
    Checking Rule : In this step, you can define checking rule for applications:
        o   Sales and distribution
        o   MRP
        o   Production order processing
    Scope of Check : Checking group and Checking rule together specify the scope of the check.
    which inward goods movements and which outward goods movements are to be included in the availability check
    which stocks are to be included in the availability check
    whether the check should take into account the replenishment lead time.
    whether the availability should always be checked at plant level.
    Strategy Group:
    The planning strategy represents a procedure for planning a material and is technically controlled via the requirements types. With the help of the planning strategy, the material is automatically assigned the correct requirements type in demand management and in sales order management.
    o   The planning strategy represents a planning procedure for planning a  material.
    It is defined by one of the following:
        -   a requirements type from demand management
        -   a requirements type from sales order management
        -   a combination of both that makes sense
    o   Strategy group
        You use the strategy group to group together all the valid planning strategies. Thus, more than one planning strategy can be allowed for  a material.
    In this section, you also see various control indicators for each planning strategy on the overview screen, for example:
    o   consumption indicator (determines whether the requirements type in planned independent requirements and the requirements type in sales order management are consumed or whether sales orders increase the  master plan, and so on).
    o   availability check (determines whether the check is to be carried out according to ATP logic or as a check with planned independent requirements).
    Hope it is useful to you.
    Thanks
    Srinivas

  • MRP settings-Strategy group

    Hello PP Gurus,
    I have a very basic question. I explain with an example.
    Scenario : MTO
    Customer orders for 1 elavator. Say Component Elev
    It has components
    1)Windows Proc key F
    2)Motor Proc key E
    Moto components 2a)Body Proc key F
                                  2b)Wiring-Proc key E
    3) Doors (Proc key E)
    My question is in reference to strategy. How do I assign the straegies to different components?If I assign a strategy say 85 to header  lever component Elev the do I need to assign the same strategy to lower level components too? Could I use a different strategy for lower level components?Do I need to assign strategy to components with proc key F too, as I dont see any need for it?When should I use MRP type PD or ND to header level material.
    Assigning strategy group and MRP type is a bit confusing for me although I understand the functionality.
    Thanks in advance.
    Cheers
    Sunny

    Hi,
    My question is in reference to strategy. How do I assign the straegies to different components?
    In material master / mrp view  , you can assign what the planning strategy you want for differenet componenets.
    It is depends how you going to procure the components -whether you are going to procure before /afte with ref to sales
    so it will bevary by planning strategy -make to stock./ make to order res.
    If I assign a strategy say 85 to header lever component Elev the do I need to assign the same strategy to lower level components too?
    No its not need actually if you going to plan the components depend upon the project. you need to have the diff strategy for components , if you procure the components before/or without ref of the projject.
    Could I use a different strategy for lower level components?
    you need to have the diff strategy for components , if you procure the components before/or without ref of the projject.
    Do I need to assign strategy to components with proc key F too, as I dont see any need for it?When should I use MRP type PD or ND to header level material.
    That moe enough to have the strategy for header . but if you going to procure the component before the pjoject . so you need to choose the make to stock strategy.

  • Verifying understanding on Strategy group (MRP 3 View)

    Hello Forum,
    As per my understanding, if we don't have  any independent requirement or customer order for semi-finished or packaging products then there is no need to maintain any  Strategy group (MRP 3 View) field @ material master .
    Am I correct or you foresee any reason to maintain it ?
    Cheers
    Sam

    Dear Sam Das,
    For semi finished material if you leave the strategy group than it is ok if you do not run mrp. In case of mrp run and your semi finished product have different requirement than make to stock scenario than in that case it is necessary. If you leave it blank and run mrp system will consider it as 10.
    Regards,
    Saurabh Kumar

  • Stock report for single material contains different material groups

    Hi Experts,
                  I have a scenario.I want to maintain material group for a material at the time of po creation.In next time i will maintain different material group for the same material.
                   But I want to view the the stocks for material group wise which i entered in po.Is it possible to achieve this?
                  Please suggest solution.
    Thanks & Regards,
    Deepika.

    Please read the KBA document  2012912 - Changeablility of the field "material group" in purchasing documents
    It clearly says that material group can't be changed in case you will use material master in purchase order.
    So, it is clear that you can't use different material group for material master in purchase order.
    For stock report, system will only show you the material group which is assigned to the material master (MARA-MATKL). System will not look into the purchase order section (like EKPO).

  • Same number range for two different series groups?

    Dear all,
    There are two scenarios
    1.Normal export under bond case, series group is 20 and number range maintained,running number is 300016
    2.Another scenario,where ARE1 document generation for Deemed exp customer(already customised) , series group is 30.
    But, client requirement is , for this second scenario also, system should pickup running number range of series group 20(under bond case)  as per excise legal requirement
    Ie running number is for series group 20 is 300016
    For the above deemed exp case (second scenario)it should pickup 300017
    And again when they do under bond case(first scenario), it should pick up 300018 like that
    Is it possible to maintain the same number range for two different series groups(20 and 30)?
    Even if you maintain the same number range for 30, as per running number range of 20
    Will the system update simultaneously the same number range for 20 and 30 series groups?
    Please suggest the way.

    With two different series groups, it is not possible to have the same number range. Even if you maintain it, they will be treated independently.
    Normally, you should not use different series groups if the same number range has to be used. In fact, the concept of series group has been developed to ensure that number ranges can be maintained separately.
    Regards,
    Aroop

  • Can I deploy 2 computer GPO for 2 different Security Groups to the same machine?

    Hi
    this is my scenario
    I have 2 different security group ( in a domain ) and i would like to deploy 2 different Computer GPO depends by the user SG membership
    this is a terminal server ( 2k12) and I would like  have the computer GPO policy/admin template/windows components/remote desktop session host/profile different for each security group.
    thanks
    Marco

    > I have 2 different security group ( in a domain ) and i would like to
    > deploy 2 different Computer GPO depends by the user SG membership
    Not really, but for some settings there is a workaround... ->
    http://evilgpo.blogspot.de/2012/03/how-to-save-my-screen.html
    > this is a terminal server ( 2k12) and I would like  have the computer
    > GPO policy/admin template/windows components/remote desktop session
    > host/profile different for each security group.
    For THIS setting, it definitely does NOT work. The profile path must be
    known BEFORE the user is logged on and this means BEFORE any user
    specific settings can be processed.
    Martin
    Mal ein
    GUTES Buch über GPOs lesen?
    NO THEY ARE NOT EVIL, if you know what you are doing:
    Good or bad GPOs?
    And if IT bothers me - coke bottle design refreshment :))

  • Is it possible to deploy 2 SCOM 2012 R2 reporting in a SQL server which already has SCOM reporting of a different management group but with 2 different reporting instance.

    Hi Experts,
    I have a typical situation in the LAB environment. Hope some one helps. I have Installed a SCOM 2012 R2 with SQL 2012 SP1 in a single server (Management group 1). I have installed another management group on another server using this SQL server for its database
    so i have everything going fine.
    The first management group has its reporting installed in the SQL server. For the second i created a new named instance for that. But i cannot run the SCOM setup in the SQL server (Also holding the Management group 1 MS) as 1 st reporting is already there.
    When i run the setup it is asking me to repair it. I don't get the install option so i can install the reporting for management group 2 in the named instance.
    Default instance is being used by the 1st management group.
    Can any one figure a possibility for installing 2 SCOM reporting services for different management groups in a same SQL 2012 server please.
    Gautam.75801

    Hi Yan Li,
    Thank you for the reply. So as you are aware If i need to instal reporting, i need to run the SCOM 2012 R2 setup in the SQL server and select reporting and select the
    instance and then mention the management server there right. I am not getting that option there it is asking me to remove or repair the existing installation as there is already a SCOM entire setup including reporting there. As it is a lab there is no problem
    in testing. I have 2 reporting instances. Any suggestions for me on how to overcome this issue and deploy the second reporting in the new named instance ?
    Below is the screenshot of the error what i am talking about when i run SCOM 2012 R2 setup to install reporting in the SQL server
    When i click on add feature reporting is greyed out (As already 1st management groups reporting is installed)
    When i click on remove or repair it
    uninstalls the existing one. But i want both SCOM 2012 r2 reporting to be there(For both Management group). Is it possible ? If yes What is the trick to run the setup ?
    Gautam.75801

  • Mass creation of common folders for different user groups

    Hello Experts,
    We are using Portal 7.0 SP12 and we have 10 different user groups created in Portal.
    Based on this group structure, we need to create two common folders in each of the user's personnel documents in KM.
    Is there is any way to achieve this kind of requirement ?
    Can we do mass creation of these two common folders which will be assigned to all of the groups. This needs to be done in user's personnel documents and not in Public documents.
    Any help in this context would be highly appreciated. points assured.
    Thanks in advance,
    Anil Kumar.

    For every user a folder is created in userhome. One approach is to capture this folder creation event and create the folder structure you need. You need to develop a portal service which will listen to events from userhome repository.
    1. Capture folder creation event for user home
    2. Create the folder structure you want in this event handler
    Check this documentation on how to do this.
    https://media.sdn.sap.com/html/submitted_docs/nw_kmc/howto/rf/client_api/rf_client_api.html
    Regards,
    Prasanna Krishnamurthy

  • Transfer of data from R/3 to APO for strategy group

    Hi,
            Can we transfer materials from R/3 to APO that donot have R/3 strategy group 10, 40, 50, 60, 70?
    I am trying to transfer a material with MRP type Z4. Everything else is maintained properly but the material doesn't show up in APO. The plant is transferred, the setting in CFC9 is 2 and the no blocks in SMQ. I tried CFP1 as well but it not even collected there. The message type CIFMAT is checked and ALE change pointer checked in BD 61.
    Thanks.
    Edited by: Visu Venkat on Apr 26, 2008 6:04 PM

    Hi
    Just to recheck what you have written, Planning without final assembly should be Proposed Strategy 30 in APO. Has the config in your APO system been amended or did you mistype? 
    If it was strategy 70 in R/3 then there is a note which would have been relavant I think:
    [Note 711107 - Transfer strategy group 70 to SAP APO without manual changes|https://service.sap.com/sap/support/notes/711107]
    Regards
    Ian

  • Different vendor group, but 1 vendor master

    Dear Friends,
    Can I have this facility in SAP.
    Different account groups to be maintained, but vendor master should be created only 1 vendor master with common no.
    Display separate balances for vendors in Balance Sheet as:
    Creditors for Material Purchase
    Creditors for Capital Purchase
    Creditors for Acceptance
    Regards,
    Ram

    Hi,
    Better to use Define Alternative Reconciliation Account for Vendors like
    1. Creditors for Material Purchase - xxx1
    2. Creditors for Capital Purchase - xxx2
    3. Creditors for Acceptance  - xxx3
    Sundry creditors -
    xxxx0 Main Recon account.
    In this step, you define accounts which show the posting of a
    corresponding special G/L transaction to the general ledger. The
    postings are made to these accounts instead of to the normal
    reconciliation account.
    Path:
    SM30 --> table V_THKON.
    Hope it clear.
    Search for More help for Alternative Recon settings.
    Regards,
    Kishore K

  • N+1 redundancy and different mobility groups

    Is it possible to backup 2 controllers with 2 different mobility groups (for example GROUP1 and GROUP2) to the same backup controller (running HA SKU N+1 (7.4)) ?
    Since a controller can only be configured in 1 mobility group, this doesn't seem to be possible. Can someone confirm ?
    regards,
    Geert

    Hello,
    As per your query i can suggest you the following solution-
    In all Wireless LAN Controller (WLC) versions earlier than 4.2.61.0, when a WLC goes "down," the LAP registered to this WLC can failover only to another WLC of the same Mobility Group, if the LAP is configured for failover. From Cisco WLC version 4.2.61.0 and later, a new feature called Backup Controller Support is introduced for access points to failover to controllers even outside the Mobility Group. Refer to Wireless LAN Controller and Light Weight Access Points Failover Outside the Mobility Group Configuration Example for more information.
    Hope this will help you.

  • Client Roaming Within Single WLC with Different AP Groups

    I am trying to setup a 4400 WLC with 2 different AP Groups mapped to its respective Dynamic Interfaces / Vlans. AP's are equally mapped to both the AP groups by Floor wise ex: First floor AP's connect to one AP group and the Second Floor AP's connecting to other AP group.
    Goal is to create separate Network policy for each Floor using ACL's and apply to their respective Vlans on Layer 3 Switch. Wireless Raoming should happen seamlessly between these Ap groups making the DHCP changes by not disconnecting and connecting every time user roam across the Floors.
    Problem is When Clients Roam between Floors i,e moving between AP Groups, they still maintain their old DHCP IP addresses when moved to new AP group even after Client re-authetication. This defies our goal of creating a Wireless Network Policy using single WLC.
    Knobs i have tuned in WLC to acheive our goal includes....
    1. WLAN Session Timeout - No use
    2. DHCP Proxy Disable - No Use
    3. ARP Time out - No use
    Looks like WLC is storing the IP address and MAC information of the Client unconditonally during roaming and clearing out untill a manual or forced disconnect or disassociation is done.
    Did anyone tried to implement this setup and made it running? Any help or suggestion would be higly appreciated.
    Thanks
    Guru

    abit late for a reply but....try going to the SSID>Advanced and ticking the "DHCP Addr. Assignment" Required checkbox and test again.
    What does the DHCP Required field under a WLAN signify?
    A. DHCP Required is an option that can be enabled for a WLAN. It       necessitates that all clients that associate to that particular WLAN obtain IP       addresses through DHCP. Clients with static IP addresses are not allowed to       associate to the WLAN. This option is found under the Advanced tab of a WLAN.       WLC allows the traffic to/from a client only if its IP address is present in       the MSCB table of the WLC. WLC records the IP address of a client during its       DHCP Request or DHCP Renew. This requires that a client renews its IP address       every time it re-associates to the WLC because every time the client       disassociates as a part of its roam process or session timeout, its entry is       erased from the MSCB table. The client must again re-authenticate and       reassociate to the WLC, which again makes the client entry in the table.

  • How to set different default interactive reports for different user groups?

    I'm probably overlooking an obvious solution, but how do I set different default interactive report for different user groups?
    For the same interactive report, I want one set of users to see a default where the default filter is based on column X. However, another group of users doesn't have authorization to see that column so I need to set the default filter to something else for them.
    Thanks

    You can set a filter on a report in a URL - would that help? I think with apex 4.x you can also link to a saved default report or alternative report...

Maybe you are looking for

  • How to print #9 (return) envelopes

    I have an HP officjet 8600 and am running Mac OSX 10.8. I am trying to accomplish the simple task of printing a return envelope. This is a totally common size envelope but it is not listed as one of the standard sizes within the HP settings.  I've cr

  • Problem with abap code in lsmw.its urgent

    Hello guys iam migrating open ar line items using lsmwand i need to create reconciliation key automatically so iam using below code which is working fine in abap editor but i inserted in the lsmw abap code block at step 5 mapping fields iam getting e

  • Where can i get power cable?

    Hi, i was wondering if there was anyway i could purchase a power cable for the Creative Labs 5.1 5300 sound system. I only require the power cable to the subwoofer as i have lost mine, is there anyway i can get hold of a new one ?I do live in the UK

  • Regarding Log4.xml to add timestamp in log file

    Dear Sir, Could you guide me how to append the timestamp got appeared in log file which has been generated from Log4j.xml?? This is my Log4j.xml. <?xml version="1.0" encoding="UTF-8"?> <!DOCTYPE log4j:configuration SYSTEM "log4j.dtd"> <log4j:configur

  • Java PreparedStatement error

    I have this statement: pstmt.setDouble(2, (double) 9000000000); where pstmt is PreparedStatement when I compile I got this error: SaveFocus2aCommand.java:666: integer number too large: 9000000000 pstmt.setDouble(2, (double) 9000000000); ^ 1 error Doe