Dispatching of Planned Order in Planning Table

Hi Gurus,
What do we understand by dispatching of planned orders?
When the orders are need to be dispatched?
Is it after firming of order?
What impact it will have on the system after we dispatch the planned order?
I observe that after dispatching the planned order, we have tick on capacity dispatched. In MD04, for the planned order there are double stars for dispatched orders?
Can anyone explain the this functionality in simple way.
Points will be rewarded.
Srini

Hi,
Normally we can do the capacity leveling  for Plannend order and Production Order. In R/3 , MRP run dosenot consider  Capacity Over load, Capacity leveling is required to for Planned order.
U reserve the Capacity  on particular date by despatching the planned order at Planning Table. Which results in Capacity is scheduled on that Particular date & time for  that Planned order.System will not allow to despatch another order  in the same date.
Firm & Capacity scheduled check box is activated when u despatch the Order.  MRP will not reshedule that Planned order.
when u convert that Planned order to production order, system will schedule the order with  same date  & set the despatch status for Each opeartion.No need to despatch the Prod order Again.
Pradeep

Similar Messages

  • Dispatching problem in REM Planning Table

    Hi,
    I have encountered a problem in REM planning Table, from REM planning table when i m accessing Bar char planning table and try to dispatch the planned order it is not dispatching the order. I have checked the scenario is previously it was working fine but now it is not working with same settings can u guide me tht which settings affect the planning table dispatch. neither it was showing the capacity requirements, i have maintained the rate formulas is work centre and formula was working fine, i doubt it relate to SPRO settings kinldy give me hints where i can check n wht standard settings i have to make for planning table..

    Plz give some suggestion on this....

  • Use of Planning Table (MF50) in Capacity Levelling with Production Order

    Hello Experts
    I wish to know that is it possible to perform Capacity Levelling in planning table (tcode MF50) with respect to a Production Order ? It is known that MF50 is used in Repetitive manufacuring to do the capacity levelling with respect to Planned orders. But in our discrete manufacturing scenario we want to use planning table to the capacity levelling with respect toa Production order.
    Any clue or help pertaining to this will be highly appreciated.
    Thanks in advance
    Regards
    Jayanta

    Dear ,
    MF50 is does the cacapcity leveling based on mateail -run schedule order (planned order ) where as in discrete manufacturing , when you run the MRP ,  MRP system assume Infinite Capacity  and schedule the order as per your selection in MD02(2,1,3,3,2)  and then you convert those planned order to Production order .Here you checkied the Capacity in Production Order level .
    In stanadrd SAP  , it is not possible to use MF50 for discrete production order.
    In discrete order or process order ,  do the caapcity leveling , there are seperate planning table available based on Over all Capacity Profile and Schedule type .This can be done  in following way :
    1.CM31-Production Order Wise -Tabular
    2.CM23-PO wise -Graphical
    3.MC88: Ruf Cut Planning
    Work Centre Wise : CM21 -Graphical , CM22-Tabular Planning Table .
    Make sure the below set up before  you carry on the Capacity leveling :
    .Define time profile in OPD2.
    Define the strategy profile in OPDB
    Define the Overall profiles in OPD0.
    In OPJK  maintained check capacity with SAPSFCG013 profile for your production order type
    In OPU3 , scheduleing parametre s: Generate Capacity , Scheduling Type , Automatic Log ,Start date in Past as per your req.
    In OPJU , chekc the contol tab of the scheduleing as per OPU3
    In OPKP- Production scheduling paranmeters assing the overall capacity profile -SAPSFCG013  with finte scheduling tick.
    Master Data :
    1.Materials Master define the Production scheduler and production scheduling profile
    2.Work Center - Define the capcity planner group,activate checkbox Relevant for Finite sceduling,on the capacity header define the shift timings,break timings and unit of measure,no of individual capaity, enter formula for scheduling in capacity view.
    3.Routing - enter the values for the standard values. Use control key with scheduling.
    Hope this will help you .
    Regards
    JH

  • Automatic dispatch of Planned Order - Reg.,

    Hi
    Here i'm trying to dispatch a planning order automatically, when a work center capacity got fully loaded. What is the necessary settings has to be done?
    Kindly explain clearly
    Regards,
    Gopi

    Dear ,
    When you are dispatching the operation for Planned Order /Production order in that day , system checks the availble capacity load in that work centre .If required capacity is not avalaible based on the work centre available capacity (Capacity Tab-Available capacity -Check overload CM05 for workcentre in that week) , operation will not be dipatched and Scheduling logg will be created
    .I suggest that you need to check the Available Capacity (can be viewed weekly /monthly -Select the weekly grid -double click -system will dipaly the daily load in a week ) of the work centre and then go back to CM25 with your work centre -select Overall Profile -Enter Work centre -Strategy -Mark "Date Entry while dispatching " which will hel you to dipatch the date based available capacity CM05.Or else try to use CM21-Graphical view (goto -settings-scale-daily split -chek the available capacity date -dispatch.
    In CM01/CM05 , please enter Plant /Work Centre in CM05-Hit DETAIL Capacit list or Varibale View -it will display with weekly bais capcity set up based on the .Select the week where this date fall on or If you want to look the daily baisi load , then goto Planning tab-Profile-Option Profile -select as appropirate to analysis the load daily /weekly
    Setting Required :
    1. Settings for Available Capacity
    2. Setting for Capacity requirements
    3. Settings for Capacity evaluation and leveling
    1.Materials Master define the Production scheduler and production scheduling profile
    2.Work Center - Define the capcity planner group,activate checkbox Relevant for Finite sceduling,on the capacity header define the shift timings,break timings and unit of measure,no of individual capaity, enter formula for scheduling in capacity view.
    3.Routing - enter the values for the standard values. Use control key with scheduling.
    4.In transaction OPU5 and OPU3Z - define the scheduling parameters for planned order and productiion orders and activate the checkbox Capacity requirement and Scheduling. what is the settings in OPPQ and OPPR for the "Start in Past" parameter, you need to keep them consistent with the OPU5 settings.
    Capacity Setup :
    Define time profile in OPD2.
    Define the strategy profile in OPDB
    Define the Overall profiles in OPD0.
    In the order control OPJK I have maintained check capacity with SAPSFCG013 profile.
    Define Scheduling parameters for Production orders-OPKP-Maintain Capacity Checked /Finite Scheduling Cheked /Scheduing Type -BW/FW .
    Hope this will help u in analysis the set up.Revert if u need any help
    Regards
    JH
    Edited by: Jiaul Haque on Apr 28, 2010 2:04 PM

  • Deleted planned order in any table??

    Hi,
    Is it possible to see the deleted planned order in any table??
    Ramagiri

    Hi,
    It is right that you will not get the planned order data which has been deleted.
    But after conversion of planned orders to process/production order the planned orders will get deleted.The planned orders data can be found fromAFPO table.But manually deleted planned order data can't be found out.
    Hope this can help.
    regards,
    kaushik

  • ASCP: How do I get the list of 1st level planned orders using msc_full_pegging table

    How do I get the list of 1st level planned orders using msc_full_pegging table, is any one having the script.

    Do you mean supply_type? If so, yes it will be in pegging table as supply_type or otherwise you can join this table with msc_supplies by joining transaction_id column and get the order_type from that which will be the supply type.
    Thanks,
    Abhishek Sharma
    P.S:- Try opening the discussion in a separate window and see if you get the option to mark it correct or helpful,

  • Planning Planned order in planning table graphic (PP-PI)

    Is it true that cannot plan planned orders, that will be destined to process orders in the table of graphical planning? (CM25).
    Because I tested with all the profiles standard and no one leaves me to dispach planned order....
    Thanks regards

    Hi
    Try following things in spro in development & test
    goto
    Capacity requirement Planning-Operation-scheduling-scheduling paramets for Planned order
    This may of help.
    regards
    Prakash

  • What is the need for planning table.

    can anybody explain me about planning table, how and where to use that..

    Dear
    Use of planning table :
    1.Capacity Requirement Planning in Discrete and PP-PI indistutry
    2.For demanad management , you can create PIR and also generate MTS production order based on planned order for those PIR
    3.Decision making on CRP in planning table for operation dispatch , work centre , scheduling , detail scheduling , time , dates of capacity avalution is possible through Planning table under particular overall profile .
    refer : Use of Planning Table (MF50) in Capacity Levelling with Production Order
    http://help.sap.com/printdocu/core/Print46c/en/data/pdf/PPCRPPPPI/PPCRP_PPPI.pdf
    Regards
    JH

  • Customizing Graphical Planning Table Views

    Where do I go to alter the look of the graphical planning tables that I find in transactions like CM21, 27, 31 and 32?  There are no labels, everything is gray and difficult to read!  Where can I go in and change the way these graphical planning tables look?  Mainly the colors of the dispatched orders into the work centers (the single gray bars).

    Dear,
    Please refer this link,
    [Lay-out Profile Set|New Lay-out Profile for CM25]
    Regards,
    R.Brahmankar

  • IW37n using the Planning Table with Overall Profile for Wrk Cnter Hierarchy

    Dear Experts,
      We are using IW37n to sort and filter our orders.  From there we make a selection and then GOTO the planning table to use for dispatch.  We copied the overall Profle to allow us to define the Evaluation Profile to allow for a Work Center Hierarchy and Plant to be defined.
    If I run CM25 using the overall profile the Work Center Hierarchy works fine.  If I use IW37n,  enter the same overall profile it does not execute the CM25.  Is there something else we should to get the CM25 to run?
    Regards,
    Roseanne

    Can I take this out a little further.  I verified with two orders that indeed both are being shown coming through IW37n or CM25.  I've determined that the profile is being called.  The layout shown in Chart 2 is correct.  It's chart 1 that is not showing the work center hierarchy correct from IW37n, it only shows the top node of the work center.  We have two scenario, one work center is defined with the employee linked to HRMS.  The lower node is a work center used to schedule too.  The other work center structure is the employees are defined as work centers.  We build the order to the top node and then use the hierarchy to schedule to each individual work center.  In both cases using IW37n, the lower level work centers are not shown in chart 1.
    If running CM25 independent it works fine.
    Regards,
      Roseanne

  • Graphical Planning Table can show quantity?

    Dear all,
    I am using Graphical Planning Table (MF50), the graphic shows the planned order number for each Material.
    How can the graphic show the quantity for each Materials?
    Pls help me to configure it.
    Thank you very much!
    Cao Huy

    Hi Huy Cao,
    why not to show the order QTY in the table section of the chart for each material? you could create a layout key containing the field GSMNG-PLAF and assign it to the layout of the charts - dispatched and pool via OPDJ.
    Cheers,
    Mao

  • Operations are not getting despatched in capacity planning table

    Hi Experts,
    I am using capacity planning table (Graphical) to level the capacities and sequence the process orders. The start date of my orders are very well in future and sufficient capacities also is available in resources. But when I go to CM25 and select one order and click on despatch, system is not despatching it. This is the case for almost all the overall profiles.
    The surprising factor is, this function was working fine earlier without any issues. I havent done any changes in configs which will affect capacity planning.
    What can be the reason for this? Any thoughts please?.
    One more thing. Is there any option to avoid the capacity planning step if Iam using R/3 and manage it by some other way?
    Appreciate your earlier reply
    Thanks & Regards
    Prathib

    Most likely you didnt define the rowsource key properly. Please look under <install>/errors folder for any file there.
    Also, please read the documentation. There is information there about how to troubleshoot a loading problem. Please always read the documentation and we would appreciate feedback on the documentation.
    http://download.oracle.com/docs/cd/E17236_01/epm.1112/iop_user_guide/frameset.htm?launch.html

  • Error message in capacity planning table

    Hi,
    I am  using REM planning table.I enter the planning table by giving the selection criteria of Plant and production line.
    System is giving following error message,
    the error message and dignosis of the error message is given here.
    'No prod. dates for material MTI_FERT011, version 0001, production line 2279'
    Message no. REMPT315
    Diagnosis
    The planned order has no production dates for the combination of material, production version and production line you specified.
    This may be as a result of the following, for example:
    The planned order was scheduled but not using the production line you selected. (The production line is determined by the production version you entered in a planned order.)
    Procedure
    One possibility of finding out what is causing the problem is:
    To access the planned order from the detailed dialog box in the table via "Change" and reschedule the planned order. Check the scheduling log by choosing "Goto --> Scheduling log". More information is displayed in the log's warning or error messages.
    But which master data to be corrected is not known.
    Experts please guide me.
    Regards,
    Ravindra

    Hello,
    I had the same error while working with the REM planning table, despite the consistency of the data.
    Another cause that can lead to the error message REMPT315 is that in the production version detailed screen, "Planning data" table you have entered the routing next to rate-based planning. You must enter the routing (number of the group and the group counter) on the line detailed planning.
    After that, choose check again and try to introduce new quantities in the planning table. It worked for me!
    Irina

  • Unable to drop or truncate a plan table

    Hi guys,
    I was trying to execute 'Explain Plan' on one of my query. However, when I tried to drop the plan table, i was prompted that the table or view does not exists:
    QL> EXPLAIN PLAN FOR
    2 SELECT * FROM ORDERS WHERE TO_CHAR(O_SHIP_DATE, 'YYYY')='2005' AND O_STATUS='PROCESSING';
    Explained.
    SQL> SELECT * FROM TABLE(DBMS_XPLAN.DISPLAY);
    PLAN_TABLE_OUTPUT
    Plan hash value: 1275100350
    | Id | Operation | Name | Rows | Bytes | Cost (%CPU)| Time |
    | 0 | SELECT STATEMENT | | 648 | 46008 | 725 (5)| 00:00:09 |
    |* 1 | TABLE ACCESS FULL| ORDERS | 648 | 46008 | 725 (5)| 00:00:09 |
    Predicate Information (identified by operation id):
    PLAN_TABLE_OUTPUT
    1 - filter("O_STATUS"='PROCESSING' AND
    TO_CHAR(INTERNAL_FUNCTION("O_SHIP_DATE"),'YYYY')='2005')
    14 rows selected.
    SQL> TRUNCATE TABLE PLAN_TABLE;
    TRUNCATE TABLE PLAN_TABLE
    ERROR at line 1:
    ORA-00942: table or view does not exist
    SQL> select count(*) from plan_table;
    COUNT(*)
    6
    Any idea what went wrong? Thanks in advance.

    Ok, I managed to find the scripts to recreate the plan table. Now it works again. Cheers.

  • Question on Plan Table

    Hi,
    This is the Explain Plan for one of my SQL queries
    PLAN_TABLE_OUTPUT
    | Id  | Operation            |  Name       | Rows  | Bytes | Cost  | Inst   |IN-
    OUT|
    |   0 | SELECT STATEMENT     |             |   101 |  7676 |    60 |        |
    PLAN_TABLE_OUTPUT
       |
    |   1 |  SORT ORDER BY       |             |   101 |  7676 |    60 |        |
       |
    |   2 |   NESTED LOOPS OUTER |             |   101 |  7676 |    50 |        |
       |
    |   3 |    VIEW              |             |   100 |  2400 |     5 |        |
       |
    PLAN_TABLE_OUTPUT
    |   4 |     UNION-ALL        |             |       |       |       |        |
       |
    |   5 |      REMOTE          |             |       |       |       | MKTG   | R-
    S ||   6 |      REMOTE          |             |       |       |       | MKTG   | R-
    S ||   7 |    REMOTE            |             |     1 |    52 |     1 | MKTG   | R-
    S |PLAN_TABLE_OUTPUT
    Note: cpu costing is off, PLAN_TABLE' is old versionI am concerned about the note "cpu costing is off"
    Does this mean my optimizer is RBO?
    Moreover, what is the cost cloumn in the explain plan table meant by?
    BANNER
    Oracle9i Enterprise Edition Release 9.2.0.6.0 - 64bit Production
    PL/SQL Release 9.2.0.6.0 - Production
    CORE 9.2.0.6.0 Production
    TNS for HPUX: Version 9.2.0.6.0 - Production
    NLSRTL Version 9.2.0.6.0 - Production
    I did 'select cpu_cost' from v$sql_plan;'
    The column results in NULL values.
    Thanks
    Rajiv

    Hi Justin,
    I ran into some serious problem here.
    As per the suggestions given, this is the modified query
    SELECT   x.rep_date,
                   x.certificate_id,
                   x.member_kit_flag,
                   y.enabled_date,
                   y.disabled_date,
                   TRUNC(y.creation_date) - TRUNC(x.rep_date) days,
                   y.csg_account_no
              FROM (SELECT /*+ DRIVING_SITE(pt_gift_cert_referrals) */ a.*,
                           /*+ DRIVING_SITE(pt_cd_mailings) */ b.member_kit_flag,
                           to_date(b.shipment_date,'dd MON YYYY') rep_date
                      FROM pt_gift_cert_referrals@mktg a,
                           pt_cd_mailings@mktg b
                     WHERE a.cert_mailing_id = b.cert_mailing_id
                       AND to_date(b.shipment_date,'dd MON YYYY') >= '22-AUG-2003'
                    UNION ALL
                    SELECT /*+ DRIVING_SITE(pt_gift_cert_referrals) */ a.*, /*+ DRIVING_SITE(pt_certificate_referrals) */
                           'Z' member_kit_flag,/*+ DRIVING_SITE(pt_cert_stage_log) */
                           to_date(b.creation_date,'dd MON YYYY') rep_date
                      FROM pt_gift_cert_referrals@mktg a,
                           pt_cert_stage_log@mktg b
                     WHERE a.cert_event_id = b.cert_event_id
                       AND SUBSTR(b.process_type, 1, 14) = 'CLUBDISH DAILY'
                       AND to_date(b.creation_date,'dd MON YYYY') >= '22-AUG-2003') x,
                   pt_certificate_referrals@mktg y
             WHERE x.certificate_id = y.certificate_id(+)
          ORDER BY rep_date,
                   x.certificate_id;Unfortunately, the query resulted in NO rows.
    no rows selected
    Elapsed: 00:02:31.03
    Execution Plan
       0      SELECT STATEMENT Optimizer=CHOOSE (Cost=60 Card=101 Bytes=76
              76)
       1    0   SORT (ORDER BY) (Cost=60 Card=101 Bytes=7676)
       2    1     NESTED LOOPS (OUTER) (Cost=50 Card=101 Bytes=7676)
       3    2       VIEW (Cost=5 Card=100 Bytes=2400)
       4    3         UNION-ALL
       5    4           REMOTE*                                            MKTG.WOR
                                                                           LD
       6    4           REMOTE*                                            MKTG.WOR
                                                                           LD
       7    2       REMOTE* (Cost=1 Card=1 Bytes=52)                       MKTG.WOR
                                                                           LD
       5 SERIAL_FROM_REMOTE            SELECT /*+ */ "A2"."CERTIFICATE_ID","A2"."GI
                                       FT_CSG_ACCOUNT_NO","A2"."CERT_PROMOT
       6 SERIAL_FROM_REMOTE            SELECT /*+ */ "A2"."CERTIFICATE_ID","A2"."GI
                                       FT_CSG_ACCOUNT_NO","A2"."CERT_PROMOT
       7 SERIAL_FROM_REMOTE            SELECT "CERTIFICATE_ID","CSG_ACCOUNT_NO","EN
                                       ABLED_DATE","DISABLED_DATE","CREATIO
    Statistics
              0  recursive calls
              0  db block gets
              0  consistent gets
              0  physical reads
              0  redo size
            338  bytes sent via SQL*Net to client
            234  bytes received via SQL*Net from client
              1  SQL*Net roundtrips to/from client
              1  sorts (memory)
              0  sorts (disk)
              0  rows processedThe thing more bothering is, optimizer is not using the DRIVING_SITE hint
    Previous Execution Plan was....
    6742176 rows selected.
    Elapsed: 03:15:20.07
    Execution Plan
       0      SELECT STATEMENT Optimizer=CHOOSE (Cost=53 Card=100 Bytes=76
              00)
       1    0   SORT (ORDER BY) (Cost=53 Card=100 Bytes=7600)
       2    1     NESTED LOOPS (OUTER) (Cost=50 Card=100 Bytes=7600)
       3    2       VIEW (Cost=5 Card=100 Bytes=2400)
       4    3         UNION-ALL
       5    4           REMOTE*                                            MKTG.WOR
                                                                           LD
       6    4           REMOTE*                                            MKTG.WOR
                                                                           LD
       7    2       REMOTE* (Cost=1 Card=1 Bytes=52)                       MKTG.WOR
                                                                           LD
       5 SERIAL_FROM_REMOTE            SELECT "A2"."CERTIFICATE_ID","A2"."GIFT_CSG_
                                       ACCOUNT_NO","A2"."CERT_PROMOTION_ID"
       6 SERIAL_FROM_REMOTE            SELECT "A2"."CERTIFICATE_ID","A2"."GIFT_CSG_
                                       ACCOUNT_NO","A2"."CERT_PROMOTION_ID"
       7 SERIAL_FROM_REMOTE            SELECT "CERTIFICATE_ID","CSG_ACCOUNT_NO","EN
                                       ABLED_DATE","DISABLED_DATE","CREATIO
    Statistics
              0  recursive calls
             14  db block gets
              0  consistent gets
          14173  physical reads
              0  redo size
      112195379  bytes sent via SQL*Net to client
        3146621  bytes received via SQL*Net from client
         449480  SQL*Net roundtrips to/from client
              0  sorts (memory)
              1  sorts (disk)
        6742176  rows processedAny help on this would be greatly appreciated.
    Thanks
    Rajiv

Maybe you are looking for

  • How to updates to 10.8.5 from 10.6.8

    Forgot the apple id security answer, cannot apply my apple id on my mac air, please help

  • Pixels on viewing screen

    I've got a 120 GB Classic--7 months old, rarely used. I noticed yesterday 3 lines of pixels on the viewing screen that aren't working (i.e. a visible "line" in 3 different places in the center of the screen. I didn't drop it or smash it--I have no id

  • Laptop device not recognized

    Hp Pavilion dv6725us s/n CNF751066W p/n KC301UA#ABA I am running Windows Vista 32 bit The following devices DO NOT show up on Device Manager: ·         DVD/CD Rewritable DriveAD-7561A ·         HP Webcam Also the following devices ARE listed on the D

  • Drop Normal Tablespace Taking several hours

    Hi, In my 1TB database there is one tablespace size (38.5 GB / used 4 GB) which we used for objects backup purpose and i am trying to drop this tablespace using every option like bring tablespace offline and drop with DROP TABLESPACE TBS_NAME INCLUDI

  • A question about JTabbedPane?

    jScrollPane1.getViewport().add(jTextArea, null); jScrollPane1.setRowHeaderView(jLineArea); jTabbedPane1.add(jScrollPane1, "File"); I use JTabbedPane to show more than 1 files, each tab includes one JScrollPane,which in turn contains a JTextArea (show