Dynamically create Variant Data Socket items with multiple writers

I want to use variant or cluster items with data socket connection. I want to allow multiple writers.
So far I can create these items dynamically but not set them to allow multiple writers.
For numeric, string, and Boolean items I can set these properties by predefining them in the data socket server manager. I could not predefine a variant or cluster in the manager.
I realize I can flatten to string the item needed but would prefer to do this in the cluster or variant formats.
Any suggestions?

unclebump wrote:
Could you accomplish this using a functional global architecture??
An interesting concept which might work and did just open up a new host of possibilities!
When I get the time I might give this a try. I just did a quick test in another program.
Through VI server I opened a reference to a remote machine. I then created strictly typed reference to a “functional global vi” that I knew would be in memory. It reads the functional global just fine!
Thanks for the suggestion.
Here is the work around I used for the data socket program.
Here is the original problem.
I needed to know on the server side when a new value was written to the message cluster, which consisted of a string and a variant. Checking the string portion of the cluster let me know what command to send the device being controlled on the server machine. The variant is used to hold the various parameters that accompanied the command. Since the same command type could be sent several times I needed to reset the string control after the server read the command. This required writing to the data socket from the client & server machine (multiple writers). Also since the client could be any PC in the subnet I needed to allow all these machines to have write access.
I solved this by using a second data socket item for the new message flag. This item is a string value that could be pre-defined and set to allow multiple writers. I then used the cluster item to handle the commands and wrote to the string item a signal that a new command was ready. The server then recognizes a new command is ready, reads the command, and then flags the string message received.
Thanks again for those who took the time to answer this.
Randall

Similar Messages

  • How to Restrict Single Delivery Date for PO with Multiple Line Items

    Dear Experts,
    How to Restrict Single Delivery Date for PO with Multiple Line Items.
    System needs to through Error Message if User Inputs Different Delivery Dates for PO with Multiple Line Items in ME21N Tcode.
    Can we achive this by Some Enhancement in SAP or Not ???
    If so how to do it.
    Any Inputs is highly appreciated.
    Thanks and Regards,
    Selvakumar. M

    Hi Selvakumar,
    we can resrict the PO to have a single delivery date in all the line items by means of giving a error message or overwiting the delivery date keyed/determined in the line item.
    You can use the BADI -> ME_PROCESS_PO_CUST. In which you need to implement the method PROCESS_SCHEDULE.
    (for technical aid - This method will be called for each and every PO line item, From the imporing parameter im_schedule we can get all the details of current PO line, even we can change the data in the current PO line. )
    Regards,
    Madhu.

  • How to create list items with multiple attachment files using rest api javascript

    In one of user form I am using javascript rest api to create a list item with multiple attachment files. So far I am able to create list item and once created uploading an attachment file. But this is two step process first create an item and then upload
    a file.
    It create an additional version of the item which is not desired. Also I am not able find a way to attach multiple files in a go. Following is the code I am using.
    createitem.executeAsync({
                    url: "/_api/web/lists/GetByTitle('UserForm')/items(1)/AttachmentFiles/add(FileName='" + aFile.name + "')",
                    method: "POST",
                    contentType: "application/json;odata=verbose",
                    headers: {
                        "Accept": "application/json;odata=verbose",
                        "X-RequestDigest": $("#__REQUESTDIGEST").val()
                    binaryStringRequestBody: true,
                    body: fileContent,
                    success: fnsuccess,
                    error: fnerror
    So somehow I need to combine item attributes along with attachment files in body: param. I visited https://msdn.microsoft.com/en-us/library/office/dn531433.aspx#bk_ListItem but no success.
    Appreciate any help.

    Thanks Mahesh for the reply and post you share it was useful.
    But this does not solve the core of the issue. You are uploading attachments after creation of item and multiple files are being attached in loop. This is kind of iterative update to an existing item with attachments. This will end up creating multiple versions. 
    What I am trying to achieve is to create an item along with multiple attachments in a go. No item updates further to attach a file.
    Please suggest how this can be done in one go. SharePoint does it when one creates an item with multiple attachment.
    Thanks for your reply.

  • Dynamically create and remove TEXT items in forms

    Hi Guys,
    Is there a way to dynamically create and remove TEXT items in form. For example I have the EMP and DEPT table and when
    I select the EMP table name from the LOV, rows of the EMP table with column name and data should get displayed on the screen and likewise a similar action for DEPT table and
    so on. I have about 90 tables from where data could be required to view and edit. They all have varying number of columns.
    Any suggestions ?
    Thanks
    KMD
    null

    Use OLE concept of developer and map Excel as an object
    Nadeem
    null

  • SharePoint Designer 2013 (2010 Platform Workflow) - How can I create a new list item with a SPECIFIC content type?

    In SharePoint 2010 I created workflows that used the 'Create list Item' Action, which then set the Content Type ID (so I could create documents of various types in a document library). 
    We just switched to the SharePoint 2013 platform, and now the drop down for Content Type ID is blank in all of the workflows that are still using the SharePoint 2010 platform.  Is there any way to create a list item with specific content
    type?  Even if I could just input a string into that field instead of using this blank drop-down.  Please help! 

    Hi Sarah,
    According to your description, my understanding is that you cannot create a new list item with a specific content type using SharePoint 2010 Platform Workflow.
    I tested the same scenario in my environment, and the Create List Item worked fine with the specific content type.
    How did you create the content type?
    Please check if the content type is added to the list/library the workflow associated with.
    Best regards.
    Thanks
    Victoria Xia
    TechNet Community Support

  • Creating a Data Guard Database with RMAN in 10&11g

    I found this notes for 9i, looking for same for 10g & 11g
    183570.1 Creating a Data Guard Database with RMAN (Recovery Manager) using Duplicate Command

    These notes just show duplicating dbs without datagurd, i am looking for Creating a Data Guard DB with RMAN in 10 &11g.

  • How do I create a drop down menu with multiple items in Adobe Acrobat 9?

    I am trying to create a drop down menu with four items within a field box.  When I try to do this
    the font is too big and it just doesn't fit.

    You can use panel widget to create manual menu where set to show target on rollover.
    Something like this :
    http://muse.adobe.com/exchange-library/menu-vertical-accordion-widget-1
    http://muse.adobe.com/exchange-library/tiptop-navigation-menu
    Thanks,
    Sanjit

  • Dynamically create varying number of buttons

    Hi.
    The website I'm currently working on has an object gallery.
    Whenever the user clicks one of the objects, it zooms in and
    displays a sub-gallery with other images of said object. The images
    that make up these galleries are loaded into dynamically created
    empty MovieClips inside a sub-gallery MovieClip. Each object has a
    varying number of images and they're loaded and unloaded when the
    zooming in/out of the object ends.
    When you click one of the sub-gallery images, the main image
    should change and display the clicked image. However, I'm having
    trouble telling the MovieClips containing the sub-gallery images to
    do anything when they're clicked. See attached code, please.
    I'm guessing this has to do with the onRelease being declared
    inside the onMotionFinished. The thing is I can't thing of a way to
    declare the onRelease for every sub-gallery image before they're
    loaded.
    Thanks in advance.

    Frank,
    Thank you for the response.
    On the page2 of the pdf link you provided there is a picture of the tree table and it shows the hierarchy of the first level(or root) parent (President, Steven King). If the data had n presidents (n first or root level ) then this will dispaly all data in the same tree table like
    King
    --Kochhar
    ----Greenberge
    King 2
    --report 1
    ----report 1.1
    King n
    --report n
    ----report n.1
    My requirement is pretty close to this but slighly different where these n first level should appear in n different tree tables like below:
    Treetable for: King
    King
    --Kochhar
    ----Greenberge
    Treetable for: King 2
    King 2
    --report 1
    ----report 1.1
    Treetable for: King n
    King n
    --report n
    ----report n.1
    That is the reason why I am playing with af:forEach and also have a separate VO which returns all the presidents(first level parents) and view linked that to EmployeesVO so that the AM looks like
    AllPresidentsVO
    -----EmployeesVO (with the view criteria wihch returns the first level parents)
    ---------reportingManagers
    forEach prints n instances for PresidentsVO King, King2.. King n but all these instances have the same children the tree for King (tree for King2 ... King n does not appear)
    May be it should be achieved in a different way?

  • Dynamic routing for a Business Service with multiple operations

    I have two business services with multiple operations. Business service A (bsA) has operations OpA1 and OpA2. Business service B (bsB) has operations OpB1 and OpB2.
    Depending on incoming Proxy message and operation, I have to do one of the following
    1. If someValue = A and operation= Op1 then invoke operation opA1 of bsA
    2. If someValue = B and operation= Op1 then invoke operation opB1 of bsB
    3. If someValue = C and operation= Op1 then invoke operation opA1 of bsA AND* operation opB1 of bsB and return aggregate data of both invocations
    1. If someValue = A and operation= Op2 then invoke operation opA2 of bsA
    2. If someValue = B and operation= Op2 then invoke operation opB2 of bsB
    3. If someValue = C and operation= Op2 then invoke operation opA2 of bsA AND* operation opB2 of bsB and return aggregate data of both invocations
    Using a dynamic route node or dynamic routing options, I am able to achieve cases 1, 2, 4, and 5.
    But for cases 3 & 6, I can not use a route node. When I use a Service call out instead, then I am forced to create a Operational branch but that does not seem like the best design since for every new operation added to the business services, I have to add a new branch to the Operational branch and redo all the functionality for that branch.
    Basically, I am looking to achieve the functionality of the Route node ( no need to specify the operation ).
    Any thoughts/ideas on what the best design would be?
    thanks

    For cases 3 & 6, why don't you route to another proxy service where you can simple do two service callouts, merge output data somehow and return them to the first proxy?
    If you look for "special route feature", that could possibly call two services for a single message, I'm afraid you won't succeed.

  • Data socket problems with LVRT 8.2

     I am in the process of migrating to LV 8.2 from LV7.1.1. My system has 18 RT targets which send data to a Host PC through data socket (DS). The Host PC runs LV on Windows XP Pro.  With LV7.1.1 on both host and RT targets DS works perfectly. The RT targets update the host every 500 ms.
    I've taken a three-step process in the migration. First tests were done with the host migrated to LV8.2 while keeping the RTs at LV7.1.1. Result: the system worked perfect. Then I changed one RT to 8.2 keeping the rest the rest at LV7.1.1. Result: DS timed out before all the data could be sent to Host. Finally, all RTs were migrated to LVRT 8.2. Result: Only about 5 out of the 18 RTs report to the Host before DS times out. However, if only one RT target is used, i.e., the other 17 RTs are diasbled, communication is very fast. Is there a special setting that I need to make? Btw, the roughly 5 RTs that report vary randomly from test to test, i.e., there is no bias towards any particular RTs.
    I am using the same source code developed under LV7.1.1, so the only changes made are the ones that take place when one opens LV7.1.1 code in LV8.2. Some VIs get converted in the process.
    Any ideas?
    Chatonda Mtika
    Algis Corp
    Vancouver, Canada

    Ben,
    I must say I am very surprised by Nadim's email. His point, which I must say I don't agree with, was made quite clear to me yesterday during a conference call between my team and the NI team comprising Chris, Nadim, and Avinash. So I don't know what purpose this morning's email is supposed to serve. Be that as it may, I think NI has gotten it wrong here. I do not think it should be one or the other. The discussion forum is a much wider forum comprised of people with varying experiences - not just NI employees. That is precisely why I posted my problem to the forum: to tap into the vast experiences of the discussants. But when I did not get any responses after I had posted answers to Nadim's questions, I decided to make a formal service request to NI, all perfectly legal. So I was really surprised when I was being blamed for tying up NI resources on one problem. I believe the resource allocation issue should be NI's to solve, not mine. I have no way of knowing that NI had formally assigned somebody to my problem. What if nobody from NI responds, am I allowed to make a service request to NI? My feeling is that NI's logic is flawed here, assuming Nadim's views are NI's views.
    Thanks,
    Chatonda Mtika
    Algis Corporation
    Vancouver, Canada

  • PO item with Multiple Goods receipt line items

    Hi Experts,
    When we create PO for specific vendor with one PO line item then at the time of Good receipt there are multiple GR line items. How to control those multiple GR line items as one GR item.
    Appreciated your help
    Regards
    Krishna

    Hi,
    If you did GR from PO with underdelivery qty in line items, SAP recognize it as partial delivery.
    Basically, in the standard system the underdelivery qty scenario is allowed, but not for overdelivery qty.
    If you intended to force the system to allow one line item in PO with only one line item in GR, therefor you could create program checking with development team.
    please check the link for your reference.
    http://help.sap.com/saphelp_47x200/helpdata/en/a5/63344643a211d189410000e829fbbd/frameset.htm
    regards,
    rob

  • Create opaque view in OBIEE with multiple tables

    Hi,
    I need some help with the opaque view since i have never created it in past. I want to create an opaque view which fetches data from multiple tables. Is it possible to do that ? Or is there any other alternate option available in OBIEE ? I read the following blog and other similar blogs on opaque views but could not find option to use it for query with multiple tables:
    Oracle Business Intelligence: Creating Opaque View in Physical Layer in OBIEE 10g
    Also can you please advice how to join two tables from different databases in OBIEE ?
    Kindly advice.
    Regards,
    Andy

    Hi Andy,
    As per my knowledge you can create Opaque View on one table at a time.Joining two tables from different databases yes we can create a report from multiple data sources.Check this
    Rittman Mead Consulting » Blog Archive » Reporting Against Multiple Datasources in OBIEE
    Mark if helps.
    Thanks,

  • OBIEE Date Comparison report with multiple measures

    Hello everyone...
    I have a requirement where I need to create a date comparison report (Current Month vs. Prior Month vs Prior Month Year Ago vs YTD vs Prior YTD vs Rolling 3 months, etc) with multiple Measures (Quote count, Quote offered count, New Business count, etc). I am to generate this report in this fashion:
    Quotes Current Month vs PM vs YoY Prior
    Month Current Month Prior Year Current
    YTD vs PM Prior
    YTD Rolling 3 Months vs PM Prior Rolling 3 Months
    Issued 120 120 123 1400 1020 1700 1580
    Unique Risks
    Offered 556 449 571 5881 6220 6101 5892
    Unique Risk Close Ratio
    Offered Close Ratio 21.6% 26.7% 21.5% 23.8% 16.4% 27.9% 26.8%
    Bitmap
    Avg Issued Premium 240 238 222 2801 2630 3104 2892
    Avg Offered Premium
    New Business
    Count
    Avg Full Term Premium
    I understand that time series is an option, and have created the time series (which show up as measures).
    My problem is:
    when creating the report (even as a pivot table) , OBIEE is not allowing me to drag the measure to rows, nor is it allowing me to drag the time series to columns. Also, I need to do conditional formating on some of the columns showing an up arrow for increased vs. prior month and down arrow for decreased vs. prior month.
    Does anyone have a solution for this issue? Any assistance would be greatly appreciated...
    Please advise and thanks!!!

    Jason,
        You've been very helpful, but I guess I'm just not explaining myself that well. The Credit Memo's throw things off because they do not contain a "Paid Date" value. That field in the record is blank. Since it is blank the report query ignores them. Therefore when the report query returns all records that have a "Paid date" range of "x to y" they are never returned. This is a problem whenever a credit memo exists for an invoice because the "invoice total" never changes. So when a customer pays on their account for a particular invoice, they only pay what is due which is the "invoice total" minus any "credit" from the "Credit Memo". So when my A/R person receives payment they are showing the invoice paid in full because MAS automatically includes all invoices and credit memo's. My report does not because there is no data in the "Paid Date" field of the record for Credit Memos.
    I've been doing alot research in trying to resolve this "exception" to my report. I think I may be on to something, but my knowledge of arrays is extremely limited. My resolution involves populating an array with the "invoice numbers" that are returned from the initial query from the supplied date range. Then using the "invoice numbers" from the array have it then populate my details section of the report with all of "invoice records" both the actual invoice record and any "credit memo" records. I can then group the records returned  based upon the "invoice number". then within that grouping I can performing my calculations to show whether or not the invoice has been paid in full. What do you think?  I've been able to populate an array with the invoice numbers based upon my date search range, but I have yet to figure out how to take that information and perform another lookup to pull in the rest of the data I need. Do you have any ideas?
    Thanks.  Bill

  • Confidential site - Create Due Date Notification Email with Nintex

    I hope you can help
    I'm trying to create a workflow that will send multiple notifications dependant on a column called 'Remediation deadline'(This is a date field) The notifications are planned for 3 months
    before the remediation date as an 'Action', 2 months before the remediation date as 'High' and 1 month for 'Critical'.  
    I have created a calculated field to put the date into the correct format using =TEXT([Remediation deadline],'dd/mm/yy') in an effort to run the workflow from this date if possible as the formats
    are correct(Not sure if the format even makes a difference?)
    I'm new to SharePoint which means my knowledge is very limited, also the site I'm currently working on is a confidential site, so I have no access to designer and if I choose to add a WebPart,
    I have to send it over to another team to action which is highly frustrating as they are not as eager as me to reach my goal.
    The problem I face is where I go from here with such limited access.  The only notification process that works is based within Nintex, but from the documentation I’ve read, you need to
    be able to run the 'CallWebPart' function.  I also have 1200 records that can't be removed from the task list, I tried a loop process but it caused the server to fall over as our main server is in a different country so each loop had to bounce back and
    forth through the process for each record!! 
    We have the availability of Nintex but are unable to use the 'CallWebAccess' function as this would require our server ID and password (and that won't be happening anytime soon).
    I have created a column called 'Notify Date3' (And so on for the additional date notifications)which contains the following formula
    =TEXT([Remediation deadline]-92,"dd/mm/yyyy") which I use to create the date around 3 months before the first remediation date so I can create a notification.
    Any advise on the best way to process will be greatly received as i'm slowly pulling my hair out
    Thanks in Advance
    Nick

    Hi,
    According to your description, you might want to implement a functionality which can send notification in different date based on the value of a column.
    If you can use SharePoint Designer 2010 workflow, there are workflow actions like “Pause for Duration” and “Pause until Date” which can pause the workflow for a period. Plus
    with using some conditions in the logic of the workflow process, it will be able to send notification in different date.
    Workflow actions
    in SharePoint Designer 2010: A quick reference guide
    Here is a demo about the similar requirement provided by Laura for your reference:
    http://www.wonderlaura.com/Lists/Posts/Post.aspx?ID=64
    If you want to use Nintex workflow, it would be more appropriate to post to its forum to get quick and confirmed answers:
    http://connect.nintex.com/forums/default.aspx
    Best regards
    Patrick Liang
    TechNet Community Support

  • Problem socket.bind() with multiple modems and multiple IPs

    I've connected 2 or more modems in Windows control panel and made up windows dail ups. Then I dail up each modem and obtain the local DHCP IPs of each modem.
    My target is : to set up sockets using separate modems.
    the code is like: create a socket instance , and use Socket.bind()method to bind the socket to a specified modem's local IP , then do socket.connect().
    but the problem is : although there are several modem dail ups and at the same time I bind each socket to different IPs , the program always connect via the first modem dailed up.
    Does Socket.bind() method really bind the socket connection to the IP's or hardwares?

    I think you are trying to use a Socket where you want a ServerSocket to accept the incoming connection. Check this out (I have underlined what
    should interest you):
    public ServerSocket(int port, int queueLength) throws IOException, BindException
    This constructor creates a ServerSocket on the specified port with a queue length of your choosing. If the machine has multiple network interfaces or IP addresses, then it listens on this port on all those interfaces and IP addresses. The queueLength argument sets the length of the queue for incoming connection requests--that is, how many incoming connections can be stored at one time before the host starts refusing connections. Some operating systems have a maximum queue length, typically five. If you try to expand the queue past that maximum number, the maximum queue length is used instead. If you pass 0 for the port number, the system selects an available port.
    For example, to create a server socket on port 5,776 that would hold up to 100 incoming connection requests in the queue, you would write:
    try {
      ServerSocket httpd = new ServerSocket(5776, 100);
    catch (IOException e) {
      System.err.println(e);
    }The constructor throws an IOException (specifically, a BindException) if the socket cannot be created and bound to the requested port. An IOException when creating a ServerSocket almost always means one of two things. Either the specified port is already in use, or you do not have root privileges on Unix and you're trying to connect to a port from 1 to 1,023.
    So once you receive a connection, it looks like it is up to you parse any
    relevant info you want out of the Socket you get from ServerSocket.accept();
    -Cludge