E-business Upgrade Plan Template

Dear All,
We already upgrad 12.0.6/solaris sparc 64/10.2.0.3 to 12.1.1/soloris sparc 64/11.2.03 in TEST env, application team tested and green sigle to move production.
we have 4 days Holiday, so we are planning upgrade on production. as APPSDBA i m doing upgrade with my team OS admin/application consultant & some of the users.
i m planing to do RDBMS upgrade first, then application, as mentioned in the Note:752619.1, to move from 12.0.6 to 12.1.1 below are REQUIRED.
1.Upgrade OracleAS 10g Release 3 (10.1.3) to Patchset 4 (10.1.3.4) (Required)
2.Upgrade OracleAS 10g Release (10.1.2) for Forms and Reports to Patchset 3 (10.1.2.3) (Required)
3.Upgrade Oracle E-Business Suite Release 12 JDK to Java 6.0 latest update (Required)
can i split the task before doing maintenace pack. i mean
after did 1.Upgrade OracleAS 10g Release 3 (10.1.3) to Patchset 4 (10.1.3.4) (Required), i start the application & given to users, likewise i will schedule for 4 week ends??
please advice me.
please share any upgrade process template for E-business suite
Thanks

i m planing to do RDBMS upgrade first, then application, as mentioned in the Note:752619.1, to move from 12.0.6 to 12.1.1 below are REQUIRED.
1.Upgrade OracleAS 10g Release 3 (10.1.3) to Patchset 4 (10.1.3.4) (Required)
2.Upgrade OracleAS 10g Release (10.1.2) for Forms and Reports to Patchset 3 (10.1.2.3) (Required)
3.Upgrade Oracle E-Business Suite Release 12 JDK to Java 6.0 latest update (Required)
can i split the task before doing maintenace pack. i mean
after did 1.Upgrade OracleAS 10g Release 3 (10.1.3) to Patchset 4 (10.1.3.4) (Required), i start the application & given to users, likewise i will schedule for 4 week ends??Yes you can.
Thanks,
Hussein

Similar Messages

  • Interface Settings Error, Business Objects Planning, Templates

    Hello all,
    I am getting an error in interface settings whenever I have tried to run a template.
    I have searched these forums and wikis and been googling for days and have not found anything even remotely relevant.
    This company is using Business Objects Planning, version 11.10.1325.0
    Platform is Windows Server 2003 SP2. Excel version 11.0
    They have been using BOP for two years. They have been manually copying actuals data (i.e. historic data) into the template-derived workbooks for budget and forecast and them saving them for users. The consultants did not leave them with templates that loaded historic data from the SQL server, nor did the consultants even tell them about write-back (save-to-database) reports (which are what I am used to building).
    In the short term I have been asked to get their templates working properly.
    A week ago I logged a request with the consultants (SAP gold partners) but have yet to hear back.
    We have tried starting at the basics and building a very simple template that follows the examples given in the users guide.
    (i.e. the Planning Professional Edition Plan Administrators Guide, note that the consultants did not leave copies of the guides that matched the BOP version, so I downloaded the correct editions for this installation, but the basics are the same.)
    So I have a template that has account ("ACC" for this organisation, "ACCT" in the Guide) in cell A1.
    Row 1 then contains the Other Column to write back to in cell E1 (ESourcePY for this test), and Row 1 is even coloured pastel green.
    Row 2 is coloured pastel yellow just like in the Guide and contains "Control Row for Interface" in cell B2 and the Time Series to read from in cell E2 - SSANYB_TOT, which basically means NYB_TOT for this company.
    Rows 3 - 6 are coloured purple and cell B3 holds "Summary Print control Row". I have tried "SRCPrintControl" in cell H3 and I have tried without it. I have tried "Monthly Print Control Row" in B4 and I have tried without it (and SRCPrintControl in H4).
    And then I have a number of natural accounts in cells A21:A24, I have tried using just one ACC and I have tried them on different lines, but in the end I put them on the same line as the ones in the Guide start at.
    I have also tried with and without "HDR" in the cells in the H column.
    My Settings sheet has been exactly as the one in the Guide, and I have tried with only a Summary in the Printing section, deleting the Monthly stuff, I have also tried changing the Border Columns and Rows but I am not too sure that is relevant.
    The relevant sheet in the Interface Setting book is exactly as the one in the Guide but using the local Time Series and Target Sheet Name etc., although I have tried using the write-back target (ESourcePY) Other Column in the Target Column Name instead of SSANYB_TOT as shown in the Guide.
    There is one difference; this organisation is not using Standard Planning Methodologies (no client I have seen uses them) and so that cell (B11) is empty.
    But all I ever get, no matter how many variations or modification I try is :
    "Error in interface settings of Default Interface interface on control row or column in temp1 sheet. Do you want to continue?"
    Can anybody please shed some light on what is missing?
    Thanks in advance,
    Kai
    P.S. This seems to lose all format/structure when uploaded, but it is all in paragraphs with white space when I write/edit it.
    Edited by: Kai Richmond on Feb 22, 2010 6:00 AM

    NOT ANSWERED
    But a month and no answer means that obviously no-one on this planet, including the SAP help desk, knows the answer.
    Business Objects used to have a really good help desk based in Singapore. Yeah, their consultant partners in Australia were not very good, but the help desk was very helpful and proactive.
    Now that SAP has acquired the product the 'gold partners' are still useless but the SAP help desk is just a joke. The help 'portal' is just a door to a void, the responses are very tardy, and the majority of the points they raise have already been answered by me in previous communications to the same staffer. Obviously they don't read your replies.
    I have already advised one client away from purchasing this product and I cannot see how in good conscience I could ever recommend BOP (or SAP) to any client in the future. Cognos is good, but IBM has no mainframe finance package; so I think that Oracle and Hyperion Planning are probably going to be the way of the future now.
    Edited by: Kai Richmond on Mar 17, 2010 12:43 PM

  • Skype for Business upgrade plan

    Does anyone has any information about the upgrade path for "Skype for business" from Lync 2013 enterprise Servers ?
    Regards, Pushkal MishrA, This posting is provided “AS IS” with no warranties and confers no rights. I request you to test the solution in lab and post successful outcome you should try this on production.

    Hi Pushkal MishrA,
    Please follow this guide to perform the upgrade process.
    http://summit.office.com/Media/Default/Office%20365%20Summits/ITP29%20-%20Servicing%20the%20Existing%20Deployment%20and%20Upgrading%20to%20Skype%20for%20Business%20Server_v04.pptx
    Best regards,
    Eric
    Please remember to mark the replies as answers if they help, and unmark the answers if they provide no help. If you have feedback for TechNet Support, contact [email protected]

  • Business continuity plans

                     Business continuation is very important to achieve the goals of the organization in thelong run. If the organiztion cannot continue in the future, it cannot achieve its targets or goals and eventually, it will come to an end creating huge loss and diverting fromthe objectives with which it was first established.
    Business continuity plan template helps us with this problem. It gives us the ideas as to how we can continue our business to the long run. We can log in to https://bccatalyst.com/templates for more on this.

    Hey,
    it is depend on the WAS version (6.20, 6.40, 7.00 and etc),
    here is some information:
    https://www.sdn.sap.com/irj/sdn/go/portal/prtroot/docs/library/uuid/89cb626b-0901-0010-d2b7-f5dcff4e74c8
    and:
    https://service.sap.com/ha

  • Business Objects Planning Database Upgrade

    I have attempting to upgrade Business Objects Planning from version 11.2 to 11.6.  The upgrade appears to run successfully, however, when I attempt to start the Planning Application Services, the service fails to start up, stating the current DB version is less than the working version.  I have spoken to our consultant, who stated he knew nothing of any changes that must be made to the database.  The first portion of the error log is copied below.  I have tried an incremental step of upgrading from 11.2 to 11.5 and have received the same error.  What must I do to configure the database either before or after the upgrade? 
    Application is set up as single server.
    OS is windows server 2003
    Database is Oracle 10.2.0.4.
    Database user is SRCAdmin, and is an owner of the db.
    FATAL|04/08/2009 13:52|General|Server startup...
    INFO|04/08/2009 13:52|Sql|Current DB Version 11.2 is less than the working version 11.6. Requesting upgrade lock
    ERROR|04/08/2009 13:52|Sql|ORA-06550: line 1, column 77:
    PLS-00201: identifier 'DBMS_LOCK' must be declared
    ORA-06550: line 1, column 77:
    PL/SQL: Statement ignored
    ORA-06550: line 1, column 147:
    PLS-00201: identifier 'DBMS_LOCK' must be declared
    ORA-06550: line 1, column 137:
    PL/SQL: Statement ignored

    hi Santhosh,
    you may be able to use the query builder tool to do this.
    BusinessObjects Query builder - Basics
    if you need further info on using this particular tool let me know & i'll move your question to the bi platform space.
    you can also look into 3rd party tools such as rpt inspector which may be able to do this.
    -jamie

  • I am seeking a good Business Plan template.

    Finding good Business Plan templates is always difficult, most are geared to business activities, I need a good template for starting a "manufacturing" plant.  Funding would be a combo of private & government participation.

    Glad someone does Peggy.
    The notification system seems to be quite sporadic.
    I go to get links for FAQs and occassionally spot the odd irrelevant comment and spam, but really unless it is totally off the wall I leave them be. At least for a month or two, then clean them off just so it doesn't bury the valuable stuff.
    Been thinking about reconstructing the entire thing using WordPress so I can get better control over the layout and sort them imto more logical groups. I have trouble locating stuff I know is there and I pity the newcomer who doesn't even know it exists.
    Peter

  • Business plan template

    Trying to figure out where I might find templates for numbers.  Specifically for a business plan.

    JL,
    If you search the web for business plan templates you will probably find many written for Excel and Wrod that will work fine in the iWork apps. They seldom take much adjustment to be workable. The problem for users of the new version of Numbers, Numbers 3, is that the app is no longer suitable for composing a printed document. You might be better off looking for a word processor template than a spreadsheet template.
    Jerry

  • Business plan template for iPages

    Where can I find business plan template for iPages?

    Although I can't recommend it first hand, this pack may have what you are looking for: https://itunes.apple.com/us/app/business-templates-for-pages/id717953908?mt=8

  • Upgrading Business Objects Planning & Reporting 11.10.1325.0

    We need to upgrade our Business Objects Planning from our current version 11.10 to 11.5x due to the Microsoft Office Service pack 3. Does anybody have any documentation or information regarding things to look out for, upgrade procedures, etc.
    On another note, we currently running Planning 11.10 on a Sql server 2000 sp4 back-end. Does anybody know if it's ok to simply upgrade this to Sql Server 2005 with out any changes? Any documentation, notes, etc are greatly appreciated also. Thanks!

    Steven,
    This post needs to be given under the BO forums for more relevant answers. Please raise a message to
    [email protected]
    to have your thread moved.

  • How to migrate changed Business Scenarios from Template Project to Solution

    SAP Solution Manager - How to migrate changes in Business Scenarios from Template Project to Solution?
    Our Global ASAP strategy is based upon a Template Project, Implementation Project, Maintenance Project and Solution with Business Scenarios.
    Changes in the Template Project for existing and new Business Sceanarios, etc. are correctly executed. Up till now we have successfully implemented our Template Project and secondly extended our Business Scenarios from 4 to 14. Our 3rd upcoming change will be changes on Business Scenarios as well. These planned changes for the Business Scenarios need to be consistent, possibly without manual intervention.
    During a Proof of Concept (PoC) in our Sandbox (SXB) we have identified a possible serious problem when trying to publish these changes in Business Scenarios in the Template Project to the Solution. SAP Solution Manager (SSM) does not seem to support a scenario where Business Scenarios in the Solution can be refreshed or updated with changed Business Scenarios in the Template Project.
    We have identified 2 possibillities:
    1.     Manual project upgrade
    1.1.     Synchronize the changes for the Template Project normally;
    1.2.     Delete the changed Business Scenarios from step 1.1 in the Solution;
    1.3.     Add the changed Business Scenarios from step 1.1 into the Solution.
    For this scenario we foresee a big problem because all Content and Issues connected to the old Solution Business Scenarios loose their coupling with the Solution.
    For the Content this may not be a real problem because the Content is also available in the Template Project.
    However the Issues are loosely coupled to the Solution Scenarios and therefore need to be coupled manually to these processes.
    2.     Manual changes using Maintenance Project
    2.1.     Synchronize the changes for the Template Project normally;
    2.2.     Publish all changes from step 2.1 in the Template Project
    2.3.     Add all new Content from step 2.1 to the structure of the Maintenance Project;
    2.4.     Relocate Content and Issues when the Business Scenario has been relocated.
    Because SSM does not support this activity we need to delete this Business Scenario first and secondly re-create it again on the correct spot.
    Our question: How has SAP done this in other customer projects?
    We need to have a working solution by the end of March, 2009.
    Best regards,
    Peter Hendriksen

    Peter,
    Did you get an anwer to this question from SAP?
    Rgds,
    Eamonn.

  • BW Upgrade Plan  3.1C  To BI 7.0 (Procedure and Checklist)

    Hi Friends,
    Pls send the template for BW Upgrade Plan 3.1C  To BI 7.0 (Procedure and Checklist)/Document. I need the exact & accurate SAP Standard Template/document. I searched SAPHelp 
    /https://websmp110.sap-ag.de/instguides . could n't find any thing for this.Pls send it to 
    :[email protected]
    ***PS: Only accurate replies will get full points**
    Regards
    CSM Reddy

    Reddy,
    please chck out
    https://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/docs/library/uuid/2e8e5288-0b01-0010-2ea8-bcd4df5084a7
    a hwo to on BI7.0 upgrade .. also as suggested check out the BW upgrade roadmap on the support portal..
    Hope it helps..
    Arun
    Assign points if helpful

  • I bought years ago CS6 - Design Standard and an expensive MLP New Upgrade Plan in order to upgrade the software after. Can I upgrade to CC, or I simply lost my money?

    I bought a license to use Creative Suite 6 - Design Standart almost two years ago. In the same ocasion, I bought a MLP New Upgrade Plan, wich were very expensive, but gave me the wright to upgrade my CS6-Design Standart for new versions within two years. I thoght I made good business, buying an Upgrade Plan that allowed me to have further versions of my software for two years without adicional purchase. What happens is that I can't find a way to upgrade my CS6-Design Standard Suite to a CC Suite. Did I simply threw my money away purchasing the MLP New Upgrade Plan, wich never alowwed me to do any upgrade, or is there a way, fairly, to use my Upgrade Plan that is almost expiring to have access to Creative Cloud?

    You are on Windows 2000, you do not have a "Firefox" button, and should consider yourself to be fortunate in that you still have menus and don't have to do anything to get the menus back instead of the "Firefox" button. (The same applies to Windows XP users).
    Use the "File" menu to get to Import. You are not on Windows 7 or Vista, and don't have to put up with the nonsense added for Aero.
    If you want the "Firefox" button you can get it with View -> toolbars -> (uncheck) Menu Bar. The menu bar and the "Firefox" button were supposed to be mutually exclusive (which is impossible in some cases without being incompatible).
    Once you are using the "Firefox" button ...
    Use the "Alt" key to view the menu bar (temporarily) containing File, Edit, View, History, Bookmarks, Tools, and Help. On Windows 7 and Vista, the menu bar was hidden by default in Firefox 4 and above. These menu items are more or less available under the "Firefox" button which has the most used of the built-in Firefox menu items available in a different format.
    To get back to having menus again. "Firefox" button -> Options (second column) -> (check) Menu Bar
    You can make '''Firefox 7.0.1''' look like Firefox 3.6.*, see numbered '''items 1-10''' in the following topic [http://dmcritchie.mvps.org/firefox/firefox-problems.htm#fx4interface Fix Firefox 4.0 toolbar user interface, problems (Make Firefox 4.0 thru 8.0, look like 3.6)]. ''Whether or not you make changes, you should be aware of what has changed and what you have to do to use changed or missing features.''
    * http://dmcritchie.mvps.org/firefox/firefox-problems.htm#fx4interface

  • Need Sample Unit Test Plan templates for SD

    Hi Experts,
    I am in need of some SD unit test plan templates used in any of your implementations.
    Pls Help.

    Dear Preethi
    As already expressed, you are asking the confidential document which nobody would like to share.
    However, AS-IS will be prepared by Core team people and your duty is to go through the process in depth.
    May be the AS-IS from SD purview, I can list as an example as how it should be
    The excel sheet of AS-IS header tabs will have to contain the following header tabs
    -  Scenario like Exports, Domestic etc,
    -  Under this scenario, Groups like OE, Aftermarket, Stock Transfer etc.,
    -  Under this Groups, Process like Business Plan, Scheduling, Preshipment activities, Post shipment activities etc.,
    -  Finally this process has to be break down into a detailed list of activities.
    So you have to go through these process in detail.
    As for as testing is concerned, there is no need to check the customer master.
    All you have to do is to carry out all standard T.Codes like order creation, create delivery, PGI, Billing and Excise Invoice.  Again try to cancel all documents from billing to sale order and ensure that you are able to cancel those documents.  Check for the FI implication on the COGS and material cost.
    Also while testing, you can also check whether you are able to create one delivery against multiple sale orders and one invoice against multiple deliveries.  If not successful, analyse the reason for split, maintain the required datas in masters and retry the process.
    thanks
    G. Lakshmipathi

  • 11i Upgrade Plan

    We are upgrading our applications 10.7SC to 11i. Can anyone supply a upgrade project plan that we can use as a sample.

    Is there any such plan/template available which we can use to gain knowledge on R12 upgrade strategies and planning?I do not think such template exists in any of the links available for public access.
    You might google and see if any docs/links are available -- For example, this link http://www.claremont.co.uk/cmsfiles/claremont/docs/whitepapers/WP_PrototypeCRP.pdf
    Thanks,
    Hussein

  • Error while creating a Development plan template

    Hi Gurus,
    I am facing errors  while creating Development Plan Template.
    This is how it goes :
    When i click on Define Forms for Talent Assessment --> a wizard pops up & i select Development Plan :
    In first step, I am giving Title,Integration with SAP Learning Solution (check) & a rating scale.
    Now after clicking next, I am adding 2 development areas :
    1) Training
    2) Mentoring,
    now as soon as I'm clicking on End Configuration, It displays 2 errors & 1 warning message :
    error1 : Element Appraisal Template 'XXXXX' contains errors.Cannot change status.
    error2 : Value type 000000XXX of value class Q does not exists
    Warning 1 : You have maintained a description that is not displayed.
    In PHAP_CATALOG, when I'm trying to manually release the Criterion Group (VB) or Appraisal template (VA), it does not allow me to do it.
    Kindly let me know how to proceed further.
    Regards
    bharti

    Hi,
    Even though it gives the error,the new RTF template is uploaded and it is reflected when I query the template again.
    But when I run the Concurent program and see the output,the output still shows me the old template.
    Regards
    Jujaar