Hi Experts,
I need to configure a Extended-Classic scenarion in SRM 5.0. Below are the activitis i have done so far.
Act.. Completed
1.RFC connection
2.Vendor/ master data replication
3.Define Backend System for Product Category :
Category ID  :: Source Sys  ::TargetSys
001::R/3:SRM
4.Define Objects in Backend System
But when i am creating the SC , the PO is generated. But I am not able to create the CNF in R/3.
Plz assist.
Thnaks,
SK

In RZ20 the below error is being displayed:
Local errors  : "Comm.. error checking account assignmnt for PO 3000444 in system R/3".
And a small query, to do a CNF in backend, is it necessary that PO should be made of Backend PO?
In my case the PO is assigned to Local Purch. Org.
Thanks for helping me - Muthu.
Rgrds,
SK

Similar Messages

  • Can we use both Stand alone and Extended classic in one SRM system

    Hi All,
    Our client is now using Stand alone SRM system with back-end R/3 FI-CO system. Now they want to go Extended classic scenario for few product categories.
             Would it be possible to use both in one SRM system? If possible could you please provide what are the sequential steps to do this?
                 Thanks in advance.
    Regards,
    Ram

    Hi Ramesh,
    How did you end up solving your problem, as i have the same scenario.  Did you use this BADI (
    SRM Server->Business Add-Ins->Control Extended Classic Scenario->Activate Extended Classic Scenario)?  Based on my reading, it seems this BADI is relevant to switch between extended classic and classic scenarios. 
    From what i understand, we can control the standalone scenario via the define backend system configuration (SAP SRM -> SRM Server -> Technical Basic Settings -> Define Backend System for Product Category).  In my scenario, I have one set of product categories, so i will likely need to implement this BADI (BBP_DETERMINE_LOGSYS, method:   DETERMINE_LOGSYS - SAP SRM -> SRM Server -> Business Add-Ins ->Shopping Carts and Requirement Items -> Determine Backend System / Company Code) in order to determine the correct backend system based on company/plant for example. 
    Did you then leave the extended classic scenario activated (IMG --> Supplier Relationship Management -> SRM Server-> Cross-Application Basic Settings->
    Activate Extended Classic Scenario)? 
    Or how did you achieve both standalone and extended classic using one SRM server?
    cheers,
    AD

  • SUS-MM integration in Classic Scenario for SRM

    Hello All,
    We are using SAP SRM in classic Scenario.
    We also plan to integrate SUS with MM .
    Looks like in the Classic Scenario with SRM , only the Direct material procurement is possible
    using MM- SUS.
    How would the SUS-MM integration work for Indirect PO's.
    Our Process is as follows:
    1) Shopping cart created in SRM for Indirect material & approved ( with cost assignment)
    2) Classic PO created in backend & sent to SUS
    After this step is it possible that the Vendor create the GR in SUS and it is sent to ECC for Approva through PI l??
    Thanks
    Kedar

    KedarG wrote:
    > Is it possible in Classic Scenario, to send the SUS confirmation to SRM instead and from there to ECC
    NO. dont think of a situation like that. if it is classic scenario except SC every thing will in ECC. how do you think confirmation creation can be possible in SRM when PO is not present in SRM!!
    > Can you provide some details on ECC workflows. I didn't find any thing on this. Does ECC even support workflows as SRM?
    >
    SRM is a kiddo infront of ECC, so workflows definitely are present in ECC(not BRFs but event driven wfs).
    any ways, your solution would be a custom solution, implement MB_DOCUMENT_BADI, to trigger a custom WF from custom event. this can be used for notification and stuff. but it wont stop the execution, so, dig on it how to stop the GR post till the workflow is not over.
    and invoice anyways has workflows which you can use

  • PO text transfer to Back-end in case of Extended Classic Scenario in SRM 4.

    Dear experts,
    My system is in SRM 4.0 in Extended Classic Scenario. We use in the PO internal note text and vendor But thses texts are not transfered to Back-end.
    Is it normal?
    Do I need to customize something?
    Can it be achieved by BADi? How then?
    OR is it only possible from SRM 5.0?
    Thanks in advance
    RD

    Yes you can do this. Implement BADI BBP_CREATE_BE_PO_NEW, Refer parameter IS_SC_DOCUMENT>LONGTEXT,  and CS_PO_DOCUMENT>IT_PO_ITEM_TEXT. Map the exact text-id of the R/3.
    Note: if this BADI is not present, use BBP_CREATE_PO_BACK
    Regards, IA

  • Classic Scenario in SRM 7.0

    Hi,
    I have a doubt. Please correct me if I am wrong:
    -  As per my knowledge, confirmation and invoice can be created either in SRM or ECC in SRM 5.0. However in the SRM 7.0
       confirmation and invoice can not be created in SRM 7.0. It has to be create ECC.
    - In plant drive procurement both confirmation and invoic has to create in ECC. It should not be create in SRM 7.0.
    Thanks in advance.
    BR,
    Jennifer

    Hi Jeniffer,
    In SRM 7.0 also, you can continue to create confirmation and invoice  in classic scenario against your shopping cart.
    Plan driven procurement is not supported for direct materials in classic scenario. You have to use extended classic scenario i.e. in such cases PO, follow-up confirmation and invoicing can be done SRM as well.
    Thanks and regards,
    Ranjan

  • BBPSC18 - Request for external staff - Classic Scenario in SRM 5.0 possible

    Hello Community,
    one of my customers wants to use "Reqest for External Staff". As far as I remember, in SRM 5.0 it is only possible in "Standalone Scenario".
    Is this assumption correct? So not possible in Classic Scenario?
    How about "Extended Classic"? Probably not possible either, right?
    Thanks for any help or input!
    Cheers, Julian

    Hi Rahul,
    thanks for your answer!
    Actually I am only looking into the part "Request for External Staff" - "Acceppt Bid" - "Create PO (Classic in ERP)".
    I have seen that this part works in SRM 7.01.
    But currently we are not planning to upgrade. We are still on 5.0.
    I tested the abovementioned process in our DEV-System. I behaves fine, no error messages. But when I want to create the PO out of the "Check Status" (yes, in SRM 5.0 this was possible), the system pretends to create a PO but it never gets created. So I just wonder if I missed some customizing, or if this also only works in Standalone or if there maybe is a smart technical workaround (some custom coding etc...).
    Cheers, Julian

  • Extended classic scenario in SRM 7.1

    Hi colleagues,
    we want top use SRM 7.1 with extended classic scenario and we want to create POs in SRM and reflect them in ERP backend. The question is it possible somehow to change those POs aftewards (e.q. add confirmations, transportation costs, etc...) in ERP? Or is there any way to trasnfer POs in hold status from SRM to ERP and then change them in ERP?
    Thanks and regards, Anton

    Hi Anton,
    PO is created a in SRM as local and a copy( copy does not contain the entire PO info, only the useful for the backend) is being sent to R3.
    DO NOT try to search a workaround for modification in the backend..sooner or later you will be incurring in incosisnten data and misalignmentes.
    SRM is the PO golden source.
    Thanks and Regards,
    Abraham

  • Classic scenario using SRM SOCO

    Dear Experts,
    We use SRM7.0.
    We want to use classic scenario u2013 creating backend PO and not SRM PO.
    Can we use the SRM SOCO if we want to create backend PO ?
    To clarify myself, can we implement this procurement process:
    1. SRM SC
    2. The SC will go to the SRM SOCO u2013 Sourcing cockpit
    3. The purchaser will create backend PO from the SC items on the SOCO
    Or in case we want backend PO, we must use ME57 on ECC system ?
    Thanks and regards,
    Lori

    Hi Lori
    It is possible to create a Purchase order in the backend from the  SRM cockpit ( but it should not be order as Direct) by the Purchaser in the classic scenario.
    Are you finding any difficulties ?
    shopping cart create and ITS  venture to cockpit  upon sourcing configuration
    add vendor  and price in the shopping cart  item or propose source of supply
    and click PO creation and PO number will be generated from SRM system and PO will be avaiulable in ECC system .
    BBP_CREATE_BE_PO_NEW - Purchase Order in Backend System
    Using BusinessAdd-In BBP_CREATE_BE_PO_NEW you can change all the data thatis transferred to the backend system for generation of a purchase order. This includes, for example, the item data, the account assignment data, and texts.
    All the shopping cart data is available as input parameters.
    Ricardo / Lisa - please confirm the same when you read this thread and appreciate your comments here

  • Offline approval setup for SRM 7

    Experts,
    I have feq uestions on OFFLINE APPROVAL set up in SRM 7.
    1. Do I need to scehdule the report /SAPSRM/OFFLINEAPPROVALGET for the inbound emails to be prcoessed and status for shopping carts/PO correctly updated?
    2.Do the backgorund jobs (for reports /SAPSRM/OFFLINEAPPROVALGET and /SAPSRM/OFFLINEAPPROVALSEND need to be schdueld with WF-BATCH user only??
    3. Also the user used to schedule the jobs should it be a DIALOG user?
    4. in S050,should i maintain the email address for the user which is used to schedule the backgorund jobs?
    5. In SICF,node configurationfor SMTP need to be maintained ?
    Any inputs will be highly appreciated.
    Thanks.

    HI,
    1. it depends on your configuration, if you will use inbound processing or not. If you use inbound (at SO50 the class is set) then you should not schedule the /SAPSRM/OFFLINEAPPROVALGET as a job.
    2. it depends on  the customer. I have seen with the wf-batch and with other names but with the same rights and config of WF-batch.
    3. you can use the swu3 to create the wf-batch user. I have set as type system.
    4. yes you need the emaill of the user who is the processor
    5. this is a basis configuration, I am not sure. ( you will need to setup the sapconnet)
    For more information about offiline approval, please check the following link:
    http://wiki.sdn.sap.com/wiki/display/SRM/Offlineapproval-generalconfiguration
    Thanks,
    Melina

  • Classic scenerio In SRM

    Hi All, In classic scenerio, I created shopping cart and I got PO in R/3 backend system. Now I want to confirm these goods in SRM server, but I am unable to get these goods in confirmation. Please explain how to proceed and what are the config steps regarding this.
    Regards
    SATYA

    hai,
    step1: create confirmation number ranges in srm server
    step2: assign those number ranges to transaction type
    step 3: activate workflow ,eventhough there is no workflow activate confirmation with out approval in oocu transaction.
        these are the prerequisites to enter the confirmation..

  • Extended classic scenario to Classic scenarioc in SRM.??

    someone pls tell me how to change from Extended classic scenario to Classic scenarion while creating in shopping cart...?
    I am using BADI "BBP_EXTLOCALPO_BADI" change to classic scenarion from extending classic..but i got confused about source code..So i request any one can help me for suitable source code..

    Hi
    Do you mean to say that you have set up Extended Classic Scenario but you want to change it to Classic Scenario?... If this is the case, remove the activation in COnfiguration for Extended classic scenario and deactivate BADIs you ve implemented for Extended Classic
    OR
    Do you want to change it to Classic only for the Document user is creating.--> Read the indicator or data from SC and decide whether the document has to be in Classic or Extended classic SCenario.... The BADI will either have Extended classic = X or NOT.... so there is no parameter for classic Scen... Depending on your requirements, implement the ext. classic badi to SET it or NOT set it...
    Regards
    Virender SIngh

  • Classic Setup - big probs

    Hi - my first time using Discussions... in need of some advice
    Was using 9.2.2 with 10.1.4, BUT big crash has forced me to restore from original disks (9.1 and 10.0.4 !!)
    - after many hours of downloading updates over internet, have now climbed back to 9.2.2, but can't get any updates for 10.0.4 - apparently jump to 10.1 only possible with CD, which I don't have.
    I'm saving up for a yummy new 15" iBook, but need to get this oldie into saleable state - do I have to stick with Classic or would it be possible / worthwhile if I buy and load newer software in order to sell ?
    thanks
    iMac   Mac OS X (10.0.x)  

    The choice is up to you, but you cannot upgrade beyond 10.0.x without purchasing the upgrade system.
    A supposedly good place to buy proper OS X installation software is www.applerescue.com.

  • New SAP R/3 Client setup with SRM

    Hi Guys,
    Can anyone guide me if I am deleting my SAP R/3 backend client and setting up a new client then do I need to delete all the current material groups and do an Initial upload by setting up the middleware settings in new R/3 client.
    Also is it necessary to delete the settings of Old middleware settings?
    Please clarify me.
    Thanks !!!!
    Regards,
    Srujank

    Hi Nagarjun,
    If you look at the exporting and importing paramters of your Method EXECUTE_SYNC...
    You would find the abap equivalent of your Message Type.  Hence you know all the fields.
    No it depends on the business Logic, or ratheer what the RFC is suppose to be requested for is filled in an an Input paramter to the Method. 
    This can be an IDOC To, in that case your MT should be similar.  Fill in the transmiaaion IDOC values.
    OR you can Actually harcode the values, make your Itab, and send it across ( as this is just for test purposes )
    Hope this helps.
    Regards
    Abhishek

  • SRM standalone and extended classic

    Hi Experts,
    Configuration: ECC 6.0  (with Ehp4 installed - (not activated)
                           SRM 7.0
    Just want to seek confirmation of my understanding re: SRM implementation scenarios. Is it possible to have a extended classic and standalone setup using the same SRM server with same client? Both will have the same product categories. These will be for two separate entities/companies.
    Thanks in advance.
    Regards.

    Hi Mike,
    How did you end up solving your problem, as i have the same scenario.  Did you use this BADI (
    SRM Server->Business Add-Ins->Control Extended Classic Scenario->Activate Extended Classic Scenario)?  Based on my reading, it seems this BADI is relevant to switch between extended classic and classic scenarios. 
    From what i understand, we can control the standalone scenario via the define backend system configuration (SAP SRM -> SRM Server -> Technical Basic Settings -> Define Backend System for Product Category).  In your scenario, you have one set of product categories, just like mine, so i assume you had to implement this BADI (BBP_DETERMINE_LOGSYS, method:   DETERMINE_LOGSYS - SAP SRM -> SRM Server -> Business Add-Ins ->Shopping Carts and Requirement Items -> Determine Backend System / Company Code) in order to determine the correct backend system based on company/plant for example. 
    Did you then leave the extended classic scenario activated *
    MG --> Supplier Relationship Management -> SRM Server-> Cross-Application Basic Settings->
    Activate Extended Classic Scenario)? 
    Or how did you achieve both standalone and extended classic using one SRM server?
    cheers,
    AD

  • SRM-SUS - Extended Classic - Purchase Order Response

    Hi folks,
    We are using SRM-SUS in an Extended Classic scenario in SRM 5.0.  When the Vendor creates a Purchase Order Response (POR) we want the Requisitioner of the Shopping Cart (not the Purchaser from the Purchase Order) to process the POR in EBP. 
    We will add the transaction Process Purchase Reponse to the Requisitioner role.  We want to ensure that the Requisitioner can only see PORs related to Purchase Orders created from the Requisitioner's individual Shopping Carts.
    Has anybody any suggestions and/or see obstacles in our way?
    Cheers,
    Pat

    Hi Pat,
    This is certainly not standard. I see the following challenges:
    a. From the system perspective, your Shoppers will need to be assigned to purchasing group(s) in Org Structure to see the related PORs. That's very unusual, and consequences can be unpredictable.
    b. From the internal controls / business process / security perspective, you may be creating some SOD (segregation of duties) issues.
    IMHO, your business requirement needs to be re-visited. My two cents...
    Cheers,
    Serguei

Maybe you are looking for

  • Testing a Web Service

    Hi Experts, I'm new to publishing Web Services. To create my first WS, I followed help step by step from http://help.sap.com/saphelp_nw2004s/helpdata/en/68/0464407b9b990ae10000000a155106/frameset.htm. After I created a service definition, when I trie

  • Adobe Premier Pro CC has stopped working win 7 64 bit

    I have a Quadro KM3000 Nvidia, in a Dell M6700.  Pre Pro has been working fine until I downloaded the latest version.  I use SSD's.   I have read other threads and already tried the following: Downloaded the latest drivers (26 Sep 2014) Tried to upda

  • Soft Edge looking not so soft.

    I am using PS CS3 on Mac OSX 10.5.8. I recently had my hardware replaced with a 2.66GHz Quad Intel. My brush tool is rendering a hard edge when I have done everything to make it soft. I am creating shadows and using a brush that has it's edge set to

  • FM8 and DITA: attribute "rotate" in table entries

    Hi there, I tried to add the attribute "rotate" for table entries. The Developer's guide and the additional reference guide were a good help here. Everything you need for your dtd and read/write rules is listed there. <!ATTLIST entry rotate %yesorno;

  • Staging, dvd.label

    hi, trying to install "Oracle e-business sute rel 12.1.1. media pack for linux x86" i am using software download(instead of dvd), have completed all the downloads. encounter error when creating staging. i deposite them(all the *.zip) under a staging