Formula Price change at P.O

Hello Experts
I have query, We are using Formula price where we are uploading quatations daily and based on that price will be caliculated.
Hence my problem is in P.O formula price was arrived , However user found  that price was wrong exm: $100 is there in P.O , bu it must be $105
Is there any way to correct it in P.O?
Thanks and Regards
srinivas.

Hello Srinivas,
Very less details are available to give you an exact solutions. But you may follow below approach -
- Open the PO in display mode and press the Term Analysis button. Are there more than one terms? If yes, which term got picked up. Is the term that got picked up the right one?
- Term analysis will show you what quotation values have got picked up for which date. How the formula value was arrived on.
- Check the F&A formula in Formula Repository (SAP Menu ->Logistics ->Sales and Distribution ->Master Data ->Conditions ->F&A pricing ->Formula Repository) and also check the "Final and Provisional Calculation Rules"
Hope this helps.
with kind regards,
Gaurang Pandya

Similar Messages

  • Dates of Price Changes per Article

    Hi,
    I have a table with the following columns:
    Date
    ArticleID
    OriginalPrice
    NowPrice
    PriceReduction
    I'd like to create calculated columns as follows:
    the date of last/first price reduction per ArticleID
    the date of lowest/highest NowPrice per ArticleID
    the number of price changes (i.e. different price reductions) per ArticleID
    I could create calculated columns to calculate lowest/highest NowPrice per ArticleID. But I don't know how to solve the questions above.
    I enclose a dropbox link to an example Excel 2013 file:
    PP_PriceChange.xlsx
    Thank you for any advice!
    Chiemo

    Hello Greg2178,
    thank you for your advice and for providing the updated workbook. The allexcept() function is indeed very interesting and helpful.
    I am still a newbie with powerpivot and learn day by day and challenge by challenge.
    I checked the measures and some are unfortunately not working as expected.
    In order to make it more obvious what I am looking for I repeat the core table columns of table1:
    Date      ArticleID   OriginalPrice   NowPrice  PriceReduction
    11/1      1001         100              
    50              -50%
    11/26    1001         100               50              -50%
    11/27    1001         100               50              -50%
    11/29    1001         100               50              -50%
    11/1      1002          50                40             
    -20%
    11/26    1002          50                30             
    -40%
    11/27    1002          50                20             
    -60%
    11/29    1002          50                25             
    -50%
    11/1      1003          20               
    30              +50%
    11/26    1003          20                20                 
    0%
    11/27    1003          20                10              
    -50%
    11/29    1003          20                20                 
    0%
    Let me concentrate on the biggest challenges for me:
    Number of Price Changes (compared to original or previous price) per ArticleID:
    the correct answer for article 1001 would be = 1, for 1002 = 4, for 1003 = 4
    formula provided in your workbook gives 4 price changes for any article
    I would think to solve this by 3 different steps, i.e. calculated columns:
    Step1: Calculate the previous price reduction. Unfortunately the following formula does not work (I think because of the Max() function; see column "FormerPriceReduction" in  updated model):
    =CALCULATE(MAX(Table1[PriceReduction]);FILTER(Table1; EARLIER(Table1[ArticleID])=Table1[ArticleID] && EARLIER(Table1[Date])>Table1[Date]))
    Step2: Check if current price reduction differs from previous price reduction; if yes = 1, if no = 0; formula:
    =IF([PriceReduction]-[FormerPriceReduction]<>0;1;0)
    Step3: Sum of all changes under Step2 = number of price changes. Formula:
    =CALCULATE(SUM([PriceChange=1]);FILTER(Table1;Table1[ArticleID]=EARLIER(Table1[ArticleID])))
    Please see updated excel workbook : https://www.dropbox.com/s/g075xhhbo7jyttw/PP_PriceChangeUpdate.xlsx?dl=0
    Date of Last Price Reduction (i.e. date of last price change) per ArticleID:
    The correct answer would be for article 1001 = 11/01, for 1002 = 11/29, for 1003 = 11/29
    The formula provided delivers for 1001 = 11/29, for 1002 = 11/29 and for 1003 = 11/27
    I would think that the use of the correct formula from Step1 above could be a starting point for getting the correct answer
    (First) Date of Lowest Price:
    The correct answer would be for article 1001 = 11/01, for 1002 = 11/27, for 1003 = 11/27
    I think the formula provided gets the wrong results because it relates to the column „MinNowPrice“ which lists for each date the all time lowest price
    Do you have any ideas to solve this problem?
    Sorry that I cannot contribute much to the solution. I hope you can give me some more hints.
    Thank you very much
    Chiemo

  • Purchase order price change report

    Hello
    How to retieve the purchase order price change report ? do we have any standard report for it or any table which gives these data?
    kindl

    HI
    Have you activate version management at your end for PO,i think this will help you to track changes of PO for qty,price etc.
    [http://wiki.sdn.sap.com/wiki/display/ERPLO/Version+Management]
    Regards
    Kailas Ugale

  • Price change summary report & approach of price change on Sales Orders

    Hi,
    I have made the setups for updating the price on Sales Order via profile options (i update the list price field on SO line the SO line price gets updated). The Customer have manual price overide in their existing system in place so they want same in oracle system as well. Their price change doesn't have any serious logic,,it is quite erratic based on market condition on that day.
    (1) How can I get the report fro the changed price wrt price on price list for all the items on Sales Orders (during a period). It seems, Audit trial functionality for changing list price is not available.
    (2) For the system whether required price change as above is better approach or maintaining new price list all the time is preferable option. In case of new price list, do we have any standard report which fetches itemwise price change details on Sales Orders for a period.
    Thanks.
    With Best Regards,
    Nirabh Nayan

    Nirabh,
    Did you say you update the List Price itself in the Order Lines? In my opinion you should never update List Price. Set the profile OM: Discounting Privilege to 'Unlimited' to allow update of Selling Price, but switch off 'OM: List Price Override Privilege' for the responsibilities so that List Price field is not Editable. So that List Price always reflect the price with which Order Line was created (From the price List). Now create a custom report wherever Unit Selling Price does not match Unit List Price.
    If you really want to go a little further then create a modifier with Application method 'New Price' that should kick in everytime the Unit Selling Price is updated. Let me know if that helped.
    Dipanjan
    Edited by: Dipanjan Maitra on May 25, 2012 2:25 PM

  • Price Change in iTunesconnect doesn't show up in the library. why?

    Hello,
    We are to have a app price discount event in a limited time. (Like 5 days)
    Our current app's price is 2.99 USD, tier3. Target price is 1.99.
    There was no problem changing price in itunesconnect. ( I already asked iTunes about this problem. it says "Bud inside your DPS app. other then that, that cannot happen")
    But it never showed up in our library or store. (I've waited for over 3 days and see if it changes. But still no change in our app library. So, waiting for more isn't a correct answer. )
    What I need to do was delete the whole app and reinstall the app. Then, the price change showed up.
    Why? I can't make our subsribers and customers erase our apps from their ipads and reinstall. 
    [ Conditions ]
    - We have done our IAP service for a few years without any problem
    - iTunes contract&payment information was all correct.
    - We build our app with Adobe DPS.
    - and yes. Or fourse, I have our local sales company (in S.Korea) to help us. But so slow that I won't be able to open our price discount event on schedule.
    Any possible solution? Please help.

    Finder>Preferences>General: make sure that External disks is checked

  • How to register price change

    We bought product from vendor.
    We created A/P Invoice;
    After checking, we found that the goods is not the same quality as promised.
    We  negotiated with supplier and they agreed to reduce the price.
    How I need to process in B1?
    I found that Credit Memo is used when we need to return goods (It subtracts from the inventory). I do not want to return, just only the price change. How to do?
    Please advice.
    Thank you.

    You should use A/P Correction Invoice

  • Moving average price changed drastically

    Hi Experts,
    i having one problem,
    i having material of ' A '  1392.5 Kg having moving average price of 6.52 $ per kg (as of  02.03.2009 ),
    i issued goods to order on 17.03.2009 with movement type 261 of 233.60 Kg for 646.74 $
    here new moving average which systems shows for material 'A' is 2.77
    please explain why system shows new moving aveage price as 2.77, also why is not considering old values to calculate MAP(stock already present )
    Also please explain what could be the possible reason for this error.
    Thanks & Regards
    Prashanth.

    follow this discussion, I think it has all you need to get your problem solved
    moving average price changed drastically

  • Price changes in Scheduling Agreement

    Hi,
    What is the best way to handle price changes in a Scheduling Agreement? From what I saw, the validity periods of the prices maintained in a scheduling Agreement is based on the GR date. Is there any way we can change this? The requirement is to make the validity price work on the delivery schedule date.
    Right now, whenever a price change happens, we have to add a new line in the scheduling agreement. This doesn't seem right. Please advise.
    Thanks
    Ranjeet

    Hi,
    Your date for pricing is controlled by Pricing date category u maintain in Vendor master >Purchasing view
    If you select delivery date as your pricing and if there are many delivery dates the first delivery date is taken as
    the reference for pricing
    But if there is no much price variation between delivery schedule date and Goods receipt you can keep that as
    goods receipt date
    Check out whatever suitable
    BR
    Diwakar

  • Unable to prevent Price change for Outline Agreement

    Dear Experts,
    Once Outline Agreement is generated in SAP, I do not want to allow users to change the price.
    I have tried with " Field Selection at Document level" using ME32-Change outline agreement field selection.
    I select "Quantity and Price" and select check box Display for  "Price and Price Unit",Price Date", "Condition Group".
    This will not allow price change at item details level (field grayed out) but user can still select Item condition (for Example PB00) and change the price there.
    Is there any solution for this ?
    Ideally I want to do this for a particular Document type of Outline Agreement only.
    Thanks and Best Regards,
    Raju

    Hi Ramki,
    Thnka s for you reply.
    This is not the desired solution. I can not ask Client to change to create different uses for create and change .
    In the buinsess process , mostly create an change users are same for outline agreements.
    I do not wna to restrict by User Authorization either as this is also not a 100% solution.
    Still  looking at configuration level only to restrict changes in Pricing for outline agreements.
    Regards,
    Mitesh Desai

  • How to set default value for Price Change Indicator in Purchase order

    Hi,
    While creating the service purchase order with item category "D" the price change indicator in the services tab of the purchase order is getting checked by default. I want to uncheck this by default.Where can we set the default property for this.
    Thanks in Advance!
    Surya

    My plsql parameter is p_arr which is of "TYPE vc2_255_arr IS TABLE OF VARCHAR2(255) INDEX BY BINARY_INTEGER"You need to declare it in a package specification and initialize in the package body:
    SQL> create or replace package pmp_lib
    as
       type vc2_255_arr is table of varchar2 (255)
                              index by binary_integer;
       vc2_255_arr_default   vc2_255_arr;
    end pmp_lib;
    Package created.
    SQL> create or replace package body pmp_lib
    as
    begin
       vc2_255_arr_default (1) := 'abc';
       vc2_255_arr_default (2) := 'def';
    end pmp_lib;
    Package body created.
    SQL> declare
       arr   pmp_lib.vc2_255_arr := pmp_lib.vc2_255_arr_default;
    begin
       for i in 1 .. arr.count
       loop
          dbms_output.put_line (arr (i));
       end loop;
    end;
    abc
    def
    PL/SQL procedure successfully completed.so in your case it would probably be sth like (assuming pmp_lib is a package):
    <%@ plsql parameter="p_arr" type="PMP_LIB.VC2_255_ARR" default = "PMP_LIB.vc2_255_arr_default" %>

  • Price Change for Revenue Recognition

    Dear experts,
    I am using Revenue Recognition of type B with Revenue Recognition before invoicing.
    I have an issue/question about the way price changes are treated in the functionality.
    The below example is used to describe the issue for your understanding:
    1.Pricing master data: $100/EA
    2.Price of item in sales order: $100/EA
    3.Qty in sales order: 10 EA
    4.Delivery & Goods issue: 10 EA
    5.Revenue Recognised (VF44) for: $1000
    Accounting Entry:
    DR Unbilled Accounts Receivable $1000
    CR Revenue $1000
    6.Change in pricing master data: $120/EA
    7.Partial Invoice for: 2 EA @ $120/EA
    Accounting Entry:
    DR Customer $240
    CR Unbilled Accounts Receivable $240
    8.Partial Invoice for balance qty: 8 EA @ $120/EA
    Accounting Entry:
    DR Customer $960
    CR Unbilled Accounts Receivable $760
    CR Deferred revenue $200
    9.Subsequent Revenue Recognition (VF44)
    Accounting Entry:
    DR Deferred revenue $200
    CR Revenue $200
    As you can see in the example above, the amount of the price difference is not credited to sales in step 7. From what I have seen so far the additional amount due to price difference gets credited to sales only after the total invoice value for the item exceeds the revenue recognized.
    Is there any option to set the system so that the price difference is taken into account for revenue recognition during each invoicing (even
    when the invoicing is partial) ?
    Thanks in advance for your help.

    The price difference will not go to Sales in Step 7.  The reason being Revenue Recognition works on the item rather than the amount.  Since you have run F-44, the system finds the same in Unbilled Receivables and posts to that account.
    For updating the price changes, you have to run VF46 to cancel the original RR entries.  In this case, it will just clear of the RR lines if realization has not happened and post a reversal if realization has happened.  This txn will also create a new RR line for VF44 which you can process.
    Refer Note 820417 Implementation guide for RR.  Download the attachments and look into Part2 doc page 13.  This explains how to deal with price changes in sales document.
    Hope this helps.
    Ravi.

  • Automatic Price Change at the time of Confirmation of PP order

    Dear Sir,
    When Production Order is being confirmed (T Code COR6), the
    price of the BOM material (Finished Goods with standatd price)is getting
    changed. PR document type FI document is created and UMB key
    is getting the hit with a very minimum amount. (0.01 Indian Rupees) . This is not happening regularly. But suddenly in one confirmation it is happening. The process order are created in
    the system for 1 month say Start Date 01.01.2009 End Date
    31.01.2009
    This is happeing when confirmation is made in first day of next month
    for previous month i.e. for process order of January 2009 (Start
    Date 01.01.2009 End Date 31.01.2009 ) confirmation is made on the
    01.02.2009. Document date is 01.02.2009, posting date is
    31.01.2009.
    The PR (Price Change) docuement is getting generated on 01.02.2009 with posting date on 01.02.2009.
    At the mont end there is no manual Price Change thru MR21 transaction.
    Regards,
    Partha Pratim Bhar

    Hi,
    You need to check that material Standard Cost estimation has run or not for the next period. Normally Standard cost run can be run every period or once in 3 periods or once in a year. Based on this the standard cost estimate will update the material prices in the costing 2 view if any changes in the existing price. May be his could be the reason you may face the problem.
    Regards,
    V. Suresh

  • Price change in material master

    Hi,
    When does the moving average price change, if the PO price or the invoice price is different from the one in material master. Is it after the creation of PO, GR or invoice?
    Thanks and regards
    Aparna

    Hi,
    Moving Average price = Total Value
                                       Total Stock
    Moving average price updates once you make GR and IV
    If you are making GR & IV for new po , then new moving average price of that material will be :
    Total stock = stock already present in plant + GR made stock of that new po
    Total Value = Total Value of the material in plant + Invoice amount for that new po
    Thanks & Regards
    Prashanth.venkategowda

  • Price Change for Consignment

    Hi guys,
    I have a situation where by there is a price change during a consignment process.
    *_17/11/2010-Consingment Fill Up_                                                                
    Material A-100 Unit                                        
    Price $15                                                  
    *_20/11/2010-Consignment Fill Up_
    Material A-100 Unit
    Price $20
    How do I configure the system that, when I do a consignment Issue for 150 Unit on the 25/11/2010, I should invoice as:
    Price as on the 17/11/2010 is 100*$15 = $1500
    Price as on the 20/11/2010 for the remaing 50 units is 50*$20 = $1000
    So total to be invoice in the consignment issue is $2500
    Is this possible?
    Edited by: Saravanand Naiker on Nov 16, 2010 10:09 PM

    hi,
    i understood your question:
    as per standard functionality provided by SAP this might not be possible by taking one single material:
    1. if you are using batch management implement LIFO strategy for your requriment.
    2. other wise this goes to development part.
    take pricing date into consideration VBKD-PRSDT & go back and check if any materials exists with previous pricing date if exists.
    system has to inform you to take that materials first.
    3. in simple terms create two materials for the same and process.
    regards,
    balajia

  • Goods Issue after STO warning "Price change of  % in month / for mater"

    Dear all,
    This is my process for Inter-co plant stock transfer:
    1. Create STO via ME21N
    2. Raise Goods Issue from source plant via MIGO_GI
    3. I get this warning message "Price change of  % in month / for mater", details as below:
    Price change of  % in month / for material
    Message no. M7306
    Due to action taken the quantity and value of the material  are changed. This leads to calculation of a new moving average price: The new price deviates from the old one by .
    Procedure
    Before you carry out the posting, you should determine the reason for this difference.
    You could check the material line items to find out which postings have led to the current moving average price. If the action taken refers to a purchase order, you could contact Purchasing to find out whether a mistake was made when entering the order price.
    Has anyone seen this before and what should be the cause of action? Well, I was still able to proceed with the GI successfully but I'd like to know what has caused the message?
    Thanks.
    Steven

    Hi Manohar,
    My previous stock was 0.
    So i received material  100 qty at 20 INR.
    Total stock value = 2000
    Now as per you:
    2000 / ( 0 *6) * 100   =    33.33
    I am not getting 390,17 %
    Utsav