Freight charges getting added to Netprice in PO item overview

Hi,
In PO,freight charge is getting added to net price of the line item.
From that 12.5 CST is getting calculated.
For example Rs 1lakh is my netprice.
Rs 10000 is my freight charge.
But 12.5% CST to be calculated on 1lakh only,but it's getting calculated on Rs110000.
How to get rid of this?
Regards

Hi,
1.  Please check the freight condition type using M/06. Tick the checkbox for Accruals in the control data of the condition type.
2. In the pricing procedure, against that freight codition type, ensure that the statistical checkbox is ticked and the Accrual key and account key assigned.
Thanks & Regards,
Amjad

Similar Messages

  • Freight Condition Gets Added Automatically In Scheduling AgreementMaterials

    Hi! Our users are encountering this type of behavior in SAP recently on a scheduling agreement. Apparently, a freight condition automatically gets added when a material is added into the scheduling agreement. Users usually add the freight condition manually when doing this in scheduling agreements.
    Is there an explanation / logic on this? Thanks in advance, gurus!

    Go to scheduling agreement conditions tab. In that select your condition and choose "goto" in menu bar. then look for condition records. You can find from where it is copying
    Regards
    Antony

  • Adding customer field into  BID item Overview

    Good afternoon,
    (SRM 5.5)
    I have added the customer field in the BID.
    Is it possible to show it, in the "Item Overvier of BID"?
    Alexey

    Hi,
    Generally through the INCL_EEW* structures,you can add the custom fields for the Bid Item only under the BASIC DATA tab.If you want to show up a field on the Item overview screen,then this will need std code modification(screen modification) or  need to  modify the HTML template for the BID item overview screen in the ITS service BBP_QUOT which will need lot of HTML expertise.
    Hope this helps.
    BR,
    Disha.
    Do reward points for  useful answers.

  • HT1711 When I download music, does the charged get added to my phone bill?

    I'm a little confused as to how this works. I'm not sure if the charge of my downloads go toward my phone bill or goes to some other account. Will I see the charges on my debit card? How does it work?

    They go to whatever card you have on your itunes account.

  • Adding a new column to item overview screen 4900 in sales order transaction

    Hi All,
    I want to add a new column to refer to a custom field in screen 4900 ( Item overview screen ) in sales order transaction. Please suggest appropriate exit or BADI for the same. Give all steps to do the same.
    Thanks in adavance.
    Jawahar.

    Hi
    As the link that RamKi let us know, this is a modification, so, I suggest to avoid. See SAP Note 862228 - Order reason for returns on item level for further information. I suggest to use the other enhancements in tabs.
    Regards
    Eduardo

  • Adding new field in ME51n Item overview

    Hi all,
              i have a requirment to add a new field in me51n item overview, there i have a tab material data, in that i have to add a new field called Warranty. can any one  kindly guide me the steps to do this.
    thanks,
    nagaraj.

    Hi,
    Implement this enhancement MEREQ001 in CMOD. Before implementing read its documentation which will guide you steps for implementation. for more help use the below link.
    Link: http://www.sdn.sap.com/irj/scn/advancedsearch?query=mereq001
    Regards
    Ahsan

  • Settlement of freight charges in KO88 not settled

    Dear Friends,
    In KO88, In Settled values - Asset of value 10000 is displayed and freight charges 1000 is displayed.
    The settlement run is completed with any errors.
    I went to the GL Account - Asset under construction, here the freight charges 1000 are being displayed as open item.
    Please suggest why freight charges are showing as open item. The user is saying the GL account should displayed zero balance.
    Regards
    Sridhar

    Dear Friends,
    When trying to execute the KO88, I am getting the following message.
    Either the sender is already settled, or there is nothing to settle
    Message no. KD213
    Diagnosis
    Possible causes:
    The balance on the sender is zero.
    There is nothing to settle for the settlement type selected.
    Example: Periodic settlement
    Distribution rule: Percentage rate 50%
    Receiver cost center 1
    Settlement type PER
    Charge in the posting period:  $200
    Credit from earlier settlement:  $100
    The distribution rule always applies to the period value (here: $200). At the month end, 50% (here $100) was settled.  This leaves nothing to be settled when the period close is repeated.  The balance (here: $100) can only be settled using full settlement or an additional distribution rule.
    Please suggest how to solve the error.
    Regards
    Sridhar

  • Freight Charges in Rate Contracts WK

    Hi All,
    I have confgured a pricing procedure and it gets determined when i am creating rate contract. The condition type for freight charges gets determined in item condition but while calculating net price it is not being used. Can anybody please help.

    Dear,
    Whenever we define a condition type in M/06 and Tick  Accruals flag in control data 2 then by default it is statistical ( does not depend whether you select statistical flag in M/08)
    Just go to M/06 for your condition type press f1 (help ) on Accruals you will get the idea
    It says
    Condition is Relevant for Accrual  (e.g. Freight)
    Indicates that the system posts the amounts resulting from this condition to financial accounting as accruals.
    Use
    If you mark this indicator, the condition appears in the document as a statistical condition. "
    Edited by: redriver on Jan 7, 2012 11:53 AM

  • Freight condition calculated on header level , not at item level

    Hi,
    I am creating PO with 2 line items..
    mat X qty 1 price 100 INR
    mat Y qty 1 price 100 INR
    Now i have given freight as 500 INR in header level...
    My prob is freight is getting calculated based on number of  item level...
    It means if i have 2 item levels my freight is coming 1000 INR....
    it is adding based on line item.....
    but it shud come 500 INR....
    I want my freight to be added at header level......
    Utsav

    HI
    What will u do if in case freight shud be 500 + 500 = 1000
    So leave this condition as it is
    Goto Tcode M/06 ... and create a new condition for freight ... by copying the present condition type and then add it in pricing procedure
    But in "details "of this new condition type  put a tick mark against group condition and header condition.
    "To go into details of a condition type ... select the condition type and then click on lens button"

  • Freight Charges from PO into MIRO is not getting copied.

    Hi Experts,
    Please see the document flow and the issue below.
    PO -> MIRO -> MIGO
    Here, I have entered freight charges manually in PO, when use the reference to create MIRO.. the freight charges are not getting copied from PO into MIRO.
    Why set of configuration I have to perform to solve this?

    Hi,
    Open you condition type in tcode M/06 which you have created for freight and check the settings as below..
    in control data 1-
    Cond. class-A(Discount or surcharge)
    Calculat.type-A(Percentage)
    Cond.category-B(Delivery costs)
    Plus/minus-A(Positive)
    Check the Accrual Key.
    Check whether Accrual key is provided in your pricing procedure for your freight condition.
    In PO select your freight condition from conditions tab and click on detailed tab there provide your freight vendor in the same screen you can view the condition value which then flows to your MIRO when posting delivery charges.
    While doing MIRO for posting delivery charges select planned delivery charges.
    Thanks

  • How to include Freight charges and unloading charges in Material price.

    Hi All,
    Can you pls. advice how we can include freight charges & unloading charges in Material price (MAP) when receive in system.
    Current Situation :
    We buy Switchgears from vendor, which transported with special vehicle arrangement from different service provider and gets unloaded at warehouse by another service provider. Currently business create seperate PO for Material vendor, Freight Vendor and for unloading service provider. But MAP is only updated with Material cost only. How can I include delivery cost and unloading cost in MAP thro standard SAP process.
    Your solution will help business heaps.
    Regards,

    Hi,
    Create three condition types namely basic material price, freight charges & unloading charges.
    For  basic material price , you can copy PB00 and rename your basic material price condition type.Now freight charges & unloading charges condition type in M/06 , do not maintain condition category ( keep it blank ), so that it will added to inventory cost .For freight charges & unloading charges do not maintain account key & accrual key in Pricing procedure.
    Cretae PO , now you will see all cost added to NET price in PO and you can for doing GR where all cost are inventoried as materisl cost.
    Regards,
    Biju K

  • How to add Freight Charges for SO Via B1WS

    I am using B1Ws for adding a new Sales Order.
    I want to enter Freight Charges details also.
    In DIAPI through expense code we can add but in b1ws what is the equivalent of that ?
    Can anbody guide me ?
    Thanks
    Vaithy

    hi,
    can someone take a look to see what I'm missing to update a document with freight add.
    I am getting a document from an existing delivery and want to add a new freight line and cost to it.
    Dim dl As New Delivery.DeliveryNotesService
    Dim d As New DocumentParams
    d.DocEntry = "1"
    d.DocEntrySpecified = True
    Dim msgHeader As New Delivery.MsgHeader
    msgHeader.ServiceName = Delivery.MsgHeaderServiceName.DeliveryNotesService
    msgHeader.ServiceNameSpecified = True
    msgHeader.SessionID = sid
    dl.MsgHeaderValue = msgHeader
    Dim doc As Document = dl.GetByParams(d)
    Dim ex As New DocumentDocumentAdditionalExpense
    ex.LineNum = 0
    ex.LineTotal = 10
    ex.Remarks = "Shipping"
    ex.BaseDocEntry = d.DocEntry
    ex.BaseDocEntrySpecified = True
    doc.DocumentAdditionalExpenses = ???
    dl.Update(doc)

  • MIRO-freight charges not coming

    Hi,
    I created my own pricing procedure, in which i have created few Z condition types..
    While creating PO, i am getiing net price, in which freight cost is not getting added..
    But at the time of MIRO, while selecting Goods/Service items + Planned delivery time..I am not getting 2nd row for freight related costs.Though freight charges are there in PO.
    Where i went wrong.
    Uts

    >
    Utsav.agra wrote:
    > Hi,
    >
    > Now my freight charges are getting added in net price in PO...And in MIRO , same condition for freight is coming im second line but amount and quantity fields are blank....
    >
    > What went wrong?
    >
    > Uts
    Now my freight charges are getting added in net price in PO...And in MIRO , same condition for freight is coming im second line but amount and quantity fields are blank....
    As per ur Qusetion it is getting added to Net Price .
    Then u have not select these conditions as Accural in M/06.
    If u make it Accural then at the time of  IR separate line item will be Shown with Qty & Value

  • Regaring Freight Charges Tables

    Hi All,
    My client is using Z Transaction ZSD54 for pending sales order report and now he wants Freight charges field to be added to this report can any one suggest me the process.............Thanks in advance

    VBUK (Header) & VBUP (Item) tables for relevant status fro delv of sales order.
    Use VBAK for document condition no.
    The same doc cond no. can be used for KONK & KONV for pricing and coorespondingly you can get other details by passing freight condition type.
    Just have look on the said tables and choose the fields accordingly & as per your relevance.
    Regards
    JP

  • Clearing Freight charges

    I have created ZFRQ condition for Freight..
    and i am seeing that it is not get added into the PO Value.. is it rite??
    while doing Miro every time i have clear the freight charges separately???
    Is it rite???

    Hi,
    first clear what you want ,add to material cost or to hit g/l account separately
    check your condition,you have add any +/- sign there
    If its planned condition and want to hit separate g/l account and then while doing MIRO select layout "goods receipt+planned delivery cost" and it will post  in one transaction
    if you want separately ,then choose layout in MIRo planned delivery cost
    If you want hit to material cost don't assign any account key and accrual key for that condition in pricing procedure
    Regards
    Kailas ugale

Maybe you are looking for

  • My iPod Touch 3G screen stopped working.

    A few days ago, my iPod Touch screen stopped working.  I tried restoring it afterwards and it worked for about a day.  After that the screen became unresponsive again.  I did this again to see if it would make a difference but the same thing happened

  • [SOLVED]When pacman is updating linux-headers and linux, catalyst-hook

    Hello- I wanted this to be out there on the web so that people could find it.  I'm not sure if this could be considered a 'bug' for catalyst hook or for.. something, or if it is expected behavior. I ran pacman -Suy on my system today, and ran into er

  • Understanding CMT, HELP!!

    I'm looking for a good explanation of container managed transactions. At my company we have an EJB app in which we are trying to set CMT attributes on. It's strucured in a way that each table in our DB has a corresponding entity bean. (we use BMP ent

  • PS Elements 4.0 and Profile Mechanics Scanner

    Does PSE 4 work with Profile Mechanics Scanner as a plug-in, or in any other manner, please? If not, are there any programs similar to Profile Mechanics Scanner that do work with PSE 4? Thanks.

  • Unknown error when updating iphone

    I just tried installing the 7.0.3 update for my iPhone 4 and it came back with an unknown error message. Does this mean I have lost all of my pictures that I hadn't downloaded yet? I just synced my phone before I updated. It has some irreplaceable pi