Hello All,
Is there any FM to check if a cost center is involved A250 relationship with any position.  The input parameter should be the costcenter and the outparam should be the position with which it has the A250 relationship.
Thanks in Advance
RK

Hi RK
I couldn't find any std. Eval.path to fulfill u r requirement. So can you create a new custom Eval.path and try to use the std.FM " " to get person managing the cost center
Custom Eval.path details
10     K     B     011     Cost center assignment     *     O
20     O     B     012     Is managed by...     *     S
40     S     A     008     Holder               *     P     
Let me know, if you find an issue to create a custom eval.path otherwise we will find a another solution
Thanks
Kamalbabu

Similar Messages

  • How to check System Center Service manager 2012 R2 license version

    Hi,
    I have installed Microsoft System Center 2012 R2 Service manager 3months before but do not have remember whether I put permanent license key or evaluation, can anyone please let me know how can I check whether this is evaluation or permanent license?
    Warm Regards, Pramod Kumar Singh Manager-IT

    Hi,
    During setup of the retail edition of System Center 2012 – Service Manager, you have the option of performing the installation without a product key and instead installing Service Manager as an evaluation edition. The evaluation
    edition times out 180 days after installation. If you start with an evaluation version of Service Manager and you rerun Setup and install the retail edition or select edition, and you decide to use the existing databases that you created originally,
    your installation will time out after the original expiration date.
    I summarize the following steps and hopefully it will help you.
    You could find the install date on :HKEY_LOCAL_MACHINE\SOFTWARE\Microsoft\System Center\2010\Service Manager\Setup"
    Try to change the system time from install date to install date + 180days.
    If you can't open the console again, you are evaluation Edition.
    Rerun Setup to install Retail Edition or Select Edition.
    For more information, please review the links below:
    System Center 2012 - Service Manager Evaluation, Retail, and Select Editions
    http://technet.microsoft.com/en-us/library/hh495604.aspx
    We
    are trying to better understand customer views on social support experience, so your participation in this
    interview project would be greatly appreciated if you have time.
    Thanks for helping make community forums a great place.

  • How can define the cost center (department) manager?

    We are on 11.5.0.10
    Financials implementation is done(GL,AP,AR,FA,IA)
    In iAssets System, we want to set up the approval method to use "cost center-based approvals". (For cost center-based approvals to work properly, each cost center must have a manager defined.)
    How can define the cost center (department) manager? Thanks.

    I believe this is done in the organization definition screen. For each organization, we attach a classification "Company Cost Centre" (the same place where we attach the classification operating unit, inv org etc). In the others section, there are 2 additional information - GL company cost centre and reporting information. In the GL company cost, you need to attach the balancing segment value and the cost centre value. In the reporting information, you need to attach the manager for that organization. This ay the relationship between the cost centre and manager is created.
    Hope this clarifies.
    Vinit

  • How to restrict cost center in ME51N

    Hi all,
    can anyone please let me know,how to restrict cost center in ME51N transaction?
    Thanks in advance for your efforts

    Dear,
    Go to Transaction,
    KS02- Change Cost Center.
    Go to the Control Tab.
    Tick on the checkbox for desired transaction activity you want to lock this cost center.
    Any postings made against the cost center will not be allowed.
    Regards,
    Syed Hussain.

  • How to assign cost center to cost element.

    Hello,
    Can any one please guide how to assign cost center to cost element.
    Thanks in Advance..
    Have a nice day...

    Hi ,
    There are 3 ways :
    1. Default the cost center in cost element - Ka02 - account assingment tab enter cost center .
    2. Use OKB9 for diffrent combinations as per your requirement .
    3. Use GGB1 for substituting the cost center based on some conditions .
    Regards ,
    Dewang T.

  • How to use cost center hierarchy?

    Hi,
                  How to use cost center hierarchy?I have created that but how to use that.Can somebody help me?
                                        Sekar

    Once the Cost Centre Hierarchy is Created, it can be used in Profit Centre Reports.
    Choose Financials -> Cost Accounting -> Profit Center Report ->Template.
    Here Choose, the Cost Centre Hierarchy the you had created and generate the report.
    Also refer these threads
    [Reg... Costcenter hierarchy;
    [cost centre hierarchy;

  • How to Enable Cost Center Field in Infotype 0001

    Dear all my Friends,
    Can anybody please tell me that how to Enable Cost Center Field in Infotype 0001, actually the problem is while hiring the employee the field itself disable and not allowing me to put any CC on that field but which should be enable while hiring or if we intend to change in future through PA30 and after that i thought i can do in Infotype 0027 also but in infotype 27 the field called Master Cost Center field is still disabled which will reflect in 0001 or Vice Versa.
    So friends pls tell me where my configuration is wrong or how will i get enable that field in 0001 infotype so that i calculated the cost of that employee.
    Waiting for ur Reply friends,
    Thanks,
    Prashant.

    Dear Rajesh,
    Thanx for ur Solution and i got the answer, actually i m maintaining through OM and u gave me the exact solution .
    Gr8 job dear. Thanx allot once again
    Thanks,
    Prashant.

  • How are non-cost center Controlling objects best modeled in PCM?

    I appreciate that ALG developed Profitability and Cost Management, and they apparently were unaware of
    or did not consider that SAP ERP uses more than a single controlling object of a cost center; specifically
    internal order, WBS element, real estate object, etc.
    My question is how are these other controlling objects best treated in PCM?
    For example,
    I have a planned trade show internal order to showcase my companies products
    in Berlin to European retailers.  I have planned travel costs, display costs,
    space rental costs on this internal order.
    Normally, I would settle this internal order to CO-PA to determine the planned
    profitability of my Europen retail customers.  Unless I make this order a faux cost center,
    I don't see how to model it in PCM.
    If I exclude this order, then the profitability resulting in PCM is suspect --
    leaving out a major chunk of customer specific marketing expense.
    Or is the process to settle the planned internal order cost to CO-PA, but
    transfer the planned costs from PCM back into CO-PA, which would have the
    benefit of being mutually exclusive and collectively exhaustive.
    Jeff Holdeman hinted at the restrictions imposed by planning in ECC.  Yet
    without a more comprehensive approach, I am concerned that PCM still
    does not represent a complete profitability planning solution.
    Bob McGaffic

    Hi Deepak.
    You can verify is the cost center was posted on document running tcode SE16N on the FALGFLEXA table, put the document number to do research.
    After you can trying to post the new document through Tcode FB50L choosing or not a legder specific, then verify the document was posted correctly running the Tcodes SKb1 or Se16N with FAGLFLEXA table again.
    Also you can check this link Checking the Allocation of General Ledgers to Cost Centres
    Kind Regards
    Jandoval Nascimento

  • Work Order & Cost Center Commitment Management

    We have a business requirement to be able to view our work order commitments (Reqs and POs) from the work order as well as from the cost center assigned to the work order via a settlement rule. Our business users do not like the work order collecting all of the costs instead of the cost center where they perform their cost controlling.
    The actuals will settle to the cost center eventually but without the commitments they have no way of planning for future costs. Commitments management is activated for both the cost centers and work orders involved. I am open to any suggestions on how to achive this requirement. Thanks!

    Any thoughts?

  • How to add cost center field to IT0001

    Hi
       How to add a cost center filed in IT 0001...I know normally this will be there but in my client system it is been hided or removed ..So can I know where to make a changes to get it back.
    Thanks

    hi
    check your infotype customizing in IMG .
    note down the screen number , and in there you can check if the fld is hidden or not.
    Regards
    sameer

  • How to control cost center authorization when do ABSO/ABAA

    Dear :
    As our system organization structure is with mutiple profit center and
    cost centers, in order to avoid processing TCODE ABSO/ABAA with wrong
    input, we want to make authorization check with cost centers, as there
    is no standard authorization check and control in TCODE ABSO/ABSS , we
    want to know how could we realize the requirement
    to control the TCODE with cost center authorization check, thanks in
    advance.

    Hi,
    check SAPNET note 370082 + related notes + 698401 / 565436.
    Best regards, Christian

  • How to change cost center in Asset Master record ?

    Hi SAP Gurus,
    My client is asking me to change cost centers in Asset Master records using LSMW. Currently, the field cost center is in display mode. In order to change the cost center, the field cost center must be in change mode while recording in LSMW. I have changed screen layout rule for Asset Master data. I have selected radio button "Optional" for cost center in screen layout for Asset Master data. But still cost center field is in display mode in Asset Master record. It must be changeable.
    Please suggest me how I can resolve the issue.
    Regards,
    K.S.K

    Hi Saravana,
    We can change the cost center for AuC Investment measure at WBS element level. For that purpose we need to go to AuC Investment measure Asset master record and check WBS element under Origin Tab. Double click on WBSE and then check the cost center under Assignment tab. And also check the cost center in Asset master record for the same. Now you can go to T.Code CJ12 (Change WBS Element) and change the cost center for the same. Once you make changes system automatically change the cost center in asset master record for the same.
    Note: - Now you have to identify all the AuC Investment measure Assets and the WBS Element for the same. Then change the cost center in WBS Element record. And the corresponding changes will be done in relevant Asset master record automatically.
    But before making the change please check with the PS/PM consultant regarding changes in WBS element. Means where it will effect?
    With Regards
    Ravinder Kaushik

  • How to get Cost Center number from a Customer

    Hi Sap Experts,
    I have a customer number from xd03. But I would like to know which is the cost center used by this customer, how can I find that?
    Because I'm getting an warning message when using FB08, it points to the Tax Jurisdiction issue. I believe at some point, it's checking the Jurisdiction field of the cost center.
    Regards,
    CHL

    Hi,
    Thank you for the reply.
    The thing is, when I run FB08 for a specific document, i'm getting this warning Msg: Account assignment object has jurisdiction code XX, line iten XX AAAAAA.
    I checked already the configurations for jurisdiction code in customer master data and the path "define tax jurisdiction code" with spro.
    I noticed something, during the debug at some point its reading the cost center's jurisdiction number, and will compare it with customer's master data jurisdiction.
    But if there's no cost center it will process fine.
    It's in the program SAPLKAIP, form CostCenter_Check. Not sure if it's SAP standard code.
    Cheers.
    CHL

  • How batch append cost center group to standard hierarchy by batch

    Hi Guys,
    Would you please tell how me how append cost center groups to standard hierarchy by batch, every time I have to do it one by one, is there  a convenient way? thanks.
    Best Regards
    FS

    Hi,
    You can create any number of cost center groups as per your requirement.
    But one thing is crucial. If you crin your eate the groups using the T Code:OKEON. those will effect  to the standard hierarchy.
    Cost centers created wil KSH1 will not effect to standard Hierarchy.
    Main point here is the main hierarchy should be maintained in OKEON. Later you can add any number of groups to that. LSMW will work, before that Hirarchy Area(Cost center group) should be maintained in the system for effective work of LSMW.
    Regards,
    Pavan Kumar Arvapally

  • Report Painter- How to make cost center report for Jun07-Jul08 ?

    Hi Experts,
    I need to make a P&L (Actual/ Plan) report for Jun 07 - Jul 08 by using Report Painter, but I'm having difficulty to make column for the next year period (2008) and some other things.
    We are using K4 Fiscal Year Variant in ECC 6.0.
    The layout is somehow like this:
    Header : Cost Center
                 Actual/Plan Report
                 June 2007 to July 2008
    Body:
    Cost Element     |   Total Actual   |   Total Plan |  Actual  June | Plan June .................Actual July | Plan July    
    xxxx       
    xxxx
    Account Group (total)
    xxxx
    xxxx
    Account Group (total)
    Grand Total  
    How to:
    a. make the header "June 2007 to July 2008" ?
    b. make the selection screen to provide parameter for June 2007 to July 2008? (e.g.: period 6 fiscal year 2007 to period 7 fiscal year 2008)
    c. provide layout (rows and columns) as described above? it should provide detail cost elements and also calculate it as the total per account group, then finally the Grand Total for all of account groups. 
    Thank you before,
    -=Meila.S=-

    Hi,
    1. Put Year and Month as your General Selection parameters
    2. In the label of the fields, if you put the parameter name with & before, it will display the value
    3. If you put cost element in General selection, it will come with a group, and when you selecting the group, the report does the sub-totals automatically.
    Regards,
    Eli

Maybe you are looking for

  • Payment Posting with Reference to Purchase Order

    Dear Experts, I've created a Purchase Order with reference to a purchase requisition. Now I want to post MIRO with reference to this Purchase Order Number to give payment to Vendor mentioned in Purchase order. But when I going to post miro amount not

  • How can I calculate a day of a week?

    I want to calculate a day of a week.But I always getting ArraysOutOfBoundException.Here's my code: import java.util.*; import javax.swing.*; class daydate{      public static void main(String args[])throws Exception      String arr[]={           "sat

  • Problem in extracting from the import transport set

    i am exporting all of the major page groups and providers from my source box to the target machine. both are using the same version database, app server and portal version 904. for one of the biggest provider, i created transport sets in the export s

  • Automatic Emails Being Sent Through My Account

    I have recently noticed emails randomly being sent out to folks in my contact list that I did not personally send out.  Here is an example of the source of one of these messages (note that I deleted the actual email addresses in the from and to): Fro

  • Unable to get the Approve option in  Salary form

    hi friends, we are implementing payroll using UAE localisation, when i try to add new salary for an employee i am unable to get the approve option in the salary form..we are working on version 11.5.10.2..i have the given the setup steps below HRMS Re