How to create Disassembly production order type.

Dear All,
I've been reading threads regarding disassemblyi type production order usage, but in my system (SAP ECC 6.0) i don't have an option to select this type of order.
So the question is how to create this disassembly type for production order, what other settiings are needed for disassembly processing. And could you pls shortly describe best practise for disassembly processing.
Thanks in advance,
Regards, Andrey
Edited by: Andrey Kruglov on Jul 15, 2010 3:45 PM

Hello
Such functionality does not exist on the standard system, however, there is a functionality called Order Combination for the industry solution DIMP.
Please take a look on the following document, which describes the order combination scenario:
https://help.sap.com/bp_fm603/BBLibrary/HTML/372_EN_FR.htm
BR
Caetano

Similar Messages

  • How to make a production order type default for a Plant.

    Hi All,
    I want to know the setting to make production order type ZP01 default for a plant so that when I create a production order using CO01 for that particular plant, it should always use ZP01 as order type?

    Hello Friend,
    One more method is to achieve this is by using Production Scheduling Profile. In transaction OPKP, for your Plant create a new production scheduling profile or use the existing one created in your plant. Inside the production scheduling profile, in order type section, for make to stock field, maintain the value as ZP01 (which you want to come automatically all the time while creating the order by co01) and save.
    Now assign this production scheduling profile in material master of all Semifinished and Finished materials.
    Now create new production order by co01. On initial screen of this transaction give only material code and production plant and enter (don't give anything in order type field).
    After giving material code and production plant, press Enter. After pressing enter system will take you inside the production order .
    Check here by default system will take order type as ZP01.
    Check and Confirm.

  • Disassembly production order authorisation

    Hello,
    Is there a way to put an authorisarion/restriction on users creating disassembly production orders?  I've had a look in SAP but i was unable to find where I can do this.
    Many thanks,
    Kate

    Hi Kate,
    You may try this one;
    if @transaction_type in (N'A',N'U') and @object_type = '202'
    begin
    if exists (SELECT T0.[DocNum] FROM OWOR T0 WHERE T0.[DocNum] = @list_of_cols_val_tab_del and T0.[Type] = 'D'  AND T0.UserSign ='10')
    begin
    SET @error = 17
    SET @error_message = N'You are not permitted to perform this action!! '
    end
    end
    Replace T0.UserSign ='10' by your user sign. This would allow only manager id to create dis assembly type production orders.
    Thanks,
    Joseph

  • Creating a new order type in OM

    Hi dear
    I have to create a new order type in order management.
    Once the order is booked, the inventory should decrease automatically without passing through "Release Sales Orders", "Transact Move Orders" and "Shipping Transactions".
    After the line status is closed, i can generate the invoice for the order through the autoinvoice master program in receivables.
    Can somebody explain me how to create such an order type?
    Thanks.
    Regards,
    Mustapha.

    Thx a lot for ur help dr.
    I have activated the material transaction interface and now the stock quantity has decreased.
    I just wish to confirm some points in the creation of the new Order Type.
    I have done the following setups:
    Order Category: Mixed
    Transaction type code: Order
    Fulfillment Flow: Order Flow - Generic
    Line workflow assignment: BO Line - Inventory Interface
    Default return line type: Credit Only Line
    Default order line type: BO Line - Inventory Interface
    Plz confirm if the setups parameters are ok especially the Default return line type: Credit Only Line
    Thanks a lot dr.

  • Planned order to production order type

    hi
    when ever converting planned order to production order system aumatically picks production order type pp01 from MRP group assignment. if i not assigned mrp group in material master means, how the system picks production order type. I think its pick from strategy assignment in order type?????
    thx in advance

    Hi, 
    Check with OPPQ..
    What is the Planning Strategy you are using??
    Regards,
    Siva
    Check with the Transaction OVZG..(Requirements Classes)..
    Depending on the Pl. Strategy you can specify the Order Type here.
    Regards,
    Siva
    Edited by: Siva Kumar M on Jul 25, 2008 3:55 PM

  • Steps to create a new order type

    could someone plz tell me how to create a new order type and what other things i should look into to make it work.
    Thanks

    Hi sri
    if you want to go for new order type then copy standard into Z doc type. for example (OR to ZOR) , because there are tables which are assigned to the doc type internally  that get copied when you copy from standard .
    If your requirement is for same sort of doc type with diff changes suggestions is go for  (OR to ZOR)
    Now when you copy form standard to Z doc type , you need to configure as per your requirement in the VOV4  also
    Regards
    Srianth.

  • Why custom production order type?

    Hi Guys,
    Why would we need a custom production order type? What is the criterion to be considered while creating  custom production order types?
    Regards,
    Sravan Kumar

    Dear Sravan,
    1.A Custom Order type might be for a specific business requirement, for Eg Order TT01 is for a normal production process and
    TT02 may be for some rework.
    2.Likewise if I want to differentiate on a shop floor basis though it might be the same production based I can create a separate
    order type for each shop floor.
    3.It can be based on different order type dependent parameters like BOM application, task list selection etc.
    4.It can be based on scheduling and also confirmation parameters we create new order types(customized).
    Check and revert back.
    Regards
    Mangalraj.S

  • Settlement rule auto created in Production Order with Receiver Type as OIT

    Hi,
    I am creating a production order with material number in CO01. The system is automatically putting OIT in receiver category, in settlement rule.
    And its populating the child materials there. I expect the parent material to be populated in the settlement receiver.
    In the settlement profile maintained in order type, I have maitained MAT.
    Please let me know, why system is autopopulating the role like above.
    Regards
    SR

    Hi,
    If you are going to settle the production order to Material, there is no need to enter Allocation structure in Settlement profile unless its used for variance settlement...
    Allocation structure has an option to settle to OIT with a settlement cost element or primary cost element...which is why i wanted you to check for that.
    Anyways, Follow the thread, this should help you
    Change the Settlement Rule
    Thx
    PG

  • How to compare the variances of production order type and get report

    Hello All,
    I want to compare the variances of production order type wise.
    for ex. i want variances of order type PP 01 and PP 02 in a single report.

    Hi Sachin,
    You have to maintain summarization hierarchies to achieve this.
    1. Maintain summarization hierachies with hierarchy level - order type in the t.code.KKR0    
    2. Generate the hierarchy in KKRC
    3. Run the report KKBC_HOE
    Regards,
    Mukthar  

  • What is Disassembly production order?

    Hi Expert
    I want to know that what is use of disassembly production order. I want to create a production order which will give two item output but issue will be one item. how it is possible ?
    When I issue main component then it automattically increase the component item in stock and issue main product. but component item cost is not shown in production order What can be reason?
    plz help me.
    Regards
    Gorge
    Edited by: Gorge Ance on Jun 20, 2009 3:26 PM

    Hi Gorge,
    Disassembly Production order used for cancel or reverse the
    receipt from production order and also check this link
    Re: Reverse/Cancel receipt from Production
    Production Order Costs
    Re: item cost in production order disassembly type
    https://www.sdn.sap.com/irj/scn/wiki?path=/pages/viewpage.action&pageid=49217723
    Regards
    Jambulingam.P
    Edited by: Jambulingam P on Jun 22, 2009 7:19 AM

  • Disassembly Production order.

    Hi,
    I have one requirement of disassembly production order, where our client gets customer returned product which can not be repaired and send it back.
    the Business process is when they receive this kind of product, they will disassemble the product and some of the high value parts will be taken into  stock and less value components will be scraped. SO main product received from Customer will be consumed during disassembly order.
    So in SAP ECC, we can create Production order without Material and components can be added with -ve qty which we are going to receive into Stock and main Product will be added as +ve qty in Component overview, So main product gets consumed and Child parts are going to stock by 531 mvt type.
    But concern is our SAP ME shop floor execution system is not accepting the Order without material.
    Please let me know is there any way of doing Production order Dissembly and how about BOM and Routing selection//
    Thanks
    Naga

    Dear Nag Krish,
    What you have said below is correct way and follow this process.
    in SAP ECC, we can create Production order without Material (do it with material and as per standard SAP, fetch  it's present BOM and Routing) and components can be added with -ve qty which we are going to receive into Stock and main Product will be added as +ve qty in Component overview, So main product gets consumed and Child parts are going to stock by 531 mvt type.
    But problem is created because SAP ME shop floor execution system is not accepting the same.
    Actually, I have worked on such scenario and my suggestion is to proceed with material. i.e. create order with material then do the GI to order and order confirmation wherein you can book the labor time etc. but only need to care that, do not perform goods receipt for order which you can avoid by manually entering the last operation control key as PP01 rather than PP03.
    After words, Technically complete the order without doing GR for production order.
    In this process the components which comes back in stock are strictly comes with the current price.
    Rest of steps like settlement and production order closure can be done as usual.
    Try this on DEV server and come back with your results.
    Regards,
    Narresh

  • Production order type dependent parameters

    Dear Frndz,
    plz help me out with the various parameters which can be set based on the production order type. and the step by step procedure to configure the same.
    Regards,
    Srini.

    Hi,
    Pls. find the step by step procedure as below :
    Define order type-dependent parameters
    In this step, you define the parameters that are valid for each order type and plant. The parameters are split up as follows on the tab pages:
    Planning
    Master data
    Here, you define the data that influences master data selection or order master data maintenance:
    You can decide whether production versions are selected automatically or manually.
    The task list application is predefined as 'P'. However, you can also specify an additional task list application.
    The routing selection ID defines, for example, the ranking order for routing selection.
    Routing selection defines whether routings are to be selected and if so, how (manually or automatically) and whether reference operation sets can also be selected.
    Alternative sequences and sequence exchange define whether alternative sequences are permitted and how the sequences are to be exchanged.
    The task list type defines which routing type is permitted for production orders.
    Operation dtl check defines whether operation detail screens are to be checked when the operations are transferred to the order.
    Routing text defines that the text from the routing header is copied into the order.
    You can activate the entry tool for operations to help you when you create operations.
    BOM application defines how the BOM alternatives are to be automatically selected.
    Search procedure defines how batch determination is to take place.
    General
    Substitute MRP controller/substitute production scheduler are proposed when you create production orders if an MRP controller or production scheduler are not specified in the material master, or if there is no reference to material.
    Reservation/Purch. req. specifies whether certain order objects (operation, components) are relevant to MRP.
    Collective purch.req. enables collective purchase requisition per order for externally processed operations or non-stock items.
    Inspection type defines how a quality inspection is to be carried out.
    Implementation
    Status change documents
    Here, you define whether you want change documents to be written if a status change occurs. You also define the level at which the change documents are to be written.
    A status change document contains the following:
    which status has been changed
    who changed the status
    whether the status has been activated or deactivated
    the transaction in which the status change has been carried out
    In the production order, you can define the status at the following levels:
    order header level
    operation level
    material component level
    production resource/tool level
    Status change documents can also be defined independently of each other, at each of these four levels.
    Note
    If you have defined these parameters such that status change documents are written for a particular order level, the SAP System only writes a status change document for a status change from this point in time if the order (or operation/component/PRT) has been created since the status change documents have been activated.
    Shop Floor Information System
    You can specify, for example, whether order data is to be stored in the Shop Floor Information System. You can carry out reports using this system, for example, for materials, orders and work centers.
    Documentation of goods movements
    Here, you can specify that goods movements are to be documented with reference to an order. Then you can display goods movements, for example, using the order information system.
    You can enter a profile for displaying documented goods movements on the tab page "Display profiles".
    PDC
    PDC active allows data to be exchanged with a PDC system.
    Workflow
    Workflow for PO chg. defines that a workflow is generated when quantities or dates that affect existing purchase orders are changed in the order. In addition, a default rule for the split is displayed on this screen.
    So that this indicator is also valid for production orders the appropriate settings must be made in Customizing for the Project System.
    Progress determination in orders
    You can determine that progress values are calculated for order progress reports.
    Controlling
    Controlling
    Here, you define the parameters relevant to controlling, such as, for example, costing variants for planned and actual costs and a results analysis key.
    Distribution rule
    Default (distribution) rule defines an automatically generated distribution rule for CO settlement.
    Display profiles
    Collective order display
    Graphics profile defines how the collective order is to be displayed.
    Graphic:
    Here, you define parameters for displaying graphics of operations and sequences in the order.
    Missing parts list
    ProfMissPrtsLstOrdNo/PrfMissPrtLstCollOr defines how the missing parts list is to be displayed.
    Documentation of goods movements
    Goods movements defines which profile is used for displaying documented goods movements.
    Activities
    Create the necessary parameters for the order type.
    HOpe this helps.
    Regards,
    Tejas
    Edited by: Tejas  Pujara on Oct 1, 2008 6:35 AM

  • Create MTO production order immedately after running MRP

    HI experts,
    Does a stragtey group can be used for a material to create MTO production order/purchase order after running MRP?
    Or how we can set a material to create MTO production/purhcase order immedately after running MRP?
    Now we are using stragety group 50 for make to order material.
    After running MRP, material will create a Make-to-order plan orders. Then we converted them into purchase order or production order based on propurment type.
    Thank you for your response~
    Boris

    Dear
    Please assing Planning Stargety -82 if you want production order just after logging sales order .Here MRP will be executed in background and it will generate Production Order fro MTO item and for depedent it will generate PR/PO .Make sure that , you have kep Individaul and Collective Indicator as 1 in MRP4 view of all the compoenets which have used in BOM .
    Regards
    JH

  • GR for create the production order without material(co07)

    Hi all,
               I am creating the  production order without  material (T-Code :co07), After creating this order i want to get the Material from W/H and after dismantling how to do GR for this Prod.order, What is the Movement type to be used?Please advice me

    Dear Kumar,
    CO07 specially meant for Rework order (Production order
    without material) or for dismantalling the Customer returns or
    Inhouse rejected,for the components which re good to reuse
    again,their quantity will be entered in -ve and so 531 movement
    takes place.
    On the other hand,if you want to use for rework purpose and
    want to consume some components,using MB1A T code ,the
    materials required are issued.
    Already our Forum member(Krishnamohan) has given clearly in his first reply.
    Regards
    Mangalraj.S

  • Report for comparing Variances of production order types

    Hi All,
    I want a report in which i can see variances of production order type wise and can compare that with other types also.
    means my input should be as follows
                1) Company Code/controlling area
                2) Plant
                3) Order type 1
                4) Order type 2 and so on.......
    like wise I want to develop a report.
    I have created summerization hierarchy  but it show order type wise data.
    i want data from multiple order type in a single report.

    Hi Sachin,
    I have attached screenshot for your reference. Please find it.