Hello,
I'm currently trying to build a macro planning for my department for the next 2 years.
In my plan, there is a task that has a variable duration and amount of work. People will start / stop working on it depending on the beginning / end of other tasks. The only way to do this I've found so far is to split the task into multiple subtasks
(one per resource) that are manually scheduled with start and end dates linked to the dates of the tasks they depend on. However, I think this workaround is really not practical and hard to manage since for each subtask I need to create milestones for linking
the start date to the next working day. Relationships between tasks are also not visible in the plan. I've also read that in general it' better to avoid using links, but is there a better way to manage this in Project 2013 ?
Best regards,
Sébastien.

Seb_Lz,
There are several elements of your description that need more detail.
You mention a variable duration. That could simply be a normal task that changes scope as the plan progresses (i.e. more work content, slipping schedule, etc.), or it could be indicative of what is called a hammock task (See Faq 19 on the MVP website at: http://project.mvps.org/faqs.htm).
You mention linking as a way to define task dependencies. That is exactly what task predecessors and successors are designed to do. Task links have nothing to do with resources. It's not clear why you say only one resource per task.
You talk about manual scheduling and entering start and finish dates. Manual scheduling is intended for a very rough first cut at a working schedule. To get the full benefit of Project's scheduling engine, tasks should be auto-scheduled and the whole logic
network sequence of tasks should be defined by durations and links, not by manually entering dates. It's fine to set critical milestones or use Project's deadline feature, but otherwise let Project tell you how your plan all works given the basic data.
You say relationships are not visible in the plan. Don't understand that at all since link lines between tasks are shown by default in task views (e.g. Gantt Chart view).
Not sure where you read that it is better to avoid using links because that is flat out wrong, at least for normal predecessor/successor links within a single file. If you are working with a linked structure (i.e. master/subproject), or using external predecessors/successors,
then yes, links become a whole new area of concern.
John

Similar Messages

  • How to run tasks with priority?

    Hello everyone,
    I want to run tasks with priority, i.e. among several simultaneous running tasks, the task with the higher priority will have more chances to occupy CPU time. I have the following 2 issues dealing with the implementation of such feature.
    - To define each task as a thread or as a method? How to change the priority of each task dynamically when they are running?
    - The priority feature of Java thread does not meet my requirement, since I can not define priority precisely. For example, I want to define that a task with priority A will occupy CPU time 3 times than a task with priority B.
    I am wondering whether I can find similar open source projects or tutorials?
    Thanks in advance,
    George

    how to run autoconfig with out effecting database
    or
    which mode i have to run What do you mean by not affecting the database?
    The database and the database listener should be up and running when you run AutoConfig on the Application/Database tier nodes.
    Please see (Autoconfig FAQ [ID 218089.1]) -- Which files / profile options get changed when I run AutoConfig?
    Thanks,
    Hussein

  • How to combine text with variable in process flow

    Hi,
    I have created a function that returns the environment that a process flow is running in, Production, Test or Development. I have been able to bind the output of the function into a variable in a process flow and bind the variable to the subject of an email activity. I'd like to go one step more and combine the value of the variable with some text to explain which step in the process flow generated the email. Is there a way to concatenate text to a variable or to add an OWB system variable? I've seen an example where the subject of the email is
    "Failed mapping <mapping name>"
    but I want my subject to be "PROD Failed mapping <mapping name>" where the "PROD" is from a process flow variable or function return value.
    Is this possible?
    Thanks
    Don Keyes

    Hi Don,
    you can perform this task with ASSIGN activity.
    For example, you have two variable V_ENV_TYPE (with type of environment) and V_TEXT ("Failed mapping <mapping name>"). Define additinal variable V_NEW_TEXT, bind Variable parameter of Assign activity to V_NEW_TEXT variable and define value in Assign activity as
    V_ENV_TYPE || ' ' || V_TEXTRegards,
    Oleg

  • How to Manage Pcs with a mac server mini?

    one of my missions is to manage Pcs with a mac  server. But since my searches are not fruitful. It is the reason why I would like to obtain from the help. Very cordially to you..

    See Meraki MDM, has administration for many platforms including PC.
    https://meraki.cisco.com/products/systems-manager

  • Fed up with iWeb's idiosyncrasies! What program accepts the FTP output file from iWeb with the least amount of work required?

    Hi...
    I have been a longtime user of iWeb and have learned many things about it the hard way. Now even after duplicating and saving my domain names constantly to external hard drives, downloading additional software such as iWebdrop and iWeb SEO, learning how to unhide files that shouldn't be hidden in the first place, and consistently finding the elusive domain files, I find myself, yet again, searching high and low for the updated domain that I spent two days doing a major rehaul on. I have proof that I wasn't dreaming as it's currently up on my website and I have the exported FTP file.
    So after years of crying over lost iWeb domains I've decided it time to make the leap to different software.
    I need something akin to iWeb as I'm not at all versed in HTML. My main goal is to minimize the amount of work by using the FTP files I exported last night.
    I've read the recomendations here but just want a simple solution with no HTML coding needed.
    Flux?
    Thanks!

    Nope. It's just no where to be found.
    I mentioned in another post that during this entire episode an icon with files from my old mobile me account kept popping up. I kept having to eject it and I thought maybe that might have something to do with the issue.
    Though it was there this morning, now I can't find that icon anywhere.
    This must be the fifth time I've had issues like this which is why I'm fed up and feel the need to move on.
    I wish there was some way to reverse engineer the FTP file.

  • Using alerts with variables-"dynamic text" not working

    Hello all,
    I'm triggering an alert from a BPM, and have set the flag "dynamic text" on for the alert category associated with it. I'm doing it in a similar way to the blog 1382 by Michal:
    [/people/michal.krawczyk2/blog/2005/03/13/alerts-with-variables-from-the-messages-payload-xi--updated|/people/michal.krawczyk2/blog/2005/03/13/alerts-with-variables-from-the-messages-payload-xi--updated]
    The only difference is that I'm just assigning a fixed text instead of a payload element to the container element, which I've defined as simple type - string.
    However, the text of the alert doesn't show anything. I'm getting an email with just "Process <id>" as the subject and "Alert ID: <number>" in the body of the email (the same in the Alert Inbox).
    I'm starting to think that there could be something wrong in PI 7.1 which I'm using, as I've configured other alerts in scenarios without BPM without problem.
    Thanks for your suggestions!

    I've solved it using an alert from the Enterprise Services Builder (Integration Repository). It's a new feature in PI 7.1. It seems the tab "Container" in the alert category didn't exist before (that's why you don't find it in the weblogs of Michal and others) and now you have to use it.

  • How to use datamerge with variable lengths of text?

    Hello,
    I'm looking for a way to automaticly format brochures from a database . I allready found out that datamerge lets you do this quite easily. But I encounter a problem when I use large amounts of text.
    How I see it, the only solution is to reserve enough space for the larges text in order to make all of the text appear in the document. But this leaves large open spaces and even blank pages in my document when I deal with less text.
    Is there a way to make the document adapt to the amount of text? So that Indesign creates more space for large amounts of text and erases blank pages when there is less text?
    Maybe Datamerge isn't the right solution for my problem, I'm open to suggestions.
    Thanks in advance!
    Iris

    I'm just finishing up a directory that I build with data merge and I have the problem of variable length business descriptions, as well as some have extra mailing addresses or websites. My solution is to do it in several steps with multiple files. I do a normal merge first (and I use a single record per page for this, but only bcause that allows me to create some alphabetical lists of business names and owners's names that I can key to a listing number), then I stitch together the individual stories into a single text thread that I copy/paste into place in the final document. If you have a lot of frames, Rorohiko.com has a nifty text stitch script that will help.
    One tip that helps with this method is to be sure you have a paragraph break at the end of each story so stiching the frames together maintains your paragraphs.

  • How to manage playlists with multiple devices?

    We have multiple devices in our household that use the same Macbook Pro.  We all like different kinds of music and we are now having a difficult time trying to manage the playlists on the different devices.  How do we manually manage playlists for each separate device?  We have iPhones, iPads and iPods.

    How to use multiple iPods, iPads, or iPhones with one computer
    http://support.apple.com/kb/HT1495
    How to Share a Family iPad
    http://www.macworld.com/article/1163347/how_to_share_a_family_ipad.html
    Using iPhone, iPad, or iPod with multiple computers
    http://support.apple.com/kb/ht1202
    iOS & iCloud Tips: Sharing an Apple ID With Your Family
    http://www.macstories.net/stories/ios-5-icloud-tips-sharing-an-apple-id-with-you r-family/
    How To Best Use and Share Apple IDs across iPhones, iPads and iPods
    http://www.nerdsonsite.com/blog/2012/06/07/help-im-appleid-confused/
     Cheers, Tom

  • How to design constructor with variable parameters?

    I'm working on a "project" where I need to make a class "book" that can store information about a book. It's name, isbn, stock, etc... What is throwing me off a little bit is the author. I'm allowed to enter up to 4 authors per book object. I'm coming at the problem with the assumption, that I should be able to load this author data within the constructor. Questions is how. At first I thought I'd make 4 different constructors, each with a different number of author parameters. Simple enough but it seems unnecessarily messy. Then I thought I'd make a variable length parameter array. e.g book( String ... author ). But what if someone wants to enter more than 4 authors or none at all?
    QUESTION:
    Is there a way I can set a minimum and maximum of inputs for variable length paramters?
    Vectors seem like they could be useful here instead of arrays. But again there is that problem of controlling constructor parameters.

    Then I thought I'd make a variable length parameter array. e.g book( String ... author ). (Otherstuff, String author, String ... otherAuthors)
    Is there a way I can set a minimum and maximum of inputs for variable length paramters?Validate it in the code itself
    Or create another class specifically for Authors
    No matter what you do you will still need validation code, for example what if the author is null? Or empty?
         class Authors
                public String Author1;
                public String Author2;
                public String Author3;
                public String Author4;
                public Authors(String auth)
                public Authors(String auth1, String auth2)
           }

  • How to create table with variable

    hi,
    i m to create many table with same starting name but last name would be vary like
    i m to create table test121 and test122 and so on
    i want to set name test then any given number by variable so i can create many table.
    so how to add it in create table command.
    i tried create table test||:var (column names) but it didnt work.
    so plz suggest me how to do it ?
    thxs

    Actually this is good.
    It has nothing to do with database design. A database is not a garbage bin.
    You need to do several things
    a) make sure your design is normalized so you don't have identical tables.
    b) In future posts specify a platform and a version and the tool you are using to create the table
    c) if the tool is sql*plus learn about substitution variables aka DEFINEs.
    Sybrand Bakker
    Senior Oracle DBA

  • How to manage items withing categories?

    I want to be able to list and sort (in admin panel) all items in a web app or other area tagged with a specific category.  However, the Category listing option is alphabetical, and what if I have more than one category that starts with A?  for example:  "Apples" "Apricots".  If you have hundreds of items with different categories, it seems that you would need a way to sort them....
    And once I can get a list of category "Apples" items, how to filter based on the data in the fields?  Say customer entered "NO" to wanting a fruit item.  I would like to be able to sort of filter all "Apple" category items, that fruit field has "NO" value.
    And after I get that sorted view, how would I manage categories on these multiple items at once?  Say add another category "Veggies" and remove "Apples" from several items at once.  (can't do this manually if you have hundreds of items!
    Please help!!!

    Suppose i ve Form having Deptno Field and Ename field and both are List Item.... and I want in ename field list select those employee who are in selected Deptno on above list.
    WHEN-New-Form Instance.
    DECLARE
    CURSOR C1 IS
    SELECT Deptno FROM Dept;
    BEGIN
    FOR A IN C1 LOOP
    ADD_LIST_ELEMENT('block.deptno',1,A.deptno,A.deptno);
    END LOOP;
    END;
    DECLARE
    CURSOR C2 IS
    SELECT ename FROM emp where deptno=:block.deptno;
    BEGIN
    FOR B IN C2 LOOP
    ADD_LIST_ELEMENT('block.ename',1,B.ename,B.ename);
    END LOOP;
    END;
    Successfully Run
    Regards
    Danish Hayder

  • Request start with variable duration

    Hello All expert,
    i got one requirement that different plant want different request start duration after WF created.
    but i saw in WF it is a fixed value to input.Is there anyway to let it be variable?

    Hi Joshua
    the approach Murali mentioned is better to troubleshoot and maintain later on. Using Program Exits and troubleshooting them is a pain in the long run. Program Exits should only be used for STATUS based secondary processings.
    Best is to create an activity step with input as plant and output as Requested Start date and time. Within that step's code you can use the same code to read the config which you were planning to do in the program exit.
    Once you have the requested start date and time in the workflow container, you can use those container variables in the deadline monitoring of the subsequent step.
    Regards,
    Modak

  • How to create variant with  variable field

    i want ot creat a variant ..when selected  will  fill up the  last date of the  previous month in one  of the fields.This  will be the variant the user will  using always.I can't code in intialization part Because they have given the variant name. and don't want to see any initail value before entering the values

    Hi,
    SE38 -> Enter program
    Select Variants button and display. In the next screen, enter a variant name, (If not existing , press Create to create new one), else click on Change.
    Now the selection screen will display with a button "Variant Attributes" at the top.
    Click on that button.
    In the next screen, go to the selection variable column of the date field. Press F4 or drop down and select 'D' for date maintenance.
    In the column "Name of Variable (Input Only Using F4)" press F4 or drop down, select whichever kind of date calculation you want and save the variant.
    Now whenever you run the prgrm with this variant, date will be displayed by default.
    Regards,
    Subramanian

  • How to open Task with out UWL

    Dear Experts,
    I want to open task without UWL.
    Suppose we created one task for one user, that user what to open task means he needs to go to UWL and click on the task.
    Requirement is to open task my custom WebDynpro  application.
    How to Get the url of all work items in uwl for one user.
    How to develop my custom UWL application.
    Can any one please help me.... very urgent.......
    Regards,
    Satya

    Hi,
    Look at the [UWL API|https://help.sap.com/javadocs/NW04S/current/uw/index.html].
    Dick

  • How to manage itunes with two ipods

    I have two iPods, a 60G photo and a 30G video. I have two macs, one at work, the other at home. My iTunes on the work computer has about 50G of music, and about 15G on my home computer. Until now, I have only synced the big iPod with the work computer and small iPod at home. I just got a very big external drive, and want to keep everything there. That raises several questions I thought someone here might know how to answer.
    1) Where are the files so I can just copy them onto the ext hard drive? (I can probably find this for myself, but with my computer skills on mac, it will be frustrating, I imagine. Since I have the other questions, I thought htis one might be easy.)
    2) How can I merge the two files? I know I have some duplicates, adn I know how to get rid of them once the two are merged, but how do the two files merge together in one iTunes file on my new hard drive?
    3) Once the two are merged, can I set it so that certain types of music are put on one iPod, and other types on the other?
    Thanks a lot, in advance.
    Brad

    1. Click on the folder in the Finder's sidebar with the house icon, and then open the folder named Music. The iTunes folder inside is the default location of the music library; if the songs aren't here, follow these instructions to locate them.
    2. Drag the files into the Library section of the open iTunes application.
    3. Use the option in this article which best fits your needs.
    (22256)

Maybe you are looking for

  • External display sleep

    I have an LG l196wrtq 19 inch monitor hooked up to my macbook using the mini-dvi->vga adapter. The monitor seems to not be able to detect when i put my macbook to sleep and stays on with a message saying" check signal cable". I've called LG about it

  • Publish in Bex Broadcaster

    I created a web template , and clicked on publish in bex broadcaster. I got a pop up message to create the settings so I choose the wizard and typed the email address , schedule time etc. and executed. It did not work at first because the SMTP was no

  • Unable to download or update apps after ios7 update

    just downloaded ios7 software update and i can no longer install new apps or updates - when i press update it will either immiediately stop and go back to the update button, other times the circle will go round a bit then ask for me to sign in but th

  • HTTP Status 404 - wwv_flow_custom_auth_std.logout is not allowed.

    Hi, Toady, if i tried to log out from my Application(s) or Apex Developer this error occur: HTTP Status 404 - Requested url http://XX.XX.XX.XX:XXXX/apex/wwv_flow_custom_auth_std.logout is not allowed. My spec: APEX 4.0.2 Apex Listener Apache Tomcat F

  • How to create a Pivot table without aggregate function

    Dear team I have the following table. Follow the link to download SQL Script to create table https://drive.google.com/file/d/0B5nQIsvTifixV2Jkb043bVd2Zlk/view?usp=sharing I want to create a pivot or cross tab so that it appear like this LocationDesc