How to remove Batch Management Check in the Material

I have one requirement to remove batch management check in the materials which should not be deleted.
I created a testing material with batch management check on and put in material through 561, then did good issue for
scrapping to remove the stock out. So existing stock is zero in Material Master.
Then deleted the batch in MSC2N by putting all the delete checks on. There was just one batch created for the material.
Then ran transaction MM74 to archive, the spool request is as below:
MCHB: 000000000010000498 2002 1002 D000000200 entry archived                             1 000000000010000498
Archiving Session Number                                  000004
Number of Written Data Objects                                1
Size of Archiving Session in MB                           0,011
Proportion of Header Data in %                             96,7
Then in MMPV changed the closing period to may as all the postings were performed in april.
Now still when I go and remove the batch management check in MM02 Purchasing view, still gives we DISPLAY ERROR message:
The batch management requirement cannot
be changed for the follow
Batches already exist.
ANY IDEAS why its not allowing me to remove the check as I guess I have performed all the steps required.

Check whether the batch master is still exists in MSC3N .if it ia archived it should not be avialble in MSC3N
Refer note:30656
Reason and Prerequisites
The message that stocks still exist refers not only to stocks in the current period, but also to stocks in the previous period.
The reason for checking previous period stocks is that postings can also be made to the previous period when entering goods movements. This would result in inconsistencies if the base unit of measure had meanwhile been changed.
Solution
Check whether stocks still exist for the previous period by displaying; for example, the plant stock view or storage location stock view of the material. You do this by selecting "Extras -> Previous period -> Prev. pd SLoc. stock or Prev. pd plant stock".
If previous period stocks exist, you can make a withdrawal posting as follows:
1. Post the same amount to current period stock (for example, using movement type 561) so that previous period stock and current period stock are identical.
2. Make a withdrawal posting in the previous period for the stock together with posting date (for example, using movement type 562).
You can now try to change the base unit of measure or the batch management requirement indicator again.
Since the posting of the previous period values to zero is identical with posting to the stocks of the current period, you should reverse the above stock postings (that is, the stock from the previous period should be booked in again) to make sure that the stock values from the previous and the current periods correspond to the state before the change. However, note that the postings are then carried out using the changed master data from the current period (for example, account determination and so on)

Similar Messages

  • Activation of the Batch management check in the Material master

    Dear All,
    Here I have one query
    Can we able to activate the Batch management check in the material master-->Purchaging view or not,
    if we have open or completed sales documents and deliveries for that materail.
    Reply ASAP
    Regards,
    Murali.

    Hi Murali ,
    you can very well do it . in fact we have done the same with our client.
    check below article .
    https://www.sdn.sap.com/irj/scn/index?rid=/library/uuid/b009b1e5-f3df-2b10-7289-ff87d139dce1
    Regards
    Ravi.

  • How to remove Batch Management in the Material

    Hi All,
    The Batch Management indicator for a Material was accidentally activated, thus upon goods movement the system required user to enter a Batch Number. The user, not knowing the implications, entered a Batch Number.
    Now we want to remove the Batch Management indicator, I already asked the user to reverse the goods movement posted and have the Batch Number flagged for deletion at both Plant and Storage Location Level via MSC2N.
    MM02 still won't allow the removal of the tick mark in the indicator.
    There are options I have looked at:
    1) Create a new Material Code in place of the old one.
    2) Archive the Batch Number then try to remove the tick mark via MM02 - will this even work out?
    But the priority is still to retain the same Material Code. Is there any other way/option?
    Thanks a lot!!! =)

    It is a little painful but here are the basic steps.
    Remove all stock.
    Cancel all demand, no requisitions, no purchase orders,
    production orders etc. Transaction MD04 must be empty.
    Use transaction MSC2N to place a deletion indicator on every
    past batch for that material prior to the end of your fiscal period or
    month.
    Run transaction MM74 to archive the "flagged for deletion" batch
    numbers.
    In the next period or month go to transaction MM02 and remove
    the batch flag from the material master.
    hope it helps

  • How to Remove batch mangement indicator from Material Master

    Hi
    I am trying to remove batch mangement indicator from Material master..but system does not allow
    Before this .. I have done all activities also ...clear open SD documnets ,deliveriy documents ,PO documents ,Process order teco and . reservations and activae deletion flag in  batch  ... and made current period  stock an previous period  stock zero... i have cleard all documnets ...still system does not allow remove indicator..could you please guide in this issue ..how to remove batch indicator.
    Regards
    Sasi

    Hi,
    Please refer the below links.
    Re: untick Batch Manegement Indicator on Material Master
    Remove batch management flag and deletion of material documents
    How to remove Batch Management in the Material
    Re: How to remove Batch Management Check in the Material
    Thanks.

  • Batch management check activation

    Dear All,
    Here I have one query
    Can we able to activate the Batch management check in the material master-->Purchaging view, if we have open or completed sales documents and deliveries for that materail.
    Reply ASAP
    Regards,
    Murali.

    Hi,
    If there are open sales orders, production orders, deliveries and WM transfer orders exists then you can't activate the batch management indicator. Also any stock exists in the present or past period, you can't activate.
    Go through SAP notes 533276 - Setting the batch management requirement indicator and  30656 - Change base unit of measure/batch mngt requirement for details.
    Check details in MM forum threads also.
    Regards

  • How to deactivate batch management at material master?

    Dear Sir/Madam,
    At the configuration,I have set "Batch Management" to be activated in plant level.  I have a problem which some of the plants do not use batch management.I understand that if you tick "Batch Management" field in material master, batch management is activated for the material in that plant.
    1. How do prevent user to tick "Batch Management" field in the material master which appears in the following views (depending on the material types):?
    - Sales: General/Plant
    - Purchasing
    - Plant data/Stor.1
    - Work Scheduling
    2. Is there any alternate way to prevent user to activate "Batch Management" in that material of their own plant despite it is activated at plant level in the configuration?
    Please advise.
    Thanks.
    Rgds,
    Esther Chong

    batch status management is just what its name says, you manage your batches with status (unreastricted use, restricted use).
    But his comes only into place after you have activated batch managment, it is not causing batch managment, it is only working with batch managment.
    Removing batch managment is almost impossible, you have to archive all batches first, to be able to archive the batches, you have to archive the production orders...creation of a new material is in most cases easier and quicker.
    Wit batch managment at plant level each plant can independently decide if a material is batch managed or not.
    if you want to restrict the entry of the batch management flag, then you have to customize your material master field selection at plant level.

  • How to Setup Batch Management Level (Material vs Client)

    Hi Experts,
    I had a question about the level at which I should be setting up Batch Management. The requirements that we have are:
    - We want uniqueness in the batch being created.
    - We have split valuation active at the Batch Level.
    Hence, we have nailed down to the following 2 options: 1. Client level or 2. Material level. (I know that I will not be using Plant level because we do a lot of STO's and we do not want to lose the characteristics in the Batch at the plant level. So the plant level is out of scope.)
    Client Level: Although the client level gives us the uniqueness and supports most of our requirements, my fear with going at the client level is that it is too rigid and MAY cause problems in the future. Is that true? What would be issues/ concerns that you have faced when you have had Batch Management activated at the client level.
    Material Level: If I setup the system at this level, I would like to be able to create a Batch number for a material across the entire client only once. E.g. MAT1 can have BATCH 123 only once across the whole client. MAT 2 can have BATCH 123 but the Material# and the Batch # uniqueness should be maintained thoroughly.
    I would like to try out this level but my problem is I am unable to understand and setup this level completely. I have gone through some pretty good discussion on this topic but still am unable to understand it thoroughly. The link to this discussion is (http://www.sapfans.com/forums/viewtopic.php?f=27&t=80407). If you refer to this link, it says u2013 Client/ Material Level. What does client/material level mean? Can you please help me understand it. Also, if I setup Batch management at this level, I would like the system to auto-generate numbers for me exactly as I have mentioned above. Is there a way to do so? I was trying to setup the BATCH_MAT number range object with the batch level at Material level but the system seems to always default to the BATCH_CLT level and give us numbers. Is there a way to fix the system to check the BATCH_MAT number range object and give the batch numbering per my requirements. What happens if I use the Material Level Batch management with BATCH_CLT number range object?
    Your help is highly appreciated.
    Edited by: TV_SINR on Jul 16, 2010 8:52 PM

    Check following customizing:
    Logistics General --> Batch Management --> Specify Batch Level and Activate Status Management
    If you want to change the batch level, you have to start conversion to activate the change.
    Note that you cannot reset conversion from plant level to a higher level, read the documentation for customizing of
    "Specify Batch Level and Activate Status Management".
    If you want to work with same batches for different materials, you should use "Batch unique at material level".
    Logistics General --> Batch Management --> Batch Number Assignment
    Here you can define how the system should create batch numbers.
    Best Regards, Dirk

  • How to Remeove Batch Management in Material Master

    hi!
    I want to remove the 'Batch management* for a material
    Made stock as 0 and reversed all its relating documents.
    but its display error as
    *The batch management requirement cannot   *
    be changed for the following reasons:
                                                                                    Batches already exist.
    how to remove the Batch management
    Regards,
    Kv

    Hi
    The error tells that some documents are stii pending in previous /current posting period.
    Pl.find that through Mb 51 ( Input only plant).
    Reverse these document also and proceed

  • Remove Batch Management and Split Valuation Dependencies

    Hi,
    I need to remove Batch Management Indicator and Split Valuation for a material. Which one should I do first? Are these dependent on one another?
    Thanks,
    Jograd

    You are correct. It did cause lots of error when i tried to do it in test client.
    I am trying to remove the valuation category of one right now. It has zero stock and no open documents.
    I saw in note Note 155874 - Change valuation category in material master that you need to do this:
    2. If you change from split to joint valuation, no valuation data must
    exist for a valuation type.
    I dont know where to start doing that? Because there is not data for the material. However i noticed that there is valuation for previous period. do i need to delete that too? But there are no stocks for the previous period.
    Please help.
    Thanks,
    Jograd

  • How to remove Seperator from check-in and profile check in pages

    How to remove Seperator from check-in and profile check in pages
    The seperator is included on the checkin pages, which is present in the std_page with name "std_namevalue_separator", this is called by td_document_checkin_fields and std_document_file_fields.
    Defination of include:
    <@dynamichtml std_namevalue_separator@>
    <$if not isUploadFieldScript$>
    <tr>
         <td width="<$captionFieldWidth$>"><hr /></td>
         <td width="<$captionEntryWidth$>"><hr /></td>
    </tr>
    <$endif$>
    <@end@>
    I have to remove the following include from some of the profile check in page.
    Please suggest if anyone have some idea, how to proceed.
    Thanks,
    Sumit

    791848 wrote:I have to remove the following include from some of the profile check in page.The key here is that you want to do this in some profiles, not all profiles or globally, if I'm reading this right.
    Without writing a component, you can put this code in the "side effects" box in the desired profile(s). This code removes the horizontal rule, and inserts a non breaking space in its place.
    <$setResourceInclude("std_namevalue_separator","<$if not isUploadFieldScript$>
    <tr>
    <td width=\"<$captionFieldWidth$>\"> </td>
    <td width=\"<$captionEntryWidth$>\"> </td>
    </tr>
    <$endif$>")$>YMMV. The non-breaking space may get stripped out in the forum.

  • How do you manually manage podcasts with the new iTunes?

    Like the subject line says: How do you manually manage podcasts with the new iTunes?
    With the previous version of iTunes, when I plugged in my iPod, I could select the iPod, select podcasts, and manually delete episodes. With the new iTunes, I can't select individual episodes when looking at my iPod through iTunes. Is my only option to Sync? If so, why is that my only option?
    This question probably has a simple answer, and I'm just not seeing it.

    Rock,
    I think I figured out a way to do what you want to do - which is the same way that I use Itunes with my Ipod. (My Itunes libary was destroyed last year so I can no longer auto synch my Ipod as I would lose thousands of songs).
    Funnily enough, I discovered this new way of manually moving podcasts while trying to figure out what cpragman was trying to say (I never could - he must be smarter than me, as I couldn't get his method to work).
    1. Open up your Itunes in your regular Library view. Choose Pocasts from the left hand side (either in the sidebar if you have that enabled, or from the little "radio" icon if you don't.)
    2. Mouse to the podcast you want to place on your Ipod.
    3. Right-click it.  A long menu will pop up.
    4. Move to the "Add to Playlist" option.  As you hover, all your playlists will be visible. But at the very top will be the name of your Ipod itself (whatever you named it originally).  Choose THAT name, and voila! That podcast will now copy to your Ipod and be easily available when you disconnect.
    A nice feature of this method is that you can shift-click several podcasts at once and do the same thing, and all your selected podcasts will copy over (if you're like me and update your Ipod only every few weeks).
    Hope this helps - let me know if it works for you!

  • How to remove my credit card from the App Store

    How to remove my credit card from the App Store

    I used a pre-loaded credit card so when it ran out i had problems, primarily because it wont let me download or update anything until the "billing problem with the last transaction" was resolved. I dont really care if the purchase goes through but i want to be able to update stuff again and it wont give me the option to select 'none' under payment type. do i have to put another card on there just so i can "resolve the billing problem" and then i have  to take it off again or is there a way around this or is it a never ending cycle?

  • Any ideas on how to remove a small scratch from the screen or whether it is covered by apple?

    Any ideas on how to remove a small scratch from the screen or whether it is covered by apple?

    Call Apple Care and ask them if your computer is still under warranty. 

  • Batch Management appearing mandatory in material master

    Dear Friends ,
    I am getting batch management tick mandatory while creating material master , In OMS9 for field sel grp optional 01 ,I have made field reference for mm01 as optional, but still its showing batch management  mandatory while creating material master
    Thanks in advance

    Hi,
    If you have checked Field reference  ROH ( as material created with material type ROM & ROH assigned Field reference  ROH),the field selection group 75 optional entry.
    Then , now check *Field reference for material master in assigned to industry sector( the material created with) in t.code: OMS3 and here also make selection group 75 optional entry for *Field reference for material master in OMS9
    Also make selection group 75 optional entry  in OMS9 for for Field reference MM01 & 0001
    Now try creating material master.
    Regards,
    Biju K

  • WHILE CREATING PURCHASE REQUISITION,THE AVAILABILITY CHECK FOR THE MATERIAL

    dear Friends,
    our users want to  WHILE CREATING PURCHASE REQUISITION,THE AVAILABILITY CHECK FOR THE MATERIAL SHOULD BE ENABLE,
    at present we maintaing KP in Material Master.  if we activated what will happen?
    please advice.
    with regards,
    Rajesh G

    Hi,
    The availability check is generally used for goods movements(GR,GI,reservation) & not for PRs.
    Regards,
    Vijay