HR Organisation UNIT hierarchy

Hi guys,
I have an Organisation Number , and I need a function which gives me all the organisations it belongs to in the Organisation structure, i.e the upward hierarchy ( Organisation Number ) as well as the downward hierarchy ( Organisation Number ).
Kindly provide me with an FM or a sample code on how do i go about this.
Thanks and regards,
Frank

Hi Frank,
Please try this Function Module GET_ORG_UNITS.
U can also find some more Function modules in SE37 Transaction code.
Goto SE37 and give GETORGUNIT in input field and click on F4 function key, u will get the function modules related to the Organizational Unit
Hope this helps...
Best regards,
raam

Similar Messages

  • How to find out Head of own organisational unit in organisation

    How to find out Head of own organisational unit in organisation
    Hierarchy after giving the transaction oopoma_crm?

    Hi,
    try RH_GET_LEADER
    Then you'll get the CP. Then get the BP number, that should be CRM_CENTRALPERSON_GET.
    Regards
    Andreas

  • Impact of moving a user from one organisational unit to another.

    Hi
    my system description :
    extended classic
    srm 5.00
    I am new to srm and i would have some questions about the impact of moving a user from one organisational unit to another.
    The senario is that:
    I have moved a user from organisational unit X  to Y lets say different purchasing organisation
    The user had PO created in organisational unit X waiting for goods receipt but even if he is now in organisational unit Y he can still create the good receipt for the PO created in organisational unit X .
    Is it ok?
    Futhermore not only can he create good receipt but the good receipt take the cost center assigned in organisational unit Y whereas the PO has the cost center of organisation X.
    I believe that is how the confirmation works in SRM. However is there a way for it to take  account assignment from the PO instead of where the user is situated in the org hierarchy when doing confirmation.
    Thanks

    Thanks for your answers
    Maybe i should explain how the user was moved.
    I did not used users_gen because i didn't want the user's partner ID to be changed.  If the partner ID is changed then the user would not  be able to access PO from old Organisation Unit. (can somebody confirm this please)
    I did right click on the wanted Organisation Unit then assign the user.  The problem is that the relationship between the user partner ID and the new organisation unit was not maintained and the user could not create shopping cart in the new organisation unit. 
    To solve this issue oss note 1041701 was implemented and the issue was solved.
    But before the the implementation of oss note  1041701, if the user had open items from old organisational unit he could not access PO thus could not confirm goods receipt when moved in new organisation unit.
    Now this is possible he can confirm goods from old unit but the confirmation is done using cost centre of user instead of the cost centre of the PO.
    Jagadish you said that the confirmation must be done using PO accounting details not the user attributes.  Then i think i have a problem in my system.
    regards,
    yannick.

  • Error While Opening dataform after creating Planning Unit Hierarchy

    Hi All,
    I created a Planning Application through classic wizard. Then i created a planning unit hierarchy, after which I am getting the following error: (when i try to open a dataform, from some user other than admin/owner)
    *"Security and/or filtering has resulted in a required dimension not being represented on this data form"*
    I know that this error occurs when some dimension members are represented on dataform but are not assigned with security rights. But thats not the problem in my case. Because I assign security rights to all members of all dimension just for the sake of testing. I later on identifed that this error occurs due to dimensions present in POV i.e. I need to select a single member of each POV dimensions, then in such case this error disappears.
    Now my question is that why i need to select a single member from each POV dimension? I general i leave POV dimensions as it is, while creating dataform
    Right now i aad a dummy member at the top of each dimension, e.g Account_UnSpecified, Entity_UnSpecified and so on . . . and then i select this member from each of POV dimension.

    Hi,
    You can try creating new Root folder and new workspace for your NWDS.
    1.  Create a new folder with name ' <userID>_NWDS_NEW_ROOT ' in your machine
    2. Create a new folder with name ' <userID>_NWDS_NEW_WORKSPACE ' in your machine
    3. Open NWDS (and logon to DTR)
    4. Remove all configurations from your Development Configuration perspective (except 'Local Development')
    5. Go to Window --> Preferences --> Java Development Infra --> Development Configurations
    6. Change 'Root Folder' to the folder created in step-1
    7. Close NWDS
    8. Create ' Run_NWDS.bat ' file in your NWDS installation folder which has 'SapIde.exe' file
    (it will be generally in --> C:\Program Files\SAP\IDE\IDE70\eclipse)
    9. Type following in .bat file -->
    SapIde.exe -data "<complete path to folder created in step-2>"
    10. Now double click on this .bat file to open NWDS
    Now logon to DTR, import configuration, create project from 'inactive DCs' and you should be able to create project and see it in respective perspective.
    Regards,
    Amey

  • Org unit Hierarchy structure between two  Key date s

    Hello Friends,
    We have an issue with displaying HR Org unit hierarchy structure between two calendar months.
    The BI Report has a selection parameter to select Org unit hierarchy , Calendar month From and Calendar month To
    The BI Report is to display the no.of sick absence days for employees in a chosen Org unit hier.
    Employee A had a sick absence of 5 days in the month 04.2011 in the Org unit X . The same employee had a sick absence of 4 days in 05.2011.The Org unit X then delimit in 05.2011 , the Org unit X is no longer in Org structure from 05.2011.
    When we run the report for 04.2011 to 04.2011 , the employee A is showing absence under Correct Org unit ie X with correct Org structure .
    When we run the Report for 05.2011 to 05.2011 , the employee A is showing absence under hierarchy Org unit Not assigned which is OK .
    But the issue is when we run the Report from 04.2011 to 05.2011 , The employee A absence days 9 (5 +4 ) showing under Not assigned Org unit hierarchy structure which is the latest Org unit .
    When I deactivate the Org unit hierarchy and choose tech name of Org unit , It is showing correct Org unit key
    But The user would like to see 5 days under org unit X and 4 days under Not assigned with Correct Org unit hier structure when we run the Report from 04.2011 to 05..2011 .
    We have a user Exit variable for the Key date in the Bex Report which seems to be taking only one date at any time .
    Is there any way to get the correct figures under Org unit hier structure where employee had absence in when we put range of calendar months on a selection screen ?
    Any advice appreciated.
    Thanks.

    Hi
    Yes, we can display the same by using time dependent hierachy's i.e. your org is converted to time dependent so that respective employee shows with respective of time.
    Regards
    Jagadeesh.M

  • Org unit Hierarchy structure  at Key date

    Hello Friends,
    We have an issue with  displaying HR Org unit hierarchy structure  between two calendar months.
    The BI Report has a selection parameter to select Org unit hierarchy , Calendar month From  and Calendar month To
    The BI Report is  to display the no.of sick absence days for employees in a chosen Org unit hier.
    Employee  A had a sick absence of 5 days  in  the month 04.2011  in the Org unit X .  The same employee had a sick absence of 4 days in 05.2011.The Org unit X then delimit in 05.2011 , the Org unit X is no longer in Org structure from 05.2011.
    When we run the report for 04.2011  to 04.2011 , the employee A is showing  absence   under Correct Org unit ie X with correct Org structure .
    When  we run the Report for 05.2011 to 05.2011 , the employee A is showing absence under  hierarchy Org unit Not assigned which is OK .
    But the issue is when we run the Report from 04.2011 to 05.2011 , The employee A absence days 9 (5 +4 ) showing under Not assigned Org unit hierarchy structure which is  the latest Org unit .
    When I deactivate the Org unit hierarchy  and choose tech name of Org unit , It is showing correct Org unit key
    But The user would like to see 5 days under org unit X  and 4 days under Not assigned with  Correct Org unit hier structure  when we run the Report from 04.2011 to 05..2011  .
    We have a user Exit variable  for  the Key date  in the Bex Report  which  seems to be taking only one date at any time .
    Is  there any way to get the correct figures under Org unit hier structure where  employee had absence in when we put range of calendar months on a selection screen ?
    Any advice appreciated.
    Thanks.

    Hi,
    You can try adding two more attributes to Org Unit as "Calender month from" and "Calender month to".
    In these attributes maintain the validity period for the corresponding master data.
    For example, in your case you can maintain the master data as:
    Employee | Org Unit | Calender month from |Calender month to | sick absence
    A | X | 4.2011| 4.2011 | 5 days
    A |    | 5.2011 | 05.2011 | 4 days
    And in report use variables for Calender month from" and "Calender month to".
    Hence, when user executes the report with selection as:
    Calender month from" = 04.2011
    "Calender month to"    =  05.2011
    The data will be read from master data based on these selections along with key date and report will show output as expected.
    Employee | Org Unit | Calender month from |Calender month to | sick absence
    A | X | 4.2011| 4.2011 | 5 days
    A |    | 5.2011 | 05.2011 | 4 days
    Hope this works for you.
    Regards,
    Geetanjali

  • Organisational unit for asset master record

    Hi,
    Which organisational units do you manage in the asset master record ?
    Thanks
    Kalyan

    Hello
    Company code / Controlling Area / Plant / Sales Organisation /
    Reg
    assign pts if useful

  • WORKFLOW, organisational unit name

    Hi,
    I am making use of FM 'SAP_WAPI_WORKITEM_RECIPIENTS' with input as workitem id and user name. I am getting the organisational unit, but the problem is it gives only the number of the organisational unit.
    Is there any FM which after giving the organisational unit number will give me the description/short text for the organisational unit.
    Report 'RHSHOWOR' gives the description, but it takes the user name only and shows all the org unit specified for the user, I want the description for a single org unit.
    Relevant answers will be rewarded.
    Thanks in advance.
    Regards,
    Neerup.

    Thanks for the quick reply.
    The table T527X does not exist in my system.
    I am checking other stuffs from the link : http://help.sap.com/saphelp_nwpi71/helpdata/en/c5/e4b239453d11d189430000e829fbbd/frameset.htm
    Is there any standard SAP provided FM, which will give me the description, or can you please suggest some other table.
    Thanks and Regards,
    Neerup.

  • User In Planning unit Hierarchy unable to see data form in editable mode

    hi all,
    we are facing a problem in planning unit hierarchy in Hyperion planning, where we have 4 users, Hierarchy is define as
    hierarchy: budget approved
    version: approved
    Entity: Finance
    Senario:Budget
    haroon asghar ( owner)
    adeel javid (Reviewer)
    Naeem asghar (Reviewer)
    Imtiaz (Reviewer)
    Issue is that,after start the budget activity (promotional path) by Admin, the data form editable to Owner haroon asghar
    but after completing his work by haroon,when he promote the planning unit ,the next user in Hierarchy "Adeel javid" unable to see data form in respective planning unit in uneditable data form not only for this user but all rest of the users as well,while i think data form should only uneditable(grayed) for user Haroon Asghar who promote the planning unit.
    we have checked all security rights to the users those are "Write access" but still Adeel javid is unable to enter data,so the budget activity is stop due to this problem.
    when i remove the planning unit then i log in with all user one by one and see all data form required version,scenario and entity were editable to all users mention above
    we want to run budget activity with the above planning unit hierarchy.
    plz any one provide the proposed solution of the said issue
    we are using Product Version     11.1.2.0.00
    Regards
    Anwar

    Reviewers will not be able to write data to the intersection. Reviewers can only review the data and follow-up with a Reject, Promote, Sign off, Delegate, Originate or Freeze.
    Please refer Article ID 1226783.1 in MOS.
    HTH-
    Jasmine.

  • Database table dip organizational unit hierarchy

    Hi, All!
    Is it possible to add organizational unit hierarchy to DIP based on database table while importing from DB table?
    Thanks!

    Hi!
    Yes, I know that map file should be used. But how?
    I have plain table with users with for example following fields: id, login, pwd, mail, OU and so on...
    DomainRules
    NONLDAP:ou=myusers,dc=my,dc=comp:uid=%,ou=myusers,dc=my,dc=comp
    AttributeRules
    ou: : :ou: ou: : organizationalUnit
    dc: : :domain:dc: :domain
    id: : : :employeenumber: :inetOrgperson
    login: : : :cn: :person
    But I can't create OU and users in required OU (as mentioned in DB record), all users created in "ou=myusers,dc=my,dc=comp".

  • Organizational Unit Hierarchy in Universe

    Hi expert,
    I created a Universe from a query, in a query I have this Organizational Unit Hierarchy in the row column. In the Universe, I can see the Hierarchy name here but there is not L00 shown in the hierarchy and the level is starting from L01 to L07. After the Universe is created here, I created the report using Web Intelligence, when I add this L01 hierarchy in the report, I cannot see any data.
    Does anyone here know why? I am new to this Universe and Web Intelligience.
    Thanks!

    Hi King,
    When you generate a universe from a BEX query, you have to specify whether or not you want to generate a level 0 or not.
    If you do not have the L00, you didn't op to do so. You can do this in a refresh structure or with a fresh generate (in the latter case, check your defaults).
    Now L00 will be the "all" level. So that may not be your problem.
    Did you select at least a key figure in your webI query?
    Test what results you get for certain selections when you run the BEX query directly.
    Then using the same conditions, you should get the same results in WebI.
    Good luck,
    Marianne

  • BEx Query Help   How to restrict  Organisation Unit  Like 'D%'    in Bex

    Hi all ,
    In a cube i have a columb   ORGUNIT     which is having Values from
    A_152,
    A8373 ,
    D_983,
    B_0293,
    C09 ,
    D6653 .
    In bex Query Designer I want to restric that infoobject  & organisation unit which is starting with 'D' .
    means  output will be   :  D_983 ,
                                            D6653
    ABAP statement    for this             ORGUNIT  LIKE 'D%' .
    how we do same in BI restriction .
    Thanks Regards
    Sanjeev Kumar
    Edited by: skarya2003 on Dec 6, 2009 9:01 AM

    Hi,
       Try using customer exit .
      chk out this doc which helps u,  http://www.sdn.sap.com/irj/scn/index?rid=/library/uuid/90f8b363-882d-2c10-ea91-9f08ce4c658a&overridelayout=true
    Regards,
    Priya.

  • Explode document distribution list / organisational unit

    I have configured document distribution. I am able to send mails through document distribution. However, I want to send mail to a group of users. Hence I have created an organisational unit with different positions and I have captured the e-mail addresses of the users in the respective positions. However when I capture the organisational unit as a recipient the following error message appears "  Orginizational unit/distribution list <Scroll Approver> contains no
    recipients". Also I am not able to explode the organisatinal unit.
    Please advise.

    Hello Sudha,
    currently i have the same problem (i want to send e-mails to an organizational unit). Did you solve the problem?
    Thanks and Regards,
    Christian
    Edited by: Christian Blatt on Apr 23, 2009 8:14 AM

  • Organizing dimensions for organisational units

    Hi Gurus,
    I discovered that in one development project, one star schema with its dimensions has a dimension "organisational units".
    In this dimension are all units put together and those units are also in the InfoCube.
    That means in one dimension is available:
    Company code
    Credit control area
    Customer number
    Profit Center
    Business unit
    Business segment
    Sales organisation
    Sales division
    Distribution channel
    Does this make sense?
    I mean will the system allow to make correct selections/drill downs etc. with those adjustments?
    As the development is still in progess I would make a suggestion to partition the dimension "organisational units" into following dimensions:
    Company code
    Credit control area
    Company code
    Customer
    Customer number
    Profit Center
    Profit center
    Business segment
    Business unit
    Sales organisation
    Sales organisation
    Distribution channel
    Sales division
    I think this would make more sense ...
    Correct?
    Thanks in advance!

    Hi Suman,
    I am really new to BW and my subject is more at report level i.e. creating queries.
    Currently I am learning more about modeling and so on to get a better technical understanding.
    For my understanding and respective to the four dimensions above (when they are separated) and for example key figure turn over is available.
    With this scenario it would be possible to analyze the turn over in relation to for example:
    customer, business unit and sales division.
    But what is the difference when the dimension customer is separated and the other three are clubbed together?
    Isn't the same mentioned analysis possible?
    It should be possible to achieve the same result I think because only the granularity of the clubbed dimensions would be more granular and the dimension would be bigger.
    Does my understanding make sense?
    Thanks in advance!

  • Head of Own Organisational Unit

    Hi,
    When I unchecked the Head of Own Organisation Unit field for existing Manager under Basic Data, still I can see the Red Cap as Icon for the same Manager.  Please let me know the reason and how to fix the same.
    Thanks
    Rajesh K

    Hi Rajesh,
    1.     Re-check in PPOMA_BBP will see existing manager as uncapped.
    2.     Check your org structure using tcode USERS_GEN.
    3.     Delete mentioned manager & add it again as normal employee.
    I hope mentioned ways will certainly resolve your issue.
    Regards,
    yaniVy
    reward if helps