Hi,
I am creating a purchase order for a material with account assigned as Order.
I have maintained a substitution wherein from a cost center Internal Order is derived.
I have created an Internal Order with Category - Overhead and activated the availability control for the Order. Also maintained the Budget for the Internal Order.
Now when I am creating the Purchase Order and giving the Cost center, it is deriving the Internal order but not doing the availability check.
What can be the issue in terms of Configuration or Am I missing any steps.
Please help
Regards
Kami

Thanks Eli,
If I activate the committment Management at Controlling Area level and the order type, the budget will be consumed at the Purchase Order level itself. I hope I am right ?
But I want , at PO level only the control and check (in terms of error message and the system should not allow me to save the PO) and not the consumption of budget. I want to utilise the budget only at the time of issuance of the materials.
Can we achieve this without Committment management active or is it mandatory?
Any help on this.
Thanks and regards
Kami

Similar Messages

  • Production order overlapping with purchase orders for outside process

    I set up the overlap option in a router so we can send 50 pieces (total order quantity is 200) of material ahead to an outside heat treat operation.  When we try to create the purchase order for the 50 to be sent out for heat treat two problems occur.
    1. The quatity in the purchase order is for the entire order of 200, not 50.
    2. We get a message "Date /23/2010 period D is not valid.
    We currently do not use the functionality of splits and overlaps so if anyone can help or guide me to a good resource I would appreciate it.
    Regards.
    Gail
    Edited by: Gail Weeks on Nov 12, 2010 4:19 PM
    If anyone could help with this question I'd appreciate it. Thanks.

    Gail:
    the next operation would be an external operation in your order ? That is, has some external Operation Control Key?
    Then the PurReq for this operation is created at creation or release of the production order by the total operation quantity. Ovelapping allows you to reduce some total time in order, but I don think that can be applied for the purpose you describe. Let us know more details about your requirement.
    Regards

  • KO22 explain with Purchase Order

    Please explain, how KO22 (Original Budget related  with Purchase order, Using Internal Order)

    Hi,
    When you create an budget for 1000 and a PO for 500. (say you have set up a max from 10 %) You make a new PO for 600 there is no problem but it is not possible to create a new one for 601.
    The rule is Budget - postings - PO = ammount to go.
    It is possible to exclude som g/l account. and create fases,  Like budget is on:
    100 procent message and send a Mail
    110 error
    Paul

  • Print document type Q02( technical delivery terms)  with Purchase Order

    Hi all
    1) I have activated the QM procurement for a certain material and I have assigned the control key that makes mandatory the technical delivery terms on the material master (standard control key 0002).
    2) I have created a Document Info Record Q02 to hold the Technical Delivery Terms assigning a PDF file. Document is released.
    3) I have assigned the DIR to the material master (object link in the DIR).
    I would like to know how to print the this DIR with Purchase Order. I am testing this scenario in IDES system and the form does not get printed.
    Could anyone please advice how to get the PDF file printed with the purchase order?
    Thank you

    Hi Sappmqm,
    There is no internal way, you would have to create an ABAP program to handle this function, where it would search the material record to pull the DIRs linked and then open them on user's screen for printing.
    Additional SAP add-ons are available as 3rd party apps, can click my name and contact me for more detail if you like.
    Good luck.

  • Statistical Internal Order on a Purchase Order

    Hi,
    We are trying to use a statistical internal order on a purchase order along with a real cost center. But we are unable to get the internal order to show up on the FI documents being posted using goods receipt.
    Purchase Order has been created with 'F" (order) as the account category. On the account assignment tab we have maitained an expense cost element & real cost center & statistical internal order.
    Internal order master data has been created with just the company code and object class as OCOST.
    Please let me know what we are doing incorrectly and how can we have the statistical internal order show up on the FI document.
    Thanks,
    Venkat

    Hi Venkat,
    Statistical Internal order doesn't work if GL account used is not a cost element. You need to make your GL account as cost element. If the respective GL account doen not need to be cost element then you can make it statistical cost element with category 90. In this case it'll not ask for CO object or it'll not create any error or issues.
    Hope it'll work.
    Thanks,
    - Mahak
    Edited by: Mahak Birla Mantri on Jun 15, 2009 11:34 AM

  • How to link asset with purchase order and PO Item.

    Hello,
           I have to generate a report which contains columns
    Asset No , po no(ebeln) ,PO Item(ebelp),Material no etc
    My query is how to link asset with purchase order and      PO Item.
    I am selecting asset and po no. from anla  but how to get
    po item no(ebelp)?
    po line item is important in this report because every line item has differrent asset and material no.
    i tried to match asset no in mseg table but i am not getting asset no in mseg .
    how should i proceed ?

    Thanks Thomas & Srimanta for the quick response.
    When I checked EKKN table by entering PO there is no asset no. in anln1 field.
    Also I would like to add that, In me23n for a PO, account assignment category we are entering 'F' for internal order settlement.
    Where can i find the link between asset and po no(ebeln) and po item(ebelp)?
    Regards,
    Rachel
    Edited by: Rachel on Aug 11, 2008 7:23 AM

  • Vendor postings with purchase order

    hi,
    I am learning SAP Fi/co.I have one doubt .what are steps we have to maintain to post vendor transactions with purchase order.if u have any material about mm plz send to me.

    Commitment
    Definition
    Identifies costs that will be incurred in the future for materials and services that you have requested or ordered. Commitments reserve funds that will become costs at a future date.
    Use
    On the account assignment objects, Commitments Management portrays the cost side of the procurement process for MM Purchasing. The costs incurred are assigned to business objects, such as orders, cost centers, or projects.
    In Commitments Management, you can specify which object the costs are to be assigned to (for example, purchase order costs). In this case, this is known as an Initial Account Assignment.
    Commitments Management distinguishes between three types of commitments, depending on the account assignment object:
    Order Commitment:
    The commitment is initially assigned to an order.
    Cost Center Commitment:
    The commitment is initially assigned to a cost center.
    Project Commitment:
    The commitment is initially assigned to a project, or to a work breakdown structure element.
    For more information, see the SAP Library:
    For Internal Orders
    Financials ® Controlling ® Internal orders ®  Manual Actual Postings On Internal Orders.
    For Cost Center Accounting
    Financials ® Controlling ® Cost Center Accounting ®  Manual Actual Postings.
    For Project System
    Financials ® Controlling ®  Commitments/Actual Updates Of Transaction Data
    Integration
    Commitments occur
    In Purchasing, due to:
    Purchase requisitions (purchase requisition commitment) define the internal requirement for a material or a service. Purchase requisitions have a control function and you change them at any time.
    Purchase orders (purchase order commitment):
    Purchase orders are contractual requests to a vendor, to supply certain goods or services according to the agreed conditions. No short-term, unilateral changes can be made.
    due to funds commitments (commitment for funds commitments):
    - You can use Funds Commitments to reserve funds for costs you are fairly certain to incur, but you cannot yet assign to a specific business transaction (such as, a purchase order or a purchase requisition).
    Regards,
    SUbha

  • No Update FMIOI and KBLP tables with purchase order

    Hello,
    We have un serious problem : No Update FMIOI and KBLP tables with purchase order
    System :  SAP ERP 6.0 /7.0 - EHP 4
    Note 965633 was read.
    1) First case: The purchase order 4510000673 does not reduce the funds reservation.
    Purchase order 4510000673 should consume the funds reservation 1200000193 because all post of the PO charge the funds reservation 1200000193.But the consumption history of the funds reservation 1200000193 donu2019t show this consumption.
    In table FMIOI, we do not have lines with amount type 0200 (reduction) but whe have the lines with the post of PO with amount type (0100).  The Purchase order 4510000673 should consume the funds reservation 1200000193.
    In table KBLP, the fields are :
    Total amount (LC) - HWGES  = 53.409,40
    Amount used u2013 WTABB = 0,00
    Reduction amount u2013 HWABB = 0,00
    Open amount u2013 CWTFREE =    53.409,40
    Reduced amount u2013 WTABG = 0,00
    Reduced amount u2013HWABG = 0,00
    To solve the problem, we executed the transactions : FM4N et FMN5 and the program RFFMRC20 but no result.
    2) Second case : Delete a item of a purchase order does not release the budget
    The single item of the purchase order 4510000597 is deleted but in the display of consumption History of the funds reservation 1200000137, the amount of the purchase order is not to zero.
    To solve the problem, we executed the transactions : FM4N et FMN5 and the program RFFMRC20 but no result.
    Somebody already had a similar problem ?
    Thank you
    Fabian

    Hello Fabian
    There are two known notes dealing with missing update on reference Earmarked Funds, I am listing them for future references:
    1376800  Earmarked funds: Incorrect open amount         
    1438487  RFFMRC20: Missing KBLE records are ignored     
    These notes correct some errors within the Standard.
    However, in your scenario, problem has to do with an incorrect execution of a Commit work inside a customer user-exit. After elimination of this commit work, new Po's are working correctly.
    Remaining task is the correction of old PO's. Manual correction via small changes with ME22N (for instance, adding a '.' to the line item text/s) will force the correct update and fix your database
    If you agree, we can close this thread (?)
    Kind regards
    Mar

  • MIRO: posting to G/L Accounts with purchase order reference

    hello
    our company want to post an invoice for other expense in MIRO through the tab "G/L Acconunt" and don't through the tab "PO reference".
    our problem that when we post through "G/L Account" how we allocate the "purchasing document" to the line of G/L Account?
    in miro there is an option to create a posting line with purchase order reference to a g/l account and i read the documentation that says proceed as follows:
    1. choose miro
    2. enter header data as required
    3. allocate the invoice to a document and check the items to be settled - i don't underdand what i need to do in this step?
    4. choose the tab page g/l account
    5. enter data as requierd.
    thanks
    meir

    hi
    in the table below your MIRO screen you will see PO Reference on this tab select the item of the PO that you need post for this PO, in the tab G/L account you can make manual post aditional to the PO, also you can in the tab PO reference modify amounts and quantity if you need, but it is not recommended

  • Invoice Verification without GR and with Purchase Order

    Hi all
    During the Logistic Invoice Verfication (MIRO) without GR and with Purchase Order, I want to exclude "Invoice to be received" account (WRX) from the posting. How can I do it?
    Let me know
    Thanks

    it doesn't work. Can you explain me better the solution?
    Thanks

  • DMS link with Purchase order,invoices and material master

    Hi, all,
    Here is my ?
    Can we link incoming material invoice with purchase orders for reference purpose throught DMS.
    rgds,
    ben

    hi
    you can link the objects through object link in dms.
    go to  tcode dc10 select the documnet type, click on define object link. click new entry and select object type as EBAN/EKPO
    this way dms is link  to purchase order.
    thanks ,
    regards,
    nitin
    award point if useful

  • Reference with purchase order

    Hi,
    This is emanuel from hyderabad SAP SD consultant, well can we do billing with reference with purchase order. for exampl.:-
    One company code -1000, and two plants one is 1000 and another one is 2000
    suppose 1000 plant raise the purchase to plant 2000 to do service. once the service is completed by 2000 plant is going to rasie the bill to 1000 plant. is this can be possible it or not please tell me.

    HI,
    You can Frame your Requirment As like STO with billing with in COmpany code.
    For STO with billing search in Forum.
    If any Specific Req Let us know...
    Regards
    raj.

  • Issues with Purchase order change documents

    Hi Gurus,
    I have some peculiar issues with Purchase order. The PO line item has deletion indicator set but I can't find who set the deletion indicator. The PO change documents doesn't show anything related to deletion indicator.
    Please help to fix the Issue.
    Regards,
    Senthil

    Hi
    Check it in Tcode SE16
    Table Name CDHDR and CDPOS
    Regards,
    Raman

  • Kanban with purchase order : avoid manual change status to full

    Dear guru ,
    i use a kanban with purchase order.
    When I enter status empty (using for example PK13N) the system create purchase order.
    I want to avoid that the users enter status full using PK13N or PKBC .
    The users execute goods receipts against purchase order using MIGO in order that the system trigger status full automatically.
    How can I avoid that users change manual status to full using PK13N or PKBC ?
    Thanks.

    We have this scenario and to solve that we did a development. I heard in the past that even you can configure it on SPRO it doesn't work.
    I made some tests recently but I didn't get any positive result. We did tests entering the kanban id into the inbound delivery and post through vl32n and migo but it doesn't work.
    Regards
    Eduardo Chagas

  • Quotation Attachment with Purchase Order

    please guide me how to attached the quotation with Purchase order
    regards

    hi
    there will be 2 types of attachment is there
    1       you can copy sales order from the quotation then the document referance is the remarks coloumn.
    2  If you want to attach the External quotation (it ia in any format . like *.Doc *.pdf  etc.,,)
    you should create the UDF called the Link  that UDF type should be general  then structure should be link
    then in the sales order if you click on that table you can able to attach the file
    Gopi

Maybe you are looking for