Hi Andrew/Kedar,
There are two things we are talking here the labour cost posting happening to Order and the final settlement to G/L. Both things are totally different from FI and CO perspective.
For labour posting to Order:
1.Define a Cost Center  - KS01(which is assigned to Work center)
2.Define a Activity type  - KL01
3.Define a Cost Element - KA01. This CE is secondary CE of type 43 - Internal Activity Allocation. You assign this CE in Activity type defined above.(Usually you dont have one to one relationship between CCtr and CE, so you dont assign Cctr on Cost ement)
4.Using KP26 you define the rates of Cost Ctr and Activiy type combination.
5.Whenever time is confirmed, the rate is picked up from KP26 and cost is posted on Order. If you see the Cost element report, this cost will be reported against the CE of type 43, defined above.
FI/CO postings
When you confirmation the Cctr on Work Ctr gets credited and the Order gets debited with the cost.
For settlement to Cctr from Order
1.This is a CO settlement. We are transferring Order cost to an Cost center, which is CO posting or internal posting
2.In this case we need a  secondary Cost Element of type 21 as a settlement cost element, which is defined in your allocation structure of settlement profile. The settlement cost element could also be debit cost element, in this case you dont need to specify settlement CE.
3.When you do the settlement the Order gets credited and the Settlement Cctr gets debited with that cost.
Kedar - For your question
1.If Settlement Cctr and Work Cctr Cost ctr are same
In this case , since the source and trget Cctr are same, the Ccts gets credited initially and Order is debited. When you settle from Order to CCtr again the Order is credited and Cctr is debited. So the same is CCtr is credited first and then debited.
2.If Settlement Cctr and Work Ctr are different
In this case, the source CCtr (Work ctr Cost Ctr) is credited and Order debited with labour cost. During settlement Order is credited and Settlement Cctr is debited.
Hope this clears your doubt.
Thanks
Sarang

Similar Messages

  • Settling Labor costs

    Hi Experts,
    How do you settle any labor costs. I have created a secondary cost element and tied it an activity type. In the work order I enter 2 hours of this activity. Can I settle these costs from a secondary cost element to a primary one?
    Thanks

    HI,
    once it is secondary cost you cannot bring it back to primary cost.
    Best regards, Christian

  • Material & Labor Cost separate in Report

    Hi Experts,
    i have some list of orders now i want to track the Material and labor cost separately.
    Is there any standard report for the same.
    Regards,
    Kavvya

    Normally cost analysis is done by order type wise, plant wise & palnner group wise with respect to technical object(FL/Equipment). If you club all order then you will not have any meaning ful analysis. As such one report for material consumption(goods movmt in order) is there -IW3M.
    You will have to develop customise report (use  table PMCO)
    Shakti

  • DBM labor cost in the pricing

    Dear Friends,
       We plan to use DBM Time Management . When the technician clocks in time, the labor cost hits the internal order correctly. But, the same cost doesn't hit my labor cost condition type in the pricing.  Due to this, my profit center in the billing is wrong.
    What am I missing here? Couldnt find any documentation regarding this
    Appreciate your help
    Best regards,
    Shafi

    Hi
    if you want to have your profit margin on the SD order 100% accurate this is the only way but this will have a big impact on performance. As normally labor rates don´t differ so much I would recommend to create a condition type where you maintain the average labor rate. This gives you a profit margin as well but not as accurate.
    In CO PA you get the right figures but normally you don´t do this order level
    regards
    Stephan

  • Actual labor cost

    Hi
    how system calculate actual labor cost in product cost by order?
    i am sure i entered actual activity quantities to the production order but it is picking planned price to calculate labor cost of an operation
    thanks and regards
    somashekara

    Did you calculate actual activity prices in TC KSII?

  • Labor COsts

    Hi all,
    In a make to stock  product costing scenario :
    1) How does the labor costs and material overhead costs reflected in FI side.?
    2) Do we need to run any specific steps for these secondary costs to reflect in FI ?
    We collect these costs using Activity types and then how does this flow in to FI.
    Thanks,
    Sai.

    Dear,
    WEmake cost elements/value categories for your requirements(like internal labour, external labour, overheads etc.) Also he will make activity type for ur requirement like: activity type : Labour hours.
    U can also try this with T-code Ka01, Ks02, Kp26, Kl01.
    The assign cost element to value categories...in SPRO.
    Also assign this activity type in ur work center(cost center tab).CR02
    And in order cost tab , u will see the labour cost.
    Then we calculate variance WIP and settlment .
    Regards,
    R.Brahmankar

  • How to capture raw materials,activity & overhead cost without order

    hi
    my client wants to capture cost of effluent  plant.
    i do not want to create a seprate  production order.
    in etp plant
    waste water enters . it goes to some processing and come out as purified water.
    some raw materials are used like alum,DAP,........
    Some activities are done so there is processing cost,power cost,labor cost...
    how can i capture all raw materials cost,processing cost,labor cost,power cost
    is it possible without creating production order

    Hi,
    Without creating a production order you can't able to get the actual costs for material cost and the activity cost. By maintaining BOM, Routing you can get the Standard cost.
    regards,
    V. Suresh

  • PM Labor Cost

    PM Experts,
    Pls explain to me where can i input the labor cost of a plant maintenance order in such a way that it will reflect in the cost center once i settled the order.
    Thank you

    hi
    you dont want to input the labor cost,it will be automatically calculated based on the hours you mentioned and the cost of the activity you maintained in KP26
    regards
    thyagarajan

  • How to read the Variance Analysis report S_ALR_87013139,  Pdt cost by Order

    Hi,
    Could someone tell me how to read the variance analysis report, S_ALR_87013139 - Cumulative for product cost by order. The report has the following fields, Target (Debits),     Actual (Debits),     Scrap,     Var. Without Scrap,     Work in Process(WIP),     Control Costs.
    I am looking to find how the numbers add up.
    Thanks for your help.
    Ram
    Message was edited by:
            Ram R

    Thanks Sridhar,
    When I analyse the report S_ALR_87013139 - Cumulative , for a product for a period (with no scrap), I get the following
    Target (Deb) -   46,855.55
    Act (Deb) - 58,315.87
    Scrap - 0.00
    Var W/O- Scrap -  11,269
    WIP- 0
    Control Cost - 0
    Here Actual - Target is not equal to Variance. What could be the issue?
    Could you please tell me how SAP would update this report  with target & actual costs with respect to open production orders, carried over from previous periods.
    Thanks,
    Ram

  • Actual Cost of SFG/FG-Product Cost by Order

    Dear Gurus,
    We have our SFG and FG maintained with Price Control "S". We have process cost by order scenario.
    (We do not have the Material Ledger
    Though it is standard price in the "Costing 2" Tab the moving price also gets changed based on the monthly settlements to process orders.
    Any report available in SAP to know line item report of such materials so as to know the Moving Price apart from the material master.
    Thanks & Regards,
    Amit Dhanurdhari

    Hi,
    Check in CKM3 transaction for the details.
    or click the button in the material master Accounting 1 view,MAP button
    Regards,
    Raj

  • COGS determination for Free of cost sales order

    Hi All,
    We have an issue regarding the COGS determination for Free of cost sales order. We created a free of cost sales order. But i need to know whether this sales order items will hit to COGS or not? If so how do i check whetehr its has been charged to COGS or not? and we have an issue raised saying thst one material in this sales order has not being charged to COGS. So please help me to solve this issue. Ihave checked the account assignment in GBB-VAX. And is there anyting to do with the settlement profile for COGS determination?.
    Thanks and regards
    Uday

    Hi,
    During PGI a material document and accounting doc gets created which would hit COGS account.
    You're talking about one specific sales order in which for one material it didn't hit COGS account or any order you're creating now with that material has an issue? If its a specific material which has an issue always..then something is wrong with that material master setup. Also you can go to the reported Sales order--doc flow to the PGI document and check the accounting doc and if its not posted..check the analysis why its not posted?
    And if its one off then I would suggest 2 options:
    1) Reverse the goods movement, cancel the delivery or if billing has already been done..cancel the billing as well. And re-do the cycle. This always ensures correct posting.--> Recommended option.
    2) Manual adjustment in FI.
    And settlement profile is Controlling concept..not sure you would get any help on this in this forum.
    Regards
    RS

  • Description on product cost by order.

    Can anyone give me a example of differenct product cost ?
    1) product cost by order and product cost by sales order ?
    Also what is the difference between those two production order.

    Hi,
    In the SAP standard (as per the transaction codes indicated by you) it is not possible to include multiple plants. Either you have to execute for one Plant or for all plants. Probably, in Test run you can execute for all Plants and check the results, and then decide.
    Thanks
    Murali.

  • CO02. Product Cost by Order.

    Hi All.,
    When i am doing the Product cost by order for PP Production Order through CO02, it is giving the details of Itemization of cost for only Raw Materials.
    Then what about the Production Costs...or at this level.......cant we get the cost of production, production overheads....and also the material overhead.
    Please provide information to clarify this doubt....
    Thanks

    Hi Arun.,
    Thx for your reply, but what i am asking is different frrom the actual cost line items.
    At the order level, when we are checking costs....only Raw material costs are picking, then what about the other costs like
             Material Overheads,
            Production Costs & Overheads.......
    Thanks......

  • Shipment Cost = Purchase Order

    Hi
    Where do I define such that one PO will be created for every shipment cost document.. Currently the line is added to the existing purchase order (from previous transactions)..
    THanks

    Hi,
    Check whether this link would help you [Shipment cost - Purchase order   |Shipment cost - Purchase order]
    Regards

  • REM profile Product Type - Cost Collector Order Type

    Hi all,
               I am trying to create a Repetitive Manufacturing Profile, at that time standard Production Type PKMN is automatically arriving from table V_T437S_GES.
    and I would like to assign the cost collector order type (self defined) to the REM profile which I am going to create.
    where I need to assign the cost collector order type for production type "PKMN" while creating REM profile.
    If I copy the exisiting REM profile and I am able to get the cost collector order type  that I am able to see in TABLE : T437S (Repetitive Manufacturing Profile Table). If I create the REM profile newly, I am unable to get the cost collector order type in the table T437S.
    So please guide to the self defined cost collector order type for newly creating REM profile.
    Thanks in Advance

    Madhan,
    Order type "PKMN", is internally defined by SAP. Forr all cost accounting purpose, we would be using standard order type "RM01" when creating a new product cost collector for material. If required you can create your own order type say "ZM02" using transaction KOT2, please remmember you need to create with order category "05"- Product Cost Collectors.
    This new Order type can be used when we are creating product cost collectors for a material.
    I really dont find a reason why a new Order type is required to be created. Can you explain why?
    Regards,
    Prasobh

Maybe you are looking for

  • Adding to the end of a file

    hi guys, im tryin to open a file then add changes to the end of it, at the mo im using the following but it doesnt add to the end, any ideas? try { BufferedReader br = new BufferedReader(new FileReader("H:\\new folder\\TransactionFile.txt"));      Bu

  • How to remove a Attachment in Module for Mail Adapter

    Hi together, we are trying to remove a Mail Attachment within a outgoing Mail with the help of a new Module executed by the Mailadapter. Since we are using the XI 3.0, we are trying to do that by this statements:       Message msg = (Message)inputMod

  • Conversion from .prn file into .pdf file

    How to convert printer file (.prn) into PDF using ghostscript in C#.Net programmatically?

  • Weird glitch noise and driver issues

    Hi, recently i bought a probook 450 g2 and i have the following problems: 1) I get an error code 28 and can't find the needed drivers to install Here is what i see on my screen: PCI bus 0, device 31, function 6  Also i got 3 unknown devices 2) The se

  • IPhone user, Can Not Access iTunes Store, Using Windows 7

    Dear Sir I used to access the iTune Store from my computer everyday. But since a couple of weeks I started receiving the following (Connecting to the iTune Store) message after clicking on the Store link in iTunes. http://i50.tinypic.com/1glc8.jpg It