Locking MRP run
Hi all,
would you please help me in locking MRP run since my plant is under plant maintanance for 15-20 days.
should i change my factory calender for 15 days as holiday or is there any other method of parking MRP
run for a plant.
marks will be awrded for a suitable answer.
Regards,
Vimal
Is your MRP run with Scope of Planning with multiple Plant or Individual Plant
When is your Planning Run date, whether start of Month or every week, ..
ok
If the Plant under maintenance, if you restrict for runnning, it will affect the Procurement Proposal for External purchase. This one is a negative impact. Because you are suppose to restrict the Production orders which came from Planned order not the Purchase requistion. You need Raw Materials ready once the plant is ready.Iam i right
so rethink and take decision
ok
if it in scope of planning remove that plant from that setting
If it is individual plant, in mdbt change the settings
thanks
K.Prabakaran
thanks
K.Prabakaran
Similar Messages
-
MRP run and creation of one cumulative purchase req
Hello,
mrp run is creating a lot of single purchase reqs with one line (quantity and dates are fine)
but how to set up MRP so that instead of multiple purchase reqs ONE purchase req with many lines is created.
Thanks, Sebastianthis is not forseen in the design.
Where would be the benefit? have a look into table EBAN.
There would not be one record less with this concept.
Further, in bigger organizations, several buyers would then work with the same purchase requisition, which could lead to lock and update problems. -
Alternative BOM problem in MRP run
Hello Experts,
We have two BOM for one material.Now I want to use BOM-1 for MRP run & BOM-2 for subcontracting.I have maintined following settings.
1) Production version.
2) BOM explosion selection method in MRP4 -2
3) Assign PV in inforecord for subcontracting.
4) Assign PV in MD61 in schedule line .
But when I run MRP it still consider subcontracting BOM.Have I missed any setting?
Kindly guide.Thanks you.Hi, Follow the below process,
1.Enter the BOM selection method as 2 in the MRP4 view of the material master.
2.In case if you have not assigned the production version in MD61 against the PIR's under schedule line
tab key (in the top menu click on settings and prod version ,then you can assign the prod version which
you need to pick during the MRP run),the system always picksup the first production version during
MRP run even if all the prod versions contains the same validity dates and lot sizes.
3.If you are not willing to assign the prod version in MD61 ,but the system should consider the second
prod version for MRP run means,then set the locked status for the first prod.version.
4.When run MRP via MD02 or MD50 in the simulation mode.(i.e w/o giving tick in simulation mode).
Click on Save,You will get a pop screen,
Now click on the continue icon, Then go to Plaining Results: Individual lines screen.where you will get Plan order on which when double click you will get pop screen below,where you have Planned order no,quantity,plant,storage location,and version.
Now here you can select the required version,and it will become firmed. This BOM will be used in the order now. Try it. -
Order of delivery schedule line counter at schedule agreements from MRP run
Currently we are using schedule agreements for our long term external suppliers, but we are facing a problem with the order of new delivery schedule lines created during MRP run.
Because of master data settings like, lot size, rounding value, plan delivery time and planning time fence to set as firm new requirements, multiple schedule lines are created with no order for schedule line counter.
Does anyone is aware of a BADI, user exit or customizing control to have this schedule line counter in order?
Thank you
Daniel Guillen
IT
Skyworks Inc.Hi,
Pls put this query in SD fourms and get immly help because this is technical fourms.
Anil -
Effect of manually created proposal on MRP Run
if there is any proposal which might have been created by the user manually & not via MRP run, does it have effect on the results of MRP.
will the system ignores the requirement as it has been covered already via manually created proposal.Dear Geetika,
if there is any proposal which might have been created by the user manually & not via MRP run,
does it have effect on the results of MRP.
Yes definitely it have effect on MRP
MRP checks All Firmed Receipts & creates procurement proposals
will the system ignores the requirement as it has been covered already via manually created proposal.
Say for example demand is there for material as 50 PCS
Now manually user created Production order for that 50 pcs
Now if run MRP than system will not create any plan order as already Production order consists for 50 pcs
Again we have add demand for the same as for another 50 pcs
so now total demand became for that material is 100pcs
Now Run MRP system will create plan order for 50 pcs
As we have already 50 pcs of production order which is created manually
Hope the above clarifies
Regards
Madhu -
Purchase order status in MRP run
Hi Gurus,
I have a doubt in MRP run.
While doing the MRP run, can there be any open PO s or is it mandatory to close them.
Can you also please suggest me on how to run the MRP.Hi,
MRP Run
Purpose
The Material Requirements Planning (MRP) function enables you to plan material requirements for complex manufacturing processes. You use the MRP Wizard to create and run MRP scenarios. The MRP Wizard generates recommendations for the production and purchasing orders required to produce the final product on time and in the required quantity. You then use these recommendations to create production and purchase orders in the Order Recommendation Report.
The order recommendation cannot be issued for requirements that happened in the past (before the present day). Since the purchasing or production process cannot be completed in time, the MRP does not mix the real past data with new recommendations for the same period.
Prerequisites
● You have defined the
○ Planning system
○ Procurement method
○ Order mutliple
○ Minimum order
○ Lead time
See also: Item Master Data, Planning Data Tab.
● You have set the time interval between orders. See also: Define Inventory Cycles.
● You have defined the appropriate items as non-production bills of materials (if required). See also: Item Master Data, General Tab.
● You have defined default warehouses. See also: Define Warehouses.
● You have defined forecasts. See also: Forecasts.
● You have selected the Consume Forecast option to make the system exclude existing sales orders from the forecast. If this is not selected, the forecast considers existing sales orders as an additional requirement. See also: Sales Order.
● You have set the planning definitions. If you chose Consume Forecast, you have defined the consumption method, days forward and days backward. See also: General Settings, Inventory Tab.
Process Flow
1. Start the MRP Wizard.
2. Create a new MRP scenario or select an existing one. (See also: MRP Wizard: Select New or Existing Scenario.)
3. Define the parameters for your scenario, such as the planning horizon and item details.
You also choose your display preferences. (See also: MRP Wizard: Scenario Details.)
4. Define the data sources for requirements that you want to include in your MRP scenario.
For example, you define whether you want to consider the existing stock or the minimum stock level. You can also include a predefined forecast. (See also: MRP Wizard: Data Source.)
5. Save the scenario or run it.
After you run the scenario, the system displays the MRP Results.
If there are red figures in the result table, solve the problem and re-run the MRP.
6. Analyze the MRP results. You can display the final stock quantity before the MRP run or after it.
7. Save the recommendations and exit the MRP Wizard.
Result
After completing the MRP Wizard, you still need to create the purchase and production orders in accordance with the MRP recommendations. See also: Order Recommendation Report.
Hope this will help.
Reward Point if helpful
Thanks,
Raja -
Is there a report to track the exception messages after a MRP run ?
We have a scenario at our client site where MRP run is not optimized to the fullest.
The planners are not trained on how to interpret those exception messages.
They are not trained on how to reschedule / expedite planned orders resulting from an MRP run.
Is there a report out in SAP that keeps track of
1) History of number of exception messages by type ( Expedite/Reschedule/Cancel)
2) History of number of exception messages that were acted on or ignored by the planner.
This is to create metrics on the usage of MRP exception reports by planners.
Appreciate your inputs..Hi
The exception messages are dynamic and time dependant. You cannot have history of exception message.. If your user is feeling difficult to use standard MRP reports. Create a new report using a function module MD_STOCK_REQUIREMENTS_LIST_API
It gives all MRP data including exception messages.
Regards
Antony -
When MRP run through background process in MDBT open PR and PO not comming?
Hi,
When MRP run through backgroung process in MDBT open PR and PO not coming in MDBT result.
Pls advise accordingaly.
Regards
rkRam,
Either I am totally misunderstanding your statements, or your business people are misinformed.
The output of MD01 (MRP total run in foreground) and the output of MDBT (MRP total Run in Background) ARE IDENTICAL, provided you have selected the same parameters.
Neither output contains a discrete listing of open Purchase orders and Purchase requisitions.
Standard output of both MD01 and MDBT are:
1. List of materials processed, with exception messages
2. Statistics
In addition, both of these programs also write MRP records to the MRP databases, provided that the "Display Material List" parameter is set. In this case, both of these programs will produce data that can be further reviewed and managed in MD05 and MD06. MD06 is the tool that most planners use to process the MRP database info.
If you wish to see a listing of the entire MRP results (either MD01 or MDBT), then execute transaction MDLD. This will produce either a spoolfile or a printed document.
For the PO or PR listings, review my earlier suggestions.
Rgds,
DB49 -
Open Purchase Orders not considered as requirement for MRP Run
Hi ,
We are facing a issue of Open Purchase orders not appeared in Stock requirements list and also it is not considered as requirement for MRP Run against reservation.
As aresult for a reservation demand of 10 units we are ending with Open POs 10 units and a additional planned order 10 units.
Material Type : ERSA
MRP Type : PD (or VB)
Lot size : EX ( HB if MRP Type is VB)
Could you please throw some light to correct our settings to MRP to consider Open POs?
SaravananCan you check to see if there is a re-order point set up for this materia? That could be causing the problem too.
-
Open order quantity for mrp run
hi
for x material i was made a subcontracting PO
ORDER uantity was say 2000
deliverd quantity was 1500
rest of the 500 nos tobe deliverad on 30th agust
ie, OPEN ORDER QATNTIY OF 500 NOS WHITH delivery date
on 30th agust.
for the same materail there was an dependent requirement of say 1500 in the month of MAY2008
while MRP RUN for the dependent reqirement of 1500
i got a purchase requistion of 1000nos
and for the 500 nos saytem taken fron the purchase order
which was made as subcontracting
and throughs an expetion message which says needs the rescheduling
my requirement here is it should not consider the open order quantity which was there for sub contracting
it sholud create purchase requirement of 2000nos
plz suggest how to achive it
regards
sasikanth/vstI wanted to the same as you where getting in subcontract po but in a std po
hi
for x material i was made a subcontracting PO
ORDER uantity was say 2000
deliverd quantity was 1500
rest of the 500 nos tobe deliverad on 30th agust
ie, OPEN ORDER QATNTIY OF 500 NOS WHITH delivery date
on 30th agust."
guide me in terms of configuration
i think i am missing some configurations -
Sale Order MRP Run for All Order Line Items
Greetings...
I have One Sales Order , in which i have ten different Line Items .
Now I have to Run the MRP on basis of Created sales Order so that all Line items wi get consider insingle MRP Run on sales order base MRP Run.
How to take MRP Run of One Sale Order for all Line Items.???
In MD50 , we can have sales Order with Item..In MD50 you can give only one item at a time.
Its a standard transaction meant to accomodate changes relevant for MRP after plant level MRP run related to specific sales order Item.
so either you need to do it multipal times by changing material or you need to go for MD02.
Please explain bussiness case in detail why you want to restrict your MRP run for items in a specific sales order.
Regards -
MRP run without one storage location
Dear All,
My client's requirement is they need to run MRP on plant level without considering one storage location stock
e.g if a material is having stock of 10 in unrestricted with storage location 1104. Now when mrp is run for 100 quantity planned order is created for 90 only planning strategy is 40....they want the MRP should not consider the stock in storage location 1104.....how this can be made possibe?
Please Suggest...
Regards,
Pawan ShettyDear all,
Pl. help me which user exit implemented for MRP RUN without Storage location ,b'coz. from slandered setting we are not able to do the same
Regards
Sandeep -
How to make Open Sales Orders consider unallocated stocks in MRP run
Dear Experts,
Maerial BOM MATERIAL TYPE STRATEGY GROUP PLANNING STRATEGY DESCRIPTION
Req-DM Req-CU
3. TF180TK fert 20 KE make-to-order
2. TH300TK halb 20 KE make-to-order
1. TA300TK roh 10 LSF KSL make-to-stock
As listed above material in line no.1 is required to produce 2 and
2 is required to produce 3.
I have open open sales orders for material TF180TK(fert).
What settings do I need to effect, to make the System consider Stocks & Open Purchase Orders for material TA300TK (roh) which are not allocated to these Sales Orders , when MRP run is carried out at plant level using MD01?
RegardsDear Bisolaaina,
I Think by mistake this duplicate thread might have been created so pls close it
Regards
Madhu -
Production orders not to be considered during MRP run
Dear SAPeers,
i want to know how to ensure that open production orders are not considered during the MRP run.
the following is the scenario.
PIR for march after MRP run creates a planned order. this planned order is converted to production order. now this production order is processed but not completely confirmed and TECOed after a certain quantity has been produced.
now we delete the old PIR and create a new PIR in the next month. now we revoke the TECO status of the production order and run MRP. I want to know how to avoid MRP from considering the open production order and create planned order for the complete PIR quantity.
Thanks and Regards
SrinivasanSrini,
what i am worried is shortfall of raw materials in case they were to open the production order in the current month after the planning has been done. how do we allocate raw materials for both the plan as well as the open production order?
Okay, you presumably had RM available for all of your production orders (and those RM were balanced by the reservations from the production orders). Now, you TECO the production order. In effect, any un-issued RM are now released and freely available for other orders/planned orders. Now you plan the following month. Those RM that were freed can and will be used for the new plan. Odd business process, but OK. Now, you re-open the production orders, and, yes, you will have a shortage unless you run RM MRP again. This is, ah, inconsistent with any business process I have ever seen.
The question that jumps to mind is, "Why re-open the old production orders at all? Alternatively, why were they TECOd in the first place?" If one knows that he intends to complete an order in production, one does not normally TECO the order, and then later reverse the TECO.
With respect to my name, I must unfortunately keep a low profile. Ever since I escaped from the mental institution, the thought-police have been hunting for me. I do not wish to be the recipient of any further electroshock 'treatments'.
Rgds,
DB49 -
Discontinuation Material in MRP run
Hi,
In our scenario, we are using Discontinued parts with (Discontinuation Ind - 1, Effectivity-out date - Nil) with follow-up material in MRP4 view of MM.
It is observed that whenever there is no sufficient stock exist, dependant requirement is not transferred to the follow-up material during MRP run. However is the same is happening during Material Availability check.
Is there any IMG setting for this to happen during MRP run also.
Thanks in advance.
Parthasarathy PHi ,Parthasarathy,
if an item to be disticontinued item , the following must be true.
1. you have to define Discont ind= 1, and followup material in MRP VIEW,
2. Both Discont item and followup items should have same base unit of measure.
3. When BOM of Header Material creation, discontinuation data is maintained for the discontinued item and follow-up data is maintained for the follow-up item -in CS01.
4. Then you have to assign some value for Discontinuation Group in "Discontinuation Data" for your Discot item in BOM. -in CS01
5. Then create a followup group with same value of Discont Group for yourFollowup item -in CS01.
During the MRP run the Dependent requirements of header material will be transferred to Followup item if it is not enough stock of Discont item.
Please check your Discont data has defined in BOM. The value of Discont group and follow group should be same.
please letus know for further doubts...
regards
pradeep
Maybe you are looking for
-
I followed the directions to install the IOS 7.0.6 update to my Ipad Mini, but when I click on install and agree to terms & conditions, it says it is unable to verify the update because I am no longer connected to the internet. Not true. Help.
-
my computer is VERY sluggish. i get the spinning beach ball all the time, even when only mail and safari are open, and more than 30% of my HD is free. i think i will have to erase the disc and reinstall everything. will i have to reinstall all my app
-
Does a 12 contract auto-renew?
Hi, In september last year I signed up for a 12 month contract in which I paid for all of it up front, howver I wasn't aware of the charges I would get if the line wasn't used for calls. This annoyed me but this is not the issue. The issue I have now
-
The Image Palette functionality was removed from Forms9i. I was wondering if there are any plans to add this back in later.
-
I had Imagemagick working perfectly fine but I got my Mac unusable so I reinstalled Leopard and did all updates and put back my user folder from time machine. When I try: $ montage *.jpg -tile 8x4 -mode Concatenate a.gif I get: -bash: montage: comman