Maintaine error message if posting date is greater than Sch del date in PO

I have maintained a delivery schedule in a PO for a material
Say PO qty 100
Del Schedule
10.04.09  - 60
20.04.09 - 40
While GRN, for 60 qty, if posting date is greater than 10.04.09, system needs to throw error.
I want to do it for selected materials only.
Is there a way to do this.
Regards,
Rakesh

Thanx for reply
If I use OMCQ message , it will be applicable for all GRNs and I want for a particular set of materials.
Can one please suggest User exits / BADi for the same. I have checkd BADIs but those are based upon MSEG and EKBE table.. and i dont have any material doc no before posting the document.
requiement is to check the delivery sch date and posting date befor posting the document is posted.
Any suggestions welcomed.
Reagrds,
rakesh

Similar Messages

  • GR posting date always greater than PO document date.

    Dear SAP Gurus,
    Am working on below requirement in a support project..
    Need to ensure GR posting date always greater than in PO creation date. Only current month is open for GR posting and at present as a standard system allows to post GR any date in the current open period.
    Is there any way, we can control the same via messages without implementing any exits or badis.
    Appreciate immediate response.
    Regards,
    GM

    there is no std sap for this
    you can use user exit to ful fill ur requirement
    in that u can write a code where is u can check all PO dated in GR must be eq to or less than GR posting and document date
    hope this helps

  • Trying to do date field greater than a specified date in condition editor

    Hi All,
    I am trying to build the XML predicate in the expression editor to check that the posting date sent is greater than a specified date to determine the reciever. I can get it to validate posting date is = to specified date, but when I change the = to > it fails to properly determine the receiver, when I send a valid document.
    Below is the expression build
    (/p1:ServiceAcknowledgementConfirmation/ServiceAcknowledgement[CreationDateTime>'2007-02-03'] EX )
    has anyone done this type of check. I have it set as a date type for the expression.
    Regards,
    Chris

    Hey all,
    I tried >= 2007-02-04 and sent in that exact date. It failed. I removed > so that it is just = 2007-02-04 and it was successful. So, is >= an allowable operator?
    Thanks,
    Chris

  • Doc Date is Greater than Posting Date in Migo

    Hi ,
    Document  Date shouldn't be greater than Posting date in MIGO .How can I restrict it ??
    Biswajit

    Hi
    We can restrict through Define Attributes of system messages
    Settings for SYSTEM MESSAGES  - Doc Date is Greater than Posting Date in Migo in that  in that Message Type we can make the Warning Message to Error Message
    regards,
    senthil.

  • I have been exporting lightroom webgaleries to my iweb site without any problem.  Suddenly I get the error message "finder can't complete the operation because some data can't be read or written" - error code -36 - thoughts?

    i have been exporting lightroom web galleries to my iweb site without any problem.  Suddenly I get the error message "finder can't complete the operation because some data can't be read or written" - error code -36 - and the move to the sites folder on my idisk fails..... thoughts?

    Try this community: MobileMe on my Mac: MobileMe: Apple Support Communities.
    And you can continue to use iWeb for some time to come. The following will explain:
    It's now confirmed that iWeb and iDVD have been discontinued by Apple. This is evidenced by the fact that new Macs are shipping with iLife 11 installed but without iWeb and iDVD.
    On June 30, 2012 MobileMe will be shutdown. HOWEVER, iWeb will still continue to work but without the following:
    Features No Longer Available Once MobileMe is Discontinued:
    ◼ Password protection
    ◼ Blog and photo comments
    ◼ Blog search
    ◼ Hit counter
    ◼ MobileMe Gallery
    All of these features can be replaced with 3rd party options.
    I found that if I published my site to a folder on my hard drive and then uploaded with a 3rd party FTP client subscriptions to slideshows and the RSS feed were broken.  If I published directly from iWeb to the FPT server those two features continued to work correctly.
    There's another problem and that's with iWeb's popup slideshows.  Once the MMe servers are no longer online the popup slideshow buttons will not display their images.
    Click to view full size
    However, Roddy McKay and I have figured out a way to modify existing sites with those slideshows and iWeb itself so that those images will display as expected once MobileMe servers are gone.  How to is described in this tutorial: #26 - How to Modify iWeb So Popup Slideshows Will Work After MobileMe is Discontinued.
    In addition the iLife suite of applications offered on disc is now a discontinued product and the remaining supported iApps will only be available thru the App Store from now on.
    HOWEVER, the iLife 11 boxed version that is still currently available at the online Apple Store (Store button at the top of the page) and those copies still on the shelves of retailers will include iWeb and iDVD.

  • Property Bee not working properly keep getting error messages about post codes

    Every time I open a new page on Rightmove I get an error message about post codes

    If you use a bookmark to reach specific pages then try to start with the main (home) page of the website and navigate from that main page to those bookmarked pages in case the bookmarks are no longer working.

  • Exit or BAdi for Validating GR posting date Greater than PO creation date.

    Hi all ,
    Is there any Exit or BAdi for restricting users to post GR date greater than PO creation date.
    Regards
    Gibi Philip

    Gibi,
    check this:
    MB_CIN_LMBMBU04                         posting of gr
    Amit.

  • I have an Apple Configurator install that wont recognize an iPad when I attach it via USB.  I cant prepare it or refresh it.  It was supervised.  I get an error message that says "policy does not have correct profile data".  Please help!!!

    I have an Apple Configurator install that wont recognize an iPad when I attach it via USB.  I cant prepare it or refresh it.  It was supervised.  I get an error message that says "policy does not have correct profile data".   At some point there was a mismatch between the profile on the iPad and the MAC server.  The profile on the MAC server has been deleted and the iPad has been erased and reset to default.  I need to be able to get Configurator to recognize this device to prepare it for deployment and issue Apps to it.   Please help!!

    Run the application 'Terminal.app' which you will find in '/Applications/Utilities' on your Macintosh.
    Type this into it: defaults delete com.apple.configurator PreprationSavedPolicyDefaultsKey
    Hit the return key.
    If you get no error message, it worked, and you can quit the app.

  • Message no 06067 "Scheduled quantity & &" greater than target quantity

    Hi,
              I change the status of the message no 06067"Scheduled quantity & & greater than target quantity & &" from W to E. Than In Se38, the schedule quantity cannot be maintained greater than target quantity.
    But in MRP Run, the message number does not work.
    How to restrict higher qty then target qty created through MRP.
    Thanks in Advance.
    Ashish Panchal

    Hi Ashish,
    The Note 83343 should answer your question.
    83343 MD01: No check of target qty in sched. agreemnt
    As described:
    "The planning run should run automatically and without interruption by some events.
    The system makes a decision either in favor of the quota arrangement or in favor
    of the source list. The system reads the scheduling agreement once in the update process.
    To have a check on the target quantity would require another read of the document which
    was determined to affect the system performance."
    A maximum quantity can be considered by means of the quota arrangement. A modification exists which will allow for a check of the maximum quantity in the quota arrangement. The note contains more details on this.
    Regards,
    Purnima.

  • Date is greater than current time plus 24 hours

    Hi,
    may I know how to pull data from a table where date is greater than current time (+24 hours)... my date field is in the following format 15-MAR-2013 20:07:00
    I want to do something like this
    select * from table_A where date_field > (sys_date_time) +24h
    as an example, when I run a query @ 4 PM on March 26, I want to pull data that has date > 4 PM March 27
    Thanks

    >
    may I know how to pull data from a table where date is greater than current time (+24 hours)... my date field is in the following format 15-MAR-2013 20:07:00
    >
    No - a DATE column does NOT have a value in a format like that. The value is stored in an internal binary format. The format you posted might be your NLS_DATE_FORMAT or just a format you provided to display that date value.
    >
    I want to do something like this
    select * from table_A where date_field > (sys_date_time) +24h
    as an example, when I run a query @ 4 PM on March 26, I want to pull data that has date > 4 PM March 27
    >
    As others have said to add 24 hours to whatever value SYSDATE has at the time the query is executed just use 'SYSDATE + 1'.
    But there are at least two caveats:
    1. You can't really run a query '@4 PM'. You don't have ANY control over exactly WHEN the query will begin execution. The only way to control the date used is if you provide it yourself as part of the query.
    2. Your 'date_field > SYSDATE + 1' query will NOT see inserted/updated data that has not been committed. So a similar query later may return a different result set even if it appears to cover the same time period. In other words you can't reliably use a DATE column like that to pull sequential sets/batchs of data unless there is no DML occuring on the data that might affect the results.

  • From Date is greater than End Date of a BBP document.

    Hi,
    There is a BBP document created in the system which has From Date (BBP Start Date) greater than End BBP Date.
    Have any one come across this type of issue.
    Can any one tell what can be the reasons for this to happen?
    Also in this case there are no entries for the items in this BBP document in database table DFKKMOP.
    Thanks in advance,
    Hrushikesh

    Hi Hrushikesh,
    Could you please check the details at billing document level if any of them is having the bad data.
    Also, please check the data passed and the importing data for the below FM's in debug mode.
    1. START_TIME_DETERMINE
    2. END_TIME_DETERMINE
    I am not sure, but have heard about the similar issue in one of the project, but it was related with invoicing not specific to BBP.
    Let me know the data received for the above FM's, also, will check if I can get any specific details for the same.
    Regards,
    Rajesh Popat

  • Elements 11:  After selection tool defines move area, error message reads "No pixels are more than 50% selected".  How to remedy?

    Elements 11:  After selection tool defines move area, error message reads "No pixels are more than 50% selected".  How to remedy?

    Are you certain that you are on the correct layer?
    As a test, try this:
    Select the object with one of the selection tools, e.g. lasso, selection brush.tool. You should see "marching ants" once the selection is complete
    Place the selection on its own layer (Layer>new>layer via copy or CTRL+J). This will place the object on a separate layer.
    With this layer active, use the move tool to move/position it
    Does that work?

  • Production finish date is later than order finish date?

    In my company, most of the plan orders in MD04 have an exception message "64 Production finish date is later than order finish date". The plan strategy of the materials are 40. The plan orders are created from Scheduling Agreements or Independent Requirements.  We set 'Scheduling' as 2(lead time) in the MD01/MD02. The self-production time in material master data is 0. The schedule margin code is 000 which all the parameters are 0.
    For a example, we create a requirement on 2007.04.24. After MRP run, plan order generate. It's basic date will be 2007.04.24, but the production date IS 2007.04.25. All the plan order like that, the production date are always later than the basic date for one day.
    Could someone tell me why? and how to settle this problem?
    Thank you in advance!

    Hi,
    check scheduling parameters for planned orders and scheduling parameters
    for production orders.In that set the various indicators like
    adjust basic dates to order start date
    do not adjust basic dates to order start dates and try.
    Tcode opu3 / opu5
    Thanks,
    s.nandhakumar

  • Update Date is older than the Creation Date

    Hi Team,
    In the Oracle Application 11i forms we are seeing the Update Date is older than the Creation Date?
    But the creation date should be older then the updated date.
    Thanks,

    What 11i release are you on?
    Can you please elaborate more on the Creation/Update dates mentioned above? Are you referring to forms or tables or specific rows? Is this happening to all data/forms? Please provide an example for us to understand your issue.
    Thanks,
    Hussein

  • Error Message during posting return delivery against materil document

    Dear experts
    I have created a purchase order with batch specific unit of measure KAI.
    I created the inbound  delivery document (say for eg: 30,000 KG)
    I have taken GRN for the above IBD through MIGO transaction with 101 movement for all 30,000 KG.
    Later i have posted the return delivery 122 movement with reference to above 101 material document. 30,000 KG
    After this i realized that i need cancel the 101 movement document.
    So cancelled the 122 movement document, and try to cancell the 101 material document.
    Then system is issuing error message VLA 321 "Movement type 102 cannot be used here".
    Also if i again want to post return delivery to send the stock back, then also i have error message. but this time it is VLA 319
    "Return delivery qty greater than previously GR-posted qty:"
    My Support package for SAP_APPL, relese 600 is SAPKH60019.
    Please suggest me solution to fix these errors as these are not relavant for the situation.
    Regards/Murali

    Hi,
    Can you please check this note...
    Note 1050944 - GR for inbound delivery using inventory mgmt as of ECC 6.00
    Note 1342935 - Error message BORGR 623 during GR reversal in MIGO
    Regards
    Bhuban