Hi,
I have read in SAP help that the maintenance planned for vehicles can be seen in PAM03 planning table. But there is no further information about the required customizing steps.
Who can help?
Udo

Hi Dean,
try this:
IMG
  > Plant Maintenance and Customer Service
    > Maintenance and Service Processing
      > Pool Asset Management
       > Edit Object Processing
    Application = Pool Asset Management
    Notification Type = M1
    Order type = (blank)
    Dir. Sched = (selected)
That should give me 10 Points
Regards and good luck
Udo

Similar Messages

  • Maintenance schedule in PAM03 Planning table

    Hi,
    I have read in SAP help that the maintenance planned for vehicles can be seen in PAM03 planning table. But there is no further information on how to get this.
    Kindly provide your valuable suggestions.
    Thanks&Regards,
    Pavan

    Hi Pete,
    PAM03 is a tcode (Planning table)used in pool asset management to monitor the vehicle requests,assign, issue, return the vehicles.
    This functionality is available from EHP3. Hope i am clear.
    Thanks&Regards,
    Pavan

  • MRS - Resources and demands are not visible in the Planning Board

    Hi Friends - I am working on the the MRSS 610. We have installed it on the our ECC 6.0 as an add-on. We have configured the system as per the configuration guide.
    But when I am accessing Manageru2019s Planning Board -  /MRSS/PLBOMGR , using the Organization unit, I am getting Notification saying that the resources assigned to the Organization unit are not available in the MRS.
    "Resource 00000000010000000000000000000000 not yet created in the WFM Core"
    The details of the Error message
    "Resource 00000000010000000000000000000000 not yet created in the WFM Core
    Message no. /MRSS/SGE034
    Diagnosis
    Resource 00000000010000000000000000000000 has not yet been created in MRS.
    System Response
    No assignments have been created for resource 00000000010000000000000000000000, even though, according to the organizational model, this resource is to be taken into consideration in the planning board.
    Procedure
    Contact technical support.
    Procedure for System Administration
    Create the resource in question in MRS."
    I have run the Report
    /MRSS/HCM_RPTWFMIF : Transfers the HR data (availability times, qualifications and the resources itself) into the MRS Basis
    But even after that I am not getting the resources in the planning board.
    Also I am not able to view the Demands from PM/CS orders.
    I have created PM Orders and
    Assigned Work centres to the operations and
    assigned the Resources to the Operations.
    The HR assignment to the work center is also done.
    I have tried T Code   /MRSS/PLBOSRV - Enter the MRS planning board using a specified order
    to pull the order demand. But it is not working
    Its giving following message
    1004280 is not a valid demand
    Message no. /MRSS/SGU139
    Diagnosis
    The order does not exist in MRS.
    This may be because:
    The order number has an invalid format.
    The order does not exist.
    The order is not relevant for planning and has therefore not been transferred to MRS.
    The order has been deleted from MRS.
    Pls help me on this.
    Thanks in advance and warm regards
    Purnendu

    Hi Anil/Saurabh - Thanks a lot for your replies.
    I have checked the MRS configuration as per your suggestion.
    It looks fine as per the configuration guide. I have done the PM/CS integration for Orders as demand.
    But the Demands are not visible on the Planning Board.
    I have checked in the debugging mode what is causing the problem - It looks like
    "The Database Table: /mrss/d_dem_h  needs entry"
    But there are no entries in this table.
    I could not find any Customizing transactions or Application transactions for maintaining this table. This is an Application Table for Master and Transaction Data and its Display and Maintenance allowed with Restriction.
    I could not also find any transaction for transferring Demand from ECC(R/3) to MRS.
    How do I maintain entries in this table?
    How do I transfer Demand from ECC to MRS?
    Saurabh - I have also been not able to transfer HR Resources from ECC to MRS.
    We don't have WFM Core installed in our instance. But MRS should work fine without WFM. MRS Basis should take care of it.
    To transfer Employee resources i have run the Program " /MRSS/HCM_RPTWFMIF". But when I execute the transaction with the selection parameters system shows that it is processing (Clock at the bottom Status bar) but it does not shows any result or status.
    So I am not sure whether it is executing the program properly.
    Pls help me resolve these issues.
    Thanks and warm regards
    Purnendu

  • Broadcasting schedule not visible

    With a webreport I can use Broadcasting with Distribute command. I this workflow I have a popup with the choice :
    Step 4 From 4: Determine Scheduling Details
    Determine when the broadcast setting is to be executed
    1/ Execution with Data Change in the InfoProvider 
    2/ Scheduling in SAP Background Processing 
        Create New Scheduling 
        Periodic All, Day(s), Week(s), Month(s) 
      Next Start at  At  
    <b>The (/2) second part Scheduling in SAP Backgound is not visible, only visible when I use a SAP ALL user</b>
    Have you any idea ?

    Thank you for your reply.  We checked RELE in the S_BTCH_JOB Authorization but the SAP Scheduling option is still not displayed for our user in the Information Broadcaster.  The first part (Data Change in InfoProvider) is displayed, but not the second part that allows the user to schedule a specific date and time and frequency.  Can you give us any other authorizations to check for?

  • Variables from workbook are not visible in the Planning function

    Hi,
    We're using a workbook with a bunch of queries in it. Every query has a lot of variables declared that are calculated based on two input ready variable that users are required to fill the first time.
    Everything works as expected until the save data function is called, which in turn calls the planning function.
    Here, the user exit variable try to be recalculated again. Unfortunately, this planning function loses track of the two input ready variables that were on the workbook, so the user exit variables have no values.
    Can you please suggest a method so that:
    a) The user exit processing in the planning function "sees" the two input ready variables
    b) The user exit processing is not triggered in the planning function and it's taking the already calculated values
    Let me know if you require further information.
    Best regards,
    George

    Hi,
    the variables in the filter of the query lives in one variable container and the variables of the filter of the planning sequence live in another variable container. They do not know each other. You need to establish a relationship between them. Usually this is done via variable binding for regular variables. For exit variables the variable binding can be done as written above.
    If as in your case you have variables in the filter of the query and you want to use their values in the variable of the planning sequence than you need to store the values somewhere where you can retrieve them in the exit. This can be in a e.g. in shared memory or in the session memory. To do this you need to spend an extra exit variable in the filter of the query. The exit variable reads the real values and stores it somewhere (e.g. shared memory, global parameter of a function group, a class member or something similar). Now as the variable value is stored it can be read in the implemenation of the exit variable in the filter of the planning sequence.
    In total we have 3 variables:
    Variable 1 contains the value which the user keys in and exists in the filter of the query.
    Variable 2 reads variable 1 and stores the value. It needs to be defined in the filter of the query as well.
    Variable 3 reads the stored value and needs to be defined in the filter of the planning sequence.
    Regards Matthias Nutt
    SAP Consulting Switzerland

  • Caret is not visible in cell of table when typing

    Hi!
    I have JTable
    1.Selected any cell (caret is not blink in cell)
    2.Start type
    When I entered any text the caret is not visible in cell. Why? And how I can set visible caret?
    Thank you

    Dear MuddasarAmin ,
    use current_date varible instead of  + "to_date('" + getCurrentTimeStamp() + "', 'dd/mm/yyyy')"
    will help u
    java.sql.Date current_date=
    new java.sql.Date((new Date(System.currentTimeMillis())).getTime());

  • Consider preventive maintenance schedule into PP order capacity planning

    Hi PP experts,
    My client's requirement is that when a preventive maintenance order is created in PM module for a particular work center (used in production) on a given date, NO production order (which is processed on that work center) should get released or confirmed. In other words, the capacity should be blocked at all for the subject work center.
    Could you please guide how to make this effective?
    We are using discrete manufacturing with capacity planning. At the time of PP order release, system shows capacity situation so as to decide whether go-ahead even with overloaded capacity.
    Regards,
    HKV...

    First, you should assign the PP work center in the location tab of the PM equipment which refers this workcenter.
    Secondly you should enter the sytem condition in the task list of the equipment.
    During preventive schedule  the work center  will be reserved by PM orders for maintenance and this can be seen from capacity planning from PP side.
    regards

  • Key fields are not visible in output condition table

    Hi,
         I have created few conndition tables using V/61. But i can not see Key field. It is not displaying. But when I check thru VK11 i can see that all fields are marked as key fields. example of table B018.
    My problem is that , i want to make few filed non key fields rest of fileds as key fields so that there should not be any duplicate ntry based on key fields. also I do not want to maintain these two fields for each record.
    Is there any exit to modify and view thesefields? or it is a security issue...bold
    Your earliest response is highly appreciated.\
    Thanks,
    AKS

    Hi Raga,
    Please check the documentation under the customizing path:
    IMG -> Sales and Distribution -> System Modifications ->
    Create New Fields (Using Condition Technique) ->
    New Fields For Pricing
    Then click on the paper icon
    Here is explained how to setup additional fields for pricing,
    not present in the standard.
    Notice the following rules:
    1. the new fields must have name beginning with 'ZZ' or 'YY' in order
       to avoid problem after upgrade
    2. add the new field in the table T681F for the application 'V' and the
       usage 'A'
    3. these new fields must be appened to the structures KOMKAZ or KOMPAZ
       (depending they are header or item fields)
    4. you should provide these fields by implementing the userexits
       USEREXIT_PRICING_PREPARE_TKOMK (header fields)
       USEREXIT_PRICING_PREPARE_TKOMP (item fields)
       in program MV45AFZZ for sales order, RV60AFZZ for invoice.
    In that documentation there are some examples too.
    Please check it.
    Regards,
    Alex

  • Demand on VC material not visible in SNP planning book

    Hi Experts,
    Is there any way to plan VC (Variant Configuration ) materials in SNP at the group level ?
    I will explain the scenario more in details below
    I have an VC material say X. Material X has end product Y attached to it (material variant). When material X is cifed to APO, it appears as configurable product in APO & is a top level product. Now when I create a demand on material X through DP, the demand appears in product view (RRP3). However the demand does not appear in the SNP planning book nor it gets selected during background planning run. The system is configured as Variant Configuration & not CDP.
    Is it possible to plan material X in SNP ? If possible how can the demand be read in SNP ?
    Thanks in advance
    Regards
    Sandeep

    Hi Sandeep,
    One of the limitations of Characteristics Based Forecasting is, CBF results can only be used in PPDS and not in SNP, hence it is not possible to plan that material X in SNP. Even though you use MC90 transaction which is release DP to SNP, but the data will not be available in SNP
    That material X will be planned only in PPDS, there are two ways to plan, those are
    1. one way is by releasing CBF results to active version using MC90 transaction, during this release, you should maintain consumption group in release settings and in product master, in this case you have to use Forecast Check/Allocation check as a part of ATP/GATP, here you can not use CTP or MATP
    2.the other way is by releasing CBF results to inactive version using MC90 transaction, during this release you should not define consumption groups,  generate the dependent requirements in inactive verison using heuristics in PPDS , and convert dependent requirements from inactive version to Forecast - active version using /SAPAPO/DMP2 transaction, in this case you can use MATP/CTP as a part of GATP
    -Deepak

  • Business Rules not visible in Hyperion Planning

    I created a group in Shared Services and added 6 (native) accounts.
    After that, I assigned Access Privileges to Business Rules in AAS for this group.
    When I open Planning Web and go to Tools - Business Rules, 5 of the 6 users can see the Business Rules,
    but one users only sees the CalcScripts.
    I think I tried everything; removed/added the account from the group, refreshing security, refresh in Planning-Desktop
    I'm using version 9.2.03
    Anyone knows whats going on here?

    Thats the strange thing; We use (native) groups to provision. This works fine for the other 5 users.
    But even if I provision this one user for the Business Rules, they remain invisible to this user. (in Planning)
    I discovered this morning that this user can create a new BR, but when I try to open it in AAS console I get an error
    "Exception occured, Please check your log file for details."
    Unfortunately, the log doesn't provide any more details. (even if I set the level to Debug)

  • Data written to Live cache but not visible in SNP Planning Book

    Hello All,
    We have an issue this morning, Customer service cordinator placed a Purchase Order in SNP (VMI). Order was sent to ECC and a sales order was created. This morning when we check the sales order, it shows 4574 cases but in TLB Pur chase order, it only some 2000 something. I went to OM16 and checked the sales order and it had the entire 4574 cases written in the live cache. Any help on how to get the entire quantity to be seen is appreciated. Thank you.
    Regards,
    Rohit.

    Hi Ada,
    Thanks for the reply. The issue got resolved by itself.
    Regards,
    Rohit.

  • Not scheduling on manual creation of planned order

    Creating planned order through MD11 and noticed there scheduling not done and capacity planning not done and on doing scheduling manually dates altered and capacity planned which are appearing in CM01 for the respective week
    Planned order created through MRP are fine with scheduling an capacity planning .
    Please let us know what could be a reason for not updating on manual creation.

    Hi
    This is standard behavior of SAP as when you create the planned order through MD11 manually , you need to do the detailed scheduling manually by executing schedule in Edit>Schedule.
    Check this thread:
    Need Automatic Lead-time scheduling in Planned Order using MD11
    Regards,
    Anupam Sharma

  • IMG setting for REM Planning Table

    Hi Gurus,
    Can any one throw light on following IMG settings-
    Path -
    IMG --> Production --> REM --> Planning --> Planning table --> Maintain Row selection --> Reciepts Other version
    Relevance of "Other version - in IMG setting for visible rows in planning table".
    Planning table output does not change with check or uncheck of version.
    Which check or unchecking, planning table is considering all the production versions of the materials maintained.
    What is purpose of having a check or uncheck, if system is giving the same result.
    Regards,
    Srini

    Hi Srini,
    We create production version to OPTIMIZE the production. We mention the routing and the BOM in the production version. Actually speaking, in the REM scenario we don't even need a planned order. Production order is absolutely not needed. So in the planning table, it shows the production data for all the versions that you have created, irrespective of whether or not you check the indicator. During planning run, the system will take the first production version by default. So in the planning table you can see the optimum production and you can do leveling also, possible through the row selection option in IMG. Hope this sheds a light on your concern.
    Regards,
    Sreekant.

  • Salesorder created using BAPI_SALESORDER_CREATEFROMDAT2 not visible in VBAK

    Hi Experts,
    I created sales order using BAPI_SALESORDER_CREATEFROMDAT2, further salesorder ID was also indicated after creation.
    But the same order ID is not visible in SD standard table VBAK.
    Pls guide me to a valid standard CREATE BAPI for Sales order.
    Regards,
    Romi Malik

    Hi Romi,
    If you created a document through BAPI and it does not appear in the database afterwards, the logical conclusion is that ...
    No it wasn't really created
    With BAPIs for sales order data loading, there is no automatic COMMIT! (check SAP notes).
    You need to add the call to BAPI BAPI_TRANSACTION_COMMIT to save to DB.
    Regards,
    Franck

  • Maintenance schedule is not getting generated

    Hi....
    Past one year, maintenance schedule is not getting generated.
    Could you please let me know to where i have to look out for this problem in Equipment & Functional Locations?
    What are all the fields will be mandatory and triggering the maintenance schedule / Notification in Equipment / Functional Locations?
    Need your response at the earliest.
    Regards,
    Mohd Ali.

    Hi
    There May be several resons...
    Check Whether Maintenace for perticualr maintenance plan is not scheduled... their could completion requirement tick might selected previous maint. not done for the equipment.
    Check any scheduling for inactive equips/fl
    check any long offset has been set....
    check while scheduling any sortfield key is set or genral...if pertiucalr sort key is belong to Eq/fl which will not help
    regards
    krish

Maybe you are looking for

  • ORA-01403: no data found when calling a web service from HTMLDB

    I am working through Section 6 How to Implement a Web Service of the HTML DB 2 Day Developer tutorial. I can get the first example to work but not the second one. I am able to add the web reference and create the form and report. However, when I run

  • Do I need the "Apple Mobile Devices" program with just an iPod nano

    I'm going through the list of programs on my computer (using the "Programs & Features" tool in Control Panel, on Windows7) and trying to figure out what's on here that I don't need & can safely remove. There's one program called "Apple Mobile Devices

  • How do I share or save my iMovie project/video

    Everytime I try to share my video to YouTube, it says to click 'Publish' and I do. Sure enough, I open YouTube and there's nothing there. No videos, no uploads. Also back on iMovie, it says 'Not Shared' in the corner of the video. Why does this keep

  • How to add ID autogenerate column to VIEW

    Hi all, Could anybody help me create a View with its own identifier column? I use to create VIEW following syntax: CREATE VIEW MY_VIEW AS t1.f1 FIELD_1, t2.f2 FIELD_2 FROM t1 LEFT JOIN t2 ON t1.f3 = t2.f3 I tried to use sequence like: CREATE VIEW QUA

  • Xcelsius Deployment

    Hi Gurus, I have BOE 3.1, Live Office 3.1 and Crystal Report 2008 installed on the Window Server 2003 (my BOE 3.1 Server). I am now working on how should we design/deploy the Xcelsius Enterprise 2008 architecture. 1) Instead of installing the Xcelsiu