Make to Order - Reservations and Mov Type

Reservations for Make to Order:
We are using Make to Order strategy for job work scenario, i.e. strategy 20. Here we will receive customer material without reference, after quality checking will be posted to Un-res stock.
1.     Now when we run a MRP for finished product the reservations or happening for movement type 261+E, but the stock available is not a sales order stock. How to issue the same without transfer posting, Or can we restrict the reservations for 261 only?.
2.     As soon as we book a sales order, is it possible to transfer post the Materials referencing a material document to sales order stock.
Thanks
RamananPV

Hi,
1. Material is going in unrest stock as there is no reference. Either post stock with reference to SO or you will have to do transfer posting. Take suitable decision as per your business requirement.
2. You mave have to go for development. Discuss with your ABAPer.
Regards

Similar Messages

  • Manual Reservation for Movement type 261

    Dear Friends,
    I want to create a manual reservation (MB21) for production order i.e. movement type 261. But system is not allowing and giving error message order category 10 (prodn order) not allowed for manual reservation.
    Can some one help to know how the setting which allows manual reservation for MVt type 261
    Thx
    Rishi

    Hi,
    After my long analyzation, I came know that, this is SAP standard setting.We cann't make any changes in order category 10. As per SAP standard procedure , the below order categories do not allow manual reservation.
    10 PP production order
    20 network
    30 maintenance order
    40 batch order (process manufacturing)
    50 inspection lot
    So please make goods issue through MB1A , if you want tracking this issue seperatly please put your production order number in text filed.
    I hope the above information is useful for you.
    Please reward points if my information useful.
    Best Regards,
    Nagapandian.

  • Make to order(MTO) and make to stock(MTS)

    Hi friends
    Please Send the details about Make to order(MTO) and make to stock(MTS) process and configuration .if u have any documents pls send to my mail ID : [email protected]
    Regards
    Balu

    dear balu
    MAKE TO ORDER AND MAKE TO STOCK notes
    Make to order Scenario
    1. Make-to-order production is a process in which a product is individually manufactured for a particular customer. In contrast to mass production for an unspecified market where a material is manufactured many times, in make-to-order production a material is created only once though the same or a similar production process might be repeated at a later time.
    2. You can use make-to-order production: (a) For branches of industry or products where a small quantity of products with a large number of different characteristics are manufactured (b) When a product has to be assembled particularly for a sales order.
    3. Stock keeping is not usually carried out for products that are made to order. In companies using make-to-order production, the demand program only determines the production area, in which various variant types are produced. Depending on how you track the costs associated with make-to-order production, there are two ways to process make-to-order items during sales order processing.
    (a) Make to order using sales order
    (b) Make to order using project system (not relevant for SD application)
    4. for make to order production using the sales order, all costs and revenues involved for an order item are held collectively at that item. A particular rule is used that can be changed manually to transfer costs to profitability analysis.
    5. make to order production is largely a production planning configuration. It is also controlled by the requirements type, which is determined by three things
    the strategy group (MRP 3) in MMR
    the MRP group (MRP1) in MMR
    the item category and MRP type (MRP 1)
    6. Make-to-order production is controlled by the requirements type. The requirements type is determined on the basis of the MRP group (MRP1) and the strategy group (MRP3) in the material master record. In addition, a plant must be assigned for make-to-order items in the sales order.
    MAKE TO ORDER PRODUCTION (PROCESS FLOW)
    First Create a material with MM
    Basic data1:
    Give Material name : Cycle
    Material group : 010
    Division : MA
    Net Weight : 10 Kg's
    Gross Weight : 10Kgs.
    Sales: Sales org.1 :
    Base Unit of Measure : EA
    Delivering Plant : RAMA
    Output Tax : 1 ( Full tax)
    Sales: General/Plant :
    Availability Check : 01 ( Daily Requirements)
    Trans.,group : 001
    Loading Group : 0003
    MRP 1:
    MRP Group : 020 ( Make to Order Production)
    MRP type : PD (MRP)
    MRP controller : 000
    Lot size : EX ( Lot-for-Lot order quantity)
    MRP 2:
    In-house Production : 1
    Schedule Margin Key : 000
    Forecasting:
    Forecast Model : D (Constant Model)
    Accounting 1:
    Price control : V ( Variable Price)
    Variable Price : 4000
    Price Unit : 1
    Then enter & Save.
    Material 769 created.
    Create a Sales order with VA;
    Order type : OR
    Sales Organization : RAMA
    Distribution Channel : RA
    Division : MA
    Sales Office : RAMA
    Sales Group : RAM, .............. Enter
    Sold to Party: 6000000000
    PO number : 55 , PO Date : 04.06.2007.
    Item Overview Tab:
    Material 769, Quantity : 100
    Enter & Save the Document.
    Sales Order 8212 Created
    Create Production Order with CO:
    Enter Sales order number: 8212, Item No. 10
    Order type: PP, Enter
    Click on FLAG,
    Select Generate Operation and enter NO,
    save the Document.
    Production Order Created: 60002725
    Confirm the Production Order with CO15.
    Enter Production Order No. 600075 and save the Document.
    Now the confirmation Order will be saved.
    Create Goods Receipts with MB31.
    Movement type: 101
    Order: 6002725
    Plant: RAMA
    Storage Location: RAMA
    Enter and Save, you will get Document Posted: 50000068931posted.
    Check the Stock Position with MMBE
    Material: 769
    Plant: RAMA
    Storage Location: RAMA
    Execute (F8), here we can see the stock at Sales Order Stock.
    Create Delivery with VL01N, Billing with VF01 and Post to Accounts.
    Make-To-Stock Production:
    Purpose
    we describe the planning of a product for make-to-stock production. After requirements planning, you analyze the stock situation and convert a planned order into a production order. You also enter a sales order that is not relevant to the planning. The production order is then released and saved. After the material withdrawals and confirmation of the operations, you analyze the production variances. The sales order is delivered and settled.
    Process Flow
    1. Planning a Product
    T.code: MD61
    Logistics Create Production  Production Planning Demand ManagementPlanned Independent Requirements
    2. Creating a Sales Order
    T.code: VA01
    Logistics Sales and Distribution  Sales  Order  Create
    3. Executing Multi-Level Requirements Planning
    T.code: MD02
    From the MRP node, choose PlanningSingle Item - Multi-Level
    4. Converting the Planned Order into a Production Order
    Tcode: MD04
    From the MRP node, choose
    EvaluationsStock/Reqmts list
    5. Withdrawing the Material for the Production Order
    T.code: MB1A
    Logistics GoodsMaterials Management Inventory Management  Goods Movement Issue
    6. Confirming the Production Order
    T.code: CO11N
    Logistics Time Ticket Production  Production Control Confirmation  Enter For Operation 
    7. Creating a Delivery
    T.code: VL01N
    SingleLogistics  Sales and Distribution  Shipping and Transportation With Outbound Delivery  Create Document  Reference to Sales Order
    8. Creating a Billing Document
    T.code: VF01
     Logistics Create Sales  Billing Billing document
    rewards if it helps
    siva

  • 3rd party order processing GR movement type

    Hi
    In 3rd party order processing the goods are delivered to customer from vendor directly, but for billing purpose we do the GR at plant level(against purchase order)>invoice>Billing
    Physically stock is not delivered to the plant, so when we do the GR(against purchase order),if the movement type is 101 it will updatet the stock. 3rd party delivery is not done,stock will not be reduced. I want to know what is the GR movement type for 3rd party order processing, is it 101 or anyother movement type.

    Hi,
    Check in t.code OMJJ.
    Select movement type 101 and click on update control/WM movement types.
    There you can see this movement type is configured for different update control/WM movment types.
    Few entries are made in the system without value and quantity updates for movement type 101. So I assume, when you do MIGO using 101 movement type against third party purchase order, special stock indicator E and movement type B will be taken for statistical posting. You can do a testing to confirm this.
    Regards,

  • Reservation with Movement Type 415

    Hi All,
    I am trying to create a reservation against movement type 415 (SL to Project) but I can not see any WBS field in the screen whereas when I am referring the reservation number in MIGO for transfer posting, system ask for WBS.
    My requirement is that I should be able to put WBS since my Store Person can not put WBS in MIGO himself unless specified by Project person. For reference take example of reservation with MT 221 which will ask for WBS as mandatory field and it will be automatically picked in MIGO.
    My requirement will be fulfilled by MT 415 or 412 and both are not asking for WBS.
    Kindly explore.
    Thanks,
    Munawwar K

    Hi
    Reservation does not ask the WBS while using the mvt type 415  or 412  as its is standard SAP setting.For you workaround could be the field unloading point will be used for feeding the WBS. This is how store person can identified aginst which WBS the transcation is to be carried .

  • Stock trasfer reservation with movement type 311

    Dear APO Experts,
    I have plant 1200 and storage location MRP area CA_03 within plant 1200.
    When planning, STRs are created and if ciffed to ERP, reservation with movement type 301 is shown.
    My question is as follows.
    Is it possible to create these reservations in APO with the movement type 311 (sloc to sloc) instead of the movement type 301 (plant to plant).
    Thanks in advance for your help.
    Regards,
    Lee, Seung Won

    Hi Lee Seung Won,
    To the best of my knowledge it may not work as you are expecting. The basis reason seems to be that SLOC is not treated as SLOC in APO when it is defined as MRP Area. MRP area (SLOC) is treated as  Plant (Location) in APO. Hence movement type will be 301 plant to plant  & not 311 sloc to sloc
    Thanks,
    Mangesh A. Kulkarni

  • Initial Stock Upload T code MB1C and Movement Type 561through LSMW - Error

    Hi,
    Trying to Upload the Initial Stock, Transaction Code MB1C and Movement Type 561 through LSMW.
    While recording the fileds, system giving a message of Code Block.
    Please let us know about Code Block while uploading the Initial Stock.
    Thanks
    Siddu.

    Check this thread
    [Re: Coding Block in LSMW recording via MB1C|Coding Block in LSMW recording via MB1C;
    thanks
    G. Lakshmipathi

  • Reservation with movement type 541

    Hello Experts,
    I am making reservation with mov type y41 (copy of 541) by allowing transaction MB21 in its customizing.My problem is at the time of making reservation system is not reflecting vendor field, whereas in t code MB1B vendor field is appearing.I also checked in field status group there vendor field is appearing as mandatory.
    Can anybody suggest me how can i reflect vendor field at the time of making reservation with copied movement type in my case its Y41
    Regards
    VS

    Its not possibled i tried

  • Debit/Credit sign settings of item and movement type usage

    Dear BCS Experts,
    According to your experience, where are Debit/Credit sign settings of item and movement type used in BCS? As I know, they can be used during data collection. Any other thoughts?
    Thanks.

    Actually, Barry, I recognised that that was not a doubt regarding BCF. It was (and still is) a doubt about the MoveType sign for that values that are generated automatically during the CoI activities.
    Since the decrease/increase for such activies is defined, there is a question if the sign of these MoveTypes may interfere with the amounts or the side to be placed in (debit or credit).
    Do you have experience in this?

  • Condition Type and Movement Type

    Dear all,
    Could anyone explain how the relationshipship between condition type and movement type are being maintain?
    Example : WE03 and Mvt 101,
                    WA03 and Mvt 201.
    Is there any table or tcodes  to view these relationship?
    Thank you.

    Hi
    Both are linked based on the Transaction event type.
    for GR movements the transaction even type is WE
    For GI Movements the transaction event ype is WA.
    Thanks & Regards
    Kishore

  • Relation between Inventory Process keys and movement types

    Dear All,
    Is there any way to find the relation between Inventory process keys (which is in SBIW-> Settings for Application specific data sources(PI) -->Logistics -->Settings for IBU Retail / CP --> Transaction key maintenance for SAP BW) and movement types .
    Thanks in advance...
    Regards,
    Raju

    Hi,
    Please read the note below.
    Note 353042 - Howto: Activate transaction key (PROCESSKEY)
    It has something for you ....
    The process key (0PROCESSKEY and 0BWAPPLNM) of the InfoSources has not been filled. As a result, no key figures are updated because of the update routine of the participating InfoCube and along with it no records are inserted into the InfoCube. In each update routine, the system checks the content of the PROCESSKEY. If this field has no contents, then no data is written into the InfoCube because of the IF condition in the update rules.
    Solution
    So that you can work in the above mentioned InfoSources, you MUST activate the determination of the process key. This is done with the help of Transaction MCB_ which you can find in the OLTP IMG for BW (Transaction SBIW) in your attached R/3 source system.
    Here you can choose your industry sector. 'Standard' and 'Consumer products' are for R/3 standard customers, whereas 'Retail' is intended for customers with R/3 Retail only.
    You can display the characteristics of the process key (R/3 field BWVORG, BW field 0PROCESSKEY) by using Transaction MCB0.
    If you have already set up historical data (for example for testing purposes) by using the setup transactions (Statistical Setup Programs) (for example: Purchasing: Tx OLI3BW, material movements: OLI1BW) into the provided setup tables (for example: MC02M_0SCLSETUP, MC03BF0SETUP), you unfortunately have to delete this data (Tx LBWG). After you have chosen the industry sector by using  MCB_, perform the setup again, so that the system fills a valid transaction key for each data record generated. Then load this data into your connected BW by using 'Full update' or 'Initialization of the delta process'. Check, whether the system updates data into the involved InfoCubes now.
    If all this is not successful, please see Note 315880, and set the application indicator 'BW' to active using Transaction 'BF11'.
    Hope this helps.
    Raj

  • Valuation class and movement type

    Hi sirs,
    What exactly mean by valuation class and is there any sublink to valuation class and movement type.
    BSR

    Hi BSR,
    Regarding the meaning of valuation class and link between valuation class and movement type, you just have to understand this.
    <b>valuation class + movement type = transaction key --> GL account</b>
    explanation :
    <b>Valuation class</b>
    It is a field maintained in the accounting view 1 of Material master. This is nothing but the classification of material like Raw material, Finished goods, WP, stores & spares etc. It is indicated as numerical number.
    <b>Movement type</b>
    This is a 3 digit numerical code which is used for all material movement in MM module. Say for example movement type 101 is used for Goods receipt from vendor or from production.
    <b>Transaction Key</b>
    The combination of valuation class and the movement type translates into a transaction key which indicates the type of transaction.
    remember:
    The combination of Valuation Class + the Movement Type helps in determining the GL accounts automatic updates.
    hope it helps and don't forget to assign points.
    regards,
    Lily

  • BAPI_GOODSMVT_CREATE with GM = 03 and Mov. type 961

    Hello,
    I keep running in to the same error message when test-running the BAPI_GOODSMVT_CREATE bapi with GM 03 and mov. type 961.
    Although for my product MM03 says that I have 999 tones of stock for unrestricted use I keep getting the message:
    "Deficit of SL Unrestr. prev. 1 T: 900253 DE01 D1CD"
    can anyone understand the reason for this ?
    The application consultants have no problems posting the goods movement but I keep getting the same error message no matter what quantity I try to move.
    Grateful for any help on this matter !
    Best regards
    //Erik

    Hello again,
    After having changed the posting date I now have error message:
    "Fld selectn for mvt type 961 / accnt 412505 differs for network (019)"
    This is starting to feel like som form of customizing missing so my guess is the application cosnultants will have to look at this.
    Ideas still welcome though !

  • Purchase Order Type and Movement Type in MIGO

    Hi
    Is there a way to have a movement type automatically posted in MIGO for different Purchase Order Document Types?
    THanks

    Hi
    If i understand correctly you want to post a single GR pertaining to 2 different PO's that are created.
    If that is the case, I think you cant even post GR for different PO's in a single MIGO.
    Thanks
    Kalyan

  • Miss value FI Posting on Sales Order Transfer Posting movement Type 413 E

    Dear Expertise
                   I've a problem about sales order transfer posting. My both of Sales order (Source & Destination) are make to order and open with configurable material(KMAT). Both of sales order contain only one item on the same material no.
    Assume scenario material vastr
    Assume that material vastr is configurable material wait for sales order to fill characteristic and it was maintained standard price value = 1100
                    Sales order A  has plan cost  on material  VASTR  1000
                    Sales order B has plan cost material VASTR 980
    When we make a sales order transfer posting(Transfer from Sales Order A-> B) by transaction MIGO_TR by use movement type 413 E. It can post a transfer complete. But my problem is when I trace to FI-Document
                    It was post like this
                    Dr. Standard price                         1100
                    Cr. price for Sales order A(src.)  1000
                    Cr. Cost Variance                          +100
    I don't want it to offset with standarad price value. I want it to do like this
                    Dr. price for Sales order B(Des.)   980
                    Cr. price for Sales order A(src.)  1000
                    Dr. Cost Variance                           +20
    How can I configure it?   I trial to clear standard price by MR21, System can do it . But I don't want to clear it because it impact to other. I want to know. How can I configure system to take both of plan cost of sales order to offset each other please.
    Edited by: Gareth John on Aug 16, 2010 2:23 PM
    Edited by: Gareth John on Aug 16, 2010 2:42 PM
    Edited by: Gareth John on Aug 16, 2010 2:42 PM

    Hi,
    411- E- sales order to own stock
    412-E- Reversal of 411 E
    & 413-E-Sales order to sales order.
    Regards,
    Piyush

Maybe you are looking for

  • How many ipod can i have on one computer??

    Currently have a 2G 8 gig, wanna get a 3g 32 or 64gig. I want to keep my 8 gig though also for the GF to use. Can i use the same computer and Itunes account for both of these?? Thre are apps and stuff off of the 8 gig i want to use on the new one.

  • J2SE Adapter Engine

    Hello Everyone, I've got a little problem. I must cover the requirement that a file adapter exactly runs each night at 2 a.m. But the "polling mechanism" only allows to say that the adapter runs each 24 hours. Any suggestions how to solve this proble

  • External user - no subscription found

    Hi, I added an external user (=> using a Microsoft ID) in my Azure AD. When this user tries to access our Azure Administration Link, there is no subscription found for him. I made this user an Administrator for Azure, but with no success. Any idea wh

  • HT1766 grayed out wifi

    I did all of the above and my wifi is STILL grayed out.  Don't know what to do.  I am going over my plan all the time in data usage because I can't use wifi at home, and my bluetooth won't work in the car which is unsafe.  Help!

  • Third Party Filters in PSE 13

    Hi, I have been using PSE 10 for some time now, and have been using 3rd party filters/plugins in the editor (Topaz Labs, DXO ViewPoint, Perfect Effects). As these other tools were installed after I installed PSE 10, I could see them listed at the bot