Material Master Price as Selling Price

I am using VPRS as my selling price on my pricing procedure and it is working just fine.
What I really want is cost plus 10% and I am having difficulty writing my VOFM Formula (alternate calculation type) to work correctly.  I built in under Formulas, Condition Base Values.
xkomv-kbetr = xkomv-kbetr * '1.10'.
is not working.  my cost is $7.06 so I am looking for a final selling price of $7.76 or $7.77.
My KBETR for one unit is $85,426.00 and my KWERT for one unit is $776.60
I am a functional analyst with no staff ABAP'r to turn to.  Can anyone help me please?

Dear Laurie
Assume your VPRS cost is $ 7.06 and your selling price should be $ 7.76.  Now the difference would be 10%. 
Go to V/06, copy any condition type, rename as ZR00 and maintain the following:-
Cond. class::::::::::::::::A
Calculat.type::::::::::::::A
Cond.category::::::::::::blank
Rounding rule:::::::::::::Commercial
Plus/minus:::::::::::::::::A
Manual entries::::::::::::D
Item condition:::::::::::::X
Amount/percent:::::::::::X
Delete:::::::::::::::::::::::::X
Scale basis:::::::::::::::::B
Save the condition type
Go to V/07, select the condition type ZR00 and maintain 535 table which is for customer.  Now go to VK11, inpur ZR00 and maintain 10% to customers.
Now go to V/08, maintain VPRS as your PR00 in step 100, on top with respective Account Key.  After this condition, insert one step (say 101) with condition type ZR00, assigning From-To value as 100.  Insert one more step 102 with description as "Sub total" with FROM - TO as 100 & 101 so that your selling price would be VPRS + ZR00 which is your selling price.
thanks
G. Lakshmipathi

Similar Messages

  • Material master price

    if we want to see when we created  the material that time what price we have entered, then how can we see,

    Hi Nitin
       Usually Materila Price will be maintained in Condition Type Vk11 or in Purchase info record. We can maintain a standard or moving average price in Material Master
    In Accounting View we maintain this price. But once the Material Master is Saved the standard price or Moving Price will be Greyed out. U willnot be able to edit it again. But that Material Master Price in Accounting willnot be same some time due to market change in price of the Product.
    So Always Price, For SD will be in Condition Record VK11 and Price for MM will be in Purchase Info-record. And always remember when we create a PO price of the material will be taken from Info_record ONly.
    Reward if Useful

  • Material master price, inforecord price and GR

    Hi gurus,
    Can annybody please clear my confusion. On the PO the price that is proposed is from the inforecord. When we receive the PO, what is the price at which the stock will be valuated? is it the material master price or the inforecord price? if we change the price on the PO after the inforecord has proposed the price, will the GR be valuated at the changed price of the PO. Please expolain
    Thanks
    ANusha
    Edited by: anusha vemulapati on Jan 19, 2010 8:11 PM

    the GR is valuated according to the price control set in the material master. if the price control is standard price, then the GR is valuated with the standard price, no matter what price the PO has.
    in case of moving average price: if the goods receipt is executed before the invoice receipt, the goods movement is valuated with the purchase order price. If an invoice is already posted, the system uses the price of the invoice. If a partial invoice is received, the partial quantity corresponding to the invoice is valuated with the invoice price, the rest is valuated with the purchase order price.
    if you change the price in the PO before you do a Goods receipt (and before you post an invoice receipt), then the GR is valuated with this new entered price.
    how the price in PO is determined can be read in OSS Note 456691 - FAQ: Price determination in purchasing

  • Purchase Order from Material Master Price

    Hi All,
    Can I customise the system in such a way without any development in which I want that while creating PO the system should take the Price from Material Master if no Info record is maintained.
    Thanks,
    Lekhram

    If you are using the requisition to create the PO then it is possible other wise not.
    If you use PR
    the do the follosing setting in OMET trasnction, select the adopt PO price
    the go to SU3 and enter the parameter id = EFB and value =  Function authorization code (e.g 01)
    now when you create the PR
    on valuation tab you can see the field PO price
    select the price as gross or net price
    this will copy the Mateiral price (PR price) to the PO

  • PIR and material master price

    Dear all,
    Say i have standard price maintained in material master as $2.00 per piece. This price is inclusive of freight cost or duty cost. Where as in PIR it is $1.20 only on material cost. the 80cents of freight and duty i built in PO condition by percentage.
    1) May I know if it is ok to have PIR and standard price at different price because 1 want to calculate the freight and duty condition in PO by percentage?
    2) when there is difference in amount during migo or miro against $2.00, then will go to price difference.
    thanks

    The frieght & duty cost should not be part of standard price. Actually the situation should be reverse where the standard price only has material prices and the info-record should have the freight, duty etc.
    Only though this way you can maintain the sanctity of standard price.
    Coming to your second query, yes during transactions the difference between standard price and PO price will go into price differences account or other account as determined automatically through account determination set-up

  • Material master: price S vs price V.

    Hi,
    when a material must be valuated at standard price and when must be valuated at moving average price?
    Best regards

    Hi,
    Generally we do use Moving average price (price control “V”) for raw material & for semi finished and finished goods for Standard price procedure (price control “S”).But its all depends on business requirements.
    Note:
    Moving average price (price control “V”): The system valuates goods receipts with the purchase order price and goods issues with the current moving average price. The system automatically calculates the latter upon every goods movement by dividing the total value by the total stock quantity( Total Value/Total quantity). Differences in price between the purchase order price and the invoice are posted directly to the relevant stock account if there is sufficient stock coverage.Overally you can say System calulate automatically MAP taking into consideration of GR/IR.
    Standard price procedure (price control “S”):The system carries out all stock postings at a price defined in the material master. Variances in price are posted to price difference accounts.Overally you can say Standard Price is calulated without taking into consideration of GR/IR.
    Regards,
    Biju K

  • Material Master Price Unit field MBEW-PEINH

    Hello,
    In my experience I've always dealt with the Price Unit being equal to 1000 (1.00 for 1 ; 1000.00 for 1000). It is my understanding that this was decided upon due to the decimal point limitation. In my new project, everything is set to 1. Is this an issue at all? If a few parts are less than .01, could just those be set to per 100 or 1000?

    Hi,
    the price unit can be set on plant level of material master.
    nd it is highly suggested to set the price unit to a level where the valuation price is something like 494,99 / 1000 units instead of 4,95 / 10 units or 0,50 / 1 unit (I've already rounded the values as SAP would do).
    best regards, Christian

  • Material master price problem

    Sir in material material master ( MM03 ) accounting view we mention price of material , there my system is showing me price in 70.000,000 format , means if i want seventy thousand then after 70 one fullstop appears and in place of fullstop comma appears .What to do to get correct no. sequence ?
    Moderator: please do not cross-post the same issue into several forums. Thread locked.

    Hi Frnd,
    Please run SU3.
    Enter the User ID. Go to Default Screen and change the decimal notation according to requirement.
    Assign Points if found Useful
    Regards,
    Jigar

  • Reg material master price

    Dear all,
    For a finished material which is manufactured inhouse we are following one process and price is 100 per unit, same material if it is going through another process inhouse it is 150 per unit. in material master if price unit is s. in my inventory there are 100 units which are made through process one, there are 100 pieces which are made through process 2. While doing initial stock uploading for the 200 pieces what is the standard price to be taken.
    Thanks in advance
    Madhav

    Dear Rao,
    In this case ,I have few queries.
    1.If you want to use mixed costing and if it is going to be 50%-50% for each process means,then use the average price,say Rs
    125 while uploading the stock using MB1C and for 561 movement,here you can enter the amount in CC.
    2.In case if you are not using the mixed costing concept then its a business decision to be made by the client side people.
    3.But generally standard cost estimate is performed before uploading the stock,so that it automatically valuates the material
    using the standard price.
    Check and revert back with your further queries.
    Regards
    Mangalraj.S

  • Material Master Price Change

    Dear All,
                 We have maintained Material Price as zero in the material master .Now we want to change the material price to the actual price .What is the process steps we have to follow.
    Thanks,

    HI,
    Go to MR 21 , here give the plant and executte,
    Next screen enter the material and new price.
    Now you in material master.
    Note: consult the inanacill and aloso also any Open orders.
    Regards,
    Andraaa

  • Price in material master

    Dear all
    the price in material master was 15.50 INR but due to client required 3 decimal place so fico consultant has changed it to 3 decimal place in spro SAP Natwear ->general setting--->currency  and maintained 3 decimal places. it changes to 155.0 when this problem occcured  he changed as before. it doesnt effect in material master price.
    the problem is that this is not for 1 material this is for all materials.how to make it as previous
    how to changed it .
    please help me out.
    regards
    Pravin

    Hi,
    Please let me know whether its a Standar Price Or Moving Average Price.
    Whatever it may be you can change the Moving average Price for a Particular Plant in MR21 Trxn code.
    If its a Standard Price Re enter the Price in the Future value Field and Give Valid from date. Bcoz once you enter Price in the Material Master it wont Fluctuate.
    Reg,
    Ashok
    Please ssign points if Its helpful.

  • Updating Price in previous period - Material master

    Experts,
    I create a new material and want to update the price in previous period. I update successfully through MR21. when i check material master price is shown only in previous period(May) and its howing current period price is ZERO.
    Is it possible to bring the previous price to current price tab automatically?
    R.S

    Hi,
    You may check in OMRN and set column price carried over.
    In the case of a price change in the previous period or in the previous year, you must define whether the change also applies to the current period. You have two options:
    The price change applies only in the previous period or previous year and does not affect the current period.
    The price change also applies to the current period; the price in the current period is thus also changed automatically.
    Activities
    If you want price changes in the previous period or previous year to also change the price in the current period, select column
    Price carried over.
    Thanks and regards,
    Polly

  • Can we bring MAP of Material Master for Purchasing price.

    Dear All,
    Can any body suggest , how to get the MAP of Material Master in Purchase Oder in PBXX or PB00 or any other condition type.
    Our Business requirement is very dynamic and requires MAP of Material master price rather PIR to avoid master data maintainance.
    Thanks & Regards
    Sudhansu

    hi..
    go to m/06 and open ur condition type...
    then..in condition category tab choose "t" i.e. Moving average price.
    try it out..
    hope it works..
    thnks..

  • Can i have a selling price in material master

    hi,
    sap gurus,
    can i have a selling price in material master
    if yes where
    if no why
    plz help me on this
    regards,
    balaji.t

    balaji timmampalli achari wrote:>
    > hi,
    >
    > sap gurus,
    >
    > can i have a selling price in material master
    >
    > if yes where
    >
    > if no why
    >
    > plz help me on this
    >
    > regards,
    HI Balaji,
    You can not have a selling price in material master.
    The reason is the selling price changes due to conditions say a particular customer you may want to charge less (a platinum customer) a particular season you may want to give discount a particular area you may want to sell the material costlier or vice versa there can be a thousand variations of selling price where as Material master it is going to be same.
    So we assign selling price in condition price and attach these condition types to Pricing procedures and hence these can be picked up automatically during Sales Order.
    It is for this reason that we maintain selling price in Condition types so depending upon the condition of sale the correct price is picked up.
    Nevertheless the manufacturing cost of the material is same to the company no matter what this is maintained in material master in costing view price per unit.
    Reward if helpful
    Regards
    Abhishek

  • Price update from Original Material to copied Material Master

    I have a scenario,
    We are selling Raw materials to outside companies who have shortage of materials on Loan Basis. Once they have materials, they will return the materials within a time period. If they don't have the materials and unable to return within the said time, they will make the payment.
    We will follow the normal sales process to sell the item to the customer.
    1. creating sales order,
    2. Outbound Delivery, and
    3. Billing
    Return process when receiving the materials from the company.
    1. Billing Cancellation
    2. PGI Cancellation
    Since this is not an actual sale, hence we need to maintain selling price same as the purchase price.
    We are planning to extend the Raw Materials to Sales View in the material master. However, we came to know that this will be Violation of Act. Hence we are planning to create a new material by copying the existing Raw Material master but the Material type will be Issue on Loan. This material will have sales view and purchase view.
    This material will have a separate Valuation Class. Price control indicator will be V, since the item should be valuated at Purchase Price and the purchase price will keep changing as and when the price changes. This moving average price will be used as selling price.
    The same price needs to be updated in the Sales Order automatically from the Loan Material Master when selling the Loan Material.
    Now, the problem we are facing is, if we create a new Loan Material by copying Raw Material master with ROH material type, how will the price update in New Loan Material since, we will not purchase the Loan Material. We are purchasing the original item as raw material. Hence, this will not update the Loan Material Price automatically and the price will remain unchanged.
    Please suggest a work around?

    Hi,
    Let me explain to you how I am proceeding.
    Step 1:
    Create new material master by copying existing Raw Material with Issue on Loan material type. I am assigning a new Valuation Class in this material master. Also, we keep the pricing
    Step 2:
    Transfer stock from old material to new material in MB1B with movement type 309.
    Step 3: Issue of Loan Material to Customer on loan basis.
    Creating Sales Order, PGI and Billing
    Step 4: Receipt of Item back from Customer
    Sales Return process.
    Step 5: In case Customer does not return goods, then we will collect payment from them
    In the entire process we need to maintain the selling price at purchase price of the original material. Can you suggest any work around, in case this process is not advisable.