MF60 (Material staging) - Display different requirement dates in pull list

Hi
I've got the following problem.
If I choose a couple of process orders, the pull list of the material staging, summarize the quantitys and shows only just one requirement date. Instead I need the different orders and the different requirement dates to be shown for the consumption of components in the pull list.
Anybody know how to configure the pull list to show this scenario?
Thanks a lot.
Francisco O.

Hi,
When you make a pull list , the system will create reservations
for the components that comes from all the open orders collectively.
The reqmts date will be the earliest one.
Now you have to click the Blue lens in which the system will
show the reqmts of components arising from various orders separately and each orders reqmts date will be shown individually.
Regards,
nandha

Similar Messages

  • Why is RoboHelp not displaying the required data content of .chm when linked as Help in my App ?

    Gorgeous Hello All,
    Has anyone encountered the below-said show- stopper. Another BIG TIME help required, will help me in tremendous fashion.
    Am using Adobe RoboHelp, Version 10 and IE version being 10.
    In my local machine :
    1.)I have completed my technical writing courtesy Design editor
    2.)Generating chm File : View -> Pods –> Single Source Layouts -> Right Click on Microsoft HTML Help -> Tagged Set as Primary Layout
    3.)Generating Primary Layout : File -> Generate -> Primary Layout (Microsoft HTML Help)…
    4.)Viewing Primary Layout : File -> View -> Primary Layout
    Everything works FANTASTICALLY till here with the required output (as Hide, Back, Refresh, Home, Print, Options, Contents, Index, Search, Glossary and with the data contents)
    Show Stopper, At my Application Server :
    5.)I copy the entire robohelp project folder from my local machine to my application Server path
    6.)My Application has been developed in ASP .NET, Version 4.0.
    7.)Help link has been created in this application wherein here the file name of < >.chm has been linked in the code to be read from the  Server’s RoboHelp project folder\!SSL!\ Microsoft_HTML_Help\
    8.)I login into my above-said application -> click on the Help page -> Displays the required structure /buttons as Hide, Back, Refresh, Home, Print, Options, Contents, Index, Search, Glossary
    a.)Clicking on any of the Books or Topics appearing beneath Contents : The System prompts out with error cautionary message called “ Navigation to the webpage was cancelled. What you can try: Retype the address ”
    *** This is a huge SHOW-STOPPER. I spent plenty of hours on this, but unable to deciper with a solution at all) ***
    ( Note : Am able to directly open and read the required data contents by Clicking on any of the Books or Topics appearing beneath Contents from Server’s RoboHelp project folder\!SSL!\ Microsoft_HTML_Help\ < >.chm )
    Why is the RoboHelp not displaying the required data contents of <>.chm when linked as Help in my Application ?
    Cheese – Vipin Nambiar

    If you looked at the error message and searched the forum, you should find the answer as this is a problem that started in 2005. You should not run CHM files from a server and cannot without editing the users registry. See the page below.
    http://www.grainge.org/pages/authoring/chm_mspatch/896358.htm
    All along your questions have been based on webhelp, why suddenly are we going go CHMs.
    See Snippets on my site for the correct form of help to use in different scenarios.
    See www.grainge.org for RoboHelp and Authoring tips
    @petergrainge

  • Error while creating requirements data in pendulum list indirect sales.

    hi all,
               i am getting the following error while creating requirement data in pendulum list indirect sales. t - code - /BEV4/PLAN
    " ERROR OCCURED WHILE DETERMINING PERIOD IDENTIFIER""
    -- help would be much appreciated..
    thanks in advance
    leo

    var spObj = $().SPCascade({
    destListColTitles: ['Continent','Country','State','City'],
    srcListColInternalNames: ['Continent','Country','State','Title'],
    srcListName: 'CitiesLookupList',
    srcListFilterCAMLQuery: "<Query><Where><Contains>
    <FieldRef Name='Continent'/><Value Type='Text'>America</Value>
    </Contains></Where></Query>"
    spWebURL: 'http://sharepointurl',
    getDataOnly: 'false',
    debug: 'true',
    });

  • Multiple posting of Components in MF60 Material Staging

    Dear friends
    Greetings.
    Issue : Multiple posting of Components in MF60
    Scenario:REM Make to stock
    We are using MF60 Transaction code for Issuing  (Material staging) materials against planned order.
    User selects the components and qty to be staged and posting happens after pressing save button.
    Material issued to the production location by  911 movement
    After staging we found that in some of the material documents qty posted is several times in the excess of the
    enterd qty. ie , Multiple postings for same material
    Ex : Material document reads as below
    Sl no         Material      Qty
    1              102020      10
    2              104255      10
    3              102020      10
    4              104255      10
    5              102020      10
    6              104255      10
    7              102020      10
    8              104255      10
    Enhancements  :we are using Packet size data for tiny componet issue (ie, To issue more than the requirement quantity)
    Is there any enhancements to restrict the material postings in case of multiple lines (excess material issue)
    Regards
    Jan

    Hi,
    When you make a pull list , the system will create reservations
    for the components that comes from all the open orders collectively.
    The reqmts date will be the earliest one.
    Now you have to click the Blue lens in which the system will
    show the reqmts of components arising from various orders separately and each orders reqmts date will be shown individually.
    Regards,
    nandha

  • MF60 Material staging (Error E7021 by staging)

    Hi,
    I've tried to stage the components through the T.Code MF60. I get 100 pc in the storage location and I need 120 for my production order. I got an error(E7021) 20 pc shortfall.
    I would like to stage the available goods 100 pc in spite of the difference and get a warm message instead of an error.
    Thanks
    Dede

    Dear Dede,
    In MF60,under global settings select all the indicator except for Include all requirements.
    Execute and you will be able to stage the available 100 quantity.
    I guess you have not selected the indicator for Stock transfer requirement in the global settings.
    If this is not included means then directly the stock will be transffered from one storage location to
    another.If included means then only a stock transfer reservations gets generated.
    This Reservation no can be seen in MB25,and stock transfer can be made in MB1B for the reservation
    no.
    check and revert back.
    Regards
    Mangalraj.S

  • Displaying different child data within another grouped child.

    Hi,
    I'm trying to configure a Siebel BI report and have come up against an issue I'm hoping someone can help with. I have a parent entity (not sure what this would be called in BI terms, en element?) which has several child entities.
    The parent entity is a repeating group and has a child entity within it which is also grouped. Within that child grouping I would like to list (and ultimately filter) another child entity but I cannot it to display any records. If I remove it from the child grouping the records are displayed fine.
    Sorry if the above is not clear!

    Do paste your XML here and let us know the requirement.

  • How can I display only the Data Logging pull down menu on my LV front panel?

    Is it possible to hide all unused pull down menu on my front panel vi like File, Edit, View etc.. and only
    display the pull down menu for the Data logging?!
    best regards
                          Norick

    Hey,
    You can build your own runtime menu (Edit>runtime menu) and then e.g. only display the application items you want to.
    Christian

  • Rounding material quantity on material staging

    Hi everyone,
    I have a situation that while material staging, every material is listed as exact quantities. But I need to round the quantities according to their unit of entry, pallet, packet etc. Could you give me a solution alternative?

    Hi,
    Maintain unit of issue in material master view PLANT DATA STORE.1 as per your requirement.
    The try with MF60, material staging,
    Regards,
    Suhas

  • Different Exception messages in MRP list & Stock Requirement List

    Hello Experts,
    When I run MRP and then look at the stock Requirement List & MRP list for the same material, I see different exception messages in these list.
    I noticed that any of the exception messages in Exception group "7 - Exception during rescheduling" (ie, 10-reschedule in; 15-Reschedule Out; 20-cancel process; 30-plan process according to schedule) is not appearing in the stock requirement list even though they appear in the MRP list.
    Does any configuration affect what message group can appear in Stock Requirement List & MRP list?
    Please advice.
    Regards
    Tom

    Hi Tom,
    For exception message - 62, just do the below checks -
    Some of the reasons as to why you may find this exception message is because the backward scheduling can drive the start date in the past so far that:
    - there is no valid BOM as of that date
    - one or more of the work centers are not valid on that date
    - there is no valid factory calendar on that date
    Check the scheduling formulas in your work centers that are set up, and/or to specify for the material master a fixed lot or a max lot size so that planned orders result with realistic lot sizes.
    Also you can set up MRP to only run on basic dates for your overall run, and to follow up with an MRP run which generates capacity planning only within the planning horizon, such as NETPL.  You would need to configure the planning horizon so that it specifies a time frame over which capacity planning is to be done.
    Also check the note : 88505 - Planned order upload generates exception message 62
    In short, do a thorough check of the parameters maintained to ensure there is no inconsistency in the master data.
    Check & revert.
    Regards,
    Vivek

  • Material Staging against planned order

    Hi Gurus,
    We are using mf60 material staging issue material to production storage location against planned order.
    If we select particular planned order to issue the material through MF60 material staging which is issuing correctly. But when if we select other planned order to issue material and for common material system considering the stock laying at production location and netting off further not showing for staging which is incorrect the material which is already issued is reserved for some other planned order.
    please advice..
    Regards
    cs

    Hi,
    In planned order bom, materials are under dependent requirement, and not in reservation.
    Unless you convert it to production order, the dependent requirement will not be converted to reservation.
    I think its okay,
    If you have any special stock indicator for this then it will not consider the stock,
    Regards
    Raghu

  • WO basic start date - requirement date

    Good morning folks,
    Would anyone be able to shed some light on any config that would be suitable for the following:
    The materials are assigned to a task list that is then assigned to a plan.  That plan is then scheduled and the work orders are generated.
    When the materials are added to the work order their requirement date is automatically assigned as the work order basic start date - can this requirement date be pulled from the scheduled dates instead?
    The problem is that the material may not be required at the beginning of the WO, so the defaulted basic start date of the WO would not be the way forward.
    Thanks
    Mantas

    hi Mantas
    you can set in scheduling parameters with following possibilities
    <b>Path Plant maintenance and customer service->Maintenance and service order->scheduling->set scheduling parameter</b>
    1)The basic dates are adjusted and the dependent requirements are scheduled for the start dates of the relevant operations.
    2)The basic dates are not adjusted and the dependent requirements are scheduled for the start dates of the relevant operations.
    3)The basic dates are adjusted and the dependent requirements are scheduled for the order basic start date.
    4)The basic dates are not adjusted and the dependent requirements are scheduled for the order basic start date.
    so when you add the components you have to assign the operations,after selecting the operation you can change the operation date, after you change the operation dates,the material scheduled dates will be changed to the operation date
    (using the option <b>1</b>)
    regards
    thyagarajan

  • Missing parts if GR date is past requirement date

    why am i getting a missing parts message if the GR date / delivery date of the material is past the requirement date of component in the order? couldn't it be possible to make these components available, for more flexibility in the system?

    Hi!,
    Please check your "availability check control" for the combination of your checking group (e.g. '02') and checking rule (e.g. 'PP') on trnx OPJJ.
    There do the following settings:
    1. Incl. Purchase orders: Select
    2. Incl. purchase requisitions: Select
    3. Incl. Planned orders: select' X'
    Or
    On OPJK, for your plant and order type combination and avlb check '2' set release material as '1' or '2''. This will help user to release the order even in case of material shortage.
    I think this may solve your issue. Please revert back in case of any further issue.
    Regards,
    Uday
    Edited by: Uday Parchure on Oct 3, 2008 7:30 AM

  • Reservation iscersue in material staging MF60

    Dear experts,
    Our users having issue regarding material staging for production order. Before proceed please take a look of activities performed by users for order confirmation.
    1)      Production order creation – co01
    2)      Material staging - MF60 – As some of materials are not available to require storage location and available to different one. Here system generates the           reservation no.
    3)      Pull list posting- MF65 – post the reservation for stock availability at storage location.
    4)      Once stock available for order, order confirmed by t. code ck11n.
    Now issue is lying in stage 2 as follows with example –
    Order 1 and order no. 2 has been created for material A and B respectively. These both material consist of some of identical/Similar component like A having x, y and z whereas B having x, y and m. here X and Y are identical in both BOM.
    Now when user stage the material with MF60, he must have to stage first order first and post the pull list otherwise system does not shows similar components in staging step, or only shows those material to stage which are not identical for production order of B.
    Is it due to collective requirement indicator set in material master ?
    Please suggest the solution. and reason for issue
    With best regards,
    Manish K. Bachate

    Dear muhammad,
    You are right. Users always unchecked the include all req. indicator from global setting.
    Well if we check this indicator while staging, would it consider all req. for that material or only for that order ?
    Secondly as i said in issue post, this problem is arises when there are 2 prod. order which having similar component. until and unless i stage first order material, it wouldn't shows requirement for 2nd order while staging.
    Can you please suggest solution for above issue or what changes we require to made in our transaction method.

  • How to display different icon within WDA alv table base on row data ?

    Hi,
    is that possible to display different icon for every row within ALV table depending on the row data ?
    for instance if the status 'S' display ~Icon/SuccessMessage and 'E' display ~Icon/ErrorMessage ?
    because base on this code below i only can set 1 icon for the whole row data.
    LOOP AT lt_columns ASSIGNING <fs_column>.
        CASE <fs_column>-id.
          WHEN 'ICO'.
            CREATE OBJECT lr_caption.
               lr_caption->set_image_source( value = '~Icon/SuccessMessage').
               <fs_column>-r_column->set_cell_editor( lr_caption ).
        ENDCASE.
      ENDLOOP.
    Thank you in advance.
    Fernand

    Hello,
    Yes it is possible to display different images based on data.
    For that what you can do is create one attribute 'STATUS' of type string in context node which you are mapping to ALV.
    And fill that attribute with the path to image based on your requirement like for status 'S' set the attribute to ~Icon/SuccessMessage and if status is 'E', set it to ~Icon/ErrorMessage at runtime.
    Now in the settings for ALV use the following code:
    * Display icon in column seatsocc
      DATA: lr_column TYPE REF TO cl_salv_wd_column,
            lr_image TYPE REF TO cl_salv_wd_uie_image,
            lv_icon TYPE string.
      lr_column = lv_model->if_salv_wd_column_settings~get_column( 'SEATSOCC' ).
      CREATE OBJECT lr_image.
      lr_image->SET_SOURCE_FIELDNAME( 'STATUS' ).
      lr_column->set_cell_editor( lr_image ).
    in the above code, column 'SEATSOCC' will be displayed as an icon.
    Sample code to fill the attribute 'STATUS'
    LOOP AT lt_flights INTO ls_flight.
        lv_seatsfree = ls_flight-seatsmax - ls_flight-seatsocc.
        IF lv_seatsfree = 0.
          ls_flight-status = 'ICON_RED_LIGHT'.
        ELSEIF lv_seatsfree <= 50.
          ls_flight-status = 'ICON_YELLOW_LIGHT'.
        ELSE.
          ls_flight-status = 'ICON_GREEN_LIGHT'.
        ENDIF.
        MODIFY lt_flights FROM ls_flight.
      ENDLOOP.
    Hope this helps!
    Regards,
    Srilatha
    Edited by: Srilatha M on Jun 25, 2010 12:02 PM

  • How to manually change the material staging date

    Hi All,
    Please help me to manually change the material staging date in MF60?....
    Problem iam facing is planned order created for 30.06.2011, but when i do staging today it is not staging due to period for july not openned...
    so I manually planned to change the material staging date in MF60...
    Please help me on this...
    Thanks,
    Manikandan.P

    Hi
    Please find the code below for changoing the status in the delivery  and the standard program for updating the status  RVDELSTA
    SELECT SINGLE * from vbfa  where VBTYP_N = 'U' and vbelv = ' '.
    if sy-subrc = 0.
    UPDATE  vbfa  SET PLMIN = ' ' where vbelv = ' '  and vbtyp_n = 'U'.
    endif.
    please go through the bote  445763   if the  problem is in inter company billing proforma
    Regards
    Damu

Maybe you are looking for

  • How to force user to enter supplier/customer name in captial letters in R12

    Dear all, Could anyone pls advise how to force user to enter supplier/customer name in captial letters in R12? Can I do it using OA framework personalization? HY

  • [package upgrade] Can't update udisks due to filesystem conflicts

    Hello everybody, after not updating my box for like two weeks I wanted to update it this morning. Unfortunately the upgrade process hangs due to several file conflicts within the udisks package. $ sudo pacman -Syu :: Synchronizing package databases..

  • Can't open old logic files

    I recently upgraded to SNow leopard. I have logic pro 9 I tried opening older tracks and they won't open due to the version I made those on logic express 7. Some of those tracks used intakt and battery 2 which now don't work on 10.6 but did on 10.5 L

  • Dynamic Tabstrip and Alv's

    Hi All, My requirement is like that dynamically i have to create tabstrip and in that each tab has Alv table to disply the data. Regards, Rajesh.

  • New Mac Pro vs iMac

    I am buying a new desktop for photo and video editing. I am trying to decide between the new Mac Pro coming out in Dec or a maxed out 27 inch iMac. If I go with the Mac Pro I will have to buy a TB display so I'm looking at about $1000 more for a base