NA KOSA012 and Product Version deletion

Good Day
I have an issue when trying to delete a production version from the material master.
The SAP message NA KOSA012 appears explaining that the version can not be deleted. I have checked the settings which the note suggests and everything appears to be correct. There are no open production orders in WIP either.
I have never had this issue before when trying to delete a version
Any idea's?

Hi,
Please check whether all the conditions as per the below link are satisfied.
http://help.sap.com/saphelp_47x200/helpdata/en/75/122e98f0bb11d2b6780000e82d81c3/frameset.htm
Regards
Kannan

Similar Messages

  • Urgent-material and production version

    Is there a way i can pull the report or details for materials and production version used in a company code?

    Hi,
    USE Transaction C223
    BR
    Diwakar

  • Subcontracting (Multiple Vendors Involved) and Production Version's

    Hello all,
    I would like to know more about this stuff. So do share your valuable thoughts.
    I was trying out a sub contracting scenario with multiple Vendors and Production Versions involved. The production version is designated in such a way that lot size/quantity of the requirement determines which of the available version's to be taken into consideration whilst generating procurement proposal via MRP.
    #1. Production Version:
    5 Version's of the BOM are assigned to various lot sizes.
    #2. I had 5 different info records created for the material-Vendor combination. Each one of them were assigned with a Prod version to it.
    Sample:
    #3. Post these settings i had a MRP run executed. Well !!! the results were different off-course. I neither did see the procurement proposals classified based on the prod version nor the first prod version assigned to the procurement proposals ( i meant i had a different prod version(version 4) assigned to the procurement proposals generated).  
    Questions:
    #1. Well the first thing that did strike my mind was how could i get the source list work for such scenario's ? I guess i can't go with quota arrangement coz which would split the procurement proposals into many halves and assign's it accordingly to the vendor.
    #2. How come production version 4 given the top priority here ?
    Source List state:
                             a. I had an item (tried the others as well) checked with fixed vendor indicator but the info record of the material-vendor combination had a different Prod. Version in it (well not PR4, i can guarantee you on that)
                             b. I had nothing marked with fixed vendor indicator. Results post MRP still did pick the same prod version (Version 4).
    #3. Last but not the least how can i get this thing to work ?
    Please do help out.
    PS: MRP 4 selection Method: 2 - Selection by Prod.Version
    Regards,
    Rahul

    Hello Rajen,
    Well as per your comment "
    Regarding the splitting, Not Always.
    There are two types of quota arrangement - Allocation quota and splitting quota."
    so meaning that allocation quota doesn't split the procurement proposal is it ? If so how are they assigned to vendors ? any other criteria being used up here
    Anyhow i had a new lot size method created with the splitting quota field unchecked. So how do i proceed from here ? meaning that how should i manage my quota file to not have my procurement proposals split ?
    Please do help out.
    Regards,
    Rahul

  • Production version deletion

    hi,
    i have two production versions for material A, there is no open orders for this material. i am unable to delete   production version 001 because its used in costing qty structure. but i amable to delete productioversion 002. we are using order based costing.. please help me delete production version which is used in costing qty structure....

    HI,
    Follow the below steps as Prerequisites before deleting the production version for a mterial :
    1. You must settle the product cost collector you created for the production version.
    2. No open planned orders exist in the system which are assigned to this production version.
    3. Check that there is no wip exists on the production line if REM mfg strategy and No production order in WIP if DIscrete Mfg.
    4. No open inspection lots are avl for the material with that PV.
    5.For the period in which the last reporting point backflush was carried out and for all previous periods in which the run schedule header or the production version is valid.
    the cutoff period is set for the WIP calculation
    the cutoff period is set for the variance calculation (operation KVAR)
    Hope this will help you.
    regards
    radhak mk

  • Costing variant and production version

    We have two costing variants "C" (used to create current cost estimates) and "F" (Used to create Future cost estimate). All of the production versions in the system have a validity date of 9999. Is there a way to tell the system to use one production version when costing using Variant C and another version when costing is done using variant F.
    Or if that is not possibel than how do we use one production version in 2011 while recosting current standards and another production version in 2012. (Remember the production version that we are using currently in 2011 has a validity date of 9999)
    Regards

    Hi
    In your Costing Variant - You have a tab callled "Qty Structure Control".... Here you can specify BOM Determination and Routing Selection id.... i.e. If the BOM / Routing attached to the prod version can be assigned a specific BOM Determination Class and Routing Selection id, it can work
    OR ELSE
    While doing CK11N, you can manually specify the Prod Version in the "Qty Struct" Tab..... Create an LSMW for CK11N and you can do a mass costing like CK40N.... CK40N does not have this option of specifying Prod Version
    I would prefer 2nd option
    Br, Ajay M

  • REM Product cost collectors and Production version

    Hi All,
    Can some one pls let me know
    What are the product cost collectors in REM and how to create the product cost collectors ?
    What is the production version and the difference between production version and controlling version?
    Thanks & Regards,
    Bujji

    Dear Bujji,
    A product cost collector is a cost object in Product Cost by Period that collects the periodic actual costs incurred in the production of a material. It can be created in txn KKF6N.
    [Product Cosr Collector|http://help.sap.com/saphelp_47x200/helpdata/EN/08/77ba810a1611d3a6b900104b55d538/frameset.htm]
    [Product Cost Collectors: Collective Entry for Repetitive Manufacturing |http://help.sap.com/saphelp_47x200/helpdata/EN/08/77ba810a1611d3a6b900104b55d538/frameset.htm]
    A production version determines the various production techniques that can be used to produce a material. It defines the following information:
    Alternative BOM for a BOM explosion
    Task list type, task list group, and group counter for assignment to task lists
    Lot-size restrictions and period of validity
    A material can have one or more production versions.
    It can be defined in the Material Master (txn MM02) in one of the following views:
    MRP 4
    Work Scheduling
    Costing 1
    The costing version is a different issue. It is a costing parameter and is used to save several cost estimates for the same material, with the same costing variant and the same costing date (e.g. in oder to cost the material several times with minor changes without creating new costing variants).
    BR,
    Antje

  • Costing and Production Version

    I am doing a costing run for material that has more than one production version defined for it. I want the costing run to pick up by default a prod version that we want to use for costing. However, it does not pick that up by default and instead we have to manually assign it in CK11n. Is there any way to make that Production Version default in the costing run. Please let me know. Thank you

    Hi,
    You can maintain the default Production version in Material Master - Costing1 View, under Quantity Structure section.
    Hope this helps... Reward your points,
    Regards,
    Prasobh

  • Capaity levelling and production version

    Dear SAPper,
    I curious about somecases in levelling.
    My client got 8 machine work center and they aware of capacity
    I create eight produciton version.
    MRP always put new planned order to first production order.
    After that my client would like to do capacity levelling.
    The problem is although they assign to other machine but the production version is not change
    leaving inconsistency of production version and new work center after capacity levelling
    is there any way we can capacity levelling considering produciton version too?
    Please kindly help.
    Best regards,
    Freddy Ha

    Dear Freddy,
    1.The system always picks up the first production version as a default,if more than one more production
    version exists for the same lot size,validity dates.
    2.Either you have to lock the production versions so that the system picks up the open production
    version or maintain different validity dates or Lot size.
    3.I'm not sure whether the system considers the prod version also during capacity leveling.
    check this link,
    http://help.sap.com/saphelperp60_sp/helpdata/en/1a/f2f33419ec8d44e10000009b38f844/frameset.htm_
    Regards
    Mangalraj.S

  • CO41 and production version

    I am converting planned orders to production orders using CO41. Is there a way I can get the production version field to appear on the CO41 output screen so that like other fields I can change it before pressing the 'convert' button
    thanks a bunch

    Dear John,
    In my understanding it is not possible in standard SAP.
    If you have manual selection of production version and if you have set the BOM selection method as 2 in
    MRP 4 view of the material master then,
    1.If you create a production order manually then the system displays the pop up to select a production
    version.
    2.If you are converting the planned order into a production order then it picks up the one which is
    present in the planned order.So obviously if 2 production versions are there with same lot size and
    validity dates,then the system picksup the first one only during MRP run.
    Even if it picks up the first prod.version in planned order,but while converting click on master data and
    change the production version if required.
    3.Otherwise what you can do is set the production version in MD61 itself ,so that its going to be
    considered during MRP run and same will be included in the planned order.
    Check and revert back.
    Regards
    Mangalraj.S

  • Urgent-production version and material

    Is there a way i can pull the report or details for materials and production version used in a company code?

    Post this in MM forum.
    SAP ERP - Logistics Materials Management (SAP MM)

  • BOM, Routing and production order

    Hello Guru,
    we notice something, our material 1256 has maintain four alternative bom as of this date:
    Alt BOM       MRP4 Prod version  BOM stat       PV lot size  Routing Grp    Route Lot
    1                          ACA                            02                 0 to 0             5000001            0 to 999
    2                          ACB                            02                 0 to 0             5000002            0 to 999
    3                          ACC                            02                 0 to 0             5000003            0 to 999
    4                          ACD                            01                 0 to 0             5000004            0 to 999
    can the difference be of lot size can be a factor why still even though alt BOM 1 with PV ACA was still pick when we do CO01 and CO41 in creating production order? we have already set-up in master data MRP4 tab Selection method = 3 which a expert also advise us to do for those inactive bom material not create a order, but doing this still not solve our problem
    and also does in MRP4, under the selection method, INDIVIDUAL/COLL can affect the selection of production version when creating order? what does the following works:
    blank = ?
    1 = individuals requirements only
    2 = collective requirements only
    thanks a lot
    ryan
    Edited by: Ryan on Dec 12, 2008 9:40 AM
    Edited by: Ryan on Dec 12, 2008 9:42 AM

    Hi Ryan,
    - As all the production version containes same Lot size.So system will pick first which system finds in C223.
      So each time you will find default selection of Production version ACA in Plan Order and Production Version.
    blank = ?
    1 = individuals requirements only
    2 = collective requirements only
    Blank means Individual and Collective both.
    What I have observe with this selection is whenever you are going to plan for MTS system will plan with collective requirement and in case of MTO it will plan with Individual requirements.
    May be others have some other idea (Actually I also want to verify it).
    - No there is no impact of Individual/Collective requirements on Selection of Production Version.
    Regards,
    Dhaval

  • Selection of BOM with Production version

    Hello friends,
    I have Finish product say A with two alt. BOM and Production Version 1 & 2
    i have semi-finish product say B  with two alt. BOM 1 and 2 in the BOM of the Product A
    Now when i create PIR in MD61 for product A with production version 2 selection,how the system will select the component B
    with alternative BOM 2
    please suggest

    Hi Mangesh,
    The production version is selected based on the setting you are maitaining in MRP-4 view for Dependent Requirement Selection Method. The selection will be based on the Validity dates, Quantity i.e. based on the Lot sizes, and based on the production versions.
    If both the versions are having same date,lot size etc, then the system will select the first version by default.
    IF you do not want any version not to be selected then you can lock that version in MRP-4 view or in C223.
    Thanks and regards
    Muru

  • PDS,PPM,supply chain model,production version in R/3

    Dear Guys,
    can some one help me to find the key difference between
    1)PDS,PPM,Supply chain Model and production version in R/3
    Thanks
    Raj

    One major difference between PDS & PPM is that PPMs can be edited in APO whereas PDS cannot be modified in APO. Any changes required for PDS needs to be done to the relevant R/3 master data and then CIFed to APO.
    Choice PDS v/s PPM?
    Functionally both are fine and can be used. However SAP recommends using PDS since it will not support any new enhancements for PPMs going forward. For some reason they want to encourage use of PDS rather than PPMs.
    - Srinidhi

  • Master Recipe / Production Version

    Hi,
    I'm looking for FM/BAPI or IDOC's for creating/changing
    master recipes (C201/C202) and production versions (C223). Can anyone help ?
    TIA,
    Rob Makelaar.

    Hi Rob,
    Message Type LOIROU ??
    Regds,
    Mano Sri

  • Delete Production Version - Error

    Hi
    When I try to delete the production version, System wont allow to delete it and following message log is created -
    Argument  not contained in table T437s
    Deleting Production Version 0001 for material XXXXXXXXXX is not possible
    I checked table T437s and there is not entry for that matierla and plant combination. Also there is NO PCC created yet
    REgards,
    Lokesh

    Dear Lokesh,
    Check these links,
    Re: Delete Production version
    Re: production version
    Regards
    Mangalraj.S

Maybe you are looking for

  • New Value Field in COPA

    Hi I have created new conditions in SD. These have been assigned to a value field which was never assigned to any conditions. Now this KE4I config is moved to test system and I found that values of these conditions are not appearing under new value f

  • Why are some web pages not loading fully or at all in chrome?

    I just updated to 10.6.8 half an hour ago, and I tried watching videos on youtube, using google chrome. The first thing that I noticed is that the page turns completely transparent, invisible. I can see the toolbar, web adress bar and bookmarks bar,

  • How can I copy a slide from one presentation and paste it into another?

    Hoe can I copy a slide from one presentation to another?

  • Wireless print XM452

    Is there a way to to connect a Windows 8.1 x64 machine to the MX452 without installing any special drivers and or program from Canon? Trying to keep the install programs as low as possible. I'm able to install the printer bt clicking find, add printe

  • Regrading standby database in standard edition

    hi gurus i m facing problem in configuring standby database in standard edition windows 2008 . os-windows 2008 standard oracle 11gr2 i have copied files from primary n copied it to same location on standby...at that time database was in noarchivelog