No values in planned total

hi experts,
i wanna know how the field 'planned total' can get values in trans cj40 or cj30.
i make a PR for my projcet,but i find the PR value doesn't transfer to 'planned total' in cj40 or cj30,should i config someting? by the way,i have actived the comitment management in contral area
best regards
zlf

Hi
1.From the Transactions CJ30 and CJ40,When you make any chage in Planned cost will adress manual inputs.
2.A PR requirement of  Material or Services will be depending upon on the Account assignment for Triggering the Purchase requistion--the it Turns into PO(Commitment Cost)--Once Material Recieved against WBS Element or Activity(Actula Cost).
3.Project Sytem is having special feature like Network Costing that will validate your PR(Materia Cost) cost into Planned Cost,which allways need Lots of Configuration and Version Management.
Let me know, if you require further Infomation..
Thanks,
Chakravarthy P.

Similar Messages

  • FM for Planned Total values of a WBS

    Hi All,
    Looking for an FM which can give me Planned Total values of a WBS element (that means, of that particular WBS element and all the objects below that WBS, including WBS, activities, etc.) just like this figure is calculated in CJ40 "Planned Total" column.
    Reply asap as this is urgent requirement.
    Thanks.

    Hi Aditya,
    see if the below FMs help you in any way
    CK_F_COST_ROLLUP
    KBPP_EXTERN_UPDATE_CO
    KBPR_READ_DATA
    Cheers
    Sammar

  • Table for "Planned Total" in CJ40

    Hi Gurus,
    I got all the other information but for the Planned Total value in CJ40. Can anyone help me with the table in which this value is stored. Is it directly available or we need to sum the other values ?
    thanks in advance.
    Regards,
    Vinodh

    Hi,
    Check following tables
    RPSCO      Project Info Database (cost, revenues)
    RPSQT     Project Info Database (quantities)
    COSP     Cost Totals For External Postings
    COSS     Cost Totals For Internal Postings
    Regards,
    Sandeep

  • CJ40: Planned amount Doesnt Show up in CJ30 (Planned Total)

    Hi;
    I came up recently witha Problem That whenever i do Planning (cj40) and after saving it when i go to Project Budget CJ30, there it doesnt show me the planned Values in the relevant column.
    your valuable input would be of great help to me.
    Regards.

    dear eguru,
    you hav two option for budgeting thru cj30.
    1) you can do mannual budgeting as like cj40 process. select wbs>go to primary cost>enter amount in concerned cost element.
    then select all>edit>totalup >check and save.
    2)you can copy your cost as it is in cj30. for that u should follow
    Step 1 : Choose the year in which u want to give the budget
    Step 2 : select all then go copy view then select planned total (100%)
    Step 3 :  total up
    Step4 : go to overall
    Step5 : select all then cumulative then again select all total up then chk any remainder
    if all OK then save
    rewards points are usefull
    regards
    Lallan

  • Getting an error while activating a planning area "Enter values for planning horizon From and planning horizon To for the storage time profile level"

    Dear S&OP community,
    I am getting following error while creating a planning ares in a newly installed sandbox. "Enter values for planning horizon From and planning horizon To for the storage time profile level".
    This what I did...
    1) Created new attributes and master data objects and activated them successfully.
    2) Time profile created and activated successfully
    3) Trying to create planing area by assigning  time profile in step 2 and assigned master data from step1..Unable to save the data and system returns 
    this error - "Enter values for planning horizon From and planning horizon To for the storage time profile level"
    My understanding is time profile needs to be active  but doesn't have to have values...
    Any help is appreciated.
    Thanks,
    Krishna

    YS,
    Here are my time profile settings
    Level       Name          Display Horizon - Past  Display Horizon - Future
    1             Monthly     -6                                       11         
    2             Quarterly     -2                                       3
    3             Yearly        -1                                       2
    Time profile is active and but time profile data is not loaded
    Thanks,
    Krishna

  • APC Value and Plan Value for an Asset.

    HI Gurus,
                      I am developing a report where I have to display the APC value and Plan value of an Asset.Can anyone pls give an insight how to find this for the Asset.

    Hi,
    why don´t you use the logical database ADA which most of the FI-AA standard reports do? The logical database is a service to get this information without developing all the READ information and translation by yourself, especially when talking about mid-year-reporting, consistence checks, etc..
    If you decide to use ADA, then the events GET ANLA0, GET ANLAV and GET ANLCV are from interest for you for information about APC and planned/posted depreciation value.
    Regards,
    Markus

  • How to stop non statistical condition type value from updating total amount

    Gurus,
    Can any body explain me how to do following setting,
    How to Stop non statistical condition type value from updating Total Amount
    Regards,
    Sai

    Dear Sai,
    You need to make that condition type as Statistical one
    Go to SPRO - Sales and Distr. - Basic Functions - Pricing - Define and Assign Pricing Proc - Maintain Pricing Proc - Control Date
    Select the proc. - select the condition type and activate the  check box Statistical
    This will show the amount of the condition but will not consider for the net value calculation
    Hope this will help you
    regards,
    Sagar

  • Add value parameter to total page

    Hi
    I want add a value parameter to total page,is possible? Thanks in advance.

    you cannot do that.

  • Planned total not show even running CJEN ancd CJBN

    Dear expert,
    Please help me on this. 
    I have set up the project, wbs elements, budget amount and release amount in the system. Some PM work orders have been assigned with the WBS element.  But somehow in CJ33, there is no planned total existed for WBS elements.  I have run CJEN and CJBN to recontruct infor database and availability control, but the problem still unresolved. 
    Is there any step I missed out in order to get the planned total updated in CJ31/33?  I even checked on report in CJE0, it has the detail amount for budget, actual, plan column.  But no subtotal in WBS element for 'PLAN--year'.  
    Thanks in advance.
    Best regards,
    FLL

    Hi,
    Activate the Appended field in OPSV (check box)for order category 30 .
    Muzamil

  • Reports fetching both PR ans PO values as planned cost

    Hello Gurus,
    SAP PS standard reports like POC, S_ALR_873013531 are fetching PR+PO value in planned cost. How can we restrict it to get only PO value
    Srinag

    Dear Srinag,
    As per my understanding of your problem, report is S_ALR_87013531 where plancost shows sum of PR and PO. Now if you want PR and PO value seperately use report  S_ALR_87013558 where values are comming in RenOrdPlan(Remaining Planning)
    Commitment (PR+PO) and actual. etc now if you want to PR and PO commitment seperately then use report CJI5.
    I think this will help you little bit
    Regards,
    Nilesh

  • BPS  initial value  at Planning Level

    Hello All
    I am getting error while using BW Hierarchy at planning level.
    i find the solution at  Including # initial value using hierachy
    but its not working
    i am getting this error "Characteristic Funds Center does not contain the initial value in the selection ".
    I try resolve the way suggested in old thread but its not working. I can only put either # or include Hierarchy at planning level.
    When I tried to use # it does not display Hierarchy in layout.
    if I include Hierarchy it gives error of "Characteristic Funds Center does not contain the initial value in the selection"
    Thanks in advance.
    Rinku

    If this error is just coming on execution of a planning layout the problem could be with your layout configuration, you should not select the hierarchy option in the first screen of layout config, only select totals by hierarchy on third screen of layout config and you should get the display you're after.
    (I think this error message can also arise when a compounding characteristic is not properly restricted)

  • Get cell value in Planning Data form and using it in a business rule

    Hi Everybody,
    if i set the data type of an Account Member as text, is there a way to get the value inserted by the user in a dataform, turning it as dimensional member and using it in a business rule?
    So, if the user insert the value "USA" in a cell, can i use any functions to tell essbase that "USA" is a dimensional member and then using it in a business rule, for example in a cross-dimension like Period1->FY12->USA?
    I tried to use the function @Member and it doesn't work, but i'm wondering if there is a way that can let me get the value inserted and use it just like a dimensional member. What are the ways that can let user input value that can be used in a business rule? I think one is by using SmartList, is there any other ways? Maybe using variables?? As an alternative i tried to use Prompt Variable but there are too many members on which the rule must run.
    Please help me, i wanna know if i can or not let the user input the member on which the rule must run...
    Thank all guys
    Bye
    Maurizio

    Thanks EW for your answer,
    YesI could use SmartList even if i think it's very tough to handle. My experience on using SmartList in caclc script is not so good. I try to enter in details of my requirement:
    I have 500 account members.
    For each one, I have to calculate the monthly budget by sharing the amount among the months. The user wants to calculate it on the basis of the actual flow(over the months) of an unspecified account of the prior year. The unspecified account must be inserted in a data form.
    So, i could use a Smart List but it colud be of 500 elements and then i should make a rule with as many IF as how many are the accounts. Or im wrong? The only way to use smart list dynamically in a business rule is by referring its values in a IF condition. Or i'm wrong.
    I tried to use execution variable ma it seems don't work. In this case the user must pay attention to write the account correctly, otherwise as you say the rule doesn't work.
    The value in PD0A020 is "PD0A000" (that is a dimensional member). The value in PD0A000 is "hello". In PD0A040 the rule returns "PD0A000" and not "hello" as i would. The function @Member appears to be not able to catch the dimensional member by the value in PD0A000.
    {Example}="test"->"Input"->"Scenario_test"->"FY12"->"PD0A020";
    Fix("test1","Input","Scenario_test","FY12")
    "PD0A040"=@Member({Example});
    endfix
    So, my doubt is: is it possible for Essbase/Planning to use the value inserted in a data form and to turn it in a dimensional member? What are the practicable ways to let the user input/choose the member on which makes the rule run?
    Thank you Ew, thank you guys
    Maurizio

  • Change Payment terms combo value when change Total Document

    Hi:
    I need to change the selected value of payment terms combo (Item 47) of the  form(133). This combo is placed in the third pannel of a form. Always appear the message “Valid Value – Value do not exist”
    The code is :
    Dim cItem As SAPbouiCOM.ComboBox
    If pVal.FormType = "65300" Or pVal.FormType = "133" Then
    'facturas deudores y facturas de anticipo de deudores
    'cambiamos la forma de pago si llega a cierta cantidad
    If pVal.ItemUID = "38" And (pVal.ColUID = "11" Or pVal.ColUID = "17") And pVal.EventType = BoEventTypes.et_VALIDATE And pVal.ItemChanged = True Then
          ' el evento es que cambie el total
          oForm = SBOApp.Forms.Item(FormUID)
          oItem = oForm.Items.Item("4").Specific
          StrCliente = oItem.Value
          oItem = oForm.Items.Item("29").Specific
          dblImporteTotal = CMonedaToNumber(oItem.Value)
          BuscarFormaPago(StrCliente, dblImporteTotal, StrFormaPago)
          cItem = oForm.Items.Item("47").Specific
       If cItem.Selected.Value <> StrFormaPago And StrFormaPago <> "" Then
           cItem.Select(StrFormaPago, SAPbouiCOM.BoSearchKey.psk_ByValue)
       End If
    End If
    End If
    Protected Sub BuscarFormaPago(ByVal StrCliente As String, ByVal DblImporte As Double, ByRef StrFormaPago As String)
    Dim StrDato As String
    StrDato = CStr(FNDameValor("[@" & StrPrefijo & "_FPAGO]", "U_" & StrPrefijo & "_OCTG", "U_" & StrPrefijo & "_OCRD='" & StrCliente & "' and U_" & StrPrefijo & "_IMP<=" & FNComPunN(DblImporte) & " ORDER By U_" & StrPrefijo & "_IMP DESC", pCmp))
    StrFormaPago = StrDato
    End Sub
    I´ve used BoSearchKey.psk_ByValue,but with psk_Index or psk_ByDescription .I have the same problem.
    Thanks for all
    Joaquin Gomez

    Hi Joaquin,
    Why don´t you use a formatted search instead of coding?
    The formatted search should be executed when the total is changed. And the value should be what BuscarFormaPago returns.
    Regards,
    Ibai Peñ

  • How to add one column value with grand total

    hi,
    this is my perform.i am just here multipling  menge and gpres value and stores into G_total variable and displing into output.
    this is my output in main window.
    ex:mat. 1           77.00(g_total value)
        mat  2             55.00(g_total value)
    now the requirement is to add the column and display the output as grand total ex: 77.00 +55.00 = 132.00
    how to do the syntax please help me......???
    FORM get_total  TABLES   in_tab STRUCTURE itcsy
                              out_tab STRUCTURE itcsy.
      DATA: lv_menge(20),
            lv_gpreis(20),
            g_total(20),
            g_total1(20).
      DATA:lc1 TYPE string,
           lc2 TYPE string,
          ls_tab      TYPE itcsy,
         l_tabix        TYPE sy-tabix.
      READ TABLE in_tab WITH KEY name = 'RESBD-MENGE'.
      IF sy-subrc EQ 0.
        lv_menge = in_tab-value.
      ENDIF.
      READ TABLE in_tab WITH KEY name = 'RESBD-GPREIS'.
      IF sy-subrc EQ 0.
        lv_gpreis = in_tab-value.
      ENDIF.
      REPLACE  ',' INTO  lv_gpreis WITH ''.
      CONDENSE lv_gpreis NO-GAPS.
      READ TABLE out_tab WITH KEY name = 'G_TOTAL'.
      IF sy-subrc EQ 0.
        g_total = lv_menge * lv_gpreis.
        out_tab-value = g_total.
        CONDENSE g_total.
        lc1 = g_total+0(2).
        lc2 = g_total+2(3).
        CONCATENATE lc1  lc2  INTO g_total SEPARATED BY ','.
        out_tab-value = g_total.
    CLEAR ls_tab.
        LOOP AT out_tab INTO ls_tab.
          l_tabix = sy-tabix.
          CASE ls_tab-name.
            WHEN 'G_TOTAL'.
              ls_tab-value = G_TOTAL.
          MODIFY out_tab FROM ls_tab INDEX l_tabix.
    ENDCASE.
        ENDLOOP.

    >
    asissahu wrote:
    > hi.
    >
    > nobody is replying my question???
    >
    > please help me
    Hi, Asissahu
    Because may be some one have problem to read your code
    Please have a look at the following link and past code this way.
    [How to post code in SCN|How to post code in SCN, and some things NOT to do...;
    @Naga Please you too
    Regards,
    Faisal

  • SAPGUI 7.20 terminated when copy and paste value in planning book.

    Hello Experts,
    I have window 7 and SAPGUI 7.20 patch level 2.  Recently, I encountered an issue where my SAPGUI terminated unexpectly when I use CtrlC and CtrlV of a value from one cell to another in any planning books (DP, SNP, ect.) 
    A window pop-up with a message "SAP Logon for Wndows has stopped working" , "A problem caused the program to stop working correctly.  Please close the program.".  The only option to select is "Close the program" and after I selected it, it terminates all of my open SAP option.  It happens everytime I use the CtrlC and CtrlV of a value from one cell to another.
    Do you know what caused this and how I can correct the issue?  Appreciate in advance for your hel

    Hi,
    Check out OSS notes on the support portal. This seems to be a standard bug; might be SAP has already released some notes to fix this. Otherwise, you may need to raise an OSS message.
    Regds,
    Ashutosh