Dear Gurus,
              In my vendor master (XK03) my currency for vendor is USD . What I want is whenever I made down payment request (F-47) or payment (f-48) it should only allow USD (currency in vendor master) ,not any other currency.Please suggest if i have to do any validation or user exit.
Thanks

Hi
You need to define a validation Rule for the same. You need to make use of User Exit to build in this validation rule. Check the link
http://help.sap.com/saphelp_46c/helpdata/en/5b/d231a843c611d182b30000e829fbfe/content.htm
for defining user exit for validation in T Code GGB0
Regards
Sanil Bhandari

Similar Messages

  • R12 Payment Process Request only picking up 1 Credit Note per supplier

    I am using R12 v 12.1 and have found an issue when I create a Payment Process Request that includes multiple credit notes for a supplier. When I create the batch only 1 credit note is selected. When I attempt to manuallly add another credit note it adds it to the batch however when I confirm the payment batch only 1 credit note is applied The nett amount for the supplier is still positive so I am unable to determine why this issue is occuring. Can anyone tell me if there is a setting to allow multiple credit notes within a payment process batch for a supplier?
    I have found something but am not sure if this is the solution. Under the 'Process Automation' tab when I create a PPR template I have noticed an option called 'Maximize Credits'. If this check box is selected will it allow multiple credit notes for 1 supplier to be added to a payment batch or is this option used for something different?
    Can someone please help with my issue.
    Thanks

    Yes, you are correct.
    You have to select the option "Maximize Credits" that will select all the available credit notes for the supplier while processing the PPR.
    Thanks
    Manish

  • Message KO020 - How to check all the open down payments and request.

    Hi Comunity,
    I need to check wich are all the open down payments in the system and then clear them, to close an order in KO02 or KO88. Please let me know if there is a  way to verify the open down payments por vendors, for customers, for AUC, or pending payments request that could be causing the error message ko020.
    Thanks a lot.
    Vero.

    Hi
    1) Use below parameters of structure SSFCTRLOP
    NO_OPEN, NO_CLOSE: These two flags prevent the print request from being closed after accepting the output of the Smart Form and allows you to include all other form output into this print request. The value should be like the following:
    1st call: 
    NO_OPEN = SPACE.
    NO_CLOSE = 'X'.
    nth call:
    NO_OPEN = 'X'.
    NO_CLOSE = 'X'.
    last call:
    NO_OPEN = 'X'.
    NO_CLOSE = SPACE
    2.SSFCOMPOP: Structure for the output option.
    TDNEWID: A flag indicating whether a new request is created.
    4)     Define one data wa_print_control referencing the structure SSFCTRLOP, and define another data variable wa_output_option referencing the structure SSFCOMPOP in the top include file of this report.
    5)     Clear the above two work areas before the print loop happens on the internal table that contains the selected invoice headers.
    6)     Initialize these two work areas with the values which would not change during the print loop as the following code fragment:
    wa_print_control-no_dialog = ' '. u201DShow print setting dialog
                wa_print_control-preview = 'X'. u201DEnable print preview
                wa_output_option-TDNEWID = 'X'. u201CNew spool request.
    7)     In the loop at the internal table which holds the selected invoice headers, set blank value to of the field wa_print_control-NO_OPEN and set u2018Xu2019 to the field wa_print_control-NO_CLOSE for the first loop at the AT FIRST event because it will be the first call to the function module of the smartform. The code is bellow:
        print_control-no_open = ' '.
        print_control-no_close = 'X'.
    8)     Set blank value to the field wa_print_control-NO_CLOSE to close the spool request for the last loop at the AT LAST event.
    wa_print_control-NO_CLOSE = u2018 u2018
    9)     Call the function module generated by the Form Design by passing the print control work area and output area.

  • Apc asset, information about payments and debts to a vendor

    Dear sap colleages
    I need to know these information about an ASSET:
    Purchased orders,
    Items from purchase orders,
    which of these items i've received, i've paid (also date), i've not paid ( amount of debt related to asset)
    payments in advanced (date),
    wich of these payments have been cleared (clearing date) and wich not,
    who is the vendor,
    other expenses (such as delivery)
    the amount of taxes,
    invoices related and NOT RELATED TO purchase order
    payments without invoice
    Which transactions do i need to follow?
    or
    Which document flow?
    or
    Which tables? Wich keys?
    or
    Is there a standard report that can give me such information?
    Any documentation and/or code will be appreciated.
    I need to program a report to integrate all these information.
    Thanks and Kind Regards

    Hi:
    Regarding payments to vendors,refer to FBL1N - Display/Change Line Items .
    Select the company code and then open items radio button and today date.It will show what are payments still to be paid to the vendor.If you select cleared items, it will show the payments paid to the vendor.If you select all items radio button, it will show all paid and unpaid payments to the vendor.
    Check this report whether it fills your requirment.
    When the user posts the business transaction, he has to input all the details, otherwise some of the information may be missing.
    Please let me know if you need more information.
    Assign points if useful.
    Regards
    Sridhar M

  • Restrict Payment terms only for vendor master

    Dear all,
    While creating payment terms I have unchecked the customer however it is showing in customer master payment terms also how to restrict?
    Kantha

    Hi,
    In OME2 or OBB8 , In the Payment Terms Detailed Screen, activate the relevant Account Type "Customer" or "Vendor" as per the this activation, it will appear in the MM and SD Master Data as well as Transactions.
    Means if Vendor is activate then that payment term will appear only ion vendor master and PO. And if Customer is activated then it will appear in Customer Master and Sales order.
    Note: - This should work, if you have configured this option and still it is not working then you might be doing something wrong. Do it as suggested above, it should work.

  • Issue with down payment tax cal and clearing it aganest vendor inv

    HI,
    I have an issue with down payment tax cal.
    1.     I had configured withholding tax and raised down payment, tax has been cal
    2.     In the next step I had raised inv, at this time also tax had been cal
    3.     When I am doing down payment clearing the tax collected at the time of down payment had to be reversed but itu2019s not.
    Can any one give me solution for clearing the tax that cal on down payment.
    Thanking you.

    Dear
    Vendor master has got tax codes both at the time of payment and at the time of invoice.  Hence system is calculating tds on both occassions. 
    Since you pay advance first tds calculated is right.  Now while doing miro remove the tax codes manually and do miro/mir7/fb60.
    If already MIRO/MIR7/FB60 done then reverse the invoice document and clear the tax GL accounts.
    Regards

  • How come i received an email confirming my second creative cloud payment 2 days ago and today i have logged on and i only have a free membership?

    about a month ago i signed up to the student creative cloud monthly subscription. today i have bought a new mac book and the first thing i did was install my creative cloud. after logging in and installed illustrator i realised that it had only installed the trial version. i then decided to log on online to see if there was any issues on there. after logging on and going to manage my account i discovered that according to online i have only got the free creative cloud memberhip. the reason i have an issue with this is that on Friday i received an email confirming my payment has gone through. so how come i am paying for a full student membership and then only receiving the trials?  as you can iamgine i am not impressed!

    Contact sales/ S&T support by web chat.
    Mylenium

  • Vendor payment and customer recipts across company codes

    Hi all,
    We are having 4 company codes in US.The vendors and customers are spread across company codes.
    1st scenario:
    Vendor "abc" has a debit balance os 5000 in company code A. In company code B, the same vendor has credit balance of 10000.
    How can we net the balances in both compnay codes and pay the difference to the vendor. The client has separate house banks for each company code.
    2 nd scenario:
    A customer sends a check for 2500. which needs to be applied against company code A (500) and Company code B (2000)
    How does the payment and receipts needs to be applied across company codes. Kindly suggest.
    Regards,
    Amulya.
    Edited by: amulya chowdary on May 21, 2010 4:31 PM

    Hi,
    You need to configure cross company clearing thru OBYA.
    Your queries can be addressed either treating other company code as the vendor/customer or clearing to a inter company GL.
    Best Regards,
    Madhu

  • Table Relation with Payment and Invoice of Vendor

    Hi all,
         I have one question about Table Relation with Payment and Invoice of Vendor.
         the scenario is.
         2 Purchase Order number : 100000001/100000002
         1 Invoice document number : 200000001 which include  2 Purchase Order.
         1 Payment document number : 300000001
         How should I found out table relation from Payment document number - Invoice document number - Purchase Order number. ?
          I try to link the following table, but it does not work.
          RBKP     *     Invoice Receipt
          RSEG     *     Invoice Receipt document line item
          BKPF     *     Accounting Document Header
    BSEG     *     Accounting Document Segment
    PAYR          Payment Medium File
    BSIK          Accounting: Secondary Index for Vendors
    BSAK          Accounting: Secondary Index for Vendors (Cleared Items)
    BSIS          Accounting: Secondary Index for G/L Accounts (Open Items)
    Does any one know about it ?
    Regards
    KY Chuang

    Hi Venkatesh,
    Thnx a lot for the reply. This has almost solved my problem, however there's one thing left. when I'm trying to take a print out after exporting the info into an excel sheet, the information really looks scattered, i.e.,  is there a way where we can go ahead and get the info in a rather unscattered manner.
    I've tried to take a print directly without actually transferring the info into an excel sheet, then each of the vendor is printed in a separate page, which again they feel is a problem.
    So, if you have an idea pls suggest.
    Thnx again for the information.
    regards
    sandhya

  • Hi, I want to purchase the complete creative cloud at S$60 , however, in my account, at the payment page, it's appear RM currency and the selection of country does not include singapore. How am I suppose to purchase?

    Hi, I want to purchase the complete creative cloud at S$60 , however, in my account, at the payment page, it's appear RM currency and the selection of country does not include singapore. How am I suppose to purchase?

    Hi there,
    The country selected while creating the Adobe account was selected as Malaysia, so you get to see the price in RM.
    ^Ani

  • How to generate payment advice in F110 and send it to Vendors Via Email

    Dear SAP Experts
    Could anybody tell me how to generate payment advice in F110 and send it to Vendors Via Email?
    It would be much appreciated if someone can provide the configuration procedure, thanks so much in advance.
    Cheers & Best Regards
    Ray

    Hi Sama,
    Thanks for your post, here I just share some of my idea.
    The following step is to configure the payment advice.
    In OBVU (payment methods in cpy code) I entered my payment advice form
    In OBVU (payment methods in cpy code)  set  "Always pyt advice"
    In OBVCU (payment method by country)  leave the payment medium program (RFFOD__T)
    For the email sending program, should develp some customized program to realize that, Thanks.
    Cheers & Best Regards
    Ray

  • I have bought a Seagate Backup Plus 1TB drive, first time I have selected Mac Windows option which excludes Time Machine to work on it, but now I want to go back and select Only Mac option to activate my Time Machine application. I request you to help me

    I have bought a Seagate Backup Plus 1TB drive, first time during plug-in, I have selected Mac Windows option which excludes Time Machine to work on it, but now I want to go back and select Only Mac option to activate my Time Machine application.
    I request you to help me with the procedure of the same?

    IMPORTANT - This will reformat your Seagate drive and hence wipe it.  If there is anything on your Seagate drive you want to keep, save it somewhere else FIRST.
    Plug the drive in.
    In Finder select Applications > Utilities > Disc Utilities.
    Select the external drive, select Partition option, give it a name (I call mine Mac Backup), select Mac OS Extended (Journaled) as the Format and under the drop down menu "Partition Layout" select the number of partitions you want (so if you want the drive to just be for Time Machine, select 1 Partition, if you want part of the drive to be for Time Machine and the rest for something else, select 2 partitions and so on).  Click apply and the Disc Utility will partition and reformat your drive ready to use.
    When this is complete, open Time Machine in System Preferences. Use  Select Disc to select the drive (or if you have multiple partitions, the partition of the drive) you want and you are good to go.
    This may be a long way round, but it gives you the option to partition your disc which you may want.

  • Automatic Payment program: Payment method not defined for vendor abroad

    Hi All,
    I have a situation wherein the client has a company code in Poland . The Company code is trying to make a payment via f110 to a vendor based in sweden. The vendor wants payment to the invoice to be made in Polish Currency i.e. it wants clearing to be done in Company codes local currency.
    But F110 is throwing the error Payment method not defined for vendor abroad. Can you suggest what could be the possible Error.
    Regards
    Nitin

    Nitin,
    Have you followed the above advice, i.e. used the same medium format just allowing foreign payments for it?
    AFAIK, the Poland banks require a separate format for foreign payments, if only because international bank nbr SWIFT has to also be given and not just the IBAN.
    At my company, the Deutsche Bank Poland requested IDocs to be set up instead, I'm working on it now..
    thanks

  • R12 Payable - Payment Process Request Report

    I need to list payments ordered by vendor name in Payment Process Request Report.
    Currently I don't see any logic how payments are printed in "Payment Process Request" report.
    Does anyone know how to resort this report?
    Thanks,
    Joon

    Hi,
    R12 AP not showing Accounting entry for currency exchange loss account where as same accounting entry is apearing in GL...
    ### Steps to Reproduce ###
    1. Create AP Prepayment and pay full with forign currency (USD) Exchange rate 3.1
    2.Create invoice with forign currency(USD) Exchange rate 3.75
    3.go to tools/view accounting events
    4. run the create accounting and go to GL and check the accounting entry
    Please advise
    Regards

  • Receipts PO and stock keeps in vendor side

    Dear All,
       I have a PO or Subcon. PO which vendor confirm ready to deliver to us, but don't want to do the GR first, beacuse this will mislead user we have stock in our warehouse .For these PO stock, we want to wait for customer confirm the order, then we can directly ship the stock to customer. In the mean time, vendor ask for payment, how can we deal with this problem which we do the GR and keeps the stock in vendor side, on the other hand, account dept can do the LIV process.
    How can we deal with this?
    Thanks!
    Hen. T

    hi
    you can deal it with  third party scenario.
                                                   THIRD PARTY SCENARIO
    In third-party order processing, your company does not deliver the items requested by a customer. Instead, you pass the order along to a third-party vendor who then ships the goods directly to the customer and bills you. A sales order may consist partly or wholly of third-party items. Occasionally, you may need to let a vendor deliver items you would normally deliver yourself.
    Process Flow
    The processing of third-party orders is controlled via material types. Material types define whether a material is produced only internally, can be ordered only from third-party vendors, or whether both are possible. For example, a material that is defined as a trading good can only be ordered from a third-party vendor. However, if you manufacture your own finished products, you may also want, from time to time, to be able to order the same type of product from other vendors.
    Processing Third-Party Orders in Sales
    Third-party items can be created automatically by the system, depending on how your system is set. However, you can also change a standard item to a third-party item during sales processing manually.
    Automatic third-party order processing
    If a material is always delivered from one or more third-party vendors, you can specify in the material master that the material is a third-party item. During subsequent sales order processing, the system automatically determines the appropriate item category for a third-party item: TAS. To specify a material as a third-party item, enter BANS in the Item category group field in the Sales 2 screen of the material master record.
    Manual third-party order processing
    In the case of a material that you normally deliver yourself but occasionally need to order from a third-party vendor, you can overwrite the item category during sales order processing. For a material that you normally deliver yourself, you specify the item category group NORM in the material master.
    If, as an exception, you use a third-party material, change the entry TAN to TAS in the ItCa field when processing the sales document. The item is then processed as third-party item.
    If address data for the ship-to party is changed in the sales order in third-party business transactions, the changed data will automatically be passed on to purchase requisition and also to the purchase order ,if one already exists. In the purchase order, you can display the address data for the ship-to party in the attributes for the item.
    You can only change the address data for the ship-to party in the sales order for third-party business transactions, and not in the purchase order.
    Processing Third-Party Orders in Purchasing
    When you save a sales order that contains one or more third-party items, the system automatically creates a purchase requisition in Purchasing. Each third-party item in a sales order automatically generates a corresponding purchase requisition item. During creation of the requisition, the system automatically determines a vendor for each requisition item. If a sales order item has more than one schedule line, the system creates a purchase requisition item for each schedule line.
    Purchase orders are created from purchase requisitions in the usual way. For more information about creating purchase orders, see the Purchasing documentation. During creation of the purchase order, the system automatically copies the delivery address of your customer from the corresponding sales order. In a sales order, you can enter purchase order texts for each third-party item. When you create the corresponding purchase order, the texts are automatically copied into the purchase order. The number of the purchase order appears in the document flow information of the sales order.
    All changes made in the purchase order are automatically made in the sales order as well. For example, if the vendor confirms quantities and delivery dates different from those you request and enters them in the purchase order, the revised data is automatically copied into the sales order
    You process third-party items by creating a normal sales order. In overview for the order, you can then overwrite the default item category (TAN in the standard system) with the special item category for third-party items: TAS
    Billing Third-Party Orders
    If relevance for billing indicator for the item category has been set to B (relevant for order-related billing on the basis of the order quantity) in Customizing, the system includes the order in the billing due list immediately. If, however, the indicator has been set to F (relevant to order-related billing on the basis of the invoice quantity), the system does not include the order in the billing due list until an invoice from the vendor has been received and processed by the purchasing department. In the standard system, item category TAS (third-party order processing) has been given billing-relevance indicator F.
    In the first case, the third-party order is considered to be completely billed only when the invoiced quantity equals the order quantity of the sales order item. In the second case, each time a vendor invoice is received, a customer invoice is created for the quantity in the vendor invoice and the order is considered to be fully invoiced until the next vendor invoice is received.
    If you have activated billing-relevance indicator F for item categories in Customizing, billing can refer to the goods receipt quantity instead of the incoming invoice quantity.
    You can control whether the invoice receipt quantity or the quantity of goods received is relevant for billing in Customizing for copying control for billing at item level.
    FOR YOUR PROCESS Individual Purchase Orders WELL GIVE THE RIGHT SOLUTION
    Individual purchase orders are used when your customer orders goods from you that are not in stock and must be ordered from one or more external vendors.
    Process Flow
    During sales order entry, the system automatically creates a purchase requisition item. The purchasing department creates a purchase order based on the requisition and the vendor ships the goods directly to you (unlike third party order processing, where the vendor ships directly to your customer). You then ship the goods to your customer. While the goods are part of your inventory, you manage them as part of the sales order stock. Sales order stock consists of stock that is assigned to specific sales orders and cannot be used for other purposes.
    Goods receipt will be posted when ever the vendor ships the goods to our customer.
    We will do this transaction in SAP using MIGO.
    Invoice receipt is done when the Vendor sends us the invoice.. ( I.e Billing ).
    It can be done using MIRO.
    THe above two steps are standard and manual. There are many other ways that the actual process can happen. If the client follows EDI standards then the Goods receipt and Invoice receipt can be done through IDOCs automatically.
    Process Flow for 3rd Party Sales
    Customize the third party sales in summary:
    Prerequisites for 3rd party sales,
    Purchasing org,
    purchasing group,
    assign the Purchase org to company code
    assign Purchase org to plant,
    should not maintain the stock in material, it should be trading goods,
    1. Create Vendor XK01
    2. Create Material u2013 Material Type as "Trading Goods". Item category group as "BANS".
    3. Assign Item Category TAS to Order type that you are going to use.
    4. A sale order is created and when saved a PR is generated at the background
    5. With reference to SO a PO is created (ME21N). The company raises PO to the vendor.
    6. Vendor delivers the goods and raises bill to company. MM receives the invoice MIRO
    7. Goods receipt MIGO
    8. Goods issue
    9. The item cat TAS or Schedule line cat CS is not relevant for delivery which is evident from the config and, therefore, there is no delivery process attached in the whole process of Third party sales.
    10. Billing *--
    SD - 3rd party sales order Create Sales Order
    VA01
    Order Type
    Sales org, distr chnl, div
    Enter
    Sold to
    PO #
    Material
    Quantity
    Enter
    Save
    SD - 3rd party sales order View the PR that is created with a third party sales order
    VA01
    Order Number
    Goto Item Overview
    Item ->Schedule Item
    SD - 3rd party sales order View the PR that is created
    ME52N
    Key in the PR number
    Save
    SD - 3rd party sales order Assign the PR to the vendor and create PO
    ME57
    Key in the PR number
    Toggle the "Assigned Purchase Requisition"
    Execute
    Check the box next to the material
    Assign Automatically button
    Click on "Assignments" button
    Click on "Process assignment"
    The "Process Assignment Create PO" box , enter
    Drag the PR and drop in the shopping basket
    Save
    SD - 3rd party sales order Receive Goods
    MIGO_GR
    PO Number
    DN Number
    Batch tab , click on classification
    Serial Numbers tab
    Date of Production
    Flag Item OK
    Check, just in case
    Post
    Save
    SD - 3rd party sales order Create Invoice
    MIRO
    Invoice Date
    Look for the PO , state the vendor and the Material
    Check the box
    Click on "Copy"
    Purchase Order Number (bottom half of the screen)
    Amount
    State the baseline date
    Simulate & Post
    Invoice Number
    *Invoice blocked due to date variance
    SD - 3rd party sales order Create a delivery order
    VL01N
    In the order screen , go to the menu Sales Document , select "Deliver"
    Go to "picking" tab
    State the qty and save
    SD - 3rd party sales order Create a billing document
    VF01
    Ensure that the delivery document is correct in the
    Enter
    Go to edit -> Log
    Save
    Third party order processing is as follows:
    Assume three companies X, Y and Z
    X - The company,
    y - The customer
    Z - Vendor
    When ever X gets a PO from Y to supply some goods, X has an option of either manufacturing those goods or procuring those goods.
    If he is procuring the goods, there are two methods that are generally followed:
    Method 1) After receiving the PO from Y, X creates a sales order against Y.
    Now at the same time he also creates a PO to a vendor Z to produce the goods
    Z produces the goods and supplies to X
    X receives the goods from Z
    Then X delivers the same goods to Y.
    After that X invoices Y and Z invoices X.
    Note : Here there is no direct/ Indirect relation between Z and Y.
    This process is known as Trading Process. and the Material here is created with Material type HAWA.
    The other method is a Third party order processing method:
    Here the glaring difference is that instead of Z supplying the material to X and X in turn supplying the same material to Y.
    X authorizes Z to supply the material to Y on his behalf and notify him once the delivery is complete.
    Now Z supplies the material to Y and acknowledges the same to X.
    Z will send a copy of delivery acknowledgement and invoice to X.
    After receiving the delivery confirmation and invoice from Z, X has to verify the invoice and this process is known as invoice verification and is done in SAP through Tcode MIRO.
    The next step for X is to create an invoice and submit to Y
    Only after the invoice verification document is posted then only X can create an invoice for Y.
    This is the business flow that is followed for third party order configuration.
    There are few steps that have to be configured to enable the system to function as mentioned above.
    Step1)
    If you are always following a third party process for a material then you have to create the material using item category group BANS.
    The procurement type should be marked as External procurement (F) in MRP 2 view of the material master record.
    if you are not always allowing third party order processing then u can create a material master record with item category group as NORM and the procurement type should be marked as ( X) meaning both types of procurement ( in house manufacturing and external procurement).
    Step 2)
    the item category in the order should be manually changed as TAS.
    For that you need to configure the item category determination
    Order type + item cat Group + Usage + High level = Item cat + Manual item cat
    OR + NORM + + = TAN + TAS
    OR + BANS + + = TAS
    Step 3)
    make sure that during the item category configuration for TAS you need to mark relevant for billing indicator as F
    step 4)
    The schedule line category for this type should be CS.
    make sure that you mark subsequent type as NB - purchase requisition in this schedule line category as this will trigger the purchase requisition order immediately after the creation of the sales order and the PO to vendor is created against this purchase requisition.
    Regards,
    Vijay