Periodic cost settlement for production order

Hello All,
Please explain me can we do Periodic cost settlement for production order in discrete manufacturing. If yes, how?
Thanks & Regards,
Alok Tiwari

WIP entry gets passed to accounts if the order is not in DLV or TECO status.
or else variance gets calculated.
Two GLs which gets hit are
Change in stock a/c Dr.
To Inventory Price Difference a/c Cr.                or vice versa......
Regards,
Divraj

Similar Messages

  • Cost center for Production Order

    Hi all,
         We are now not able to get a report of Material consumption cost, Cost center wise. It is Because cost center is not linked to Production order or not linked to material issued to production order. Can we get the cost of material cosumption for  production order cost center wise. Please give us a solution.
    With Regards,
    R.Mahendiran.

    Hi,
         Prod order is linked with controlling, for the direct costs like material cost linked with accounting view, costing view and secondary costs are linked with costing tab in work center and inturn workcenter is assigned to cost center, and for the prod order controlling part you will be assigned to the costing variant in transaction OPL8, if you remove this you can't get any reports.
    To understand the difference
    201 - Goods issue against cost center. Means you create reservation through MB21 and do posting of cost directly at cost center.
    261 - Goods issue to Production order. Means you create a reservation through Production order  and do posting of cost to Production order. When cost settlement of production order is done cost from production order will get transfered to cost center mentioned in settlement rule of production order.
    Hope this clarifies your doubt.

  • Abolish product cost collector for production order

    Dear Experts,
    we use for some production order types the product cost collector. Now we plan to abolish them and change the settlement for production order. Which things do we have to pay attention? Do we have to finish our running production orders first or is it possible to change customizing during running production process. Thanks for your hepl!
    Best regards
    Steffen

    Hi Ajay,
    thank you for your answer.
    We have tested two variants:
    1. new order type, so we can process two separate settlements, for orders with PCC and the new orders without PCC. After archiving of all prodorders with pcc, archiving of pcc it should be possible to switch back to old order type.
    2. change customizing without finishing existing orders, settlement for existing orders, all orders which already have been processed will be settled by pcc (status pcc usage in order header) We have not be seen any strange system behavior.
    We use the pcc collector for different order types in different plants and want to abolish plant by plant. In this time the pcc will still be customized/exists.
    Best regards
    Steffen

  • Period end closing for production orders

    Dear all,
    what is period end closing???
    Pl. enlist all period end activities for product costing by order scenario.
    what inventory adjustments are necessory.
    what FI entries required to post??

    With respect to PP- Period end closing is the procedure to close all the production orders and see that cost is flowing from production order to material
    During period end - we TECO all the orders and see that production is complete from PP angle. Then costing will calculate over head/variance and settle the difference to production material or price difference a/c depending on the production material price control.
    Just see below the example of a production and costing entries. Thi8s may be helpful to understand the concept.
    Planned price
    Planned Material cost = 115.15USD
    Planned Activity cost = 6 USD
    Planned Over head = 25% of material cost+ 250% of activity cost = 28.79+15=43.79
    Total cost = 164.94
    Product cost as per “S” price = 1 USD (example)
    After GR and confirmation
    Actual Material cost = 7456.55 USD
    Actual Activity cost = 2USD
    Total cost = 7458.55
    Actual O/H  = 0
    Production variance = 7293.61 USD
    After o/h calculation
    Actual Material cost = 7456.55 USD
    Actual Activity cost = 2USD
    Actual O/H = 25% of material cost+ 250% of activity cost = 1869.138
    Total cost = 9327.69
    Production variance = 9162.75
    After settlement
    Actual Material cost = 7456.55 USD
    Actual Activity cost = 2USD
    Actual O/H = 25% of material cost+ 250% of activity cost = 1869.138
    Total cost = 9327.69
    Production variance = 0
    Variance will be settled to Price difference a/c.
    When we do the GR the FI a/c will hit as below
    Production order expense a/c -
    stock a/c +
    When we GI the following a/c will hit
    Raw material a/c -
    Production order expense a/c +
    When we settle
    Production order expense a/c + or -ve
    variance a/c = + or -ve
    I hope this will help you.

  • Error - Settlement for Production order Co88

    Hello,
    Before Dec 2009 the FG material xxxxx has been goods movement post without maintained split valuation. Then Dec2009 the material xxxxx has been extended to split valuated.
    While process of production order settlement against said material through CO88, we are facing one error Valuation Type not set for material xxxx.
    What could be the reason that system is showing the error.
    Best Regards,
    Avijit

    Hi,
    If no valuation category has been assigned to a material (MBEW-BWTTY is
    blank), and you wish to assign multiple valuation categories (split    
    valuation) to this material, then the material must not have linked    
    documents and the stock must be zero for both the current and previous 
    periods.
    The reason of this restriction is that objects that are open and              
    refer to valuation data without split valuation can result in                 
    inconsistencies if the valuation category is changed.                         
    So If you want to subsequently change the valuation control for a material       
    to split valuation, you should previously check the following:                                                                               
    - No stock is available for the material                                      
    - All production orders must be closed                                        
    - No purchase order can still be opened                                                                               
    These checkings will avoid inconsistencies or undesired side-effects.    
    Consequentely you can not change a valuation category of a material    
    if there are purchase order item lines (even if the purchase order is  
    completed) or if a stock balance exists for that material.             
    For more information concerning limitations associated with changing the
    valuation category, you can see note 30656.  (Although this note is  
    used primarily regarding a change to the Unit of Measurement, the      
    functionality is very similar).                                        
    Please also check note 155874, which outlines what must be performed   
    in order to change the valuation category.                             
    Best regards,
    MLM

  • Error in cost calculation for production order

    Dear All,
    I got error of cost calculation while release of Production Order due to price of some material is not mantain .
    What will happen if I release , save the Order with error & do Good Issue ???
    Ishwar

    Dear Ishwar,
    Check the log's created for costing and rectify the same.
    I feel its better to rectify the cost related errors and then release the production order and proceed to Good's Issue.
    Check whether there is a MAP for all the Raw-materials and an origin group in costing 1 view.
    The Finished product must be having a standard cost estimate that's valid for the current period.
    Revert back in case of any more help needed.
    Regards
    Mangalraj.S

  • Standard Vs Actual Cost report for Production Order

    Hi Expert,
    I have an requirement that i need report for Standard Cost (CK40N) and Actual cost (261 Movement) for multiple production order or Multiple Material.
    Please suggest standard report if available or FS for creating Z Report.
    Regards,
    Pranav

    Hi Pranav
    There are Standard reports
    Option 1
    You can use Product Drilldown reports in KKO0
    For this:-
    a. Do settings in OKN0 - assign a Cost Comp Structure and Choose Material group = Product Group
    b. Run KKRV to collect data and then use KKO0 reports
    I have replied this in SCN many times.. You can search here. Just google as "SCN" "Ajay Maheshwari" "OKN0" and you can see some posts answered by me
    Option 2
    You can use Summarization Hierarchy KKBC_HOE
    For this
    a. Set up Summ Hierarchy in KKR0.
    b. Run KKRC
    c. Run KKBC_HOE report
    Br Ajay M

  • Coste Center for Production Order

    Hi all,
    Can anyone please provide me the table details, which stores information on cost center for the PP orders and PM orders.
    Thanks in advance.
    Regards
    Prashant

    AFPO
    AFKO
    AUFM
    regards

  • Automatic Settlement for Prod.orders & Product Cost Collectors.

    Dear all,
    Please help me how to carryout the Automatic settlement of Production orders &
    Product Cost collectors on every month last working day mid night.
    Please tell me how to schedule this as an automatic scheduled job.
    This program is not been allowed to schedule as a job.
    Waiting for your inputs.
    Please help me.
    Regards
    Mangalraj.S

    Hi
    Create a Variant with the order types need to be setteled at the period and schedule the same in background processing.
    Regards
    Venkat

  • Settling of Cost for Production Order via WBS Element

    Hi Gurus,
    Just would like to briefly understand, how I can make use of the WBS Element in the Production Order (Assignment tab) to use as cost settling for a production order? How do i automate the WBS Element in the production Order for a set of given parameters? Is there a config I can use to set a profile?
    I have a scenario here as below:
    I have various types of production orders:
    PO 1 = Production A
    PO 2 = Production B
    PO 3 = Production C
    And for each of the above, I will individually have a WBS Element.
    PO1 - WBS Element A
    PO2 - WBS Element B
    PO3 - WBS Element C
    And WBS Element A, B and C is a Level 2 WBS Element which are tied to WBS Element Z (Level 1 WBS Element), which will be settled to a project.
    Appreciate your kind feedback on the above on how I can make it work in the PP Order.
    Thanks.
    Rgds.

    Hi Manoj,
    I need to understand your process in more detail.
    How do you procure?  Create a sales order with TAS item category to create a PReq and PO?
    Very simple explanation: Resource Related billing/DIP profiles are used to accumulate costs on WBS elements and then bill the client as needed.

  • Authorization check for production order settlement

    Hi All,
    Production order settlement currently can be done by any user of any company code. there is a high risk involved in the same since unauthorized postings may happen. Hence we need to add authorization check for production order settlement. Can we maintain the same at the plant or the company code level?
    Waiting for your replies. Thanks in advance!
    Regards,
    Aman Goel

    hi
    What venki has told abt the exit, its absolutely correct.Even i have used the same exit
    •     From table CAUFV pick Material(PLNBEZ),Basic Start Date(GLTRP),Plant(WERKS) .
    •     Pass parameter Material(PLNBEZ) and Plant(Werks) in table MBEW in respective fields i.e. Material(MATNR) and Plant(WERKS).
    •     Pick the latest record for the current period(LFMON) and year(LFGJA).
    •     Pick Product Cost Estimate number(KALN1) from the record and pass it to table KEKO.
    •     Check if Production Order Basic Start Date(GLTRP)<= BIDAT, if NO post Error Message.
    This is the FS for EXit PPco0007
    Reward if useful
    Amit

  • Variance calculation for production order with settlement receiver as SDI

    Hi...
    I have one query reference to Variance calculation for production order with settlement receiver as SDI(Sales document item).
    I am working on Varaint configuration with strategy 25(Make-to-order for configurable material) with requirement class 046.
    I have created sales order ref. to configurable material,subsequently created planned order & then converted to production order.
    In production order settlement receiver is SDI(Sales document item).
    While doing production confirmation ,variance has been created.
    Now during variance calculation KKS2, I have got error message as no suitable settlement rule found for object Order no.
    Is there any way to come out of this?Or variance calculation KKS2 is not applicable with settlement receiver as SDI(Sales document item).
    Pl. guide
    Redards
    Tushar

    Hi
    In case of non valuated material, concept of variance does not apply...
    Variance is Actual Cost - Cost of Goods receipt posted in stock.. If the later value is zero, your entire actual cost is variance... That is one way of saying it
    But, in SAP, var not calculated in case of non valuated material and that makes sense as well.. Since you are in MTO scenario, it would make sense to analyse costs vs revenues @ sale order level as each SO will be unique in itself
    Regards
    Ajay M

  • Actual Costs for Production Order

    Hi All
      I have a scenerio where they dont want any product costing methods say WIP,Variance calculation & Settlement.
      When the Goods receipt is done for production order the actual costs and the Activity costs to be valuated.
    Regards
    Jayshankar.A

    Hi,
    In our case the Standard price is updated in the material master. For this, you need to create a costing estimate using T-Code CK11N and update & release in CK24.
    When CK11N is executed the standard price is calculated for the material by taking Moving Avg Price of RM (Price indicator V) and the activity costs are calculated as per data given in KP26. These cost components are added and a final cost estimate is prepared, which is updated using T Code CK24.
    the pre-requisites are:
    1. BOM should be maintained.
    2. Routing should be made.
    For executing the same procedure for all the materials, you can use T Code CK40N.
    Hope this is what you were looking for.
    Revert for further details.
    Regards,
    Rohit.

  • GR  for  Production order not possible with  settlement receiver as IO

    Hi
    I   have  created a  production order  and  the settlement rule is  to  an internal order.  But  it  does not  allow me to do  goods receipt.    Pl  tell me  what to do.
    Thanks
    kamala

    Hi,
    SAP recommands production order settlment to be beow object and additional CO Object COPA.
    Settlement Receivers Depending on the Scenario
    1.Make-to-stock production >>The make-to-stock inventory (receiver = material) >> COPA
    2.Sales-order-related production with a valuated sales order stock>>The valuated sales order stock (receiver = material)>>COPA
    3. Sales-order-related production with a nonvaluated sales order stock>>The sales order item (receiver = sales order)>>COPA
    The scenario you are trying is doesn't fit into standard SAP framework for production order so please try said scenario with CO production order. Again CO production orders mostly recommondable without PP so figure out impact on cross modules.
    Regards,Ashok.

  • Settlement of Cost Center And Production Order Variance

    Dear All
    I have just started to learn SAP Controlling. I am able to get hold of  some materials on Controlling. May I request the experenced forum memebers to please explain the following
    1. How data flows from FI to CO and PA
    2. When cost center and production orders are settled, how the variance are settled and which accounts/ modules get effected
    and a source where I can get some material on this topic. Your immediate replies  and valuable peice of advice will help me a lot
    Thanks
    Arvindh

    Dear All
    I have just started to learn SAP Controlling. I am able to get hold of  some materials on Controlling. May I request the experenced forum memebers to please explain the following
    1. How data flows from FI to CO and PA
    2. When cost center and production orders are settled, how the variance are settled and which accounts/ modules get effected
    and a source where I can get some material on this topic. Your immediate replies  and valuable peice of advice will help me a lot
    Thanks
    Arvindh

Maybe you are looking for

  • How do I manuallly download the latest version of Firefox on top of my current version?

    I have an iMac version 10.7.5. I'm currently running Firefox Version 14 and I keep getting prompts to allow automatic updating (currently to version 17). However, when the prompt says "connecting to the update server," it never connects. So my questi

  • Regular expressions and limiting matched input

    Hi everyone :) I am trying to put together a regular expression that matches strings that contain elements of the form; {<some text>} However, each piece of text may contain multiple embedded instances of this pattern. I want to ensure that I am alwa

  • 5800 XM Few Issue

     I purchased my 5800XM 2 days ago....so i wanted to update its firmware After Reading all the problem with v20 i have decided not to get FM update... But i have some problem with my v11.. 1. when i forward a msg it is sent in three part althouth it i

  • Premiere Elements.exe 7.0 Stops working.

    Hello. My Adobe Premiere Elements 7.0 keeps doing the following: When I open my project file, it stops and I get the message: Adobe Premiere Elements.exe has stopped working. A problem stopped the program from working correctly. Windows will close th

  • Intra Company STO pricing Procedure assignment

    Hi In intracompany STO we need to raise invoice from the supplying plant to receiving plant.So i created STO pricing Procedure with Cost price plus Profit margin and transportation cost .Now where to assign this pricing procedure?Whether to assign th