Settling of Cost for Production Order via WBS Element

Hi Gurus,
Just would like to briefly understand, how I can make use of the WBS Element in the Production Order (Assignment tab) to use as cost settling for a production order? How do i automate the WBS Element in the production Order for a set of given parameters? Is there a config I can use to set a profile?
I have a scenario here as below:
I have various types of production orders:
PO 1 = Production A
PO 2 = Production B
PO 3 = Production C
And for each of the above, I will individually have a WBS Element.
PO1 - WBS Element A
PO2 - WBS Element B
PO3 - WBS Element C
And WBS Element A, B and C is a Level 2 WBS Element which are tied to WBS Element Z (Level 1 WBS Element), which will be settled to a project.
Appreciate your kind feedback on the above on how I can make it work in the PP Order.
Thanks.
Rgds.

Hi Manoj,
I need to understand your process in more detail.
How do you procure?  Create a sales order with TAS item category to create a PReq and PO?
Very simple explanation: Resource Related billing/DIP profiles are used to accumulate costs on WBS elements and then bill the client as needed.

Similar Messages

  • Actual Costs for Production Order

    Hi All
      I have a scenerio where they dont want any product costing methods say WIP,Variance calculation & Settlement.
      When the Goods receipt is done for production order the actual costs and the Activity costs to be valuated.
    Regards
    Jayshankar.A

    Hi,
    In our case the Standard price is updated in the material master. For this, you need to create a costing estimate using T-Code CK11N and update & release in CK24.
    When CK11N is executed the standard price is calculated for the material by taking Moving Avg Price of RM (Price indicator V) and the activity costs are calculated as per data given in KP26. These cost components are added and a final cost estimate is prepared, which is updated using T Code CK24.
    the pre-requisites are:
    1. BOM should be maintained.
    2. Routing should be made.
    For executing the same procedure for all the materials, you can use T Code CK40N.
    Hope this is what you were looking for.
    Revert for further details.
    Regards,
    Rohit.

  • TX CNS41 - settled cost from internal order to WBS element not displayed

    Hi PS Expets,
    I have a question regarding transaction CNS41 "Structure Overview" where cost settled from an internal order is not displayed in in the report for a selected project. This is in a ECC version 5.0
    Settled costs from internal orders are posted with transaction type KOAO on WBS elements and when you check report RCNSTFCO you can see that the following transaction types are deselected when executing transaction CNS41:
    delete t_rpsco_m where vorga = 'KOAO' "<   insert
                          or vorga = 'KOAL' "<   insert
                          or vorga = 'KOAP' "<   insert
                          or vorga = 'KOAQ' "<   insert
                          or vorga = 'KOAR'."<   insert
      CALL FUNCTION 'HFPM_RPSCO_TO_RPSCO_LIS_CONV'
    This is implemented according to OSS note 51971 in order to eliminate internal business volume in the project structure when executing a PS hierarchy report.
    But this also eliminate the display of the cost  from the internal order.
    Any ideas or a work around in order to display settled cost from an internal order on a WBS element in transaction CNS41
    Kind regards,
    Anne

    Hello Tison.
    I guess you have the Project created with a BAPI in your system in background. As far as I have seen I'd try the following in ABAP to create Partners in the Project Definition: BAPI_BUS2001_PARTNER_CREATE_M or the corresponding method ProjectDefinitionPI.PartnerCreateMultiple. This should happen in background when the Project is created also.
    Best regards.
    Jens Schmid

  • Cost for Production Order

    Hi,
    How can I display the cost incurred for a production order?
    Regards,
    Prashant

    Hi
    In CO02 or CO03 you can view the order cost.
    In GOTO - COST you can go to the primary screen of the cost analysis.
    Go to change layout and select second option of cost trend.
    Depending upon the order status you shall see the costs.
    After the order confirmation and delivery you shall see the primary costs.
    After completion of CO cycle you shall see the settled costs.
    Narendra Lohokare.

  • Recognizing external production costs for production order

    Hi Experts,
    Our company is new to SAP and one issue we have not resolved is whether it is possible to attach costs to an Inspection Plan, and ultimately have these costs flow with the production order to Cost of Goods Sold (COGS).
    The objective is to enable us to analyze which specific customers/products require us to incur these additional costs.  Any advice you have to accomplice our objective would be appreciated.
    We are a Process Industry, and many materials are sent out for external testing. These costs are significant and some customers and/or products require more testing. We currently have Inspection Plans set up for each Material that requires testing, but have not found a way to burden the material with the appropriate COGS for the external testing.
    For example, if a product must be tested for the following characteristics, and each test cost is known, how do we get the test costs attached to the production order for the total of $200?
    Product 1 Inspection Plan
    Salmonella $70
    EColi $59
    Coliform $25
    Yeast/Mold $46
    Thank you!

    Richard,
    Are you able to advise which forum is the proper one for this question?
    Thank you,
    Esther

  • Planned costs for production order

    Hi,
    I have a requirement where the actual costs and planned costs for a production order have to be displayed. I got the actual cost details from the table COEP.
    Please let me know if anyone knows the table which stores the Planned Costs / or any function modules which can be helpful.
    Thanks in advance.
    Neethu Mohan

    Hi ,
    Please refer the thread,
    How To get Planned Cost for a Production Order
    Best Regards.
    *Reward if it is helpful.

  • Auto generation settlement rule for Production order

    Hi Expert,
    I 'd already create sett profile with GL Account as receiver.  Then I assign to Order Type PP01.
    I also create strategy seq. PP01 and activate enhancement COOM0003 which I define startegy seq & GL account.
    But when I create prod. order type PP01, it still request for GL account ??
    My requirement is to settle all cost in production order to GL account. 
    Any feedback will rewarded.
    Thanks

    HI
    kaindly go for OKO7 seettilement profile. u gest see the allocastion structure and see in OKO6 allocastion structure who is ur resiver. object. GIVE as G/L.
    if it not solved this issue gest check the rules in ur settilement profile. resiver objects .

  • Without Production order confirmation How to settle the cost of prd order

    Dear all,
    How to settle the cost production order with out production order confirmation.Any setting is there Or program.
    Regards,
    Naresh Redddy.

    Dear Naresh,
    To settle the cost of production order, you need not to confirm it. But on the same time if you want to settle the order when its not confirmed then WIP amount will be posted. WIP value will be posted if your order does not have DLV or TECO status. In your case, if you not confirmed the order, only material cost if any issued for order will be calculated, no activity cost will be calculate. And if you want to post the variance then order status needs to be either DLV (Completely Delivered) or TECO (Technically Completed). Here also the cost of activity will not be considered as you didn't confirmed the order.
    So if you want to settled the order without confirmation, then Activity cost will not be added in your settled cost. So your product costing will not be accurate.
    Please revert if you have any other doubts.
    Regards,
    Hiren Ramani

  • Function module for calculating planned and actual cost of production order

    Hi ,
    Do we have any standard function module for calculating planned and actual cost for production order?
    i need to implement this in a Z-report.
    Thanks
    Srini

    Hi,
    try below function module
    CRMCO_GET_PLAN_ACTUAL_COSTS
    CO_IH_GET_PLANNED_COSTS_TOTAL
    Regards,
    Sankaran

  • Plan v/s actual materail consumption report for production order - urgent

    Dear all Hi,
    Is there any report or T code from which i can get the plan v/s actual material consumption for a production order or wbs element after completion of order, please suggest / help, the requirement is very urgent.
    thanks in advance

    Hi shaiz,
    You can get that in COOIS tcode
    Select components again List
    then give the plant,Order details
    execute
    You can find 2 fields reqmn qty(nothing but planned) & qty Withdrawn(Actual consumption) in the report
    Hope this hepls
    Rgds,
    SVP

  • GR for production order

    Hello,
    Perhaps somebody has faced this problem...
    During goods receipt for production order via MIGO with 101 movement
    type for split-valueted materials a new valuation type is not created
    for the materials despite it is set on the screen (batch number =
    valuation type). No error messages occur.
    Thank you.

    Alexx,
    I do not know if I have misunderstood you question.
    Are you asking that you want a new valuation type to be created during goods receipt. If yes then let me tell you it is not possible.
    Valuation types are assigned to the valuation category in customisation. You cant create new one during GR. You need to enter the Val type and batch number during GR. Then the Val type is assigned to the batch. You can see this in MSC3N.
    If the valuation type is already entered in the prod order then automatically the val type is populated in the GR. You need to enter the Batch number alone.
    Hope this clarifies your doubt.
    Regards
    Ram

  • Internal orders to WBS Element

    Hi,
    I,m working in a Project System implementation project, where all other modules are already in use.As per the existing process, Internal orders are created for asset accounting.Those are of statistical. All the purchase orders & costs are booked referring to the internal orders, the same cost is directly settled to Asset Under Construction or Asset.As the internal orders are created as statistical, there is no seperate settlement process & all the costs are directly settled either in AUC or in Asset as & when they are incurred(posted).
    Now as we are implementing Project Systems, Internal orders are going to be replaced by WBS Elements. Customer requirement is the same process of online settlement of costs to Assets from WBS Element & he doen't want to settle seperately.
    Now the issue is, 1) how the process can be mapped in SAP?
    I feel creating the WBS elements as statistical, the same process can be mapped. Is it possible/
    2) As one project is already in progress & some postings have been taken place against internal orders, customer wants to see all those postings on new WBS element, now how to migrate the same to respective WBS element in the new system?
    Thanks
    Kishore

    Hi Kishore Ji,
    For your question, simple answer is, you want to continue all AUC under Project Systems.  So far, you have considered statistical internal orders, anyway, which is not possible for you to settle directly.  So, please take that amount generate uploading document by using same account and using WBS element as debit and internal order as credit and status you release for internal orders.
    WBS elements you create as statistical without selecting account assignment category.
    Your problem will be solved.
    Assign points without fail.
    ALL THE BEST.

  • Periodic cost settlement for production order

    Hello All,
    Please explain me can we do Periodic cost settlement for production order in discrete manufacturing. If yes, how?
    Thanks & Regards,
    Alok Tiwari

    WIP entry gets passed to accounts if the order is not in DLV or TECO status.
    or else variance gets calculated.
    Two GLs which gets hit are
    Change in stock a/c Dr.
    To Inventory Price Difference a/c Cr.                or vice versa......
    Regards,
    Divraj

  • Actual cost of Production Order settled to Fixed Assets

    Dear all,
    My client is doing in-house production of moulds (internal order suggestion is not accepted by the client) for which
    they have the following
    1. BOM
    2. Machine hour
    3. labour
    4. overhead etc
    5.plan value
    6. actual value
    Can i settle the actual cost of production order to Fixed Asset ?
    If yes
    what are process kindly give me if any process other then the below
    1.production order created
    2. settlement profile - FA is settlement optional
    3. allocation structure
    4. Asset created
    5 define asset in settlement rule
    Kindly give me your valuable input
    regards
    elango

    Hi,
    Although i am not CO expert , please check with your FICO consultant who are expert before make the final call.
    During settlement to a G/L account or a fixed asset, the system ignores additional account assignments that were manually specified in the distribution rule.
    Based on what i know .
    you can stipulate that settlement may be made to cost centers and orders, but not to fixed assets.
    The Settlement profile is something that you need to create a settlement rule to settle the actual costs of a sender object.
    About the Settlement rule is something that  contains the distribution rules for the sender. It will define how the way to settle the cost.
    Allocation Structure
    In the settlement structure you combine the primary and secondary cost elements into groups, in which debits are then posted to the sender objects. For each group, you specify whether (for settlement to a given receiver type) settlement is performed
    by cost element or using a settlement cost element.
    For example, you might use settlement cost elements:
      To document the purpose of an order (such as, repairs or maintenance)
      To reduce data volumes (you can combine a number of debit cost elements
    under one settlement cost element).
    TQ

  • Cost center for Production Order

    Hi all,
         We are now not able to get a report of Material consumption cost, Cost center wise. It is Because cost center is not linked to Production order or not linked to material issued to production order. Can we get the cost of material cosumption for  production order cost center wise. Please give us a solution.
    With Regards,
    R.Mahendiran.

    Hi,
         Prod order is linked with controlling, for the direct costs like material cost linked with accounting view, costing view and secondary costs are linked with costing tab in work center and inturn workcenter is assigned to cost center, and for the prod order controlling part you will be assigned to the costing variant in transaction OPL8, if you remove this you can't get any reports.
    To understand the difference
    201 - Goods issue against cost center. Means you create reservation through MB21 and do posting of cost directly at cost center.
    261 - Goods issue to Production order. Means you create a reservation through Production order  and do posting of cost to Production order. When cost settlement of production order is done cost from production order will get transfered to cost center mentioned in settlement rule of production order.
    Hope this clarifies your doubt.

Maybe you are looking for

  • HP Spectre X2 Replacemen​t screen

    Hello, Can anyone tell me if HP sells replacement screens for the HP Spectre x2 computer? I recognize that HP can repair the device, but find the $300 repair cost outrageous.

  • USB Ethernet is not working after upgrade to 10.8

    Hi, I am not getting connected to the LAN with my USB ethernet. Anyone with similar situations? Don't tell me to convert to thunderbolt please.

  • Offline Form Issue in SAP GRC System

    Experts: I am working on creating a Offline Form for GRC Process Control  in SAP GRC System. I have couple of doubts. 1. In the Form property, there is a new field call 'Inbound Handler'.    The document which I referred says  that, this 'inbound han

  • How to identify the follow control in form

    a person who can write the trigger in the write place the form is going to be a successful one so please guide me how to know about the follow of control in form

  • IPhoto not saving simple edits

    I have been using this current version of iPhoto for several weeks with no problems. Yesterday, it stopped saving simple edits even after hitting the done button. For example, I would crop a photo, click done, move onto the next photo and the previou