Hi,
We have service contracts on annual basis for whicg we have created service contracts.But we have errors regarding the date rule.
we get the following errors:
1. start datebilling plan:base line date for rule 13 not set
2.end date  billling plan :base line date for rule 14 not set
3.dates to: base line date rule  09 not set
at header level
4.start  date billing plan : base line  date  for rule  05 not set
Can any one teell us the step by step to set up the dates and the billing plan.
Also the value for AMC is 1350/- but the system is calculating it as 17356/-
Please suggest
AJ

Hi
GO to spro sd -> billing plan->define rules for determining date and press
you wil get the screen ,ouble click on the rule , again u will the another screen here  u can set the base line date , time period ,time unit
Regards
Chowdary

Similar Messages

  • Wrong period values in Text template for upload of Plan data (KP06/KEPM)

    Hi,
    We are facing an issue in the upload template in text format for Upload of Cost Centre Planning data (Transaction KP06) in ECC 6.0.
    We have some User defined layouts for Excel upload of plan data. If we save the file as a text (tab delimited) file, the Period values above the Column"Period" do not correspond to the correct periods in ECC 6.0. for e.g. the values above Period 1, Period 2, Period 3 are shown as 6, 5, 4 instead of the correct values 1,2,3. These values are considered by the system for uploading the Planning value in the appropriate Periods and hence the values entered in the Column Period 1 in the text file are incorrectly uploaded by the system in Period 6 based on the values generated by the system in the text file.
    However, we do not encounter this issue in the 4.6C system where the values are correctly shown.
    We are facing a similar issue with the text upload template for Sales Planning data in CO-PA (Transaction KEPM), where the values generated by the system do not correspond to the correct period.
    Regards,
    Rajaram

    Hi Christian,
    Thanks for the quick reply, i followed your earlier reply in the below thread and resolved the issue. Thanks.
    How to delete CO plan data
    Hi Ajay,
    Thank you, We are uplaoding through KP06, Menu -->Extras --> Excel Planning --> Upload.
    Regards,
    Raj

  • Settings for entering plan-data? No clue!

    Hello,
    In a BPS layout (BW3.5) I have different colums which should be enterable.
    But it is not working. I can't enter any plan data.
    The columns "Comparison" is deactivated. My WebInterface look fine.
    When I execute my WebInterface I can see my colums - but with zeros.
    Any ideas where I can make a setting that I can enter plan data?

    Hello,
    In a BPS layout (BW3.5) I have different colums which should be enterable.
    But it is not working. I can't enter any plan data.
    The columns "Comparison" is deactivated. My WebInterface look fine.
    When I execute my WebInterface I can see my colums - but with zeros.
    Any ideas where I can make a setting that I can enter plan data?

  • How to add a mm-dd-yyyy date field type in a Planning Data Form

    Hi John,
    pls, I have one question regarding the possibility of adding a date field type for example 03-03-2009 in a cell of Planning Data Form application.
    for example, I created:
    - 2 members in Period dimension: StartProject and EndProject and I need to enter and track date for these fields;
    - one Account member called Project;
    - and a simple form with these collumns and row;
    Trying different settings for my members - seems that I cannot input date in the cell and rcvd errror: "you have entered invalid value".
    Pls, can you confirm me if it's possible to enter date type in a form?
    If yes, what is the specific setup for the Account and Period properties: Data storage, Time Balance, Data type, Account type etc
    many thanks,
    Robert

    Many thanks John!!! that's it!!!
    I had to change it in Data Type evaluation Order because I'm using EPMA and it's working now!!
    Thanks again!!!
    Rgds,
    Robert

  • Error on invoice "specify payment period baseline date".

    Hi Experts,
    When I create ZMIRO, ZMIRO it keeps
    asking for a baseline date which we have never had to do before
    Payment terms  filled blank, but teh system throughs error message "specify payment period baseline date".
    I
    Please help.
    Thanks,

    Dear,
    System will want to calculate due for payment to vendor for this invoice it must know baseline date from which it should start calculating the due date. Generally baseline date is determined from payment term but it is empty in your case. Enter a payment term in vendor master so that system will default the baseline date from settings done in payment term.
    Baseline date has to exist in the invoice document.
    Regards,
    Chintan Joshi

  • The Basic Finish date is a Day earlier than Planned date

    Dear Experts,
    I am getting a strange behaviour about Maintenance order Basic Finish Date when generated from Maintenance Plan. I have Customizing settings (TCode : OPU7) Adjust: "Adjust Basic dates, adjust dep reqmts to order start date" and scheduling type : Backwards in Time. For this setting Order Basic Finish Date is a day earlier than Planned date , but when Schduling type is Backwards instead of Backwards in Time, Basic Finish date is same as Planned date.
    Example: The start of cycle of a monthly plan is 14-Nov-2010, 1st Planned date is 14-Dec-2010. When Scheduling type is " Backwards in time" , the order generated is having Basic Finish Date as 13-Dec-2010 .And when Scheduling type is "Backwards" , Basic finish date is 14-Dec-2010.
    Thank you.
    -Malay-

    Hi there,
    Please check the primilinairy buffer in your strategy package. This field have an effect on your order start date.
    But I agree on Pete, you should use a forward planning.
    Regards,
    Johan
    Edited by: Johan Zeeman on Dec 17, 2010 11:29 AM

  • In Report output, Missing Plan data with the Seletion option - Single Value input (more than 10 values)

    Hi ,
    I am running the Query (Actual Vs Plan) in the BEx Analyzer, with the input for the characteristic like Fiscal Year, Posting Period and Cost Center(20 Single value) it not comming up with the plan data - Actual data is coming up fine.
    If i gave 10 or less than 10 inputs ( single values input in the selection - option ) for the characteristic COST CENTER it coming up with all the data (Both plan and Actual).  if the COST CENTER input values more than 10, it not coming up plan data (Actual data is coming)
    Cost Center Variable is designed with an Authorization Variable.
    Can any one please help me to know why plan data is getting miss when the input limit more than 10 (single values input in the selection - option) in the Cost Center Variable? 
    An also could you please share that, What is the Max limit for the Single values and Range Value for an Selection - option in the BEx Variable.

    A)    Hi ,
                 In Report, I am having 2 variant.
    1.   For one variant, i have saved the input values for both the Select Single values & Select range for the cost center.
    8 Values in single & 4 Values in Ranges         
    It coming up with data successfully.
    2.    Another variant having input only for select single values for the COST CENTER, it contains 20 records (This variant also have restricted with the same values as above variant for COSTCENTER variable)
    Fiscal year                         : 2012
    Posting period                   : 8
    Cost Center                        : 20 values in Single                                             (Here I have separated the range values into single)
    It’s not coming up with plan data. 
    B)   If I gave only first 10 values in the Single value, Output for both actual and Plan are coming up…………. If I gave the Second 10 value in the Single value and got the Output for both actual and Plan.
    C)    I have also checked the following details of this query, 
    Executed the query in RSECADMIN and checked the Authorization log as below,
    Relevant Characteristics for Detailed Authorization Check  (Characteristics with Full Authorization Are Not Listed!)
      List of Effective Authorization-Relevant Characteristics for InfoProvider ZPCA_M36: 
    List Is Empty:
      There Are No Characteristics That Have to Be Checked in Detail 
              2.  Checked the Single value input by iteration, 1 to 10, it retrieves data.  More than 10 like 11, 12 … is getting failed to pull plan data.
              3. checked the selection Value range by iteration and I gave the range value count up to 25        inputs, its works fine.
    Thanks.
    Regards,
    Subashini.

  • What are the setting for Save button for saving plan data in WAD template

    Hi,
    i created SAVE button in Webtemplate for saving plan data.But this button is not
    active.is there any setting for this?
    thanks in advance
    chandu

    Hi Chandu,
    The settings to Configure the  Save function.
    Right click the Button Group Item ® Properties ®  * Button    ® 
    Type Caption  ‘Save’ ® Command    ® Select ‘All Commands’ Tab ® 
    De-select ‘Execute Planning Function’ and then select checkbox ‘Save
    Changed Data’ ® Double click on ‘Save Changed Data’ ® OK ® OK ® Save your template.
    *pls assign points,if info is useful*
    Regards
    CSM Reddy

  • Can it be possible to create invoice without billing plan date?

    Hi Gurus,
    I have made settings for billing plan in contracts. But, client wants billing plan at contract level only for the sake of reporting. Client doesnt want invoice to be created according to these billing plan.
    Now, consider this scenario,
    I have created contract A with billing plan values in it.
    I have created sales order B with reference to contract A. There are no billing plan values in sales order B.
    There is no delivery and PGI.
    Now, when I try to create invoice with reference to sales order B, system doesnt allow me to save the same and says "No billing plan date found".
    Will it be possible to create invoice irrespective of the billing plan in contract?
    Please guide.

    Hi,
    Then in that case i would advise not to use billing plan for your contract document type.
    If you intend to create a sales order in reference to your contract document which has billing plan type attached, then in that case you need to maintain billing plan for your sales order document too.
    Reward if helpful.
    Regards
    Ravi

  • Profit center - actual data and plan data question -?

    Hi Gurus
    Please clear my doubts in profit cneter accounting.
    1) what is PLAN data  -? (What is planning in a bigger picture)
    why do we need plan data -?
    2)ACTAUL data will be posted in the profit center from other SAP moduldes.
    So with out PLAN data  prrofits can not be figured -?
    OR
    Plant data is for some other purpose -?
    Please can some help me on these -? Alos any examples are really good for me to understand
    Really appreciate.
    Thanks
    Kris

    Hi,
    Profit centers captures actual revenues & expenses of the business transaction.  The company arrives the
    net of income over expenses and analyses whether the Profit center is making Profit or not.  Now they
    want to control the expenses and have a target set to expand the revenue base to optimize profit.
    For this they have to plan each costs and revenues over a period for a Profit Center.  When they
    plan values for these profit centers they have to take into consideration the business trend over
    next 12 months and the plan is set for each period.  Actuals are posted in normal day to day transactions.
    During period end, the analysis is being done to see the variance between plan and actual and measures
    are taken to control the areas to reduce these variance which may affect Profit.
    Regards,
    Sadashivan

  • How to run automatic plan data transfer to Profit Center Accounting?

    Can anybody help me telling how to transfer plan data automatically to Profit Center Accounting?
    At the moment I use 1ke0 to transfer manually.

    Hi,
    You can the option in Customizong "Define Versions"  > Settings for Fiscal Year > choose the Integrated Planning,
    but if already exists planned data, set the indicator by tcode KP96.
    Regards
    Elza

  • Table for Cost center plan data by version

    Hello,
    I need to find out which tables in sap hold the cost centre and profit centre plan data by version.
    I am having trouble finding the tables if anyone can help?
    Thanks

    COEP     CO Object: Line Items (by Period)(costing document line item information)
    Orders, sales document items or cost centers can be described as object types. The connection of an object to its CO data is given by the general object number (OBJNR field in the CO tables, such as COEP-OBJNR). This field provides you with information about the object type and, if needed, about the object key (such as the order number).
    GLPCP   EC-PCA: Plan Line Items

  • Plan data posted to a special ledger

    Hello,
    I can't transfer plan data to a special ledger although actual data is posted correctly, and the system says that is because of customizing settings
    Which are these settings?
    Thank you very much

    Hi,
    I does not appear any error, when I use KP06 transaction plan data is not posted to special ledger and I try to do it in GCU6 and appears a message that says "This document was not posted to any ledger because of Customizing settings"

  • Version 999 Project System Plan Data Issue

    I am using transaction CJ9B to copy the Project System related plan data i.e. plan data at the WBS element level from Version 10F, period 1 to 12  in year 2010 to version 999, period 1 to 12 in year 2010. The transaction CJ9B runs successfully in the update mode. But when report CJI4 is executed for version 999, period 1 to 12 in year 2010 then we do not find plan data in sync with version 10F.
    I analysed this issue, had a meeting with end user and blanked out target version 999 using source version 9ZR for the year 2010. Then I again copied version 999 from version 10F. Still plan data in version 999 do not exist as they are in version 10F. I have checked the version 999 master data in transaction OKEV. Integrated Planning for SPL, COPA, cost center accounting and business process is active. COPY Allowed is also enabled. Version 999 is unlocked as well.
    Hence I am not sure why the copy functionality is not working fine for version 999, period 1 to 12 in year 2010.
    Can you please take a look and revert with your opinion so that this issue can be fixed ?
    Thanks,
    Umesh

    Hi,
    If you want to copy all the plan date from 10F to 999, then in Txn CJ9B
    select the indicator reset and overwrite in target version and execute in test mode.
    Regards,

  • Upload Plan data for GL account

    We want to upload plan data for the GL accounts so that the plan data shows with the actual data in the financial statement.
    The question is what is name of the program/tcode
    1. To upload plan data for GL accounts?
    2. To upload plan data in the cost center accounting?
    3. Most important - to transfer plan data from cost center accounting to GL accounts? Currently we have a custom program to upload plan data to CCA.
    Thank you very much in advance
    Praful

    You can plan at GL level using T code GP12N, Planning profile SAPFIGL & summary table GLT0. You will have to define plan version & planning period in t code OBP6.
    Once plan is entered the same will be available in FI reports e.g. F.01
    For Cost center plan use t code KP06. Alternatively you can activate excel integration for planning profile and upload from excel.
    Regards
    Rakesh Pawaskar
    Message was edited by:
            Rakesh Pawaskar

Maybe you are looking for

  • Updated to 10.3.9, QTSS will not start

    A year after updating my OS X Server 10.3 to its final version release, QTSS still refuses to start. Server Admin, either at the colo or on a remote desktop, yields no error message. I've been content producing fast-start 3 minute .mp4 and .m4v downl

  • Need help in displaying the status in one query

    Query: SELECT START_DATE,END_DATE,ABSENCE_TYPE,APPROVAL_STATUS,SUM(ABSENCE_DAYS),absence_attendance_id FROM( SELECT * FROM (SELECT NVL (paa.date_start, paa.date_projected_start) start_date, NVL (paa.date_end, paa.date_projected_end) end_date, paattl.

  • How can I stream video from a P/DVR to my Mac

    Hi, How can I stream video from a Motorola dcx3400m P/DVR to my Mac? I have tried a Slingbox but the audio is out of sync witht the TV and it drives those watching on iPads or on the iMac in another room NUTS. Is it possible to use a TV tuner of some

  • Unable to find "Adobe PDF" resource files

    I get this error when trying to merge several files into one PDF document. The files are a mix of JPG, PDF and DOC (Word 2003 running under Windows 7). It fails with the Word file but converts the rest. Where do I find the missing resource files? I h

  • Does BAPI call the validations defined for standard transactions ?

    Hi Experts, Can anyone tell me if BAPI handles the validations defined for standard transactions ? I have a standard transaction KB15N. Validation defined for a field works fine when run thorugh the transaction. But if same data is updated using BAPI