Planning for requirement after TECO production order

Hi, I would like to understand how do I plan the remainder of an independent requirement if the production order sourcing it is TECOed.
The scenario I'm proposing is the following:
- There's an independent requirement for a given quantity (e.g. 100 tons) and there's an associated production order to fulfill it. Production has already started and goods receipts have been made for partial quantity (e.g. 50 tons)
- The production order is TECOed but I still need to re-plan for the remaining 50 tons
how does the fact that part of the independent requirement has been  partially fulfilled impacts my re-plan? how does the system knows that I have to plan for 50 and not the original 100?
Many thanks,
Diego

Diego, assuming that you are working with a make to stock strategy (i.e. delivering from anonimous stock), after GR of 50 Tons and TECOing the production order, there is a negative balance between IndReq(-100) and stock (50). So, the MRP will create a new planned order for covering the demand.
If a delivery is made from the stock, then the sales order will reduce both IndReq and stock and the balance still remains.
Hope this help you...
Regards

Similar Messages

  • Open TRs not getting deleted after TECO production order

    Hi,
    We're having an issue.  We're using WMPP interface to supply the production line for the production orders.  The auto TRs are generated when the production orders are released. 
    After TECO the production orders, the open TRs are not getting deleted automatically.
    Could anyone know if these TRs get deleted automatically when we do the TECO production order?
    If yes, do we have any restriction or condition based on this, the TRs get deleted?
    Please explain.
    Thank you.
    with regards,
    Muthu.

    Hi Abhijit,
    Thank you for your reply.  It does not help me.
    The auto TR creation is happening now as required.  No issue on this.
    When you do the TECO, it also cancels the TRs.  I tested this also. 
    There're some scenario this open TRs cancellation is not happening.  I do not know when these open TRs are not cancelled.  If you know answer for this, please let me know.
    Thank you for your help and time.
    with regards,
    Muthu.

  • Deleting the reservations for components of a production order without TECO

    Dear Gurus,
    I forgot to activate the backflush indicator in the beginning. I activated the backflush indicator in between. But for the confirmations already made I had to issue the material as unplanned consumption for the order. This is not clearing the reservations for the material.
    How to delete the reservations for components of a production order without TECOing the production order? My order is not completed.
    Thanks and Regards,
    Raghu

    Hi Kumar,
    I have a production order for 1000 header (A) qty. My control key is PP03 (auto goods receipt from confirmation in CO11N).
    For this order the component B qty is 1000 (BOM consumption is 1:1)
    Without doing GI, the confirmation is done for 300 A qty. I realized that auto GI is not done for the 300 qty of component B as there was no backflush indicator.
    Now the backflush indicator is activated in the production order for component B.
    In the next confirmation for another 300 A qty, automatic GI is posted for 300 B qty because of backflush now.
    Now my confirmed and GR qty for A in two rounds is 300 + 300 = 600.
    GI of component B done is only 300 (through backflush).
    Qty yet to confirm = 400.
    So I did GI of 300 B qty through MB1A (which is an unplanned issue). This does not update the withdrawn qty in the production order. Also the reservations for component B for this 300 qty are not reduced in the system.
    Now the reservations against the order for component B = 1000 - 300 = 700 (which is 300 more than the qty yet to confirm).
    Now when I run MRP for another 2000 qty of A, the procurement proposals for B will be 2000 + 300(undeleted reservations) = 2300. Though the system is behaving properly, this 300 is additional and unwanted.
    For this reason I need to delete these reservations before the MRP run. As order is still open, I cannot TECO the order. Nor can I clear all open reservations from CO11N.
    Thanks and Regards,

  • Withdrawal Qty exceed requirement Qty in production order

    Hi: guys
    In our system, withdrawal Qty can exceed requirement Qty for a production order, even we use planned GI. That means when we use MIGO/MB1A to process GI to reference production order, we can manually change withdrawal Qty. Even this Qty has exceed requirement Qty of production order, system also not give me any message.
    Anybody can tell me how to customize settings to limit this function, such as give me a message (error or warning), and ensure withdrawal Qty can not exceed requirement Qty.
    thank you.
    Henry

    Henry,
    I got what excatly the problem is in your case, the guy who executed has done it very cleverly.
    What must have happenned, is that in the change mode of the order, the component quantity was increased and then Issued. Latter on in the change mode of the order again the quantity was reduced.
    I think this is the excat case what you are having now in the system, the only clue left out for us is to check whether the manual change was perfomed or not. In the components overview scroll to the right side of the screen till you reach column with heading "ChngeProc.", here if the field value is "1" - then it is obvious that there was a manual change in qty for the component.
    The possible resolution to prevent in future is to Make the dynamic message "CN" - 752 as Error in the prodcution order change program. You need to work with your ABAP person for this.
    Hope I was able to get to the right problem and possible resolution.
    Regards,
    Prasobh

  • Standard Report for missing parts at production order operation level?

    Hi PP Gurus,
                We have standard report for missing parts at production orders level.
    For our client, they need a report for missing parts analysis at production order operation level. Do we have any such standard report in the SAP?
    Please help.
    Thanks,
    Reddy.

    Hi Arvind,
          Thanks for for your response.
    1. List: Components,  Layout: Standard layout          set the Missing part
           It shows the component requirement/withdrawn  quantity for each operation of production order. It is not showing the commit quantity.
    2. List: Components,  Layout: Pick list          set the Missing part
           It shows the component requirement/withdrawn  quantity for each production order.
    3. List: Components,  Layout: Missing Parts List-Material View          set the Missing part
           It shows the component requirement/commit quantity for each production order. It is not showing the commit quantity at opertion level.
    4. List: Components,  Layout: Missing Parts List-Order View          set the Missing part
           It shows the component requirement/commit quantity for each production order. It is not showing the commit quantity at opertion level.
          We are unable to get the solution from all these 1 to 4 reports from COOIS.
    Do we have any option to change the existing layout (ex: 3 ) to get the commit quantity for operation with missing parts indicator?
    If avilable, what is the procedure to be followed?
    Thanks,
    Reddy.

  • Number range for serial Number in production order

    Hi all,
                I want to use the Serial Number in production Order ... It should be generated automatically ... when i try this system creating the serial number from 1.....i want the number to start from 2000000 , How to configure this number range ....
    Please advise me ...
    Regards,
    kumar

    Dear
    Following steps are required in Serial Number Management :
    1. OIS2 or Go to path SPRO > Plant Maintenance and Customer Service > Master Data in Plant Maintenance and Customer Service > Technical Objects > Serial Number Management > Define Serial Number Profiles. There enter "2" in Stkck column for your serial profile.
    2.SPRO->SAP Customizing Implementation Guide->Plant Maintenance and Customer Service->Master Data in Plant Maintenance and Customer Service->Technical Objects->Equipment->Equipment Categories->Define Number Ranges
    3. IQ01 Create Serial Number
    4. MM02 You need to add the above created Serial Number Profile in the Material Master ion the work scheduling view .
    5. CO02 Assigning the Serial Number through Production Order,
    Also Serial Number can be created automatically by clicking on u201CCreate Serial Number Automaticallyu201D , Release the Order
    6. MB31 Do the GR for the above created Production Order and Check in MMBE for serial Numbers
    Try and check
    Regards
    JH
    Edited by: Jiaul Haque on Nov 22, 2010 7:43 AM

  • Revision number for Header material in Production order.

    I have maintained Revision number in material mster  for Header material in Production order and also for components.
    1)Revision number for Header material in Production order is not appearing in AFKO table against production order.
    2)Revision number for components in Production order is not appearing in RESB table against reservation.
    Any settings for that please guide.

    Hi,
    Revision number generation is using ECM only possible. Are you using the ECM with revision levels. Check this.
    Regards,
    V. Suresh

  • Filter for batch determination of production order

    Filter for batch determination of production order
    Dear guru ,
    We trigger batch determination manually for every production order using CO02.
    How can I understand whose are the production orders arenu2019t taking place batch determination?
    Checking all the production orders is too heavy ?
    Does exist a massive transaction (coois or others)  where I can select the production orders with components not assigned to the batch ?
    Thanks in advance

    Hi
    In COOIS > In the initial screen select  Documented Goods movement  in the list Field along with and other selection criteria and run the Report
    In the list of orders > Expand corresponding order to view Documented goods movements list with the components with and w/o batch numbers
    Regards
    Brahmaji

  • Tick for goods movement in production order

    Hi,
    I have one query with reference to tick for goods movement in production order.
    Where it comes from as soon as i released the order.
    Is there any customized setting or it is stanadard functionality?
    Tushar

    Hi,
    I am not sure about which tick you are talking. So pls clarify exactly which check boxes you are talking in Production Order.
    If you are talking about check boxes of Goods Receipt,  GR Non valuated & Delivery Completed check boxes then those are standard SAP functionality which comes automatically at the time of creation / release of the order.
    Revert with more details in case your query is not resolved.
    Regards,
    Tejas

  • Table names for Material Characteristic againgst production order

    Hi Guys,
    Actually I have a problem in finding the table name for material characteristic against production order such as Individual length, factor, color, etc. I really spend more than a day to find this. But I cudn't make it. Finally I found the flow some how, but is working only for few cases. Here is the flow.
    AFKO(RSNUM) --> RESB(OBJNR) --> INOB(CUOBJ) --> AUSP(OBJEK).
    T-code: CO02 / Fast Entry tab / Change Configuration(Item Level) / Change Characteristic values.
    Anybody knows about this. Please help me out on this. And please note that, it is not the material characteristic from MM01, it is against production order from CO02.
    Thanks
    Yasin.

    Hi Yasin,
    The best way to know Table Names in SAP is to use a Transaction Code Called : SQL Trace. Tcode : ST05. This will tell you about all the database tables that have been accessed while the Transaction was executed. And then you do a complete analysis of it, what are all the Tables that have been accessed, the fields and the data transfered. So, it's a complete trace of the SQL Query but you can use the information as needed.
    Have a look at the following Links:
    http://help.sap.com/saphelp_nw04/Helpdata/EN/17/358df9c9fee2469105731e10756921/content.htm
    http://help.sap.com/saphelp_47x200/helpdata/en/d1/801f89454211d189710000e8322d00/content.htm
    The best things is that you can use it across any SAP Transaction as it is available in SAP NetWeaver .
    Hope this helps.
    Thanks,
    Samantak.

  • How do I cancel my one year plan for Adobe After Effects?

    So i signed up for a one year plan for Adobe After effects, and I have only had it for less than a week, so how can I cancel my plan, and get my money back?

    Hi Jarlwhynot,
    Please contact the support to get the refund processed for your cancellation:
    Contact Customer Care
    Regards,
    Sheena

  • Function module for calculating planned and actual cost of production order

    Hi ,
    Do we have any standard function module for calculating planned and actual cost for production order?
    i need to implement this in a Z-report.
    Thanks
    Srini

    Hi,
    try below function module
    CRMCO_GET_PLAN_ACTUAL_COSTS
    CO_IH_GET_PLANNED_COSTS_TOTAL
    Regards,
    Sankaran

  • Booking Costs after closing Production order

    Hi all,
    There is a production order for which all components have been issued, plus GR done. Finally all variances were calculated and settlement completed. This is an MTO order.
    Now I need to know how to book additional costs against this order for the following scenarios:
    1. Time booking
    2. Addition of a materials (Users forgot to add a material, but on the shop floor it was consumed)
    What would be the most logical business solution for the above two situations. Do we need to reverse settlement in such a case or not?
    Plus additionally I would like to know why does KKAX show WIP costs on production orders already settled and closed?
    Thnks
    Regards,
    G. Coelho

    Dear Mr.Godwin ,
    Let me explain you the various stage when you add extra material/Time  in a production order :
    1.Good Issue aginst production order reservation completed  -Status GMPS  but operations are not Confirmed -CNF
    2.Production Order Final Confirmation done  but Final Issue Indicator not marked or Clear Reservation not marked  at that time .Through MIGO you can issue the extra material if they are added in the Production Order -Componenet Overview .
    All the cost will be shown as variance in Production Order -Cost anaysis -Select Costing trend -Select required field for information .
    3.You can add extra hrs only in CO11N not any other Txn based on the Define Confirmation Parametre set up -OPK4 (not over or under delivery tolerence in general valid settings )
    4.You can add extra material just after order is Created (CRTD), Relased(REL)  at Componenet-Overview -select line itm and assing at operation with item categoery L
    You can't add extra material and Time in the following state in production process :
    1.Goods Issue with Final Issue Indicator -GMPS
    2.Production Order Technical Complete for settlement -TECO
    3.Production Order Confirmation done -CNF with clear reservation .
    4.Production Order is under Settlement process duing the month end or order by order .
    Best option what we follow :
    1.Update the Production Order with fresh item which are physically issuesd from Store in SAP  to capture in the same reservation nuber
    2.Compare COO2-Dcuments Goods Movement  and MB25-Open reservation for production order , which are required to issue through MIGO.
    3.Perform MIGO for the fresh item which are added in the production order .
    4.Follow BackFalshin of compoenent during CO11N if you have Back Falshing activated in MMR/Work Centre
    5.Apply Enhancement for production  order confirmation to avoid the issue .
    CONFPP01            PP order conf.: Determine customer specific default values 
    CONFPP02            PP order conf.: Customer specific input checks 1           
    CONFPP03            PP order conf.: Cust. specific check after op. selection   
    CONFPP04            PP order conf.: Customer specific input checks 2           
    CONFPP05            PP order conf.: Customer specific enhancements when saving 
    CONFPP06            PP Order Confirmations: Actual Data Transfer               
    CONFPP07            Single Screen Entry: Inclusion of User-Defined Subscreens 
    Hope this will be usefull  for your requirement
    Regards
    JH

  • Purchase order for stock material in production order

    Hi
    does anybody know how to link a purchase request to production order in case of stock material ? When MRP runs aggregate all requirements for stock materials in one purchase request, and I wold like to find list of order that generated the request,
    thanks
    Gabriele

    Gabriele Montori wrote:
    >
    > 2) I would like to know if there is a way to bind purchase request to Production Order (not planned order) BEFORE the MRP runs and create a Purchase Order, because when creates a PO for stock it aggregates all requests in one order.
    I think I understand what you are trying to achieve -> this sounds like you would want to do what SAP standard would do with KD/E-requirements (customer specific) = every material=item=position in a SD-order will create it's PR or production order. In the same way you want to generate one PR-item per production-order component - wait! - Maybe you want to create a single PR for every component in the production order???
    Gabriele Montori wrote:
    >
    > I hit that road but for stock material, RESB-AUFNR is left empty in table..
    You will have to talk to your MM/PP-functional ... if you do not have RESB-entries I have no idea how this process is setup. You probably do not have components in those production orders, only one header-material (CAUFVD-MATNR).  Depending on what is configured in the material-master MRP views + what modifications/enhancements are installed around the complete process, you could have almost any setup. It's impossible to say without seeing it. Make sure s/he explains to you exactly, since even with different stock-materials there could be different setups for procurement.
    Edited by: Mylène Dorias on Jul 22, 2010 11:37 AM

  • Capacity Requirement From Released Production Order

    Hi PP Gurus,
    Can i limit capacity requirement only from released production order ? I don't want to count requirement from production order that just created but not yet release.
    Regards,
    Arman Lie

    Dear Arman,
    As a standard practice the system creates the capacityrequirements once the production order is created.
    Check this,
    When a production order is created the following actions are carried out:
    ·        A routing is selected, its operations and sequences are transferred to the order
    ·        The bill of materials is exploded and the items in the bill of material are transferred to the order
    ·        Reservations are generated for bill of material items held in stock
    ·        The planned costs for the order are generated
    ·        The capacity requirements are generated for the work centers
    ·        Purchase requisitions are generated for non-stock items and externally-processed operations
    Regards
    Mangalraj.S