Planning strategy change from 52 to 20

dear all,
my client wants to change the planning strategy from 52 to 20, if we change the strategy what are all implications it will affect,kindly explain what are the things we have to check in PP,QM,MM and FICO modules
it will be very helpful if it has explained by individual modules
regards
thyagarajan
Message was edited by:
        thyagarajan krishnamurthy

Changing from 52 to 20
following effcets
See that all the PIR's are consumed before switch over.
Do you have any part of BOM items specific to sales order, if so need to be carefull about the consumption...may have to plan sme stock before switch over as in 20 and 52, the important difference is procurement before and after.
Usually in 20 VPRS condition type is anabled for costing if the product.
Mainly need to plan for sub assembly and component well in advance as change will definetely effect the procurement cycle and may end up with shoratge.

Similar Messages

  • Planning strategy change

    Hi,
    My client is going for strategy change from 52 to 20. I want to know which all reports are affected due to this change and the impacts of this change.pls share your knowledge.
    regards
    Ashok

    Hi
    The report which will affect is MD04.
    It is a major change .To avoid inconsistencies, pl. make sure all requirements should be cleaned.
    Othe wise the report MD04 shows lot of inconsisitecies.
    Regards
    YMREDDY

  • Promotion planning level change from product to product  category.

    Hi
    About the promotion planning level, currently we use product level which means we adds individual products and assign money to there.
    But we are thinkin of changing this to product category level planning.
    Could anyone please teach me some good references or links or how to do it in step by step?
    It seems we need to do a lot of work to change the level of planning, but hopefully it might be not too difficult?
    If you know the solution, could you point me some directions?
    Thanks.

    Looking at all that code, I can suggest one way of debugging the issue(Its a bit hard to guess what went in this case,particularly when the problem could be at so many places).
    1. Run your PLSQL as an anonymous block and check if the generated XML structure is what you expect.
    2. Check Firebug Console (if you have it) if an ajax request is send when the item is changed.
    3. Print out the return XML as a string on the screen so that you can make sure it what you wanted(use alert function or append to some page element)
    4. Now try your XML parser JS section starting with the obtained XML as a static variable, trying printing out the parsed out values at different stages
    5. Setting the page items shouldn't be much of a trouble if everything else worked fine.
    Some Observations: If you are on Apex 4.0 wouldn't a Dynamic Action save you all this trouble (Two SetValue processes). Even otherwise you seem to be fetching two id's from the Ondemand process..Can't you just concatenate them with some separator and send that as the result stream(htp.p), handling them in JS would be simple using the split function. If the data is more complex you could return it as a JSON string and parse it with fewer lines of code.
    Found a problem with the code :
    get.add('PRODUCT_ID',pValue)Do you have a page item by that name(PRODUCT_ID) ? else change it to
    get.add('P4_PRODUCT_ID',pValue)and change the following in ur PLSQL process code
    PRODUCT_ID = TO_NUMBER (v ('PRODUCT_ID'));to
    PRODUCT_ID = TO_NUMBER (v ('P4_PRODUCT_ID'));But as I said earlier, Debugging it step by step might be easier.

  • Planning calender change from 12 months to 13 months.

    Hi Experts,
    Can anybody suggest me how to change the planning from 12 months plan to 13 months plan,the is presently we are running MRP Every month 1st the is once in a month..
    But the requirement is we want to change the plan as below format.
    month 1 :  1st to 29th
    month 2:   30th to 27th
    month 3:   28th to 24th
    month 4:   25th to 22nd
    month 5:   23rd to 19th
    month 6:   20th to 16th
    month 7:   17th to 14th
    month 8:   15th to 11th
    month 9:    12th to 9th
    month 10:  10th to6th
    month 11:  7th to 3rd
    month 12:  4th to 3rd
    month 13:  4th to 31st
    so can anybody suggest what changes can be done?
    Thanks and Regards
    Bhargavi Desai

    Hello,
    You can't create a 13 months year on SAP for your business process, but you have an option to achieve this goal.
    You can use a time-phased MRP with a Planning Cycle with 13 periods in the year.
    But if your requirement is just run the MRP 13 times every year simply create 13 jobs in MDBT.
    Regards,
    Daniel

  • Invoice Plan Status Change

    Friends,
    Here is my requirement...
    When a batch program runs (using RMMR1MIS), based on certain criteria, the Invoice plan status changes from A to C (table : FPLT-FKSAF).
    I would like to start a workflow by tracking the status change, but I do not see any default event or update in any change document....
    Thanks in advance.
    Muthu

    HI,
    Unfortunately I can only confirm that there is missing functionality
    for change management in area of MM invoicing plan. No change documents
    are created in CDHDR and CDPOS tables for any change for invoicing
    plan.
    Best Regards,
    Arminda Jack

  • How can i change from my single app to creative cloud membership? the 'switch plan' doesn't appear in my account?

    how can i change from my single app to creative cloud membership? the 'switch plan' doesn't appear in my account?

    Locking this discussion.  Please see my response at how can i get some help to cancel my single app month to month and/or upgrade to full creative cloud membership? please don't tell me to follow the guidelines because i've tried several times but the options to 'switch plan' or cancel plan' are not availa.
    John T Smith please feel free to also reference this discussion.  I believe it partly explains the frustration individuals face when attempting to cancel their membership.

  • Changing from Creative Cloud Photoshop to Photography Plan.

    Does changing from Creative Cloud Photoshop Anual subscription (before running the all year contract) to Photography Plan has a penalty?

    Please contact Adobe Support via Contact Customer Care
    Regards
    Rajshree

  • MRP exception message 64 and planning strategy group 52

    Hi Gurus,
    I have done extensive search online in the forum to find the route cause why we are getting MRP exception message 64 for a specific material in one of our plants. This exception message does not occur for the same materials which is also produced in another plant.
    I was just wondering whether the planning strategy group of 52 in MRP 3 view would have any effect on the frequent occurrence of exception message 64. I know that the 64 message occurs when the routing time is higher than the in house production time. If that's the case where to look for in routing to correct this, apart from this do we need to look at work centers and other details. I'm not a  PP person but still was curious to know see if i could take a shot at it.
    Also the MRP settings that we follow in the plant where this problem does not occur is NETCH, Create PR - 2, Schedule lines - 3, create MRP list - 1, Planning mode - 3, scheduling -2
    in the plant where the 64 message occurs quite often is Netch, Create PR -2, Schedule lines - 3, create MRP list - 1, planning mode - 1, Schdeduliing - 1
    I was  thinking do MRP settings and planning strategy group would have any impact on why we are getting the 64 wexception message
    Because of this 63 exception message, the downstream components are getting wrong signals.
    Thanks
    Ravi

    Hello Ravi
    Generallt, exception message "64 - Production finish after order finish" is triggered when the order start date is in the past and system automatically changes to forward scheduling to calculate the finish date.
    Note 1913017 explains how the order basic date is calculated and adjusted in case of forward scheduling, however, you are using strategy 52 and this is a very special scenario, whever VP planned orders are generated.
    The VP planned orders will always be adjusted to the requirements date even if the requirements date is in the past. This is a special feature in the planning segment, since these orders are only kind of 'virtual' planned orders. These orders only have to provide the demand requirements for the components in time.
    Therefore, there is a relationship between strategy 52 (VP planned order) and the exception message observed.
    BR
    Caetano

  • Reg:Planning Strategy 40

    Hi friends,
    i need to know about planning strategy 40.
    For EX:
    1. suppose if we have  planned and created PIR from january to march(quarterly plan) for any product, now if we want to change the plan how the system will behave..can we change the PIR  which we have generated from JANUARY TO march.
    If it is possible to chnage ,,how to change the PIR..what will be the impacts.
    2' Can we create another PIR once again from january to march...or feB to march apart from existing PIR
    3. suppose if i have created PIR from january to march , and splitted into daily  plan, in between if the sales orders comes how this planning strategy 40 will behave.As it is make to stock.
    For Ex:
    We have planned 1000 numbers in the month of january, daily 50numbers production.
    Suppose if we get sales order for another 2000 apart from our planning 1000numbers ,how this planning strategy will behave.
    Thanks in addvance.

    Dear
    Planning startegy 40 works like follows :
    It is basically Consumption of PIR not Reduction of PIR .
    Example :Let say you have  PIR for 1000  for January  and it is appearing in MD04
    Now you have sales order for another 2000  for same month .Here PIR quantity is less than the Sales Order Qty ! Now run MRP -MD03/MD02 -NETCH , 2,1,3,3,2 and check the Result .Here PIR will be vanished and PR/Planned  of 2000PC will be appearing in MD04.So PIR is consumed by Sales Order .
    Now you have   PIR for 2000   and you have sales order for another 1000  for same month .Here PIR quantity is more  than the Sales Order Qty ! If you goto MD04-Sales Order will not appear at all .That means Sales Order is geting fullfilled by PIR deamnd. Now run MRP -MD03/MD02 -NETCH , 2,1,3,3,2 and check the Result .Here Sales will be vanished and PR/Planned  of 2000PC will be appearing in MD04.
    Refer : Re: Industry wise planning strategy usage
    Answer of your questions :
    1.You can goto MD62-Change and add PIR questiy at Material level , Plan Numbers , Product Group Level
    2.You can create but it will update th exsiting motnhly requirement  in the same planning table in MD62
    3.This question is answerd in the above explanation .
    Hope it helps
    Regards
    JH

  • Cutover planning strategy doc

    Does anybody have Cutover Planning/Strategy document for PI/XI? I do have the ASAP standard.. but I feel there must be one with lot of good information.. please send it to my  gsvas81at gmail dot com

    Hi,
    We restricted from NEUPL................
    When i have gone thru entire process my findings for this problem is as follows
    1) When A planning strategy is changed in a plant?plants the existing/Pending PIRs need to closed or deleted. If there are any PIRs pending the system can not select new req Type automatically.
    2) All the Depending requirements schedule lines and purchase orders for existing PIRs need to be closed before going to new Planning Strategy
    If the user follows this procedure then the system will automatically uses  "Control of Requirements Type Determination " and a required "Req Type" populates in user parameters. otherwise there will be planning inconsistency
    Please correct me if i am wrong
    Pavan

  • MRP exception handling for planning strategy 52

    Hi All,
            How to handing MRP exception in Mass? For example, header material having two sub assembly and 3 raw materials in it's BOM. As per planning strategy 52, we maintain PIR for finished part, if we run MRP planning will be generated with respect to Planned Independent Requirement(PIR). Now, the problem is the higher/upper level material planing date is lower than low level material, It means Semi finished material(SF2) planning date is for example ( 15 june 2014) at the same time another lower level semi finished material (SF1) planning date is (18 june 2014). In this case without completing SF1, we can't produce SF2 because SF1 is an component of SF2. In the same way, system will propose the planning info for all raw material/semi finished. How we will handle this exception in mass since we using more materials in shop floor.Hence, it's really hard to planner to adjust the planing date for each and every material wise. How to handle/adjust this MRP exception? How to make system to calculate dependent materials availability to calculate next level material's planning date (start,end)? We understand that we have to maintain proper master information like in-house production days, planned delivery date, Gr processing date etc., to get planning information. Apart from that how we handle or to get without this kind of exceptional message? Please suggest
    Thanks

    AKS,
    There is absolutely nothing wrong with having exception messages.  Expecting to be able to perform some mass transaction that will magically make all messages "go away" is unreasonable.  In any real life business, there will be new exception messages with every MRP run - sometimes thousands of them.
    These messages indicate that there is something the matter with the plan; but they don't really tell you what is the best way to fix the plan.  There may not be an easy way to fix this plan, it may actually require having your planners examine each PIR, trace down the BOM, and determine what is the best solution for that PIR.  Once you have decided what is wrong with your plan, then ask me what mass changes are available to fix THAT problem.
    Now, to your question.  If you want all the dates to line up, then allow dates in the past. Although this solution doesn't give you results that are any more realistic than your current solution, you will eliminate most of the exception message 10's; and, if all your master data is correct, most of the supply and demand dates should line up.  The messages will be replaced with a boatload of "new, and start date in the past" or similar.  You can allow MRP to create procurement proposals with start dates in the past by changing the appropriate settings in OPPQ and/or OPPR.  Also affected by scheduling parameters found in OPU5 and OPU3.
    This is a business decision.  Some planners prefer not to allow dates in the past.  Others just the opposite.  You (or the client, if you are a consultant) have to decide which is best for your company.
    Best Regards,
    DB49

  • When will EK02 appear in the Sales Order?? For different planning strategy?

    Hi Experts,
    In our SAP system ,when you create a sales order with a material which planning strategy is
    50 Planning without final assembly (MTO) , in the item detail screen , on the "Conditions"
    TAB, we will see condition type EK02 and its value.
    But when I create a sales order with a material which planning strategy is 40 Planning with
    final assembly (MTS),in the item detail screen , on the "Conditions" TAB, condition type
    EK02 will not appear.
    I have checked the customizing of our SAP system ,as follows:
    For planning strategy 50, the Requirements class is "045"(MTO val. with cons.),and on the
    configuration screen of Requirements class,we see "Condition type for copying costs from
    line items" (CndTyLineItems) is null ,no value ,not "EK02".
    And for planning strategy 50,the the Requirements class is "050"(Warehouse consumpt.) and
    and on the configuration screen of Requirements class,we see "Condition type for copying
    costs from line items" (CndTyLineItems) is also null ,no value ,not "EK02".
    And on the configuration screen of Sale Order Type screen(VOV8), we see  "Condition type for
    copying costs from line items" (CndTyLineItems) is "EK02" for all the sales order type we
    have used.
    So I am very confused.
    Why material with planning strategy 40 there is no EK02 in the sales order?
    Why material with planning strategy 50 there is EK02 in the sales order?
    Where is the EK02 come from? The requriement class ? Or the Salse order Type?
    Are there any other customizing for Condition type EK02 determination?
    Thanks very for any reply!!

    Hi,
    In MTO you will create Process order.
    And to Produce a Item you use Sub components that is Raw material
    That raw material cost is EK02 which you maintain in the Material Master - Accounting View 1.
    You can see cost in the Process Order also .
    Note : Dont post same in different posts

  • CO88-Error :Perform the planned price change for material

    Hi Experts,
    While running CO88 i get this error. "Perform the planned price change for material ". My material is manage at S and it doesn't have any marked cost. The status is FR and no other status on cost etimate for the article are active. what i shoul do? why if i run the PP order with KO88 i don't have any error?
    Please help i'm facing the closing period.

    Hi,
    If dynamic price change is active in your system the first posting in the new period of this material tries to
    - release a future cost estimate of that period OR
    - change the price to the future price in accounting view
       (if the future price date is reached)
    Unfortunately this dynamic price change does not work in order settlement. Therefore you are asked to perform the price change first by t-code CKME (or CK24).
    If you are using price determination control 3, any price change or release should always be the first transaction in a new period to avoid any inconsistencies.
    The dynamic price release will only release the price with transactions which involve material movement and this is not the case by posting invoices and order settlements.
    if you are in period 12/2009 then a settlement in 12/2009 does not require the release cost estimate of 01/2010.
    But if you are already in 01/2010 therefore settlement in 12/2009 is a posting into the previous period. This will change also data of the current period. Therefore the cost estimate has to be released first.
    Another option, if you don't want to receive this message, would be to change this message from Error to Warning (check note 434752).
    Please follow the following steps:
    T-CD:OMRM
    Message M8 394
    =>you set the message type to '-' for error message M8394, that means no message is to be issued.
    regards
    Waman

  • Reposting of Planned Line Items from One Cost Ctr to another

    Hello SAP Gurus,
    Can you tell me the process hoe We can repost planned line items from one coct center to another ?

    Hi,
    You can use Transaction code KP06 to update the changes to the plan data for the Cost Centers. There is no separate transaction code to repost plan data for Cost Centers.
    Thanks
    Murali.

  • Planning Strategy

    Hi all
    i am pretty confusion about decide the planning strategy.
    here my client requirment is construction project and  they have their own plant to full fill their requirments.process flow is like this
    get requirments from different projects
    Project Plann dept will raise the indent to commercial dept(purchasing)
    procure raw material and they will send to storage location
    production will run MRP and create pln order
    then execution of production
    issue of finished Goods (Hot Mix and WetMix) to projects
    reconcilation of rawmaterial consumption to tht project.
    can any one tell which strategy will suits my client requirment

    Hi there,
    you can use strategy 40 Planninh with planning with final assembly....
    Regards
    Hemant g