PM- plant maint Prev-maint planning/ scheduling how ? change, add, etc

Dears,
appreciate your assistance.
we are having many PM work order in same near by area for related equip/ amchines.  we like to generate one work order for all pms which are in limited area.  if we get it we shall beable to generate one work order rather than ten work orders. how we can do it.
thanks
Mansoor.

dear Pushpa,
ya it is for palnt maintenance and for "preventive maintenance" planning and scheduling jobs.
u mean cover the equipments in equal number og maint-plans, cover all such plans in / under one maint-item.
now we have in way that one maint plan has more than one maint-item, and we are getting many work orders may be equal to number of maint-items, but our maint engineers want that all those being done at same time, so why not we make one work-order - but it should maintain equipment history.
i notice you are proposing opposit to what we have now.
In your proposed way will the equipment hisotry will be maintained for each equipment, that PM was called on --, planned for -- and completed on -- has been done.

Similar Messages

  • Tcode to see Prev Maint order in PP

    Hi,
    PP WC is used in Eq Master. Prev Maint order is created with sys condition as 0 as per scheduling
    1.In which Tcode i've to see whether this WC is blocked for the period as per Maint order
    2. In which Tcode i've to see Prev Maint order in PP
    Kindly share your views.
    Thanks
    Prasad

    Hi,
    I would like to see the Prev Maint orders as per scheduling in PP module.
    In Capacity evaluation or capacity levelling  it's not blocking PP WC
    Kindly share your views.
    Thanks
    Prasad

  • How to find the existing sql server backup plan/schedule is there a script for that?

    Friends,
    Is there a easy way to find out in SQLServer (for All DB's) what is the current backup plan/schedule ? is there a script for that?
    Thanks,
    Karthikeyan Jothi

    To check the database backup 
    Select
    SERVERPROPERTY('ServerName'),
    db.name,
    CONVERT(VARCHAR(10), b.backup_start_date, 103) + + convert(VARCHAR(8), b.backup_start_date, 14) backup_start_date,
    CONVERT(VARCHAR(10), b.backup_finish_date, 103) + + convert(VARCHAR(8), b.backup_finish_date, 14) backup_finish_date,
    case
    when (DATEDIFF(hour, b.backup_start_date, getdate())<24)then 'Success'
    when (DATEDIFF(hour, b.backup_start_date, getdate())>=24)then 'Failed'
    end Status,
    DATEDIFF(hh, b.backup_finish_date, GETDATE())BackupAgeInHours,
    (b.backup_size/1024/1024/1024 )BackupSize,
    case b.[type]
    WHEN 'D' THEN 'Full'
    WHEN 'I' THEN 'Differential'
    WHEN 'L' THEN 'Transaction Log'
    END Type,
    ISNULL(STR(ABS(DATEDIFF(day, GetDate(),(Backup_finish_date)))), 'NEVER')DaysSinceLastBackup
    FROM sys.sysdatabases db
    Left OUTER JOIN (SELECT * , ROW_NUMBER() OVER(PARTITION BY database_name ORDER BY backup_finish_date DESC) AS RNUM
    FROM msdb.dbo.backupset) b ON b.database_name = db.name AND RNUM = 1
    where dbid<>2
    OR
    SELECT
    DISTINCT
    a.Name AS DatabaseName ,
    CONVERT(SYSNAME, DATABASEPROPERTYEX(a.name, 'Recovery')) RecoveryModel ,
    COALESCE(( SELECT CONVERT(VARCHAR(12), MAX(backup_finish_date), 101)
    FROM msdb.dbo.backupset
    WHERE database_name = a.name
    AND type = 'd'
    AND is_copy_only = '0'
    ), 'No Full') AS 'Full' ,
    COALESCE(( SELECT CONVERT(VARCHAR(12), MAX(backup_finish_date), 101)
    FROM msdb.dbo.backupset
    WHERE database_name = a.name
    AND type = 'i'
    AND is_copy_only = '0'
    ), 'No Diff') AS 'Diff' ,
    COALESCE(( SELECT CONVERT(VARCHAR(20), MAX(backup_finish_date), 120)
    FROM msdb.dbo.backupset
    WHERE database_name = a.name
    AND type = 'l'
    ), 'No Log') AS 'LastLog' ,
    COALESCE(( SELECT CONVERT(VARCHAR(20), backup_finish_date, 120)
    FROM ( SELECT ROW_NUMBER() OVER ( ORDER BY backup_finish_date DESC ) AS 'rownum' ,
    backup_finish_date
    FROM msdb.dbo.backupset
    WHERE database_name = a.name
    AND type = 'l'
    ) withrownum
    WHERE rownum = 2
    ), 'No Log') AS 'LastLog2'
    FROM sys.databases a
    LEFT OUTER JOIN msdb.dbo.backupset b ON b.database_name = a.name
    WHERE a.name <> 'tempdb'
    AND a.state_desc = 'online'
    GROUP BY a.Name ,
    a.compatibility_level
    ORDER BY a.name
    To check the schedule you can try the below script
    https://gallery.technet.microsoft.com/SQL-Jobs-Complete-eabe0050
    --Prashanth

  • How to Add plant in report?

    Hi ,
    I have to create a cost center report which is for actual and plan comparison.
    Situation is i don’t have a business area, i have only plants to value my costs in my report in the column. I am using CCSS table to data extract .I have a field name werks in the table .
    How to add Plant into my report ,Can any body help me on creating a set on this. Or is there any solution for this .

    Hi,
    If a field in FBL1N is not filled it might be because the field has to be created as a special field.
    In the Line item Display list in FBL1N follow this menu path: Settings -> Special fields, and add the fields you want from relevant table.
    The fields are later available for display,and you can choose them from the Line item Display list following this menu: Settings -> Display variant -> Current. From the hidden list you can now choose the fields you want to have shown. If the technical name is shown for the fields, the special fields are all starting with '1-U_'. It's important, that you add the Special field, if the field also exist as Standard field.
    The Special fields are shown in the buttom of the Hiddden list.
    Please also read the solution part of note 215798 for some very import- ant steps to be aware of.
    But, for having a field shown in the vendor Line Item Display (FBL1N) the field has to exist in the vendor Line Item. If this is not the case, you will evt. be able to see the field in FBL1N by using Offsetting account info.
    Check if field WERKS is in the structures RFPOS and RFPOSX. If not, then you need to add the field to the structures RFPOS and RFPOSX. When the structures have been extended with the field then you need to run the reports  RFPOSXEXTEND and BALVBUFDEL (in the same way as seen in the solution part in note 215798).
    Please assign points if it useful
    Regards
    Ravinagh Boni

  • In scope of planning ( md01), How to maintain MRP areas in scope of plg?

    Hello PP members,
    In scope of planning ( md01), How to maintain plant or MRP areas in scope of planning ?
    What is the transaction code for maintaining plants or MRP areas in the scope of planning
    I tried transaction code SAMP, Also went to SE93( Maintain transaction) for any related transaction codes for maintaining plants in scope of planning, it wasn't much help
    Thanks for your time,
    Thanks Again,
    Suren R

    Hi,
      we can use Total planning(MD01) for a single plant or use scope of planning to control whether total planning is to be carried out for single plant/sevaral plant/ for one MRP Area/sevaral MRP areas/ combination of plant and MRP Areas.
    Steps :
    1.Group together the plants which are to be planned in spro in --->Define scope of planning.(OM0E)
    2. Define the scope of planning as 999 for ex and give description. 
    2. Now select that and Specify the sequence in which Plants and  MRP Areas are to be planned,
    3.Goto new entries and enter the plant as 1000/MRP Area as 1000 with counter 1 and plant as 1100 with counter 2 and save.
    4.Execute the total planning either as online job or as background job.
    5.The planning run has to be always started with paralle processing.
      In SPRO in define parallel processing in MRP enter the destination for parallel processing for ex your server name and enter the no .of sessions as 1 and save.
    6.Tcode MD01 enter the scope of planning group and selet the parallel processing and enter.
    7. All the materials to be planned in the plant / mrp area will be planned now.
    Regards,
    nandha

  • Maintenance Planning & Scheduling of calibration order

    Hi
    I have to schedule calibration inspection of a few equipments in such a way that system automatically create inspection lot & calibration order daily.
    Whether user enter calibration result or not, inspection lots in future should be created automaticallly.
    I created a single cycle plan using IP41 and start the schedule using IP10, the system created first inspection lot automaticaly but always require me go to to scheduling and save the plan again if I want to create next inspection lots. How can I configure/set the system in such a way that it creates inspection lots/calibration order automaticaly
    Plz also tell after taking usage decision of inspection lot whether I need to do some act on calibration order such as technical completion or business completion.
    Thanks in advance

    Dear Chris,
             In maintenance plan go to Maintenance plan scheduling parameter & put Schedule Period '360' Days in sub screen under Call control parameter.
    Then Go to IP10and make automatically scheduling it will make plan for whole yera.
    Regards... Rakesh Saxena

  • What is Setting Resource Manager plan SCHEDULER[]:DEFAULT_MAINTENANCE_PLAN

    "Setting Resource Manager plan SCHEDULER[]:DEFAULT_MAINTENANCE_PLAN "
    1. I would like to know what is this.
    2. How to disable this message from alert ?
    Please provide your comments or doc for this subject.
    Thanks,

    References:
    http://download.oracle.com/docs/cd/B28359_01/server.111/b28310/dbrm005.htm
    http://www.dba-oracle.com/job_scheduling/resource_manager_plan.htm
    http://oradbpedia.com/wiki/Oracle_11g_Resource_Manager_Changes
    Regards,
    Venki

  • HT201250 Hello i am using TimeMachine to back-up entire Mac image (data + system) on an usb-local drive. I would like (on top of it) add a specific plan to back up some files on a remote network drive. Does TimeMachine support multiple back-up plans ? How

    Hello i am using TimeMachine to back-up entire Mac image (data + system) on an usb-local drive. I would like (on top of it) add a specific plan to back up some files on a remote network drive. Does TimeMachine support multiple back-up plans ? How ?

    Time Machine is capable of backing up to multiple locations, and can be used to back up to both a local hard drive and a networked drive (provided that that drive is in or connected to a Time Capsule or another Mac that is sharing it over the network). The catch, though, is that you can't specify different things to back up to different destinations. Whatever you exclude from Time Machine backups is excluded from ALL backups, and whatever is included is included on all.
    So, get a large enough drive that you can back up everything you want in all locations, or use something else for maintaining the network backup.
    More information on these topics can be found here:
    How do I set up Time Machine to a shared drive on another Mac?
    How do I set up Time Machine to a Time Capsule or Airport Extreme?
    "Rotating" Time Machine backup disks

  • I purchased a monthly pack and havent been able to use it. I have been getting charged for 3 months now and I still get an error message saying "unable to load all your plans". How do I re-install or dowload and get my last 3 payments reimbursed?

    I purchased a monthly pack and havent been able to use it. I have been getting charged for 3 months now and I still get an error message saying "unable to load all your plans". How do I re-install or dowload and get my last 3 payments reimbursed?

    Link for Download & Install & Setup & Activation problems may help
    -Online Chat http://www.adobe.com/support/download-install/supportinfo/
    or
    Adobe contact information - http://helpx.adobe.com/contact.html

  • HT4847 I had to upgrade my iCloud storage plan, but I was still charged for the original $20 a year plan. In addition to the new $40 a year plan. How do I remove the $20 plan and get a refund? Can I stop them from charging both plans?

    I upgraded my iCloud plan from $20 to $40 a year. However, I am still being charged for both plans. How do I get a refund and or remove the original $20 a year plan?

    I have the exact same situation as you mattiger18.  I cannot install Lion or I will disrupt programs that I run on Snow Leopard that are critical for my work.  Apple is not providing a solution for us.  Last time they migrated from Mobile Me to iCloud they lost months of emails and had emails bouncing to my accounts.  They destroyed 8 weeks of my business.  They have done it again.  They have already lost several months of my emails and they are bouncing my business email.  It's outrageous!
    I spent thousands of $ on my software and I have no intention of installing Lion or other OS iterations.  It is bad enough that Apple's service patches are crippling some of my applications.  My biggest regret was not altogether getting off of iCloud and setting up all my business email on other email servers like gmail, etc.  It is so outrageous what Apple is doing it is beyond words.  They are supremely greedy and totally uncaring for their customers.

  • How to add a new schedule line?

    Hi folks,
    Please help to tell me is there any user exit can be used for adding a new schedule line? I want to keep the old first date data, add new shedule line with new updated schedule line date. Pls. help to advise how to do it in VA01/VA02 ?
    If i simply use the following update statement in MV45AFZZ, then the first date will be updated by the new Schedule line date, which is not what i want. (Since new order always the First line "0001" will get updated)
    xvbep-edatu = t_temp-edatu .
           modify xvbep TRANSPORTING edatu "UPDKZ
                         where posnr = t_temp-posnr
                           and ETENR = '0002'.
            if SY-SUBRC <> 0.
               modify xvbep TRANSPORTING edatu "UPDKZ
                            where posnr = t_temp-posnr.
            endif.
    Tks,
    Jenny
    Message was edited by:
            Jenny Zhuang

    Hi Ferry,
    Many thanks for the reply. But i still have the question, seems the user exit 'USEREXIT_CHECK_VBEP' in 'MV45AFZB' is used for addtional checks on the schedule line, my questions is how to add a new schedule line? It maybe very difficult. so is it possible to change the configurable Sales order's Finish Date for it's production order, and force it to generate a new schedule line?
    Tks,
    Jenny

  • NWA Job scheduler, how to change parameters?

    Dear guys,
    moving to AEX (java-only) the ABAP Stack is gone.
    Regarding job scheduling there is no more transaction sm37, but Job scheduler within NWA to be used for scheduling jobs.
    I configured a job for the predefined job definition AlertConsumerJob to get emails in case of alerts.
    Doing this the questions arises how to change parameters once a job is scheduled e.g. add additional email receiver.
    So far is seems you have to stop the configured job and define a NEW one from scratch by providing all job parameters. It seems not possible to adjust a job.
    This is not very comfortable?
    Is there an workaround / solution for this?
    Best regards
    Jochen

    Hello Gaurav
    thanks for your reply.
    It's a pity, but shows that there is still some room of improvement regarding AEX functionality (java only)
    Best regards
    Jochen

  • How to add new product in interactive demand planning(IDP)

    Hi gurus,
    How to add new product in interactive demand planning(IDP), can you suggest me, when i click data view in IDP, it will show new product.
    Regards
    babu

    Hi Raj,
    Since the New Product is already in MPOS what you need to do in your Data view is to go to "Selection Window" on the left side of the screen(make sure you dont click on the existing selection ids). Select Product at the top, the planning version will come in the next row and then you again select the Product as charateristic and enter the New product name against the Product(Characteristic) and then save it in case you want it to use for your future references. When you will double cilck on the newly made selection id you will be able to see you product with the keyfigure details in right side.
    Please let me know if it works.
    Thanks,
    Anand.

  • I need to add a license to my VIP Plan. How do I do that?

    I need to add a license to my VIP Plan. How do I do that?

    I need to add a license to my VIP Plan. How do I do that?

  • How to add another Planning Server to the Shared Connections?

    Hi,
    This is for version 11.1.2.1.103
    Currently all of our users use Planning in Prod environment. I would like to open the UAT environment to a smaller set of users. UAT environment is in our Test environment. I couldn't figure it how to add the UAT environment to the current Prod Shared Connections. I was hoping it would be as easy as right click on the Prod Planning Server > click on Add > Add the UAT server > Click OK.
    Instead I had to follow couple of steps to add the UAT environment to the SV:
    1. SmartView > Options > Advanced > Edit Shared Connections URL with UAT environment URL > Click OK
    2. Connect to Shared Connections > Planning
    3. Right click on the Plan Type > Click on Add to Private Connections
    4. Follow the same steps for the PROD Plan Type.
    Now, I do have two environments under Private Connections and I do not need to follow the first step every time I want to switch between environments.
    Was it a overkill or I did it right?
    Thanks,
    Mehmet
    p.s. I just noticed that in Shared Connections, you can add another Essbase Server, but that's not an option for Planning.
    Edited by: Mehmet Sevinc on May 8, 2012 2:48 PM

    Hi Again,
    following up my previous comment on this, you can create a macro and assign to an event or macro in the excel to change shared connection URL.
    Declare Function HypSetSharedConnectionsURL Lib "HsAddin" (ByVal vtAPSURL As Variant) As Long
    Sub SubHypSetSharedConnectionsURLTest()
    Dim lRet As Long
    lRet = HypSetSharedConnectionsURL("http://UATserver:19000/workspace/SmartViewProviders")
    End Sub
    http://docs.oracle.com/cd/E17236_01/epm.1112/sv_user/ch17s01s08s10.html
    Hope this helps,
    Ahmet

Maybe you are looking for

  • Portege M200 - Keyboard is not working and I can't boot from CD/DVD

    Hi I recently tried installing VM Player on my Toshiba M200. When I rebooted my machine I found my network connections did not work. I tried to uninstall the VM Player but it failed half way. As the program had created a number of virtual network con

  • USING INDEXES DEFINED ON TABLES IN SELECT STATEMENTS

    Hi there, I would like to ask a simple question, how i can use indexes defined on certain columns on one of my database tables in a select clause: table name: B2TECDOC schema name: AWDBT1M4 indexes defined: AWDBT1M4.B2TECDOC_B2TECDOCKEY index AWDBT1M

  • ABAP code needed to populate data in the fields............

    Hi, I have added 3 new fields to the datasource 0PROJETC_ATTR fields names are : ZZPROFL , ZZPLFAZ and ZZPLSEZ Can some body tell me the ABAP code to fill data in these 3 fields. Thanks, Jeetu

  • Pixelated problem with PE 12

    I am trying to create a video of still images.  I brought the original images into my organizer and they were clear.  When I bring them over to my video editor and play them, they become very pixelated.  However, when the video stops, the images beco

  • Recompiling de distro

    I've been recompiling my entire system with the ABS packages, and while almost all packages compiled well under gcc4.3, some packages had trouble with it. So I've discovered the 'bugs' and made some patches. I would like to share them with the commun