PP-MM issue in material reservation for production order.

Dear Friend,
I am in confusion that this is PP issue or MM issue.
If any issue if any one knows please provide me solution.
I run report -MO24- missing part info system.
System givening me material and requirement date and requirement quantity.
If stock is availble then it is comming in commited quantity. Thats is agreed.
But My problem is that that committed quantity is repeated daily though stock is not available in system. Why this is happening???
Regards,
Mahesh.

First, there no such transaction as MO24!
And secod, please try to clarify your question; what do you mean that committed quantity is there every day without stock?

Similar Messages

  • Issue/Bug in reservation for production order

    Hello,
    We have a bug with the reservations for a production order, which in turn is causing a problem with clearing a cogi error. I have a COGI error for material 123 in plant A.they are trying to remove 14,312 lbs that was confirmed to production order 1000123. According to the error message the production order only has 6,400 lbs that can be removed. in CO14 my material 123 show two quantities in different batch 14,312 and 6,400. In Reservations shows only 6,400 as being consumed. this amount should be 20,712 (14,312 + 6,400). The reservation did not get updated correctly. Why this happen? How could we correct this RESERVATION to add up 14,312 in my material 123)?
    Please give me feedback ASAP, need help.
    Thanks and Regards,
    JJ

    Hello,
    thanks for the answer you have given me..
    as to make sure, does it is safe to delete the error? even that it tells that RE qty moved exceeded by 7.912 lb? it so weird how come was the reservation was complete since when they raised it it just 6,400 it shows? how could i make sure that document goods movement for my production order as mr. pradeep told me to do? what should i do?
    thus when deleting the error in COGI, it will change the my material in CO14 COMPLETED and have QTY WIDTHDRAWN and will be encluded in the same RESERVATION NUMBER?
    Anyone please revert back to me.
    Thanks
    JJ
    Edited by: John Jay Palisoc on Jul 22, 2008 7:08 AM
    Edited by: John Jay Palisoc on Jul 22, 2008 8:02 AM

  • Exclude stock reserved for production order from availability check

    Hi Experts,
    We have a problem in the availability check.
    There is a material used as selling product and components in the same time.
    When the material has been reserved completely for a production order, the new sales order still get confirmed despite there is no physical stock at all!
    Please advise how to exclude the stock reserved for production order from the availability check in sales order? Many thanks!
    Regards,
    Qiang

    Go to MM02 and check what availability check is maintained for that material.  Next go to OVZ9, select that available check with the combination "A" and maintain "X"  or  "F"  in the field  "Incl.production orders".
    thanks
    G. Lakshmipathi

  • WM Material Staging  for Production Order

    Hi,
    In the process order txn Cor3, Go to > List > WM pick list>  the initial screen is  Display WM Material Staging  for Production Order. In the All parts tab, could you please help me on how to be able to populate the fields in the  BSI, Category and Storage Bin. Your help is greatly appreciated.
    Thanks

    Dear Ellen,
    If you set the cursor on 'BSI' field and push F1 you'll get an explanation about the meaning of each category.
    '"<i>1" pick list item
    This materials are picked according to the required quantity specified in the production order.
    '2': Crate or kanban parts
    These materials are always removed from the warehouse in full cases. These can be ordered, for example, as soon as a case of needed parts is emptied in production.
    '3': Release order parts
    Release order parts are scheduled individually and the quantities are supplied manually to replenishment storage bins based on the requirements of production orders and the stock levels in the scheduled production supply areas.
    "0" not relevant to WM-PP
    These materials are not relevant for WM production supply and cannot be requested using the WM system.</i>'
    For instance:
    You can set raw materials / SFG as pick parts if warehouse workers have to collect those parts from high racks (from different places) and they have to provide an exact qty for the PrdOrd.
    We use '4' (manual staging) for huge alu rolls that are near the machine and WH workers have nothing to do with it - the operators, who deal with the machine, have to put the new rolls on it.
    When we issue the PrdOrd the requirements of this material won't appear in LB10 since WH has nothing to do with them.
    'Storage bin' filed will contain a value automatically, if your settings are proper.
    E.g. you have to define the default 'stock removal' & 'stock placement' storage type on WM view of material master.
    Additionally you have to define control cycles for materials you use for your production. (LPK1)
    The control cycle says from which storage type & bin you want to consume the components.
    BR
    Csaba

  • Report to check open reservations for production orders where GI not posted

    Hi experts,
    Can we get reservation details from any report/ table for production order where material has not been issued, report should also display the value of the reserved material.
    I could not find desired details in RESB (it has price but not value) and MB25.
    Thanks in advance, useful ansers will be rewarded.
    Thnx
    Anand

    Hello Anand,
    there is no report but you may use the production order info system with list "components" and create a layout contaning the issued quantity and/or the final issue indicator. With a correct sorting, the list should show all orders with non-issued components at the top.
    Regards, Andreas

  • Material Staging for Production Order

    Hi,
    I am doing Material Staging against production Order using T Code MF60. We don't have WM setup in the enterprise structure so the Staging is done via IM Mvmt. Type 311. My problem is that the material document created using MF60 does not have a reference of Production order or vise versa. Can anyone suggest a configuration or a user exit that can be used to make a reference link between the Production Order and the Staging Document?
    Thanks
    Arvind

    Hi!,
    Though whatever you are asking for is not possible with standard SAP but you can try this work around solution:
    Click on replenishment element.
    Now in MF60  Menu > View > Table column > Select " All Column" (after clicking ).
    Now system will show some open fields (like Goods recipient, unloading point etc) on replen. element.
    There in one of the field like unloading point (which you are not using elsewhere) you can enter the production order number so when you stage the same that order number will be saved in that document and you can get it from RESB table against the reservation number.
    To automate the same you can use some enhancement with above logic.
    I hope this helps in resolving your problem.
    regards,
    Uday
    Edited by: Uday Parchure on Jul 29, 2009 12:50 PM

  • Material reserved for production

    Dear guru ,
    I have a material that can be used by PP for a production order reservation and can
    Be used by SD for a sales order.
    I have stock for this  material and I need that only PP can use it.
    Which solution do you suggest in order to avoid that SD can use this stock ?
    Specific storage location ? Specific Stock type ? Other ?
    Thanks in advance.

    Hi cristiano,
    Please letus know what is planning strategy has set for material  for which reservation has created.
    It is seems to be, the reservation has created  for material is Component which is used a child for another material, and it produced in Both MTS & MTO at the same time. ifyes, create new  Planning Startegy group which allows Both MTS & MTO and assigh to that Components.
    In the MTO  , sale order stock will be created, now the sale person will not use the palnt stock avilable for that component.
    Regards
    Pradeep

  • RE: Goods issue posting through Migo for Production Order

    I have released the production order, when I want to post the goods issue through migo to the concerned order I am getting error saying that material "No components exist but there was stock in the storage location for unresticted use.
    I have checked through MMbe transaction.

    Are there components in the Production Order? If yes, is the reservation created and movement allowed for the reservation?
    Lakshman

  • Manual Reservation for Production orders with automatic reservations

    Hello SAP Experts, i have a question regarding Order Reservations, in my company when we create a Production order the reservations for each component are created automatically and assinged to a reservation number, the thing is when i try to create a Reservation through MB21 for the same Production order the system says that" for that type of production order i cant generate manual reservations", can you please guide and tell me if i can change this in the configuration ?? , if you need additional info please tell me , thank you in advance.

    Dear German,
    Your system working according to std SAP setting, u don't need to change any config setting. Because wehn u release order, it automaticaly genarates reservation for each and evry component of the order.
    when u do goods issue to order or to reservation either way it gets issue to the order.
    suppose if u need to issue any extra component to the order u can just add in order componet overview before u release the order. so reservation gets genarated for this componets too along with BOM components.
    In case afer release, if u need further components go to MB1A give mov type 261 and S.Loc and then click on new item push button, it pop ups one more window give all required parameters and post the goods. These goods issue will also gets updated in the order.
    But for the order uc an not manually create the reservations
    sree

  • Goods Issue Control & confirmation control for Production Order.

    Dear ALL,
    Please let me know how to control,
    1) Unauthorised consumption of component quantities in excess of quantity defined in BOM?
    2) Posting of Confirmation (At operation Level) against production order for which no components have been issue?
    3) Posting of goods receipt against production order for which no components have been issued or no confirmations have been posted?
    4) Posting of goods reversal quantity in excess to issued quantity.
    Regards,

    Prashant,
    Not all the requirements you mentioned can be controlled in Standard SAP system. For some of the requirements you could configure User status (Tcode :BS02).
    exmaple :
    Posting of Confirmation (At operation Level) against production order for which no components have been issue?
    SET user status XX on Business  transaction : Release that forbids CONF.
    SET another user status YY on Business transaction : Goods movement that allows confirmation.
    With this kind of tricky user status you can control/prevent some transactions in production order till certain transactions are done.
    I know this is not the ideal solution but I have used it for various purposes to meet certain business needs.
    Hope this helps you.
    Thanks,
    Ram

  • Best practice - material staging for production order

    Hi Experts,
    could any of You pls, support me with some hints of best practice how to handle material staging WM-PP interface in a certain case?
    Up till now we had a system, where production had no separate location in IM, but one location existed including raw material wh and production. In the same time in WM we had separate storage types for production and raw materials u2013 hence we did material staging transferring goods only inside one IM location between different WM storage types. The material staging should be done based on separate prd. orders.
    Now this need to be changed and separate location need to be handled in IM for production u2013 which means the staging should be done between different IM locations and WM administration also need to be handled.
    Up till now we used LP10 for staging, then LB13 for TO creation etc. We can keep going like that, but if do so, there is another step required in IM u2013 movement 311, where material numbers and qty need to be added manually to finish the whole procedure. I would like to avoid this u2013 which makes the administrational procedure quite long.
    I have been checking the following possibilities:
    1.     Set released order parts-staging at control cycle and use MF60 for staging u2013 but I can not select requirements based on pro ordders here (only able to find demand if component including into selection)
    2.     Two step transfer 313/315 u2013 but this not a supported procedure u2013 313 TI /TO / 315
    3.     Try to find solution how to create 311 movement based on TO or based on WM stock at certain storage type / dynamic bin.
    I have failed.
    So, could any of You pls, support me with some useful ideas, how to handle material staging where 311 included and definetly the last step of procedure, but administrator does not need to enter items manually one by one in MIGO.
    All answers will be appreciated

    Hi,
    Storage location control should be able to take care of your problem.
    If you want to stage the material to a different IM location then the WM location then make the following settings
    If location xxxx is your WM location and location yyyy is your Production location.
    You have defined Production storage type ZZZ for production storage location YYYY and have maintained the supply area for the same
    In WM configuration - For interfaces - IM interface-Control of Assignment "Plant / Stor.Loc. - Whse Number"
    Assign location XXXX as the Standard Location. Maintain entry donot copy sloc in TR for location YYYY
    In WM configuration - For interfaces - IM interface-  Storage Location control for WH
    This entry ensures that there will be a WM tarnsfer Posting between your WM and Production storage Location automatically when you confirm your TO. You can have this done via a btach job also if you want cumulative posting. (schedule job RLLQ0100)

  • Reservation for Production order

    HI experts..
    The system will reserve the qty once the planed order get generated.
    Will it be possible after the production order release.. the reserved stock should get blocked
    and we sud not use the planed reserved qty for other production orders.
    pls guide me how to do this..

    Sri Ram,
    Availabiltiy checking can give you the functionality I think you seek. 
    Available To Promise (ATP) doesn't exactly 'block' stock.  Instead, each order (planned order, or production order, or Sales order) can be configured to execute an ATP check for components.  You can configure that production orders cannot be released unless they pass an availability check for components.  So, the first production order is released, and because of the way you have set the ATP up, there is no more component stock available.  Now, when you try to release an additional production order, the ATP will fail, and you may not release the order.
    http://help.sap.com/saphelp_erp60_sp/helpdata/en/fc/836ae8f66111d2b6a70000e8359890/frameset.htm
    Rgds,
    DB49

  • Material reservation for process order

    Dear PP experts,
    We convert planned order to process order. Whenever a process order is created components in the process order get reserved, i.e. automatic reservation is created for the components in the process order.
    Is it possible to exclude a selected material or a selected material type to avoid getting eserved whenever a process order is created?
    Regards,
    Prashant

    Hi
    Yes you can do that, go to material master of the material MRP 2 view and tick the Bulk Material check box so it will automatically set in the BOM item. So it will not create reservations.
    If you want this same for material type you can use BULK material type.
    Prerequisites:
    Therefore planning for bulk materials should be consumption-based.
    If bulk materials are subject to material requirements planning, you must create planned independent requirements for them.
    Thanks
    S.murali
    Edited by: S. Murali on Jul 1, 2009 1:37 PM

  • Assignment Profit Center to Plant on material master for Production Order

    Hi Experts
    Can you help me !
    Now I'm trying to lock a profit center to the plant.I've tried searching on the standard menu and customizing but do not get it ?
    How to assignment profit center to plant or plant to profit center.
    Regards
    Dodo M

    Hello Dodo,
    1.
    You can make an assigment between the profit center and the plant in Customizing (SPRO) in two steps (through the company code), under the following menu path:
    Step 1:
    Enterprise Structure
    Assignment
      Financial Accounting
       Assign Profit Center to Company Code
    Step 2:
    Enterprise Structure
    Assignment
      Logistics - General
       Assign plant to company code
    So, first you assign the profit center to the company code, then you assign the plant to the company code.
    2.
    Or you can use the Enhancement MGA00001 for implementing your own check in function module EXIT_SAPLMGMU_001.
    You can also check the following help to understand the relationships in details:
    Controlling (CO) - SAP Library
    http://help.sap.com/saphelp_erp60_sp/helpdata/en/02/30793485231774e10000009b38f83b/frameset.htm
    Best Regards,
    Dora

  • Material staging for production orders- NO TR

    Dear Experts,
    I have created a Planned Order for which Component materials are to be supllied.
    I am not able to see the Transfer request for the same.
    Kindly help.
    Please also let me know if there are any configurations for this?
    regards,
    Shetty

    Any suggestions pls?

Maybe you are looking for

  • Advance Receipt issue

    Dear Sapgurus, If any customer advance paid 1000 rs i wna t go to customer account 1000 rs and advance royalty 900 and service tax is 100 but in advance roaylty i will give 1000 rs only. Regards Hanuman

  • (Creative Muvo TX FM) FM tuning Prob

    hi, I just got my TX FM, now I have a problem. It seems that it can't find an FM Station (autoscan), It can scan but cant find a frequency. before I have presets (it works a while ago), now all my presets was gone. I also tried setting an FM station

  • Widget creation in Captivate 4 (combobox)

    Just download the trial version in hope of augmenting our screen designs prior to build the application. Currently I am using the ComboBox widget to simulate dropdown menus, but for longer menus the widget gets distorted. My thought was to create a n

  • Facetime HD Camera not working. Resert SMC or sudo kill does not work

    Please help me. Thanks alot! I have tried to reset the SMC and doing a sudo kill on the VDCAssistant. Both do not work.

  • SRM7.0 Meta Data Handling or Component Configuration

    Hi Experts! Let's say you for some reaseon want to remove the a field in the Shopping Cart at item level. To achieve this you could e.g. 1. Use the Component Configurator (SE80) - and use the browser-based Editor for the WDP ABAP Component Configurat