Process Order operation scheduling duration calculation

Hi
We have following formula has been maintained for processing time calculation in resource.
Machine * ( Operation quantity / Base quantity / Operation splits ) + Setup + Change-over
As per above formula for following procee order qty and time, SAP caulates time.
Opeartion qty - 100,
Base qty - 100,
Op split - 1
Machine - 0.5 hrs (30 Mins)
Processing time calculated as 30 mins (.5hrs)
When I schedule the process order with same resource for same qty and machine time, processing time is calculated as 33 mins. We dont have maintained any floats in scheduling margin key in material master. We dont have any wait times also.
Can you please let us know why process order operation is having 3 mins tolerance? Any idea where such settings has been maintained?
Any pointers will be helpful.
Edited by: nilesh sankpal on Dec 8, 2011 5:47 AM

Hi Mangalraj,
Thanks for your reply.
We have not maintained ay reduction levels in OPUZ for plant and order type combination.
In resource, we have 2 hrs break time and total operating time is 18.50 hrs.
I got following SAP help link for calculation of duration for processing time.
http://help.sap.com/saphelp_46c/helpdata/en/b1/c04387439a11d189410000e829fbbd/content.htm
Is processing time is calculated based on following formula.
Processing time u2013 Calculated Processing time * (1+ (Length of break / Operating time)
Can you please correct my understanding here?
Thanks in advance.
Nilesh

Similar Messages

  • Process order operation information

    Dear Experts,
    I want to know the name of table from where I can get information of process order no., process order status and the operations which are still to be confirmed for the order. I think I will have to create a view by using two tables but let me know which tables should I refer.
    Thanks in advance.
    Prashant

    Dear
    Find below the SAP tabel  for your report requirement :
    Order tables :
    AUFK Process  order headers
    AFKO Order header data PP orders
    AFPO Order item
    AFVC Order operations
    AFVV Quantities/dates/values in the operation
    AFVU User fields of the operation
    AFFL Work order sequence
    AFFH PRT assignment data for the work order(routing)
    JSTO Status profile
    JEST Object status
    AFRU Order completion confirmations
    Process Order operation tabel :
    PLAS Task list - selection of operations/activities
    PLFH Task list - production resources/tools
    PLFL Task list - sequences
    Order and Operaton syetm Status :  SAP Table and field  : JEST-OBJNR 
    1.Orders/Operation  with status CRTD : JEST-STAT = I0001 .
    2.Orders/operation  with status REL/PREL : JEST-STAT = I0002 /I0042
    3. Orders with status MSPT  : JEST-STAT = I0004
    4. Orders with status PRC  : JEST-STAT = I0016
    5. Orders with status DLV/PDLV  : JEST-STAT = I0012
    6. Orders/operation  with status CNF/PCNF  : JEST-STAT = I0009/I0010
    7. Orders with status GMPS  : JEST-STAT = I0026
    8. Orders with status TECO : JEST-STAT = I0045
    9. . Orders with status DLFL : JEST-STAT = I0076
    Hope this will help you to include required table in your BI report
    Regards
    JH
    Edited by: Jiaul Haque on Jun 3, 2010 9:12 AM

  • Change Resources in a Process order operation

    Hello
    Is there any way to change a resource in a process order operation?, I have 5 machines, but sometimes I use the machine1 and machine2 to produce the material A, but if i dont have capacity to produce or if one machine is not working, I could use another machines. I know i could use products versions, but if I do thar, there will be a lot of convinations.
    Thank you in advance.

    Dear Saly,
    as correctly said by Caetano in standard SAP the only tool to change work center in production orders is in leveling activity through CM21 (graphics or tabelar - CM21 , CM22).
    In this strument (CM21) according to customizing setting in strategy profile (belonging to overall profile)
    you can change resource through drag / drop method or (with special setting in strategy profile)  insering manually a new resourse.
    As alternative tool is possible to create a custom report and change work center using a BI custom using a filter tool present in the production order after go to operation details. Unfortunaltely in the standard SAP there isn't a bapi/fm (released by SAP)  to change work center in production order.
    Let me know if i've been useful for you.
    Daniele

  • FM or BAPI to Modify or Delete Process Order Operations (COR2)

    Hi Experts,
    As a part of Process Order Migration, we have a requirement where in we need to pass the confirmation quantity of the Old Process Order number to the Unloading point field (ABLAD) in the Process Order Operation details and set that operation as marked for deletion.
    Please suggest if you have come across similar scenarios.
    Thanks in advance,
    Anand

    Hi Anand
    Try This BAPI_PRODORD_SET_DELETION_FLAG and it will work for your requirement.
    Thanks,
    Adil

  • User Status Profile for Process Order Operations

    Hello Experts.
    I have a need to set up a User Status at the Process Order Operation level that will prevent operation confirmation when the status is Active .
    I have been successful at the following:
       --- Created a new Status Profile (transaction BS02),
       --- Creating a u201CHoldu201D status,
       --- Defined the Influence on Business Transactions,
       --- Set the allowed Object Types for the profile.
       --- In an individual Process Order operation, I can now select the Status Profile, and set the Hold status, and it functions correctly.
    My problem is that I canu2019t figure out how to set my new profile as a default for Process Order Operations.  For Production Orders, this is done in the IMG definition for the Order Type (transaction OPJH), updating field T003O-VRG_STSMA.  However the Order Type definition for Process orders (transaction CORN) only has a field for a status profile at the header level.  Iu2019ve searched through Configuration and the Recipe, and the Production Version, and the Control Key, but can find no where to set the default status profile for a Process Order Operation..
    As a final desperate act, I manually edited a T003O record for a Process Order Type in our test system, but even this failed to set a default Operation Status Profile for subsequently created Process Orders.
    If you have any knowledge about this, then please help.

    As of this date, we have still not implemented a fix, but I did get some information from someone else who has.
    I'll post his information here for all to see.  Hope you find it helpful.
    From: Joe
    Yes we managed to do it.
    After several false starts and CMOD/projects which suffered because only the default keys (for order number, aufpl etc) were in place and not the actual, we coded up the IN_UPDATE method in the WORKORDER_UPDATE badi. This gives us the final format after the DB save (but before the commit). The update of the STATUS using the SAP std function module was actioned successfully but the status profile was not actually passed through. We assumed that this was because of the update task - so we introduced an INSERT into JSTO instead (a bit naughty I know, but desperate needs etc). If you require anything more let me know.
    Best Regards
    Joe

  • Editing of scheduled dates in Process Order Operations

    Hello,
    I have a requirement, in which the client would like to change the Scheduled dates in the operation details of a process order.
    In the header screen of a process order, if we change the basic start / finish dates (depending on forward or backward scheduling), and reschedule the process order, the process order is rescheduled, with the new dates.
    The client's requirement is, they should be able to change the Scheduled dates in the tab "Operation - Dates", of the "Operation overview" screen, in a process order. Normally the field is not editable, and the system calculates the dates, based on the start / finish dates, entered in the process order header.
    I would like to know, what is the way out, to meet this requirement.
    Thanks.

    Hi,
    As every body else is explaining it is not possible for standard SAP ,  as of normal business or any business scenario why would a client want to change the operation dates from Production order ( still not understood.....)
    There are two options to do that:
    1) Copy the whole transaction ( programmes ) into some Z - transaction and in the programme you can change the object ( CO_VG_OPR_*) from being grayed out.
    This will alllow you to change the dates.
    2) you can go for enhancement with the following FM
        BAPI_ALM_ORDER_MAINTAIN
    I suggest you to clear these things with client.These things require more of ABAP work.
    And as said changing the standard behaviour of the system can cause performance issues.
    Please close the thread if satisfied.
    prakash

  • BAPI_PROCORD_CHANGE for process order operation level change

    Hi,
    Can any buddy tell me how to change operation dates in process order with following requirement:
    Process order scheduling type is 'Forward',
    1st step, read operation start dates 'Earliest Dates' and 'Latest Dates',
    2nd step, change operation 'Earliest Dates' and 'Latest Dates' directly, this step can't be done in foreground,
    Can use BAPI_PROCORD_CHANGE to update operation dates directly?
    Best Regards
    Amy

    Hi Amy
    BAPI_PROCORD_CHANGE cannot be used to change operations.
    According to note 1694267 you can use the remote-enabled function module CO_SE_PRODORD_CHANGE that is released by the customer to change the order header, sequences, operations and production resource/tool. See the detailed documentation for the function module.
    BR
    Caetano

  • Process Order detail scheduling picking the std values from Phase.

    I'm working on an Implementation scenario, where the Master Recipe contains only one Operation and one phase. After the Process order is created the basic start and End dates remain same. I did check the formula in the resource(on testing its working fine). I did check the control key, formula parameters, scheduling parameters of the process order. I have maintained the std values in the phase appropriately.
    Still the process order basic start/end dates are same, even though the process order quantity is of any quantity.
    Request all to please provide some inputs.
    Thanks,
    Nil.

    Sorry, this is not the right forum for technical questions - please log a note in OSS or contact SAP services. Thanks

  • Table to find the phase number in process order operation

    Hello All,
    Is there a way to find the table for phase details which are assigned to operation in a process order.
    Regards,
    Rohit

    Hi Rohit samant,
    Go to Process order Change or Display mode ie Tcode : COR2 or COR3.
    Enter the process order no , click on "Operation Overview (F6)", Click on the Phase field on any one operation, Click "F1", the Performance Assistance Screen will be displayed, Click Technical Details, you can get all details, like programe Name, Status, Table Name, Fieldname & all Technical details.
    I hope the above information is as per your request, Hence Reward Points,
    Regards,
    Nayeem Ahamed

  • Process order operation

    Hi
    In Process order we are using Operation & Phases in master recipe.
    Standard values are giving to phases only.
    Individual Confirmation (COR6) are performing using Phases only..
    Process instructions are also giving to phases only.
    For  creating phases operation is required( superior operation)
    Just i want to know  where these operations will be used in a process order  other than this.
    I want  to know the difference between Primary & Secondary resource and their application in Process order..as these terms are not there in REM/Discrete Mfg..
    Regards,
    srihari.

    Hello Shrihari,
    What you have observed is right.
    In process order processing we need to use the phases instead of operations in production order eg. when you want to do the partial confirmation, you need to do it for the phases and not the operations.the GI of components( if attached to the Phase )will then take place at that time.
    About primary and secondary resources I can give you a practical example.
    If you consider a washing machine as a resource then it has two parts the Wash tub and the drying tub. You can consider the washing machine as the primary resource and the washing tubs and drying tubs as secondary resources of the washing machine.
    Hope this helps you.
    Award points if benefitted.
    Hemant

  • Target cost calculation in Process Order based on Variance Calculation

    Hi all,
    I have a question on Target cost calculation in Process Order. My understanding is, the Target Costs gets calculated when the confirmation and GR is made for the Process Order.
    But if the confirmation/GR is not done, whether the target costs gets calculated for only the activity types after the Variance Calculation (KKS2).
    I have two scenarios. In one, the target costs got calculated for the activity types without the confirmation/GR after the Variance calculation.
    In another scenario, the target costs are not getting calculated for the activity types without the confirmation/GR if I try to do the variance calculation in KKS2.
    SO i want to know which scenario is correct?
    Can anyone answer this question?
    Thanks and Regards,
    Brijesh

    Hi,
    In general, the target costs are calculated once you deliver the order.
    Target costs for the components and the activities are updated only once you deliver the order and the target cost for the finished product gets updated when you do the variance calculation.
    Consider your scenario number 1 - you said the target costs got calculated for activity types without confirmation / GR after variance calculation.
    Now, if the order is not having any status like PDLV, DLV or TECO it will not calculate the variances in the first place.
    Your second scenario is correct - without GR the system does not calculate any target costs. Also it will not calculate any variances because the order status is still not DLV.
    Best Regards,
    Sameer

  • Process order - Forward scheduling

    Hi,
    I need a clarification on scheduling in process orders for below mentioned scenario:
    SO is created for a future date
    MRP run
    Planned order is created (scheduling for planned order not done)
    Planned order converted to Process Order
    My query is how the dates of process order will differ in case of forward schduling.
    whether start date of process order will be as per basic start date of planned order or the start date of process order will be current date?
    regards,
    Mohit

    Dear Mohit
    Converting a Planned Order into a Production Order
    If material requirements planning has already created a planned order for producing the material, the basic dates are copied from the planned order and the order start and finish dates are determined in a new scheduling run. If necessary, reduction measures are carried out.
    Creating a Production Order Manually
    If no planned order exists and you create the production order manually, the scheduling type determines which basic dates you have to enter.
    If you enter both basic dates, the system tries to adhere to these dates when carrying out forwards or backwards scheduling. If necessary, the system also carries out reduction measures.
    Regards
    Sachin

  • Fm for processing time in processing order operation

    Hi
    I need to obtain processing time from processing order's operations. ASAIK there are some formulas to calculate this but i cannot find it. Could you give me some tips about that? Is there a fm or bapi to obtaint this?
    regards
    Wojciech.

    Hi,
    Please let me know what is a processing order to which module it belongs so that I can help you out
    Thanks & Regards,
    Chandralekha.

  • Regarding prod order operations scheduling

    Hi all,
    We are using CTM planning scenario.
    After CTM planning, the operations in a planned order are scheduled as per the capacity available at
    resource for each operation. So there is may be a gap between end time of one operation and start time of
    the successive operation which is as expected.
    Now the issue is:
    In ECC, when the planned order is converted into production order, it is eliminating the time gaps between
    operations and next operation is started immediately after end time of the preceding operation.
    This is happening even after converting planned order into production order using conversion indicator in
    APO.
    The requirement is, in ECC, system should keep the operation times as scheduled in APO.
    Please let me know if any details required.
    Regards,
    Yogesh

    Hi,
    Can you check the " Scheduling parameters for production orders" defind in ECC under Adjust scheduling tab
      the the various options defined.
    Also enable the scheduling with breaks indicator and see whether you get the proper results.
    Thanks,
    nandha

  • BAPI to dispatch Process order Operation

    Hi PP experts,
    We need to build interface with External production execution system and SAP
    Which BAPI can be used to dispatch the process order start and times in SAP by passing the time values from external system. A custom BAPI can be built using standard BAPIs which do the task
    Thanks in advance
    Vikram

    You can use the RFC CLOI_CHANGES_UPL_31.
    See the recommendations of OSS Note 184471. I send you a example of how we've filled the internal table IT_CLOIOPERU:
    Line    AUFNR            EXTAUFNR       APLFL           VORNR FIELD         VALUE
    1       000001008294            000000  0100    FSAVD           20081023
    2       000001008294            000000  0100    SSAVZ           000000
    3       000001008294            000000  0100    METHOD  DISPATCH
    4       000001008294            000000  0100    SSEDD           20081125
    5       000001008294            000000  0100    SSEDZ           000000
    6       000001008294            000000  0100    METHOD  DISPATCH
    7       000001008294            000000  0102    FSAVD           20081023
    8       000001008294            000000  0102    SSAVZ           000000
    9       000001008294            000000  0102    METHOD  DISPATCH
    10      000001008294            000000  0102    SSEDD           20081120
    11      000001008294            000000  0102    SSEDZ           183524
    12      000001008294            000000  0102    METHOD  DISPATCH
    I hope help you.
    JMota

Maybe you are looking for

  • Editing html css in dashboard page

    Hi experts! My client wants to delete all blanks dashboard, to make it as compact as possible. So I'm try to get good results I found and Addon in firefox called FireBug. And I can to see all blanks in my dashboard. I add a picture with difference of

  • Bulletin Board for A505-6980

    Does anyone know how to find the Bulletin Board on a A505-6980?  The advertisement for this machine says that the Bulletin Board in available on this machine but I cannot find in on the computer.

  • Nokia N95 Recorded Soundclips to PC

    Hi Guys, Would anyone know how I can transfer my recorded soudclips from my N95 to my PC? I use it to record guitar riffs & ideas and I'm afraid if I lose my phone, i'll lose all my soundlips! Thanks Simon Solved! Go to Solution.

  • I Can't Install Photoshop CS4

    I download .7z file and .exe file. I run .exe file to extract all files in .7z files to C:\Documents and Settings\Administrator\Desktop\Adobe\Photoshop. I click on Ps icon (Setup.exe) and it's doesn't do anything. I already install Photoshop CS3 Exte

  • How can i avoid sharing information automaticly between my iphones

    i have 3 iphones with the new software, but i dont want to share information among them, how do i do that