Good morning Gurus,
I have some semi-finished materials whose procurement type is given as X in material master. When I run MRP I am getting planned orders for the same. But in the planned orders the system is giving the procurement type as E (in-house). Why is the system picking up E? The order created is LA.
For materials for which the procurement type is F, the system is creating planned orders of NB. Here the procurement type is not changed. I am getting F only. This is ok.
Why in the case of X, it is creating planned orders with procurement type E? Any settings?
Thanks and Regards,
Ram
Hi Ram,
The system behaviour is correct.
While maintaining order profile, once can choose Procurement type as E or F (X can not be given here). The Procurement type for the material in the material master is X.
While running MRP, the system would first try to create planned order with E if it is possible to produce the material in-house. In case, it is not possible, system should propose F.
Even though the procurement type in planned order is E, it is very much possible to convert the planned order to Production Order as well as Purchase Requistion. This gives flexibility to the planner to take a call on whetner to produce in house or procure externally.
I hope this is clear.
Regards,
Sandeep
Similar Messages
-
Settings for order type in planned orders
Dear All,
Where can i customise the order types for planned order.?
My scenario is.. i can not send complete product in vehicle , which has to be dismantle and send in different vehicle, so the different invoices are required. i can dismantle the product and add these assemblies as line item and invoice. in this case i will loose the main product code which i dont want. i wanted this to behave similar to phantom item , where i can see the phantom item and plan only components.
Please throw sme lite on this...
Thanks
RaghuHi
You can customize the planned order profiles in
SPRO--- Production MRP- Procurement proposals -
Planned orders--- Define order profile.
Thanks
S.Murali -
Different type of planned orders
Hello Friends,
I went to an interview, in which I've been asked a question to describe different type of Planned Orders ?????????
Is there type's of planned orders in MTS or MTO environments ???
Pls enlighten me on this.
Thanks Sir,Rahul,
For interview questions, you should first consult with SAP online help before posting a question on this forum.
In SAP, there are not planned order types, there are planned order profiles. SAP supplies some basic ones, and you can create additional profiles as well. Reference to order profiles when creating planned orders
http://help.sap.com/saphelp_erp60_sp/helpdata/en/f4/7d310944af11d182b40000e829fbfe/frameset.htm
and surrounding pages.
Configuration for Planned order profiles at OMDD. Doc:
http://help.sap.com/saphelp_46c/helpdata/en/48/e92c7dd435d1118b3f0060b03ca329/content.htm
Standard as-delivered Planned order profiles are
KB Standard purchase order
KD Individual customer order
LA Stock order
LB Standard purchase order
LBE Standard purchase order
NB Standard purchase order
NBE Standard purchase order
PR Project order
UL Standard purchase order
You can see the details of these in OMDD.
Best Regards,
DB49 -
Settings for the relation of requirement type and planned order type
Dear Gurus
Where we maintain the settings for the relation of requirement type and planned order type?Actually I have maintained strategy 60 for a particular material (planning material) so the requirement type is vsev and along with that the planned order type is coming is vp i.e non convertible planned order.That is ok the system is behaving right.But nowhere I can find the setting of vp with vsev how the system is picking vp?
Regards
Sandip SarkarHi!,
That is an inbuilt sytem setting and you can't change that.
Regards,
Uday -
Determination of Production Order Type when Planned Order is Converted
Hi SAP Expert,
Is there anyway to determine the Production Order type by Sales Order type when the planned order from APO is converted? Currently, all the planned orders converted from APO will be a Normal Production Order.
The requirement as example below:
>> If Sales Order Type = Normal Sales Order, then the converted Production Order type = Normal Production Order
>> If Sales Order Type = Replacement Sales Order, then the converted Production Order type = Rework Production Order
Thanks.
Regards,
Hooi ChiaHi Pascal,
Our requirement is exactly same as yours. Can you please elaborate more on ZXCOXU13? I can see the function module suggested by Santosh in the SAP Note but I couldn't find any details regarding ZXCOXU13.
Thanks.
Regards,
Hooi Chia -
BOM Explosion - special procurement type 52 (collective order)
In BOM explosion, special procurement type -> collective order (52) for the item is considered as phantom assembly. I wish to know the business reason for this. Any help please ??
hi Janardhan,
phantom assembly is the assembly which is not kept in stock rather it consumes directly.
Use of phantom assemblies are as below
Phantom assemblies are assemblies that have their own product structure, but whose assembly does not actually physically exist. The components of the phantom assembly are incorporated directly in the superordinate product. The product structure of the superordinate product contains a reference to the phantom assembly.
example - A car with music system.
During backflush, only the goods movement for the phantom assembly components are posted. The phantom assembly is marked as backflushed but does not trigger any goods movement.
Experts pl correct me if i'm wrong.
Regards,
Anil -
Reg : Order type for Planned order
Hi ,
After MRP when i checked planned ordre created in the order type it is showing " VP " instead of " LA " ordertype
My pegged requirement is PIR where i need to check for this . My planning strategy group is " 52 " Planning without
Final assembly without MTO. More over i am not getting any PR for component parts
Please suggest me where I need to check for this .
Regards,
jaya VimalHi Prasobh ,
I am happy to see you again in SDN forum after long ,
Yes you are correct the requirements are not convertible on receiving STO in Planning Plant only it will consume PIR
and I am using Strategy group 52 with requirement type is VSE.
In this how can I test for a complete production cycle I am unable to convert planned order manually in to Production Order.
to complete testing . Why system showing PIR order type VP instaed of LA order type. Marks will be awarded further more for
further answer. Further marks will be awarded for further Answer. I checked there is no component for this planned order is
only for FERT and Halb part .
Regards,
Jaya Vimal
Edited by: jaya vimal on Jun 11, 2010 11:15 AM -
Order type for planned order in repetitive manufacturing
hi
In repetitive manufaturing there is no prodcutiion order
planned order only. so i want know what is order type for repetitive manufacturing
In configuration order type for reptitive is required or not if yes then how will define order type ,where
In Discrete order type will define to control prodution order
like that i want know details about order type in repetive manufature
ravikumarHI
Planned order in REM is of PE type thar s non convertible in PO and also these planned orders are assigned to PVs thru Planning table and the Confirmation is done agianst these planned orders.
check these links:
Re: order type in repetitive manufacturing
http://www.sapfunctional.com/PP/REM/page1.htm
Regards
Anupam Sharma -
Type of planned order created by MRP run
hello,
I have one concern regarding planned order creation through MRP run..
our MRP creates automatically order type LA
I wanted that for some materials, the MRP creates planned order type PR ( with account assignment Q -> WBS element, coming from sales order)
what is the customizing point to make this ?Hi,
I think that this happens automically when the requirement is created in the WBS SEGMENT, AND cOLLECTIVE INDICATOR IS NOT SET TO 2 -
Default PR Type when convert from Planned Order
Hi all,
How can I default my PR Type when convert from Planned Order after MRP run. This can done via MRP Group control but how to go about controlling via Planned Order profile?
Which planned object type and planned order profile to be used? assuming that i need my planned to be output at LA type and convert to NB1 PR type instead of the default NB PR type?
Thanks.
Regards,
AndrewHi,
The system determines the document type from the stettings u are making in "planned order Profile" in Customising for MRP. There u define the order type, the procurement key and the special procurement key and also the account assignment category. So based on the procurement key and the special procurement key maintained in the Marterial master, the document type is selected.
Production > Materials Requirement Planning > Procurement Proposals > Planned Order > Define order profile
Choose the planned order type - NB1 Within this you specify the P req doc type to be used.
Through MRP group and the different PR document type for MRP generated PR is possible only if you assign the document type to MRP group in the MRP configuration.
Please try and come back.
Regards,
R.Brahmankar
Edited by: R Brahmankar on Aug 28, 2008 10:54 AM -
Default PR type for MRP (planned order -- PR)
Hi Expert,
Is there any posibility to set default PR type for planned order - PR conversion from MRP?
in SAP standard, PR type is NB, we have configured specific PR type, let say PRM. The purpose is we do not need to change NB to PRM while converting the planned order into PR.
Pls help.Thanks
Rgds,Hi Gurus,
This is my first post in this forum. Have been trying to search this forum for my case all day and found some answers but when i implemented it in my SAP , the answers didn't work.
The case is:
When i try to convert Planned Order to PR through tcode MD15/MD16, the system will propose PR Document Type NB as default. In my company we don't use that NB PR type. We have another 10 customized PR Type and one of them is for Replenishment. I'd like to set this ZR09(Replenishment) PR Type as default and it's not possible to choose another PR Type.
I have read several answers and implemented them, for example:
1. OPPR with MRP Group 000, and I found no indicator except Scheduling/Doc Type. I typed ZR09 in field Doc Type SPO but in MD15/MD16 other PR Types still appear with NB as default.
2. SPRO-MM- Consumption based planning u2013Procurement Proposal u2013 Define Order Profile or SPRO-PRoduction - MRP- Procurement Proposal - Planned Order - Define order Profile, when creating new entries with Object Type Planned Order/PR still canu2019t find my customize PR Type in field Order Type. Field Order Type only consist of 2 digits order type such as NB,LA,RS,KD,KB,PE,PR,VP. No place to choose PR Type ZR09 or other customized PR Type.
Can anyone help my case?
Thanks and regards,
IC BUMA -
Hi All,
I would like to ask where in SPRO can I define a new Planned Order Type (not the Planned Order Profile).
For example, the existing Order Types are :
NB - Standard Purchase Order
LA - Stock Order
RS - Reservation
KD - Individual Customer Order
KB - Consignment Order
OE - Run Schedule Quantity
VP - Planned Independent Requirement
I would like to add a new Planned Order Type Z1 and change the scheduling type from Forward to Forward Time.
Thanks in advance.Dear
In SAP Standrad , there is nothing called Planned Order Type .Basically , it is the planned order profile which decides all the realted category like accounting assingment , special procurement , prcurement type etc .
So you need to fgo SPRO-MRP-Procurement proposal -Define planned Order profile -New entries .At the saem time assing the accouting assingment categoery in OME9 and define scheduling parameters in OPU3 ( Scheduling Type , Adjust scheduling , Logs ,Automatica scheudling , CRP etc )
Hope this helps
Regards
JH -
Hi All,
Is it possible to create new planned order types. I need to create a copy of NB, LB etc.
If so how and how do I get MRP to use the new ones?
I now how to create a new planned order profile but I still have to select the original order types!!!
Thanks
StuartDear Ramesh,
I think, you must post your thread in to Forum - [SCM - PP|SAP ERP Manufacturing - Production Planning (SAP PP);
Best Regards,
Amit
Note: Check with:
Re: Planned Order Type
Re: Planned Order type -
Determination of Planned Order Type based on Requirement
How does order type for planned order gets determined?
For example
planning strategy 50, planned order type is VP
planning strategy 10/40, planned order type is LA
planning strategy 20, planned order type is KD
Checked in tcode OPPS & SAP forums, could not able to find how
does system determines planned order type based on type
of requirement i.e. sales order/PIRHi,
please check the link below:
http://help.sap.com/saphelp_scm2007/helpdata/en/87/04f73b8003b409e10000000a114084/content.htm
Regards,
Alok Tiwari -
Automatic Plan Order Creation on Sales Order save
Hi friends,
We are having an requirement where Automatic Plan Order should be created on Sales Order saving.
We have Material A in Plant 1000 & Plant 5000.
Plant 5000 in plant where Manufacturing is carried out & Plant 1000 is service Plant.
We are using Special Procurement key for Material A in 1000 Plant which triggers procurement from Plant 5000.
When Sales Order is entered in Service Plant 1000, after saving Order Plan Order should be created in both Service Plant 1000 & Manufacturing Plant 5000 along with Sales order reference.
I have tried using Strategy Type 81 but Plan Order is created while saving Order only in Service plant (1000), but with Procurement Type (E - In-house Production) & No Plan Order created in Plant 5000.
Can you please guide me how to meet requirement?
Thanks in advance.Hi Jiaul,
Thanx for reply.
I have already assigned the Special Procurement Key to Material A in Plant 1000.
In Plant 1000 procurement type is F (External procurement)
But when Plan Order is created after saving Sales Order it is created with Procurement type E (In house production).
If I delete Firm Plan Order generated & run MRP for Sales Order / Item. It gives me required output generating Plan Order in both Plants.
Regards,
Rameshvar
Maybe you are looking for
-
Relational access to XML Content: can not display line level details
Hi folks, there is one record at the header level and two records at the line level in the xml data file. I created the following view and when i see the results, I see two records as expected but the value for the line level coloumns is null but the
-
I bought the PSE 13 disc and put it in my laptop( macbookpro) and for some reason it won't read- all it does is run and then spit the disc out not sure what to do. Is there maybe a digital download since there is no customer service number to call-
-
Posting rule for assembly order for item 000000 could not be generated
Hi all, While creating production order from sales order system giving an error message 'Posting rule for assembly order for item 000000 could not be generated.' Kindly help to resolve the issue. SmanS
-
Integration to BOE dashboard builder
Hi, Is it possible to render BPC content (Xcelsius dashboard or basic BPC web functionality) in BOE Dashboard builder, thus combining in a single dashboard the ability to write-back with reporting done on BPC cubes as well as other content. /Thomas
-
Can someone tell me if the adobe suite cs5 works good on lion
also anyone running the magic bullet plugins do those work as well.. do the video copilot plugins work please let me know before i update, because i dont want to update if these dont work. thanks