Production order backflush - Batch determination

Hi,
We are following discrete manufacturing with backflush setup for auto GI of materials.
The entire flow is functioning smoothly, like
1. Creation of production order & release to production.
2. Auto goods issue upon first operation confirmation.
The qty of goods issue is automatically taken from component qty in the order. This works fine for some materials with out any Batch information.
Where as for those materials require match information, upon order confirmation system throughs an error
1. "Error in material 75-106674A41 order 8200019041 item 0001"
2. "Enter Batch"
Confirmation is through, after we enter the batch details manually.
How to auto determine  the batch information. Is there any setting that will eliminate the manual batch input.
Please help and provide me  the steps / setup required to AUTO select the batch details.
Thanks in advance.
Raj.

Hi,
you have to configure the foll settings in IMG for the batch determination to happen automatically.
IMG – Logistics general - Batch management – Batch determination & batch check  – strategy types
1.Define prod order strategy type –
   (you can use CO01 - assign Class type : 023  & name of the class here , also assign sort rule created in step4 CU70 here )
IMG – Logistics general - Batch management – Batch determination & batch check  – Batch search procedure definition
2.Define Prod order search procedure (you can use CO0001 in std)
IMG – Logistics general - Batch management – Batch determination & batch check  –
Batch search procedure allocation & Activation check
3.Assign the search proc to prod order and activate check (same as OPL8)
IMG – Logistics general - Batch management – Batch determination & batch check  – Define sort rules
4. Create sort sequence CU70
5. Create Batch search Strategy  COB1 & Assign Sort rule here
Now you can trigger batch determination in Prod order.
Regards,
Sheik

Similar Messages

  • Production order component batch determination : Over delivery allowed in b

    Iu2019m using production order component batch determination in CO02. System is not allowed to allocate an excess component split batch quantity. System is always allowed to allocate exact requirement quantity where to make open quantity is 0.
    It generates the following massage once click enter after selecting an excess component quantity. My requirement is to add the excess quantity in component batch determination.
    Massage details:
    Quantity of batch 0052902459 is reduced to 9.300 KG as split qty > req. qty
    Message no. LB034
    Diagnosis
    The split quantity of the chosen batch has lead to the split quantity total exceeding the required quantity.
    System Response
    The quantity is rounded down by the system.
    Procedure
    An overdelivery is not allowed by the current business transaction.
    Procedure for System Administration
    If necessary, check the batch search strategy to see whether an overdelivery is allowed.
    I have maintained the configuration in transaction COB1 as follows to enable over delivery batch determination.
    Strategy type: CO01- OrdType/Plnt/Matl
    Key combination:     Order type
    Over delivery allowed in batch determination: Tick on
    Please let me know the configuration to enable to do component batch determination with minus open quantity (Excess component quantity)

    Hi,
    As I understand it seems that you do not have batch split allowed in the auto batch determination for component materials. And you need to have batch split on a need to basis?
    If thats true, then on the line item in the component overview. Select the item details for the Batch that has been determined (general view, there is a field for split in terms of %, change that from 100% to a the lower value you want to pick from that batch). It should then allow you to add more batches.
    let me know if my assumption and answer helps.

  • Production order - Backflush items

    Hi,
    How to reversal the Production Order compoent Backflush items
    we are cancel the confirmation for that all operation in that production order, Backflush items not reversed.
    All material set Backflush for material master MRP view 2
    pls advise how reversal Backflush compeonets items
    Regards,
    Sankaran

    Hello Sankaran,
    In general if you do the confimation cancellation, the backflushed comonents will also be reversed with 262 Movement.
    Why these components not got reversed?
    whether COGI entry i there? Is there any Process Control, Post processing defibed for this?
    If not, you please reverse the Components with 262 Movement with MB1A Transaction.
    Regards,
    Siva

  • Production Order backflush creating Negative in Storage Type

    Hi All,
    We have setup storage types into which stock is replenished based on Min/Max. These storage types have been setup in a control cycle and supply area to backflush upon confirmation of the production order.
    I know this is user error, but when doing confirmation (CO15) or clearing COGI the user enters a batch not in one of those storage types (but available at IM level), it creates a negative in these storage types for that batch even though the storage types are setup NOT to allow negative stock.
    Is there any other setting or any notes that can be applied to avoid this issue?
    Thanks
    J

    OSS note 489754:
    The settings in Customizing which define that no negative stocks are allowed for the storage type, have only an effect on the transfer orders. In addition, you must also set message L9040 as an error message. For this, call up the Customizing and branch to: 'Logistics Execution -> Warehouse Management -> Interfaces -> Inventory Management -> Allow negative Stocks in Interim Storage Types'. There, execute point 'Control of System Messages in Warehouse Management' and enter message type 'E' for message number L9040.

  • In production order backflush  how components select valuation type

    Hi,
       i am using backflush in production order planning where components have valuation type. when i stage them i give the valuation type. but when i confirm a operation the backflush is giving problem.
      the problem is i have to enter the valuation type of componet which has to be backflushed. is there any provison to make it as default. which valaution type componenet is staged it has to be backflushed automatically.
    thanks in advance
    regards
    madan

    Madan,
    During MF60-pull list where exactly do you enter the valuation type?
    Try to understand the concept?
    Let us say i have storage loc A and production storage loc B.
    Now in production order/REM order you have entered the storge loc as B and you have stock in A.
    After running MRP and when you goto MF60, for that component, system will create storage loc order during staging.
    Once it come into storage loc B, how system will identify the stock that it is reserved for this order?
    If you have eneterd valuation type(I could not find), once it is in storage loc B, is there any identification for that order in storage loc B.
    Please come back so that I can help you?

  • Production Order Component Batch Assignment Enhancement Needed

    Dear Experts,
    In a Production Order CO01/CO02 under Components you could assign Batches to a Component/Material. To do this in the Production Order screen click Component Overview button and then select a Component/Material and click Batch Assignment Button. You would be now in u2018Maintain Batch Fixed Reservationsu2019 screen. Here you find right below the u2018Batchesu2019 screen. Where Batches to be assigned to Component are found, I need to add a Column to this Screen and populate at the time when Batch Assignment Button is clicked. I went through all enhancements of Production Order and could not locate any. Please let me know if you find one that could modify the u2018Batchesu2019 screen.
    If you are unable to find one to help youu2019ll further there is an Application Toolbar button called u2018Customer exitu2019 in u2018Maintain Batch Fixed Reservationsu2019 screen and I am unable to locate the Enhancement for this Button.
    Thanks,
    Sri

    Had to close because of Rules

  • Production Order backflush does not occur

    Hi Gurus,
    PLease help on the below issue.
    In my company, all the components in the production are using backflush. When GR the production order,  the backflush will be automatic.
    Issue is we found one order did not backflush after GR. Other orders with same material did backflush well.
    I checked the reservation agains the problem order, I found the only difference is that the reservation item is from 10.
    The item number of reservations in those good orders is from 01.
    I am not quite sure if this is the reason.
    If it is, how system worked like this and how to resolve it, please suggest.
    If i am wrong, please direct me the right way.
    Thanks for your help.
    Bryan

    Hi Bryan
    1.Check whether you have set backflush ind for all those material or not. if set then check COGI.
    2.This case arises if you are doing backflush through customizing i. e. through oder confirmation parameter you set Goods mov All comp is set. Then you wont required backflush to be set in Material master but at the time of confirmation if dont go to goods movenent screen then this material will not be backflush.
    Check it out
    Regards
    Abhijit Gautam

  • Production orders in Batch manufacturing

    Hi,
    Please consider this scenario
             X, Y ,Z .... are the  production orders for which operations 0010,0020 are completed.
    For production orders X,Y,Z operations 0010,0020 are not same.
    The third operation is batch managed in which X,Y,Z... are to be included.(ex special coating) and to be managed with batch number A for tracking purpose in future.
    and once 3rd operation is over they will go individually for different operations .
    How to map this
    Thanks in advance
    Sandeep

    Thank you....
                        X, Y , Z are different production orders for different materials(Eg A,B,C), It may be possible that we may include some more production orders to reach required batch quantity.
            and I want to add some more information
       The operation 0030 is done using different recipe P,Q,R( dont mistake with PPPI recipe), if it is done with recipe P then end product will become AP,if with Q then AQ,if with R then AR similarly BP,BQ,BR,CP,CQ,CR.

  • Post to Cost Centers on Production Order Backflush

    I have a question.
    Is it possible to post Goods Issue (Backflush) of components to a Cost Center when doing this via the Production Order Confirmation?
    Normally, when the components of a Production Order are backflushed, instead of posting to a cost center, they post to the Production Order.
    My intention is to use the Cost Center from the Work Center assigned to the Operation in question.
    Is this possible?

    dear Fernando,
    the cost center which u r using for the work center to capture the operation cost only. Ur GI is taking automaticaly with ur confirmation, and goods are getting posted to order. finally the cost which is costing for that work center usage is also go order only.
    if u dont want material cost to flow to order u tick all for all component materials as bulk material in MRP view and issue material aganist cost center in MB1A with mov. type 201 and do the confirmation, so GI will not take place to order.
    i hope this will clear ur doubt
    sree

  • At the time of Process order creation Batch determination

    Dear All,
    When i am creating process order at the time system not allowing me to execute batch determaination after release only it is allowing me to do.
    My requirement is At the time of order creation i want assign batches ( Execute Batch Detrmination)for the material.
    how to do this one, kindly hel me
    Regards,
    s.sakthivel

    Hi sakthivel 
    Go to OPKP (Production scheduling profile)  txn code and select in Batch management tab Automatic Batch creation at order creation (1) and check this profile is assigned to material in work scheduling view
    Regards

  • Production order settlement Account determination

    Hi All,
    When i run variances analysis settlement,in FI/MM account determnation what accounts should hit?
    one side of the entry is hitting GBB-AUA and what is the off set to this account?
    any help is appreciated.
    Thanks,
    Anusha

    Hi,
    In GBB > AUA, if the GL is maintained for COGM, then your variance GL would be in PRD > PRF which is right.
    But in our case, We have maintained the GL for Variance in AUA and GL for COGM is maintained in AUF (of which the prerequisite is goods receipts for orders without account assignment and for order settlement if AUA is not maintained).
    So settings in both of the systems are right.
    Ultimately, while settling the PO, the entry would be as above thread.
    Regards,
    Jigar

  • Automatic capture of batch number as production order

    Hi,
       How to make the order number to capture automatically while confirming the production order.As it should pick the order by default in the goods movement screen.
    Abap coding and user exit to perform this.
    Regards,
    Deepak GS

    Hi,
    Batch determination uses characteristic values assigned to batch classification for sorting batches and make a selection. A series of customization steps should be completed for batch determination. You will have to learn by reading SAP help or threads throughout this forum. Check out threads below.
    [Batch Determination within Production Orders;
    [Automatic Batch Determination;
    narainmech wrote:
    >      But for GR it is ok, if this is required for the child item level , while doing the confirmation when the issue is happening in bith cases 1. BAckflush 2. Manual issue
    >
    > Here in both the case it should pick the batch automatically.
    According to which criteria do you want batches to be selected, order name? Are there batches in the system named after production order for components of the order? No matter what, selection must be based on batch characteristics.
    Regards.

  • Batch determination in production order

    Hi all,
    Raw materiala are manged in batches and finished products are in serial numbers.
    when I release the production order the batch is not determining automatically.
    can any body expalin the SPRO settings for automatic determination of batch.
    Thanks
    Chindam

    Hi,
    Batch will not determeined at Production order release. only at the time of GR for Produ. order.
    Regards
    sam

  • Batch no assigning during production order creation

    Sir,
    We are manitaining the batch management for inut raw materials. During production order creation it is mandatory to assign the batch no for raw materials then only production order releasing is possible.In our case due to batch assignement to production order while order creation,we are facing the lot of problems like batch no not assign for full req qty and also if unavailabilty of stock for particular batch no it will come to COGI.hereby i need experts help for,
    1.I want to determine the batch no during confirmation instead of order creation and also allow to release the production order even batch should be in blank.
    Kindly help
    Regards,
    PS

    Hi
    For Rawmaterials why cant'n you assign Batch nos buring GR of purchase order.
    Then you can do automatic batch determination during confirmation of order for mvrmt type ;261...
    This is  easy  to handle.
    Please check and come back
    Regards,
    srihari

  • Batch determination during process order release

    Dear Experts,
    I am facing a problem, and not able to figure out the reason. There is material having base unit as 'EA' and Issue unit as 'NO' and conversion is 10 NO= 1 EA. The same material is maintained in the BOM as 1 NO. At the time of creation of process order, system is copying the same quantity in the process order (1NO). When I release the process order, the batch determination is happening. Now the issue comes, instead of doing batch determination of 1 NO, system is doing batch determination for 1 EA (which is equivalent to 10 NO.!). Can anyone help me to find out the reason for same.
    Thank you.
    Sagar

    Dear Mohit,
    If you want to go for external batch numbering during order release then
    - Set no automatic Batch creation in order in T.Code CORY.
    This setting only restrict the automatic Batch Creation in order only.But to fulfill second your requirement of restricting order release or save without assigning external batch no you have to either go for,
    - User exit.Below are the user exits which are trigger at the time of order saving
    PPCO0006 to predefine entries for order header fields when
    an order
    PPCO0001 to provide information at the time of saving (for
    production orders and process orders)
    PPCO0007 to check or change header data when saving
    or
    - Create screen variant using T.code SHD0 and make Batch Field compulsory.
    Regards,
    Dhaval