Production Order Master Data tab

Hello Guru,
we have question, in the production order itself, in the master data tab we find weird thing, in the production version it pick PV01 (has inactive bom), in routing field all was been filled up, while in the BOM field it was been blank? why this happen? is it possible BOM is not explode since it was inactive but it create production order?
I doubt that there were changes occured some where in the BOM or in the material master data of my material but in doc changes i cannot find, is there any way deside looking at the mat doc changes could i find the changes?
thanks
Edited by: Ryan on Dec 15, 2008 9:42 AM

Hello Guru,
I finally find why this happen to us, the order come from a planned order which converted via CO41, but why thus when i production version was indicated in creating a planned order (MD11) which has alt bom that is in inactive status already, SAP allows the conversion/creation of production order?
Any inputs R.Brahamankar?
Thanks
Edited by: Ryan on Dec 15, 2008 12:09 PM

Similar Messages

  • Profit center field in production order master data in KKF3

    Hi GUrus,
    is there any way of mass updating the profit center field in production order master data in KKF3 transaction. PLease help
    Anusha

    HI charlie,
    When i try to change the profit center, the system gave this message. We already have a profit center for a production order and we need to change the profit center, That is when we are getting the errror message.
    You have changed the profit center from AR00620800 to AR00620301. This is only allowed when the corresponding configuration was made in Customizing. Then this message is only a warning, which you can ignore.  PLease help
    Thanks
    Anusha

  • Production order - Master data explosion date

    Dear Team,
    I am creating the production order in CO01. While creating the production order, i am choosing the backward scheduling. Since i have selected the backward scheduling, i have given the finish date as "27.02.2012". And in the tab "Master Data", i was refering the field "Explosion Date". The explosion date is been displayed as 20.02.2012 (Routing and BOM explosion date).
    How this explosion date been determined based on the scheduling types (forward scheduling, backward scheduling)?. Is any configuration to be done to calculate this explosion date?
    What is the importance of explosion date in production order? will it affect the production order? Because in my production order the explosion date occurs in future ie, 20.02.2012. (as mentioned above).
    thank you
    psk

    Dear PSK,
    The explosion date refers to the date when the BOM & Routings are exploded on the orders i.e. applied. The explosion date can be controlled based on the settings in the SPRO.
    Go to SPRO - Production - MRP - Plant parameters - Carryout overall maintenance for plant parameters  (Transaction: OPPQ).
    In the plant pameters for a particular plant and in the tab 'BOM Explosion' we can determine how the system should can calculate the explosion date.
    Explosion date is controlled based on the order start date or finish date. If  the production order is added manually the system determines the explosion date as follows:
    Case 1:
    If you have specified the order start date on order creation the system takes this date as the explosion date for the bill of material.
    Case 2:
    If you have specified the order finish date on order creation the system calculates the explosion date from the order finish date minus the in-house production time defined in the material master.
    As per your example it looks like in your system the explosion date is controlled by the 'Start Date' due to which the explosion date equals the order start date.
    Hope this is helpful. Pl let me know if you need further help.
    Thanks,
    Satya

  • Production orders: Master data updating

    Hi everyone,
    This is my scenario:
    I had created hundreds of production orders with a previously defined BOM and routing. Now both the BOM and the Routing have been modified.
    I was wondering if there's any way for updating the master data in all the former production orders without doing it explicitely accessing one by one.
    Points will be rewarded.
    Thanks and best regards.
    Ben.

    Dear ,
    I hope you can do it by Mass processing of  Production .
      Logistics ---Production -- Production Control  Control --- COHV Mass Processing to go to the Mass Processing Production Orders screen
    Transaction Code :
    COHVOMPP
    Here u have to capacity and availability check for all the orders.Now u can include the function in the Mass processing tabe page in COHVOMPP ok  and also set the error log.Once u have executed a list of PO will be displaed and u have select all of them and hit the mass procesing button.
    2.In case your order beyond the shop fllor ,u can do it through Order Change Management 
    3.Or U can perform Read PP Master Data in the CO02 --Function tab  which will ask u to include your BOM/Routing.
    Hope it will help u to clear ur idea.
    Reward point if useful
    Regards
    Jia

  • Production order control data tab

    Hi,
    Is there any chance the costing data under control data tab in production order can make out "grayed" so that users can not change costing sheet, RA key.
    Thanks in advance.

    Dear Sprint,
    Try with SHD0, make the field as display only
    [http://wiki.sdn.sap.com/wiki/display/Snippets/TransactionVariant-AStepbyStepGuidefor+Creation]
    [http://sapfunctional.com/General/ScreenVariants/Index.htm]
    [http://help.sap.com/saphelp_nw04/helpdata/en/7d/f639fb015111d396480000e82de14a/content.htm]
    If possible take help from technical person
    Regards
    Madhu

  • SAP PP (Production Planning) Master Data Definitions

    SAP PP (Production Planning) Master Data Definitions and Transaction codes.

    SAP PP (Production Planning) Master Data Definitions
    • Factory Calendar
    • Material Master
    • Resource • Bills of Material (BOM)
    • Production versions
    • Master recipe
    Factory Calendar: The factory calendar is defined on the basis of a public holiday calendar. The public holiday and factory calendar is a central module in the SAP System. It is assigned to a specific plant during the initial system setup and therefore used in many areas (e.g. in Logistics and in Human Resources) in the system.
    Material Master: Material master comprises if all the basic data of the material for each department. The data covers all the relevant information required for the transactional flow e.g. sales, Planning, Production, Quality, Purchasing, Costing etc. Material master covers all the descriptive and control data and the flow of information depends on fields maintained within it. The integration of all material data in a single database object eliminates redundant data storage. Material Masters are created once and can be changed or extended whenever required
    Bill of Materials: Bill of Materials or commonly called BOM is a formally structured list of components that make up a product or assembly. The list contains the material number of the component together with the quantity and unit of measure. BOMs are used in their different forms in various situations where a finished product is assembled from several component parts or materials. Resources: Resources are production facilities and persons involved in a production process that have capacities. They are subdivided into categories to specify their suitability for certain purposes or their use in certain processes
    Product Versions: A production version determines which alternative BOM is used together with which task list/master recipe to produce a material or create a master production schedule. For one material, we can have several production versions for various validity periods and lot-size ranges. The production version determines the following:
    • The BOM alternative for a BOM explosion.
    • The task list (master recipe) and any alternate, as needed.
    • Lot-size restrictions and validity parameters.
    Master Recipes: A master recipe defines the following data that is required for the production of materials without relating to a particular order: processing steps, resources, material components, and control information for the process control level. Master Recipe enables to plan the production of materials (products). Therefore, Master Recipe is used as a template for process orders and run schedules as well as a basis for product costing. In a Recipe
    • The Phases (work steps) to be carried out during production.
    • The activities to be performed in the operations as a basis for determining dates, capacity requirements and costs.
    • The use of materials during production.
    • The use of resource.

  • Default Results Analysis Key in Internal Order Master Data

    Hi Expert,
    I would like to default specific Results Analysis Key in Internal Order Master Data.
    Please advice is the any configuration can perform that?
    Results Analysis Key is under Period-End Closing tab (Internal Order Master Data)
    Thanks
    regards,
    ng chong chuan

    HI
    1. Go to T code KOM1 > Order Type would $$
    2. CReate an Order and maintain default values in it like Comp code, etc and also the RA key
    3. Now, maintain this model order in your Order Type in KOT2_OPA
    4. Transport this customizing request across to all clients
    BR,Ajay M

  • How Production Order finish date and time is being comptued by SAP?

    Hello Expert,
    How Production Order finish date and time is being comptued by SAP? for example, we create a Production Order via CO01, the basic start date is 29.09.2008 and time is 04:00 it gives us basic finish date is 29.09.2008 and time is 13:28.
    how does SAP compute the time 13:28 as it finished time
    Please explain me briefly.
    Thanks
    Ryan

    Hello Guys,
    When we create Production Order in R/3 the time is calculated by routing but it is extended at SetUp machine time. It is not correct?. SetUp imachines time used only for first Production Order for the same product and it is plan manually, for others Production Order we need calculate time for production without SetUp machine time being pick up to compute finish time. how could we achieve this? only those Machine time will be check.
    thanks

  • Production Order Completion date

    Hi All,
       Can I know from which table can I get the production order completion date.

    Priya,
    There are different thoughts as you did not clearly explain what you meant by Order Completion date.
    If you are looking at based on,
    Confirmation then AFKO-GETRI
    Goods Delivery then AFPO-LTRMI
    If you are looking at Based on Status CLSD then you need to find the status change document using table JCDS-TJ02 with referance to the Object Number of the Production order from AUFK table.
    Regards,
    Prasobh

  • Production Order  Start Date

    Hello All,
    I am facing a problem in a Production order.When I am trying to change the  Production order Start date  and saving the changes I am getting a termination error (program termination).
    The error message is as below
    Nested call of PERFORM ON COMMIT: NESTED_PERFORM_ON_COMMIT caller: SAPLMCEX program: SAPLMCEX form: MCEXLOG_WRITE_04_DIA
    Regards
    Dhananjay

    Hi
    Check for the order scheduling parameters and confirm that the order in past are also allowed.
    Krishna

  • Internal Order master data change

    Hi all
    My requirement is to change cost center and profit center in Internal Order master data using KO04. In my project cost center and profit center are same. I am able to change and save but my question is...
    How come History(Posted transaction) of cost center and Profit center can be transferred to new CC and PC?
    Is it possible?
    Please help.
    Thanks
    Hari

    Hi, Hari:
    Do you mean Manual Reposting of Costs ?
    You can try KB11N for Cost Center.
    Best Regards, Lawrence

  • Screen/ User Exit for Internal Order Master Data

    Hi,
    I would like to one more field in Internal Order Master Data in TC KO01. I know the Table AUFK and i know there is one Include Structure (CI_AUFK). but i dont know how to add the field in that.
    if you go to Screen Exit COOPA003.  There is a Structure like CI_AUFK Structure there is no Calling screen in SMOD.  
    Can anybody please let me know how to do that?
    It's really really very urgent.
    your help would really appriciate.
    Thanks,
    Dhaval Shah.

    Hi Chandra,
    Thanks for the reply, can you please let me know from which TC i have to do. and i will be really appreciate your help  if you write down the whole process.
    Because i am aFunctional Person and i am using this Screen Exit for the first time so i'll be really thank ful to you.
    Thanks,
    Dhaval Shah.

  • Table for field "delivered" in production order header general tab

    Hallo everyone,
    I am looking for the field "Delivered" in the production order header on tab General. Can anyone tell me in which table it is stored?
    Thanks and regards,
    Jessica

    Hi,
    Field "ELIKZ" ("Delivery Completed" Indicator) is available in Table "AUFM" (Goods movements for order).
    Here You can co-relate this with field "AUFNR" (Order Number)

  • Enhancement in the Master data Tab in the BP transaction

    Dear all,I need to create news fileds in the Master data tab in the BP transaction. This fields are not imput fields but the content of this fields are customer specifics number which will be generated when creating a BP.  This numebr will be generated in the BUT000 Table in the BP number field.
    My Question is : How can i create New Fields in the Master Data Tab, is it possible to use the EEWB for that or not ?
    thanks in advance for ur help.
    liliane

    Hi liliane,
        You can use eewb however it should be used very cautiously as once changes are made there are  tables and attributes that are created correspondingly. I mean activities like Bdoc creation for the fields added happen simultaneously and you may not be able to revert changes.
    Thanks,
    vivek

  • Characteristics - Master data Tab- infosource with direct update

    Dear Experts,
    Please explain me in Laymans Language as i am new to BI (but am an ABAP consultant).
    In Info Object Characteristics,  Master data Tab there is infosource with direct update with an application Component.
    1. Now my doubt is,  when i specify the Application Component, this infosource would appear under the application component in Modeling->Infosources.
    Then on this infosource i would right click and create the info pakage and then data transfer process.
    is it correct?
    2. Suppose for this characteristic if i dont specify the infosource with direct update  then it wont appear in the infosource, so how can i load data in this case?
    Regards
    BI Learner

    Hi,
    Using an InfoSource with direct updating, master data (characteristics with attributes, texts, or hierarchies) of an InfoObject can be updated directly (without update rules, only using transfer rules) into the master data table. To do this you must assign it an application component. The system displays the characteristic in the InfoSource tree in the Data Warehousing Workbench. You can assign DataSources and source systems to the characteristic from there. You can then also load master data, texts, and hierarchies for the characteristic.
    You cannot use an InfoObject as an InfoSource with direct updating if:
    i. The characteristic you want to modify is characteristic 0SOURSYSTEM (source system ID).
    ii.  The characteristic has neither master data nor texts nor hierarchies. It is therefore impossible to load data for the characteristic.
    iii.  The characteristic that you want to modify turns out not to be a characteristic, but a unit or a key figure.
    To generate an export DataSource for a characteristic, the characteristic must also be an InfoSource with direct updating.
    1. *Now my doubt is, when i specify the Application Component, this infosource would appear under the application component in Modeling->Infosources.
    Then on this infosource i would right click and create the info pakage and then data transfer process.*
    The characteristic will be available in info source tree, you can assign a datasource->assignsource system->create package->load data.
    2. Suppose for this characteristic if i dont specify the infosource with direct update then it wont appear in the infosource, so how can i load data in this case?
    For a characteristic If you dont specify 'InfoSources with Direct Updating' then it wont appear in infosource tree.