Profit Centre - Transfer Price

\We are doing the settings for Profit Centre transfer pricing using PCA settings.  Here I see that 3 types of accounts have to be given for account determination:
1. Internal Stock Changes a/c
2. Internal Revenue a/c
3. Internal Transfer a/c
I am confused about the type of GL account - whether balance sheet or p&l type ?
Could you please clarify on this

HI,
1. Internal Stock Changes a/c                       PL  - This is to reflect Change in Stock postion.
2. Internal Revenue a/c                                 PL  - This GL Account will have I/C Revenues
3. Internal Transfer a/c                                 BS  - This Account will be used to show Stock Transfer /Stock Movement.
Regards
Jaydip

Similar Messages

  • Report on revenue of Profit Centre Transfer pricing

    We want to have a report on the revenue earned on profit centre transfer price.  We have maintained all the settings for the transfer price and the document is also posted correctly.  We want to see a report showing the revenue and profit earned on each transfer between profit centres.  When I go to the accounting document and in the "Display currency" and select "Local Currency/Profit Centre valuation" I can see the revenue and transfer price for profit centres involved in the document.  But how can I take a straightforward report on this rather than going inside the document and changing the currency, etc.?

    Hi Nikkitha ,
    Have to checked the standard SAP Report .. S_ALR_87013355 .. Transfer Price Reconcilliation  it should solve your purpose.
    Regards
    Sarada

  • Profit center transfer price Without activated material ledger

    Hi
    May I use profit center transfer price without activated material ledger as well?
    Regards

    Hi Alaa
    This OSS explain the Transfer Price Activation.
    Note 122008 - Activate transfer pricesmult.valuation approaches
    ML activation is a Must.
    Arturo.

  • Profit center Transfer Prices

    Is it only possible to work with transfer prices when selling goods between profit centers?
    Is it also possible in case of selling services between profit centers? .
    Does it require implemetation of the SD module?
    Thanks is advance,
    Yael

    Hi,
    I think it should be possible to work based both on services and goods.
    Thanks
    Aravind

  • Transfer Prices between different departments in the medical center

    Hello,
    Here are internal service sales between different departments in the same medical center. For example: Radiology center/department sells X-rays services for the cardiology center. We need the ability to sell a service to a different department in a different price than to an external payer/customer/insurance provider.
    Is it possible to implement profit center transfer prices along with the ISH_CO integration?,
    How is it getting along with the posting of internal activity allocation when services transfer to Controlling?
    At standard the costs are allocated (by means of internal activity allocation) between profit centers. The responsible cost center (assigned to the performing organization unit) is credited and the case based order (which is assigned to different profit center) is debited.
    Is it possible to implement transfer prices in case the performing organizational units are connected to the same profit center? (because some of departments are subdivided to several medical organizational units; and each unit represents a different cost center at the same profit center/department).
    Do you recommend defining a different profit center also for each sub-department?
    Do you have any other proposed solution for this issue?.
    Best Regards,
    Yael

    Hello,
    Here are internal service sales between different departments in the same medical center. For example: Radiology center/department sells X-rays services for the cardiology center. We need the ability to sell a service to a different department in a different price than to an external payer/customer/insurance provider.
    Is it possible to implement profit center transfer prices along with the ISH_CO integration?,
    How is it getting along with the posting of internal activity allocation when services transfer to Controlling?
    At standard the costs are allocated (by means of internal activity allocation) between profit centers. The responsible cost center (assigned to the performing organization unit) is credited and the case based order (which is assigned to different profit center) is debited.
    Is it possible to implement transfer prices in case the performing organizational units are connected to the same profit center? (because some of departments are subdivided to several medical organizational units; and each unit represents a different cost center at the same profit center/department).
    Do you recommend defining a different profit center also for each sub-department?
    Do you have any other proposed solution for this issue?.
    Best Regards,
    Yael

  • Transfer Price of Profit Centre

    I am trying to activate the Transfer price setting for the Profit Centre.  We have one controlling area with currency INR.  I have made the settings for Profit Centre account with currency type 20 (controlling area currency-INR) with valuation view (Profit Centre valuation).  However when I try to execute 8KEP for Multiple valuation, I get the following error. I have maintained the C+V Profile for both Legal valuation & Profit Centre valuation with Currency type 10 (Company code currency).
    No PCA valuation is defined in company code 1000
    Message no. FAGL_LEDGER_CUST140
    Diagnosis
    No PCA valuation has been defined in company code 1000.
    System Response
    If classic General Ledger Accounting is active, the system only checks the Customizing settings of (classic) Profit Center Accounting.
    If New General Ledger Accounting is active, the system first checks the Customizing settings of (classic) Profit Center Accounting. If (classic) Profit Center Accounting is not active, the system only checks the Customizing settings of New General Ledger Accounting. In all company codes of controlling area 1000, the PCA valuation must then be set in the currency specified in the currency and valuation profile.

    This is a BUG in std SAP ..there is a SAP note to resolve the error...
    ROMY

  • Transfer prices for Profit Center

    Hello Gurus,
    SAP describes the following regarding transfer prices
    "In order to use transfer prices in the R/3 System, you need to store multiple valuation approaches in parallel throughout the accounting application components"
    Does it mean if transfer price are set for valuation of internal goods movement between profit center, multiple valuation should be activated in other areas like FI (through currency and valuation profile), CO and MM (through Material ledger)
    Any prerequisites to be done in FI and CO for this activation for transfer prices, not getting the right approach between multiple valuation and transfer prices
    Any help is appreciated!!!
    thanka
    Nellikka

    SAP provides mechanism to capture various prices involved in transfering goods to another intercompany or on behalf of intercompany.  They are
    Legal price (recorded in the company code and reflected in financial statement report to the country tax authorities)
    Profit Center price (This price is agreed upon between the profit center managers) and
    Group Price (The bare price, with no profit element, The group profit readily provides the profit made by the group, in the company that sells the goods to the final customer).
    Once activated, the transfer price cannot be reversed within SAP. Also the Material ledger need to be activated with transaction based price determination to capture PC and Group prices.
    To your question, "Does it mean if transfer price are set for valuation of internal goods movement between profit center, multiple valuation should be activated in other areas like FI (through currency and valuation profile), CO and MM (through Material ledger)"
    the answer is yes.

  • Transfer prices in Profit Center Accounting

    Hi Friends,
    There is one scenario that, there are 4 divisions in one company one division produces the product for another division. They consider these transaction as internal sales revenue, we have created divisions as profit centers. To meet this scenario I am trying to configure transfer prices but unable to get the out put. Kindly enlightem me by providing customizing flow and process flow of transfer prices.
    Regards
    Ramesh

    Hi Ramesh,
    Check out this link
    http://help.sap.com/saphelp_ides/helpdata/en/e9/f9db357cc311d3851400104b55af8e/content.htm
    Assign points if useful
    Regards
    Genie

  • Customer & vendor balance transfer to Profit centre

    Hi Experts
    this is Geetareddy . pls could any body help to me abt
    how customer & vendor balance transfer to Profit centre
    thanks
    get points
    Geeta

    Hi
         It is through Material master, if your client is using SD and MM, or it is through other line item, vendor or customer balances are identified to profit center.
    assign points if found useful
    KM Naidu

  • Profit Center Accouting-Transfer Prices

    Hi,
    For Profit center valuation, Activation of Material Ledger  is mandatory?

    Yes,
    For Transfer Prices & Multiple Valuation "Activation of Actual costing / Material Ledger" is mandatory..
    Once ML is activated it cannot be deactivated again.
    Between, if any one having any material on Transfer prices nad multiple valuation kindly share with me.
    Especially AC650
    Thanks- aravind

  • Transfer price mechanism between profit centers

    Hi friends,
    My requirement is how to maintain Transfer price Mechanism between Profit Centers with in the Plant.  If the transfer price mechanism is between the plant we should activate MATERIAL LEDGER our client not require Material Ledger concept.
    But here we are having 3 profit centers with in one plant only so they require Transfer price mechanism between profit centers to show the dept wise profits in Financial Statements between the Departments (profit Centers) this postings should be done automatically in the respective profit centers.
    So friends my Q is how to configure Transfer Price mechanism between the profit centers.  Please suggest me.

    Hi,
    You need to to maintain Conditions in the basic settings.There you need to maintain for Material, Overhead etc and need to maintain access sequences.
    You need to assign accounts with T.Code 0KEK.
    While doing transfer from plant to other plant the system generates value based on the condtions you maintained.
    Thanks and regards.
    S.Subbiah.

  • "In material transfer profit centre link is mandatory" how to do this

    Hi Friends,
    How to do this validation , can any one guide me.
    "In material transfer profit centre link is mandatory"
    Regards
    Mahesh A

    Hi
    While creating material choose costing view1,you will find there profit center its required field there,maintain costing view1 to material master all your material master and maintain profit center it will come automatically in grn accounting doc and same you can see in accounting tab
    Regards
    Kailas ugale

  • Activation of Transfer Price; Profit Center;

    Dear All,
    As I have no prior experience in CO/ Transfer Price , I sincerely seek the  assistance and help of kind souls in giving some pointers on the following questions after reading so much from everywhere.
    Currently we are having a Production Profit Center selling to a Selling Profit Center at a neogotiated price. Thus we would like to activate Transfer Price in Controlling and Material Ledger to document internal revenue, internal costs and changes in stock in each Profit Center.
    My queries as follows:
    Activation of Transfer Price
    1) The Currency & Valuation Profile has to be maintained.
    As we are interested in activating the Profit Center Valuation View in Material Ledger to store the transfer price in company code currency, we will need to create a new Currency & Valuation profile as the Company Code Currency + Profit Center Valuation here. Is this correct? Is there a need to create the valuation profile for Company Code Currency + Legal Valuation?
    2) Assignment of Currency & Valuation Profile to Controlling Area
    If we have 2 profiles such as Company Code Currency + Profit Center Valuation and Company Code Currency + Legal Valuation, how are we to assign only a single profile to the Controlling Area? Or is it possible to assign 2 profiles to the Controlling Area?
    3) Create Versions for Valuation Methods
    As we are using Transfer Prices, SAP Help says we specify "Operational Actual Version 000" for the valuation which becomes the leading valuation in CO. How do we do this in the configuration?
    4) Define Valuation Clearing Account
    The transfer price is actually used between 2 Profit Centers within a Company Code. Thus is the defination of Valuation Clearing Account applicable in our case? From the postings that I saw from your above reply regarding the recognition of AR/AP from both Profit center, is it here or other area where we config for such posting?
    5) To assign additional Postings in PCA for Internal Goods Movement
    Are the GL Account postings that you displayed in your above reply configured here? Do you encourage to use Valuation Grouping Code?
    6) To assign additional Postings in PCA for Production Variance
    Since we have a Production Plant, does that mean we would have to assign GL Accout Postings to account for Production Variance?
    7) Define Special Handling for Internal Goods Movements
    If possible, kindly enlighten for what kind of expenses or situation we should use this?
    Activation of Material Ledger
    1) Can we use the Standard ML as we will only be using the company code currency where in the Controlling Area, we are using Controlling Area Currency. For both The Co Code Currency and Controlling Area Currency is the same currency (SGD). Thus in this case, the ML will adopt the currency type from FI and CO?
    2) To allocate the transfer price, we will need to create pricing conditions and access sequence.
    Also we should be using the Actual Transfer Price Variant 000 for actual postings, is this reasonable?
    3) Where do we store the transfer price in the Material Ledger (Material/Profit center)?
    4) When the STO is created, based on the Material/Profit Center, will the STO automatically retrieve the price from the ML? Can the price be overwritten in the STO?
    Your time and efforts in reading and response are greatly appreciated!
    Best Regards
    Edited by: wishy washy on Nov 30, 2008 11:16 AM

    Hi Sridhar,
    Thanks for the inputs.
    Here, I am getting the new G/l values in all the related reports after running this transaction.
    For example : A perticular G/l a/c say 333100 was having value 100000.
    Now after running this transaction 1KEI , the new balance of the G/l has become 250000.
    For all reporting purpose, this new value is flowing for that G/l. However, now we understand that previous value of 100000 was correct for the reporting style which we were carrying out uptill now.
    As a result , we would like to have the value of this G/L as 100000 again as against the current value of 250000.
    In short , I want to nullify/ reverse the effect of tr. code 1KEI.
    How to achieve this?
    Warm Regards,
    George

  • Customer balance transfer from one profit centre to other profit centre

    Hi friends,
    We want to transfer the customer balance from one profit centre to other profit centre.  How is it possible.

    Hello
    Balance sheet items in PCA can be distributed during period end closing activities.
    Please read the documentation in the link and config the same / execute
    http://help.sap.com/erp2005_ehp_02/helpdata/en/eb/13706b43c411d1896f0000e8322d00/frameset.htm
    Reg
    assign points if useful

  • Profit centre line item report after transfer

    Dear All,
    I have activated Document splitting. And it is working fine.
    But when i take the report at profit centre level i am not able to see the Balance sheet line items.
    Then i transferred the Balance sheet items to profit centre through customizing. Even now i cannot see line items but a consolidated figure which was transferred is appearing.
    Is it correct or is there any way through which i can see the line items trasferred to the profit centre as period end activity.
    Please help to resolve the issue
    Sapfrido

    done

Maybe you are looking for