Project Plans Costs not shown in CJI4

Hi
I have planned costs input in CJ40 against a WBS plan version "0" but when I run CJI4 no planned values are shown.
However if I run S_ALR_87013532 I can see the planned costs, why does CJI4 not show the costs?
thanks
Joe

Hi,
CJI4 does not display plan cost eminated from CJ40.
Even to display the plan costs in CJI4 you need to have user status to be maintained "write plan costs' activated at WBS element level and costs should be planned using CJR2.
Just wanted to add here, S_ALR_87013532 is Hierarchy Cost Planning report - so you will see there.
Thanks,
Sudhakar

Similar Messages

  • How to extract Project Plan Cost

    Hi SDNs,
    I need extract the Project Plan Cost which we can display via t-code CN41N,which datasource can I use to do it?
    Thanks a lot.
    Best regards
    Simon Liu

    all the info you need :
    http://help.sap.com/bp_bw370/BBLibrary/HTML/D11_EN_DE.htm (and click on configuratin guide)
    M.

  • Project Plan icon not working

    The little icon found on the left that allows you to access your project plan is not working for one of my project managers, who is the owner of that specific project. However in the Admin's view they are able to access it by clicking that button.
    Any thoughts why?

    Hi EPM Admin,
    The issue occurs only for 1 PM? Is the icon working for this PM with another view? Can the PM try on another machine? When you say that it doesn't work, do you have any error message or just nothing happens? Have you tried refreshing IE deleting the cache
    (press CTRL F5)?
    Hope this helps,
    Guillaume Rouyre, MBA, MVP, P-Seller |

  • Project Plan cost report - not showing any output.

    Dear Experts,
    I have created several projects and done the planning.  I have used work centers and activity types for manpower cost planning. Also created some PRs against the project.
    When I goto the network activities and select the line item in the menu path Edit - costs - Planned/Actual - cost planned /actual
    It shows me the planned cost of the activity correctly.
    But when I am running the report CJI4, it shows nothing. The report is not at all executing.
    I dont understand why it's \not showing.
    I have checked the control key PS01 for the cost field is enabled (tick available on the cost friled)
    Can any one please help me??
    Thanks and Regards,
    Praveen

    1) Please check that the WBS element is integrated in plan, and the plan integration is fully activated in the project.
    2) Plan line items are only written in certain cases.
    The following rules are valid:
    1. Plan line items can be written in
    a) structure-oriented cost planning CJ40 (total values, annual values),
    b) cost planning on orders KO12,
    c) unit costing independent of cost elements,
    d) structure-oriented revenue planning CJ42 (total values, annual values)
    e) structure-oriented financial budgeting CJ48 (total values, annual values, period values)
    f) primary cost planning,
    g) activity planning,
    h) revenue element planning.
    2. Plan line items are never written in
    a) Unit costing on cost element level
    b) Network costing
    3. Line items are only written if a user status permits the business transaction 'Write plan line items' explicitly.
    Exception:
    For plan-integrated WBS elements and orders, line items are written in cost-element oriented planning if integrated corporate planning is activated in the fiscal-year parameters of the respective plan version, regardless of the user status.
    4. Plan line items for structure-oriented planning can only be displayed in the respective planning transaction under menu option "Extras-->Line items".
    Let me know if this was useful
    Ritesh

  • S_ALR_87013532 report -plan cost not rolling upto the WBS/Project level

    Dear All,
    Plan cost from production orders is not rolling up to the WBS/Project level in S_ALR_87013532 ( Plan/Actual Variance report).
    Where as plan cost from network is properly rolling up to the WBS/Project level in the above report. 
    Please suggest what could be the reason for this issue. Is any configuration needs to be done for this.
    Thanks & Regards,
    Vishal

    Dear sir,
    Thanks for the reply & sorry for late response from my side.
    OPSV settings are already maintained in our system.
    Some how i realized  later that cost are actaully getting rolled to the WBS level, but we have observed one more discrepancy.
    Example -
    Production order "X" value - 100 (  as seen through co03)
    Production order "X"value- 40 ( as seen through report s_alr_87013532).
    We found that  in report  s_alr_87013532 , although my total  producton order value of 100 is represented at the WBS /Project level, but at the production order level , it is showing value of 40. 
    On further analysis we found that for production order X
    Materail cost- 60
    Labour cost-40
    The material cost of 60  is not getting fetched against production order "X" in report " S_ALR_87013532".
    There are very few cases , where such discrepancy is seen.
    Kindly suggest.
    Regards,
    Vishal

  • Cost Not shown properly

    Dear Friends,
    I am issuing material through 281/Q from WBSE to Activity,
    but cost is shown against WBSE not activity (S_ALR_87013532)
    Previously Cost was booked correctly on activity (and also rolled up cost against WBSE).
    may be some setting is changed.
    Can you help to sort out?
    SSanjay

    Hi Sanjay,
    Pls check if you are using a non-valuated project. Because the cost will be booked at the WBS element and not at the activity level when you are issuing the material (project specific material ie indiv/coll indicator '1' ) to the project using 281Q when you are using non-valuated project.
    When you said previously you were getting the cost at the activity level,  one of the following should have happened.
    1 . Either the project should have been the valuated project and you have issued the material (project specific or plant stock material) using 281Q.
    2. Or the project is non-valuated project and you have issued a plant stock material using 281 instead of 281Q.
    Pls check and revert for any further clarification.
    Regards
    K Ramaiah

  • CProjects Planned costs not replicating in PS

    Hi,
    We are on PPM5.0. We are able to create cProjects Project and replicate to PS upon u201CFlag for transferu201D.
    We also have cost/revenue rates, for roles. We have roles assigned to tasks, and intend to transfer the costs (product of cost-rate and role-task-assignment hours) to show up in PS.
    We are not using the HR org. The question is regarding the cost element and activity types.
    After replicating  the Project Type, Cost/revenue rate from cProjects to the accounting system, we link a cost element, activity type to the Cost/Rev rate.
    Suppose, we have Cost Element u201CCu201D, and Acticity Type u201CAu201D, linked to the Cost/Revenue rate (the Org. is marked to u201C0u201D). How do we need to link the corresponding u201CCu201D, and u201CAu201D to the WBS elements to be able to see the Planned Costs?
    Currently, we get Planned Values as 0, and are not sure whatu2019s more to be done to get the planned costs.
    Please advise.
    Thanks.

    You have rates maintained I assume.
    One thing worth checking is the "tick" box called "costing" in spro>cProjects->Connection to external systems>Accounting integeration--->Make General settings.
    You should have a cost/rev rate with correct validities which should be replicated in SAP PS as well.Also, do "Replicate accounting relevant charateristics".
    PS: I am no expert in this area so try and test your changes.

  • Order plan cost not appearing in PS report.

    Dear PS friends,
    I have an issue in order plan cost updation ( budget report ).
    Used the prescribed WBS in maintenance order ( additional data ), but its not appearing in planned cost of CJ31 screen.
    Checked the following
    a)  WBS is account assignment element.
    b) Network type order appended indicator in OPSV.
    c) Setting in network type parameters for " determine plan  
        cost".
    d) WBS and order - both are showing plan cost when booked separately, but not integrated.
    Can anybody help me to resolve this ! 
    Thanks in advance
    --  Sri  --
    Edited by: Srinivasan Madaswamy on May 18, 2008 2:15 PM

    Hi,
    In case of the maintenance order (Order Category:30)
    Please check the follwoing in Tcode OPSV:
    1. type is maintained default i.e ++++ (this will consider all the order types mantioned for maintenance order.
    2. Please selelct the appropriate controlling area.
    3. Appended plan indicator has to be checked mark,
    4. Assigned funds in the plan indicator has to be checked mark,
    5. In Tcode IW32: In the additional data Tab assign the WBS Element. Save the maintenance order.
    Hope its useful.
    Reward point if useful. Revert abck if any other issue.
    Thanks..

  • Project Commitment Cost not visible for Purchase Orders with Item Categry Q

    Hello All
    I have a problem. My project commitment cost is not visible for PO's with Item Category Q. I assume that as the stock can be issued against any WBS elements I might not be able to see the cost against a single WBS element. But the cost should get recorded against the project right? If so where can I see it?
    Request your help with this problem
    Regards
    Renjith

    Hello
    Could you please explain how to maintain that?
    Best Regards
    Renjith

  • Planned Cost not coming for CO Activity in PM Order

    Dear All,
    I am putting up the entire configuration process i am carrying out for CO activity and using it in the PM Order.
    Please see the link and guide me through as to why the Planned Cost for the Activity is mssing.
    http://www.scribd.com/doc/21375098/PM-Activity-Configuration
    Regards
    Praveen Dhankar

    Hi,
    Kindly check the logs in the maintenance order,it will show that the valuaton variant defined wasnot successful.
    The problem is The activity price is not calculated properly,ask the CO consutant to maintain the activity price proprerly with updation. against that cost center.
    The second one is no need to maintain the activity in workcenter as per your attachment sheet.
    Maintain in Basic data of workcenter as standard value key as SAP0 No standard value key & in Costing view maintain the cost center,Activity in below field & maintain the formula as SAP0008.
    Regards,
    Raj

  • Master Project Plan is not updatineg

    I'm running in a situation where I have a master plan with sub-projects, the master plan will not show the updated sub-project plans in the web app until you open the master project in project professional and expand the sub-project summary task every time
    it get an update, then you have to publish the master plan, then the master project will show the date changes in the web app.
    Is there a way to make the updates on sub projects show up on the master project immediately without going through all that?

    Sgasgous --
    It appears so.  I have not extensively used master projects in Project Server 2013, so I will gladly invite the others in this forum to correct me if my answer to you is wrong.  For me personally, I have never expected the behavior you expect from
    PWA.  My habit is always to open the master project in Microsoft Project after updates are applied, expand all of the subprojects, and begin doing variance analysis.  The process of applying updates will inevitably cause variances, which need to
    be known and addressed.  After doing that, only then would I save and publish the latest schedule changes.  In fact, I would recommend this approach as a best practice for you as well!  Hope this helps.
    Dale A. Howard [MVP]

  • Project plan cost

    Hi
    We are working with Project system and we trigger project from Sales order.
    We are using Assembly order for this purpose.
    When we are looking at plan cost of the project, cost is directly picked up from the material instead of referring to WBS BOM and production lot cost estimate.
    When we are creating project manually cost is picked up correctly from the WBS BOM.
    Do we need to do any special setting for cost when we are triggering project from the sales order??

    I think you might be using the Sales document as cost object in your configuration. For your requirement, you should use the Project as the cost object. Please check the account assignment category in the requirements class. It should be D (projects).
    Hope this helps.
    Regards,
    Ajinkya

  • Maintnance Plan Costing not running in foreground

    Hi All,
    When I want to execute the T Code IP31 to do the maintenance plan costing after giving the inputs, the system throws a message saying "This report can only be executed in the background".
    When I click "Program" -
    > "Execute", then system throws a same message "This report can only be executed in the background"
    Is there any change in settings required in the background so that the report can be executed in the foreground?
    Kindly help.
    Thanks in advance.................JK

    Hi,
    The inputs I gave were
    maintenance plan no (from -
    > to)
    Maintenance Category (from -
    > to)
    Start Date:
    End Date:
    The point is that when I gave only one maintenance plan no, the the system generated a report directly in the fore ground; but when I give a range of maint. plan nos then the system does not run a report in foreground
    May be this is due to the amount of data that the system has to process which makes it to throw such a message.
    Pls. suggest
    Thanks...............JK

  • Material Cost Not Shown in Production Order if planned with MD50

    Hi,
    We have run MRP MD50 for a sale order item ie FERT material which has BOM Items. All the stock of the BOM items is tranfered from Unrestricted Stock to Sales order stock. FERT ITEM planned order is converted to Production Order and all the BOM items sales order stock is issued against PO & Sales order no with Movement Type 261E.
    After confirmation and goods receipt stock of FERT is shown under sales order Stock of Fert Material.
    We can see the cost of operations but cost of materials consumed against the Production order is not displayed in Production order Cost analysis..How material cost can be displayed????
    If i create PO with out refering the sale order that is normal process i can see the cost of materials triggering in Production Order.
    Can we settle the varience when we are planning against sale order???
    Some one Pl help us.
    John

    Dear,
    Check your variant which showes the cost. See the following report
    KKAC - For Sales Order with Assigned Orders  or
    KKBC_KUN - For Sales Order or
    KOB1 - Actual Costs

  • Actual shown PLan is not shown

    Hi,
    I a working on BI 7.0.
    In my report I have 2 RKF's. Actual & Plan.
    I have restricted both to:
    Fiscal Year  & Posting Period (Range from 1 to current posting period)
    I am getting the values for Actual while Plan is shown blank.
    Please let me know where I might be going wrong.
    The report is on a MultiProvider. Plan Cube is also having a posting period which is derived from Fiscal Year/Period.
    I look forward to your suggestions.
    Thanks
    Kumar

    assuming you have data in plan cube and have done identification on the multi provider right, in the RKF try to further restrict with the dataprovider (ur plan cube). that should work ...
    make sure to have restricted request id(under datapackage) with most current data. even there is a chance the data wont show up if you have loaded the data (trying to see) in the second or subsequent run.
    Message was edited by:
            voodi

Maybe you are looking for