Hi,
We are on PPM5.0. We are able to create cProjects Project and replicate to PS upon u201CFlag for transferu201D.
We also have cost/revenue rates, for roles. We have roles assigned to tasks, and intend to transfer the costs (product of cost-rate and role-task-assignment hours) to show up in PS.
We are not using the HR org. The question is regarding the cost element and activity types.
After replicating  the Project Type, Cost/revenue rate from cProjects to the accounting system, we link a cost element, activity type to the Cost/Rev rate.
Suppose, we have Cost Element u201CCu201D, and Acticity Type u201CAu201D, linked to the Cost/Revenue rate (the Org. is marked to u201C0u201D). How do we need to link the corresponding u201CCu201D, and u201CAu201D to the WBS elements to be able to see the Planned Costs?
Currently, we get Planned Values as 0, and are not sure whatu2019s more to be done to get the planned costs.
Please advise.
Thanks.

You have rates maintained I assume.
One thing worth checking is the "tick" box called "costing" in spro>cProjects->Connection to external systems>Accounting integeration--->Make General settings.
You should have a cost/rev rate with correct validities which should be replicated in SAP PS as well.Also, do "Replicate accounting relevant charateristics".
PS: I am no expert in this area so try and test your changes.

Similar Messages

  • Order plan cost not appearing in PS report.

    Dear PS friends,
    I have an issue in order plan cost updation ( budget report ).
    Used the prescribed WBS in maintenance order ( additional data ), but its not appearing in planned cost of CJ31 screen.
    Checked the following
    a)  WBS is account assignment element.
    b) Network type order appended indicator in OPSV.
    c) Setting in network type parameters for " determine plan  
        cost".
    d) WBS and order - both are showing plan cost when booked separately, but not integrated.
    Can anybody help me to resolve this ! 
    Thanks in advance
    --  Sri  --
    Edited by: Srinivasan Madaswamy on May 18, 2008 2:15 PM

    Hi,
    In case of the maintenance order (Order Category:30)
    Please check the follwoing in Tcode OPSV:
    1. type is maintained default i.e ++++ (this will consider all the order types mantioned for maintenance order.
    2. Please selelct the appropriate controlling area.
    3. Appended plan indicator has to be checked mark,
    4. Assigned funds in the plan indicator has to be checked mark,
    5. In Tcode IW32: In the additional data Tab assign the WBS Element. Save the maintenance order.
    Hope its useful.
    Reward point if useful. Revert abck if any other issue.
    Thanks..

  • S_ALR_87013532 report -plan cost not rolling upto the WBS/Project level

    Dear All,
    Plan cost from production orders is not rolling up to the WBS/Project level in S_ALR_87013532 ( Plan/Actual Variance report).
    Where as plan cost from network is properly rolling up to the WBS/Project level in the above report. 
    Please suggest what could be the reason for this issue. Is any configuration needs to be done for this.
    Thanks & Regards,
    Vishal

    Dear sir,
    Thanks for the reply & sorry for late response from my side.
    OPSV settings are already maintained in our system.
    Some how i realized  later that cost are actaully getting rolled to the WBS level, but we have observed one more discrepancy.
    Example -
    Production order "X" value - 100 (  as seen through co03)
    Production order "X"value- 40 ( as seen through report s_alr_87013532).
    We found that  in report  s_alr_87013532 , although my total  producton order value of 100 is represented at the WBS /Project level, but at the production order level , it is showing value of 40. 
    On further analysis we found that for production order X
    Materail cost- 60
    Labour cost-40
    The material cost of 60  is not getting fetched against production order "X" in report " S_ALR_87013532".
    There are very few cases , where such discrepancy is seen.
    Kindly suggest.
    Regards,
    Vishal

  • Planned Cost not coming for CO Activity in PM Order

    Dear All,
    I am putting up the entire configuration process i am carrying out for CO activity and using it in the PM Order.
    Please see the link and guide me through as to why the Planned Cost for the Activity is mssing.
    http://www.scribd.com/doc/21375098/PM-Activity-Configuration
    Regards
    Praveen Dhankar

    Hi,
    Kindly check the logs in the maintenance order,it will show that the valuaton variant defined wasnot successful.
    The problem is The activity price is not calculated properly,ask the CO consutant to maintain the activity price proprerly with updation. against that cost center.
    The second one is no need to maintain the activity in workcenter as per your attachment sheet.
    Maintain in Basic data of workcenter as standard value key as SAP0 No standard value key & in Costing view maintain the cost center,Activity in below field & maintain the formula as SAP0008.
    Regards,
    Raj

  • CProjects Planned costs display

    Can you display planned costs in cprojects after doing financial integration(Calculated on Role/Task revenue rates) against each phase or task without going into each individual task separately.
    Which all options of displaying planned costs are available and how are these configures ?
    Is this carried out via the planning mechanism chosen Role-based resource planning or Task Based.If yes, Where do you specify which of the 2 options to choose ?whether you want to choose role based or task based planning.

    Hai Pooja
    Costing is carried out in cProjects based on the project roles r tasks.
    Reg tasks based cost planning u can assign the required capacity to the individual tasks during the planning of the project structure.This required capacity is multiplied by the cost/revenue rates ti determine the planned costs and planned revenues.
    Task is done by a role  - means for example Project Manager specifies which positions are to be filled up - these positions are called in cProjects as Roles(resources for the project). Thye are assigned to the tasks in which the positions are involved.
    Check the configuration in - SPRO - cProjects - Connection to external system - Accounting Integration - Integration using Single Object Controlling in SAP R/3 CO - Make General settings
    ENJOY mySAP PLM
    Regards
    PP

  • Maintnance Plan Costing not running in foreground

    Hi All,
    When I want to execute the T Code IP31 to do the maintenance plan costing after giving the inputs, the system throws a message saying "This report can only be executed in the background".
    When I click "Program" -
    > "Execute", then system throws a same message "This report can only be executed in the background"
    Is there any change in settings required in the background so that the report can be executed in the foreground?
    Kindly help.
    Thanks in advance.................JK

    Hi,
    The inputs I gave were
    maintenance plan no (from -
    > to)
    Maintenance Category (from -
    > to)
    Start Date:
    End Date:
    The point is that when I gave only one maintenance plan no, the the system generated a report directly in the fore ground; but when I give a range of maint. plan nos then the system does not run a report in foreground
    May be this is due to the amount of data that the system has to process which makes it to throw such a message.
    Pls. suggest
    Thanks...............JK

  • Project Plans Costs not shown in CJI4

    Hi
    I have planned costs input in CJ40 against a WBS plan version "0" but when I run CJI4 no planned values are shown.
    However if I run S_ALR_87013532 I can see the planned costs, why does CJI4 not show the costs?
    thanks
    Joe

    Hi,
    CJI4 does not display plan cost eminated from CJ40.
    Even to display the plan costs in CJI4 you need to have user status to be maintained "write plan costs' activated at WBS element level and costs should be planned using CJR2.
    Just wanted to add here, S_ALR_87013532 is Hierarchy Cost Planning report - so you will see there.
    Thanks,
    Sudhakar

  • CPr-PS integration - cProjects costs not showing up in PS

    Hi,
    We are on PPM5.0. Accounting integration results in successful replicaition of cPro structure as WBS in PS. However, the costs do not flow.
    We have used PS06 (ECP) as the costing variant. All configurations seem to be done, and yet, we do not see the costs replicating.
    Additinal Information:
    We are not using "Org" structure. We understand that "Cost Element" and "Activity Type" aligned with the cost/revenue rate is all that we need to maintain for costing to take place.
    Please advise on what we might be missing.
    We are able to replicate all accounting charateristics including cost/rev rate, and project type to the ERP system.
    The costing variant has been defined as PS06 (both under "Create and Change controling scenario", and "Settings for "Easy Cost Planning"). And yet, when we click on the "costing" button (under the "accounting" tab), we get the following warnings:
    - Error occurred in controlling cockpit (and yet we see nothing in COCPCPR)
    - Costing data may not be up to date
    Please advise.

    HI Deepak
    Please advise how you got the planned costs to show up in PS.
    I face the same issue now.
    I have exactly the same settings as you have PS06 on both sides.
    However, when i look at ECP in PS, it requests a planning form and no planned data is being pulled through, its just blank.
    I am not sure what i could be missing, is a costing model mandatory ?
    Please advise soonest.
    thanks
    Ihsaan Mayet

  • CProjects to IO, IO to RPM - costs not showing up

    Hi,
    Having created an internal order from cProjects, I can see the costs in IO.
    To start with, costs from cProjects Role-Task assignment is all I am trying with (using role rates).
    Simultaneously, I have created the Finance Categories, Groups, and Views in RPM.
    I have tried a few juggleries to bring this cost under a finance view in RPM. Not through yet.
    I have run the programs that fetch this IO cost into RPM. But the link doesn't seem to have been estd. and therefore, though the program shows all green, it says there's no cost in the db to fetch.
    What all should I have completed before I get this through?
    Thanks...

    HI Deepak
    Please advise how you got the planned costs to show up in PS.
    I face the same issue now.
    I have exactly the same settings as you have PS06 on both sides.
    However, when i look at ECP in PS, it requests a planning form and no planned data is being pulled through, its just blank.
    I am not sure what i could be missing, is a costing model mandatory ?
    Please advise soonest.
    thanks
    Ihsaan Mayet

  • Dashboard content is not populated with Planned Cost and Actual Cost

    Hi
    We are working in cProjects 4.0 + ECC 6.0 implementation. I could not get the data for columns in Planned Cost and Actual Cost in cProjects Project Dashboard. I have properly mapped the config settings and created and assigned a Project in PS
    Has anybody got this data in the Dashboard?
    Kindly suggest the solution
    with regards,
    K Rama Krishna
    9394712743

    Hi Rama,
    It is difficult to say, where the problem is.
    but typically, the causes of the problem are
    customizing is  set incorrectly or the evaluation is not carried out.
    You can run the the evaluation DPR_EVE_BATCH_DPO additionally, please untick the flag 'check the last changed date'.
    Hope, it helps.
    Kind regards,
    Zhenbo

  • CN41N and S_ALR_87013533 report not showing Production order planned cost

    Hi Experts,
    I am having issue to get total planned production order values in my CN41N or S_ALR_87013533 cost report. I am facing 2 issues :
    1. CN41N repoet does not show individual material cost planned in BOM.
    2. CN41N report and S_ALR87013533 report does not show total value but only picking fixed value.
    Example :
    1. CN41N report :
    Above screenshot shows no values in Project plan cost & Order cost column but it shows total cost as a lumpsum on top for project. I need to know how can i get material cost populated here for Project Valuated stock material?
    2. S_ALR_87013533
    This report shows Total Cost of BOM as 1 line under Material Procurement activity similar to CN41N report. Also Order value is picking from Fixed cost from planned order and total cost is added on top. How can i get Total cost picked from production order?
    Is there any Setting in PS config which allow me to pick the detail production order plan cost in both report under planned cost.
    Thanks in advance.
    Ashish

    Hi Ashish,
    I doubt whether Item level reporting  in S_ALR... (hierarchy report) is possible or not because I haven't seen item level cost in them only the lump-sum cost because they are summarized at cost object level itself. Navigation path are there which we use to go into details of cost.
    Please check the following links:
    https://scn.sap.com/thread/1743833
    (In the above thread,focus on  Mr. Mohamed Rafi comment.)
    http://scn.sap.com/thread/3530080
    http://scn.sap.com/thread/1311820
    Order cost plan in report CN41N
    Display of plan cost., CN41N | ABAP, SAP, benX AG, benXBrain,&…
    Just an additional pointer ,have a look on your costing variant and variation variant settings for material section.
    Regards
    Saurabh

  • Settlement of planned deliv. costs not possible if GR-related data entered

    Hi gurus,
            While doing T-code MRRL if i am entering the GR posting date and ticking the good + delivery check box an error message is trigerd 'Settlement of planned deliv. costs not possible if GR-related data entered'.PLZ reply the reson for this error.

    I Have the same problem them I realise  that :
    This message just appear if i am using doc. selection = 4 .
    tks
    Teresinha

  • Cost Centre Plan data not updating FAGLFLEXT

    Dear Experts,
    In our production environment, our cost centre plan is not updating FAGLFLEXT table. Profit centre plan using GP12N is fine.
    We are using the New GL and have FIN-CCA and FIN-PCA scenario activated.
    Integrated planning is ticked in the planning versions for both Controlling and New GL Plan versions.
    Controlling plan version and New GL plan version have the same name.
    In table Controlling table COSP, I can see the plan data on business transaction type RKP1.
    I expect to see it in FAGLFLEXT with RKP1 but I see no plan values at all.
    In fact, in the previous 3 environments, we have not had this problem and cost centre plan and actual has updated FAGLFLEXT. Only in Production...
    Any suggestions? Help if you can! Thanks alot,
    Deb

    Dear Ravi,
    I don't think this is the problem.
    It seems that:
    - the CC plan was created -> it updated CO tables e.g. COSP -> no update to FAGLFLEXT
    - the CC plan was deleted -> it updated CO tables with negative value -> updated FALFLEXT with negative value
    -the CC plan was update again -> it updated CO table -> updated FAGLFLEXT and balance with negative value is zero
    - the CC plan was deleted again -> it updated CO tabe with negative value -> FAGLFLEXT  is in minus value!
    It seems like somewhere between first and second steps, the scenario FIN-CCA was not behaving like it was active!
    Have you come across this before?
    Thanks!
    Debora

  • Planned Cost & Planned revenue - Not displaying data in Bex.

    Hi BW Experts,
    I have installed 0PS_C04_Q002 query from the business Content and loaded the data for the Cube 0PS_C04.
    While executing the query, I am not getting data for Planned Cost and Planned revenue. I am getting data for Actual Cost and Actual revenue. As I am using standard restricted key figures, I am not getting the data. Can you please help on this Issue.
    Thanks in Advance.
    Thanks,
    Jelina.

    Hi Jelina,
    Is the load successful to the cube?
    Did u check the data in the cube?
    Is the data populated fine?
    Otherwise check the properties of Planned Cost and Planned Revenue by changing the Infoobjects. And check the lengths given and the datatypes. Compare them with the length and the datatypes of the fields u  are retrieving from your source system.
    Hope this helps u...
    Regards,
    KK.

  • Planned cost for int labour and non stockable material not visible

    Hey gurus,
    While creating an order with a material, ext service, non stock material, I am able to see the planned cost for materials in stock and ext services procured. But i'm not able to see the planned cost for non stock material and int labour. However i'm able to see the actual cost for all the items. I think I have missed some config. Please help.
    Regards,
    Abhishek

    Hi,
    As said by Pithan there is a problem in costing variant for planned cost which you have assigned to prder type at plant level.
    Problem underlies within valuation variant assigned to costing variant.PM01 is your costing variant here.Check diiferent heads within valuation variant for this costing variant.There under activities tab what is calculation parameter you have selected.If it is blank you will not get any internal activity cost.You need to select at least one from dropdown like cost from previous period or avaerage cost etc.Then you will get planned cost for internal activities.SAmething applies to non stock material.
    Check in OKP6 for all these and make sure that you have selected at least one cost calculation schema there for activities and material and external.
    Regds,
    atul

Maybe you are looking for

  • Work flow in 4.6c

    Dear all,                Is workflow sysytem is attached with the 4.6c version, If not is it possible to create with the help of abap in 4.6, Please tell me your suggestion Best Regards, Kumar

  • J6480 not printing to word 2007 or word 2003!

     Relatively new J6480 AIO will not print a word document from  Word 2007 or 2003 version. All other forms of documents from the office suite can be printed  i.e. Excel, power point, microsoft pub. etc. Even pdfs. Any suggestions?

  • Anyway to get Tiger for old iBook G4?

    I've just dusted off my old 2004, 10.3.9 iBook G4, reinstalled Panther from scratch and found it to be surprsingly serviceabe! I'm now wondering if there's any way to get the 10.4 upgrade to Tiger. How would I go about finding that in 2012?

  • ?my ADE is not recognizing the Nook HD+.

    I have authorized my HD+ with my email and number.  I attached the HD+ to my computer.  Then I opened ADE.  It still is not recognizing my nook.  What am I missing.

  • Node crashing on quitting

    Hi Folks Every time I quit Logic then quit the Node app on my Macbook Pro it crashes and I have to force quit anybody with the same problem? TTFN arrgh-let-me-login