How to extract Project Plan Cost

Hi SDNs,
I need extract the Project Plan Cost which we can display via t-code CN41N,which datasource can I use to do it?
Thanks a lot.
Best regards
Simon Liu

all the info you need :
http://help.sap.com/bp_bw370/BBLibrary/HTML/D11_EN_DE.htm (and click on configuratin guide)
M.

Similar Messages

  • Project Plan cost report - not showing any output.

    Dear Experts,
    I have created several projects and done the planning.  I have used work centers and activity types for manpower cost planning. Also created some PRs against the project.
    When I goto the network activities and select the line item in the menu path Edit - costs - Planned/Actual - cost planned /actual
    It shows me the planned cost of the activity correctly.
    But when I am running the report CJI4, it shows nothing. The report is not at all executing.
    I dont understand why it's \not showing.
    I have checked the control key PS01 for the cost field is enabled (tick available on the cost friled)
    Can any one please help me??
    Thanks and Regards,
    Praveen

    1) Please check that the WBS element is integrated in plan, and the plan integration is fully activated in the project.
    2) Plan line items are only written in certain cases.
    The following rules are valid:
    1. Plan line items can be written in
    a) structure-oriented cost planning CJ40 (total values, annual values),
    b) cost planning on orders KO12,
    c) unit costing independent of cost elements,
    d) structure-oriented revenue planning CJ42 (total values, annual values)
    e) structure-oriented financial budgeting CJ48 (total values, annual values, period values)
    f) primary cost planning,
    g) activity planning,
    h) revenue element planning.
    2. Plan line items are never written in
    a) Unit costing on cost element level
    b) Network costing
    3. Line items are only written if a user status permits the business transaction 'Write plan line items' explicitly.
    Exception:
    For plan-integrated WBS elements and orders, line items are written in cost-element oriented planning if integrated corporate planning is activated in the fiscal-year parameters of the respective plan version, regardless of the user status.
    4. Plan line items for structure-oriented planning can only be displayed in the respective planning transaction under menu option "Extras-->Line items".
    Let me know if this was useful
    Ritesh

  • Project plan cost

    Hi
    We are working with Project system and we trigger project from Sales order.
    We are using Assembly order for this purpose.
    When we are looking at plan cost of the project, cost is directly picked up from the material instead of referring to WBS BOM and production lot cost estimate.
    When we are creating project manually cost is picked up correctly from the WBS BOM.
    Do we need to do any special setting for cost when we are triggering project from the sales order??

    I think you might be using the Sales document as cost object in your configuration. For your requirement, you should use the Project as the cost object. Please check the account assignment category in the requirements class. It should be D (projects).
    Hope this helps.
    Regards,
    Ajinkya

  • How to Remove "Project Plan Template" from Project MSP client Enterprise tab / Project Server 2013

    Hello All,
    This should be easy one.
    I have created a "Project Plan Template" and applied to the EPT. Now i open my MSP Client 2013 and go to New--> Enterprise tab and select the template i want to use to create a new project. However, there are unnecessary Plan Templates which
    i want to remove from enterprise tab.
    Please Help. 
    sandeep

    Hi Sandeep, Go to PWA,server settings, delete enterprise objects. Then select the project combo box. You will see the list of all projects of your instance, with a column named "type". In this column you will find projects, sub projects, master
    projects and templates. Just sort along this type column, look for the templates, select the template to remove and click on the "delete" button.
    Hope this helps,
    Guillaume Rouyre, MBA, MVP, P-Seller |

  • Project Plans Costs not shown in CJI4

    Hi
    I have planned costs input in CJ40 against a WBS plan version "0" but when I run CJI4 no planned values are shown.
    However if I run S_ALR_87013532 I can see the planned costs, why does CJI4 not show the costs?
    thanks
    Joe

    Hi,
    CJI4 does not display plan cost eminated from CJ40.
    Even to display the plan costs in CJI4 you need to have user status to be maintained "write plan costs' activated at WBS element level and costs should be planned using CJR2.
    Just wanted to add here, S_ALR_87013532 is Hierarchy Cost Planning report - so you will see there.
    Thanks,
    Sudhakar

  • How to extract hyperion planning metadata to sql by ODI?

    I don't find any LKM for that. How to achieve it? I just wonder why Oracle doesn't provide it ?

    Hi,
    No you can't directly extract metadata from planning, this follows on from the HAL days where you couldn't do it either.
    It is possible to extract the dimension information from essbase which is nearly the same, it just needs a bit of transformation.
    I did write a couple of blogs covering this area, try [here |http://john-goodwin.blogspot.com/2008/12/odi-series-essbase-to-planning.html] and here
    Ok?
    Cheers
    John
    http://john-goodwin.blogspot.com/

  • Uploading capital planning/cost control/project delivery mgmt modules in Primavera Unifier 9.12

    Hello All,
    I have successfully installed Primavera Unifier R9.12 on my system. I had searched a lot but I didnt find any document which tells you how to upload capital planning/cost control/project delivery management module in Primavera Unifier R9.12. Can anyone pls share the steps or document.
    Thanks
    AKHIL

    HI Akhil,
    I'd love to help you in this area but i only know the product from a tech/install side of things.
    My functional colleagues had the exact same gripe that you have regarding sample data - unfortunately with the way Unifier is designed in regards to it being both customizable and difficult to delete/change some objects it doesn't quite lend itself to having sample data the way P6 does.
    Good luck playing/learning the tool
    Regards
    Alex

  • CN41N and S_ALR_87013533 report not showing Production order planned cost

    Hi Experts,
    I am having issue to get total planned production order values in my CN41N or S_ALR_87013533 cost report. I am facing 2 issues :
    1. CN41N repoet does not show individual material cost planned in BOM.
    2. CN41N report and S_ALR87013533 report does not show total value but only picking fixed value.
    Example :
    1. CN41N report :
    Above screenshot shows no values in Project plan cost & Order cost column but it shows total cost as a lumpsum on top for project. I need to know how can i get material cost populated here for Project Valuated stock material?
    2. S_ALR_87013533
    This report shows Total Cost of BOM as 1 line under Material Procurement activity similar to CN41N report. Also Order value is picking from Fixed cost from planned order and total cost is added on top. How can i get Total cost picked from production order?
    Is there any Setting in PS config which allow me to pick the detail production order plan cost in both report under planned cost.
    Thanks in advance.
    Ashish

    Hi Ashish,
    I doubt whether Item level reporting  in S_ALR... (hierarchy report) is possible or not because I haven't seen item level cost in them only the lump-sum cost because they are summarized at cost object level itself. Navigation path are there which we use to go into details of cost.
    Please check the following links:
    https://scn.sap.com/thread/1743833
    (In the above thread,focus on  Mr. Mohamed Rafi comment.)
    http://scn.sap.com/thread/3530080
    http://scn.sap.com/thread/1311820
    Order cost plan in report CN41N
    Display of plan cost., CN41N | ABAP, SAP, benX AG, benXBrain,&…
    Just an additional pointer ,have a look on your costing variant and variation variant settings for material section.
    Regards
    Saurabh

  • Planned Costs by Quarter

    Hi all, does anyone have any suggestions on how we could enter planned costs per quarter for a project? I see we can enter planned costs per monthly period per cost element but not per quarter. Preferably, I would not need to use cost element planning and could simply plan overall, yearly, or quarterly per project. Thanks for the advice.
    Shaun.

    Hi Shaun,
    Before going to implement cost planning, Pl. refer the following link of SAP Help on COST.
    [http://help.sap.com/saphelp_erp60_sp/helpdata/en/86/98853478616434e10000009b38f83b/frameset.htm]
    Once you get overall brief or clear idea of  different cost planning functionalities of SAP PS, based on the need of your project, you can go with cost planning : cost element Planning /Activity Type Planning / hierarchy cost planning(Overall/Yearly)/unit costing(Not relevent to period)/asynchronus network cost planning.
    And we have Std Cost element and Hierarchy reports to compare the Project's  Actual cost with Planned Cost.
    You can compare project cost in many ways like  WBS element wise, Value category wise,Period/Financial wise, Business Transaction wise and cost element wise.
    And also  compare project costs in different versions.
    Vemula

  • Distribution of planned cost of activity and its linked to PS cash flow

    Dear PS Gurus
    Kindly tell us how to distribute my planned cost (in result of internal,external activities ) should be equally distributed in the over planning period of activity (Say six months) and  also it should  have linked to my cash flow  also.so that by fund get adjusted .
    For Eg My activity A has planned cost 1,20,000 /-  which is going to complete in  6 Months  .Hence my planned cost should be distributed 20,000 / month and that should be reflects in cash flow.
    Regards
    Project Team 1

    Hi,
    You can distribute your planned costs at activity level based on the distributionkey you specified. The distribution is done for the entire duration of activity depending on the Dist key you select. If you do not put any Dist key, then the costs would be distributed equally across the entire duration of activity. If you want to have equal distribution of costs, you can use DK- SAP020 which distributes on earliest dates of activity using Factory calender. If you want you can also define your own DK in SPRO under: Production->capacity requirements planning->operations->capacity requirements->distribution.
    Hope this clarifies..
    Best regards..

  • Raw material planned cost and qty in table MCKALKW

    Hi,
    Raw material planned cost and quantity in table MCKALKW is not equal to cost analysis in CO01 / CO02.
    Could you please let me know how to get the planned cost and quantity for production order components for report development. i checked other tables like AFPO and AFKO and it is showing only for main material and not for its compoen

    Hi,
    You can check the cost of the individual components in Bill of materials of each material seperately. Hope this works for you.
    Thanks and regards,
    Murali krishna Maganti

  • Planned Cost WBS Element = which extractor

    Der all,
    i try to extract the planned cost for an WBS element.
    The extractor 0CO_OM_WBS_2 delivers no data and 0CO_OM_WBS_3 only a few.
    Am I using the correct extractors.
    I want to extract the same figures you can see in R/3 with transaction CJ41.
    Thanks for help !
    Marc

    Hi,
    Please try the 0CO_OM_WBS_1 extractor for WBS Element Costs (Plan). Data can be extracted using Currency Type = 00 (transaction Currency), 10 (CC Currency) and 20 (Controlling area currency).
    Refer to the below link for fields of origin in the extract Structure.
    http://help.sap.com/saphelp_nw04/helpdata/EN/dc/f8ab39bae14c67e10000000a114084/frameset.htm
    Thanks.

  • Planned cost for processing the component

    Hi All,
    How to see the planned cost for processing any component or finished product in SAP.
      I don't want actual cost for processing the component.
    Regards,
    Shailendra

    After releasing production order all primary and secondary costs get attached to the order.
    You can see planned cost in Tcode:CO02>>>>Goto>>>>>>>Costs>>>Analysis>>>under cost trend layput.
    Yogesh Thorat

  • PM Budget Vs Planned Costs

    Hi Freinds,
    Is there a way to map Budget Vs Planned Costs for a PM Order? We know by Tcode:KO22 we can assign budget to a PM order against the actual costs.
    Anybody can throw some light on how to map the planned costs against the Budget.I have checked in SPRO on internal order where
    1. Budget profile is created for PM Order
    2. Budget profile is assigned to PM order types.
    So other than the above i couldnt get anything more to map the planned costs.
    This is quite urgent. Please throw some light on this
    Regards,
    Selva

    Some additional information:
    - after creating another PR with a different cost element, the costs are still not visible
    - I'm purchasing a text material (no number) and i'm purchasing a service without a service master.
    no idea if this has to do with it, but maybe it will help you

  • Project plan Publish in stake holders

    Hi,
    How the approved project plan will be published to all the stake holders in SAP PS

    Hi,
    How the approved project plan will be published to all the stake holders in SAP PS

Maybe you are looking for

  • Is there anyone who can tell me how to post a form?

    Hi, I am totally new in Iphone Application. I start developing a simple iphone application in which I design a form that contains the following fields: username, password, and an image (.png). I want to submit these data into the server which will st

  • What airport works best for an extra large apartment?

    how do i get an airport product to work in a large apartment?

  • Shockwave crashes system in limited user account

    I am having a problem with shockwave content playing on my system. I have followed every single step in this article kb403082, except for formatting my system and reinstalling windows and shockwave alone (atomic bomb option). I couldn't do step 5 com

  • Adobe Reader/Professional or Browser

    Hi,      My application can open a pdf document, developed in ADOBE Livecycle Designer, either in ADOBE Reader/Acrobat Professional or a browser having the pdf plug-in installed. I need to capture the 2 scenarios in some way and do some operation bas

  • Premiere Pro CS5 Mac 10.6.5 not releasing memory

    I have a Mac Pro running 10.6.5 Mac OS, 16GB Ram that I just installed today (had 8GB).  I opened up a rather large 11 minute PPro project.  I rendered it out.  Noticed that the Used Memory was getting larger, up to about 10GB where it leveled off fo