Project Server 2010 - create a custom enterprise project field for persons (no text, no lookup table...)

I want to create a custom enterprise project field and would like to use instead of for example a text attribute or a look-up table a field for employees (e.g. project manager) which are coming e.g. from the Active Directory. But when creating this custom
project field I cannot see such an option. What solution do you suggest as I want to avoid that everybody uses different names and spellings for e.g. the project manager and without having to fill the lookup table with all resources of the company.
Thank you so much for your help!

Hi,
Are you using Proejct Server 2007, 2010, 2013?
In case you're working with 2010 version, here is an excellent
blog about how to insert a resource picker in a PDP (project detail page).
Hope this helps,
Guillaume Rouyre, MBA, MVP, P-Seller |

Similar Messages

  • Project Server 2010 - Build Team from Enterprise Greyed out

    I am trying to find out why the Enterprise Resources are greyed out when I try to build an Enterprise Team for a project?
    Starting from Project Server, I open a project in Project Pro.  Then go to Resource..Add Resources..Build Enterprise Team.  In the Build Team window, the Enterprise Resources are greyed out and I am unable to add them to be Project Resources.
    Any ideas?

    David --
    To add to the excellent replies from Guillaume, if you are a member of the Project Managers group, you should be able to add resources to your project team (the resources should not be grayed out in the Build Team dialog).  This is assuming, however,
    that your Project Server administrator has not edited the default permissions in the Project Managers group or in the My Organization and My Projects categories that are part of the Project Managers group.
    Assuming that your Project Server administrator has NOT modified the permissions in the default Project Managers group, the other action that can cause your problem is if you are members of MULTIPLE security Groups, and in at least one of those Groups, your
    Project Server administrator has set a Denied value on one, two, or all three of the permissions that Guillaume references in his first post.
    So, to echo what Guillaume has told you, your situation is most likely caused by a permissions issue.  That being the cause, your Project Server administrator would need to track down and resolve the source of this issue.  Hope this helps.
    Dale A. Howard [MVP]

  • Project Server 2010 - PDP updates not triggering Project Server Events

    Hello,
    We're experiencing an issue whereby when a user updates a Project PDP, no update is triggered and reflected in the reporting database.
    My question is, which Server Side Event Handler is responsible for picking up PDP changes (i.e. Changes to Enterprise Custom Fields)?
    Can someone please assist?
    Thanks in advance.
    What we have configured and is working as expected...
    Event: Reporting
    Event Name: ProjectChanged, ProjectCreated, ProjectDeleted

    There may be multiple reasons for this.
    1. SharePoint timer Job is malfunctioning:
    For this try restarting SharePoint timer Job. through SP Powershell:
    Stop SPTimerv4 , Start SPTimerv4
     2: SharePoint Cache is full:
    Reset SharePoint Cache by deleting all XML files ( except cache.ini
    )  in SharePoint Cache located in System Drive\ProgramData\Microsoft\SharePoint\Config\<GUID>
    3: Check if Microsoft Project Server Event Service is running in Services.msc, try restarting it.

  • Project Server 2010 cannot compile proxy assembly Project Server Services

    I am trying to compile Project Server Services dll by opening the source folder in the SDK and running compileWCFPRoxyAssembly.cmd. However, it fails to compile giving me error:
    'sn' is not recognized as an internal or external command,
    operable program or batch file.
    Microsoft (R) Visual C# 2008 Compiler version 3.5.30729.5420
    for Microsoft (R) .NET Framework version 3.5
    Copyright (C) Microsoft Corporation. All rights reserved.
    error CS1548: Cryptographic failure while signing assembly 'c:\Program Files
            (x86)\Microsoft SDKs\Project
            2010\Documentation\Intellisense\WCF\ProjectServerServices.dll' -- 'Error
            reading key file 'c:\Program Files (x86)\Microsoft SDKs\Project
            2010\Documentation\Intellisense\WCF\PsiKey.snk' -- The system cannot
            find the file specified. '
    Any suggestion what is missing?
     Or any suggestion for precise steps to be followed to compile the proxy assembly?

    Check this location which has the PSI.snk key C:\Program Files (x86)\Microsoft SDKs\Project 2010\Documentation\Intellisense\WSDL
    Copy the key file to the desired location and re run the proxy compilation
    However on a side note if you use the ProjectServerServices.dll in your project it has all the references precompiled for all WCF's all you would need is a reference and call any WCF you would want, i prefer this method over using individual files or
    references to services  
    Thanks | epmXperts | http://epmxperts.wordpress.com

  • Project Server 2010 - Find query size file project in database ProjectServer_Reporting

    Hello guys,
    Is there any way to find out * .mpp file size (MB, GB, KB) in database ProjectServer2010_Reporting?
    If there is a script ready and I thank you can share.
    Thank you.
    Obrigado por contactar o fórum Microsoft Technet!

    Hi Zeca Lima,
    there is no programmatic way that I know of....  you could save the file as an .mpp file and view the properties though.  The size will depend on whether you include enterprise custom fields in your .mpp file.
    Ben Howard [MVP] | web |
    blog | book |
    P2O

  • Project Server 2010 - Issue with correct recording of timesheet actual hours with decimals

    We have Project Server 2010 and are using the timesheet functionality for recording resource times/costs in the schedules.
    It has come to light only recently, that for one user, suddenly the times she is entering are not being summed up correctly. An image of her timesheet and the manage timesheet screens are shown below. Note she entered 9.5 hrs but the total that
    appears in the manage timesheet screen is 9.514hrs.
    If you look at the history of the previous weeks as well, the weird change toi the total hours has occurred in the previous 4 weeks as well.  I have no idea why this has started happening and am not aware of any change to the resource's details (apart
    from a change to her hourly rate).
    Has anyone experienced this before? 
    Thanks
    Peter

    We have this issue and are past the patch that discussed decimal rounding (April 2014, though it was more related to the application of resource rates).  This seems different from that noted rounding problem.
     We have at least three users (out of 625) that have this problem every week and it isn't always the same users.  If we re-enter the time and zero fill the cells for the problem task it will fix it. 
    It is almost like when a user deletes a value that it is leaving residual numbers in the field. 
    Our 2010 server version below which is through Sept 2014 CU:
    14.0.7132.5000 
    Any help on this would be appreciated.
    Thanks!

  • Create a Custom View in Project Server 2010 that is Visible in MS Project

    Hello All,
    We want our PMs to consistently report Physical % Complete, but couldn't find an existing "Status" or "EVM" view.  So, in Project Server 2010, using Server Settings > Look and Feel > Manage Views, I created a customized project
    view using existing fields (no customized fields, if that matters).  The problem is that I cannot find the view when I open MS Project.  Under Manage Views, in the Format View section, I have selected "Gantt Chart (Views)" for the Gantt
    Chart format field.  The view defaulted to "Timesheet" for the Grouping format field.  Under the Security Categories section, I have selected My Projects and My Tasks.  I have not applied a Filter.  Any ideas why I cannot find
    this new custom view in MS Project?  
    Was I supposed to create the new customized view directly in MS Project?  If so, where would I find the steps to do that?  Thank you!
    Julie

    Julie --
    Nice try, my friend.  Your only mistake was trying to create the Microsoft Project view in PWA.  You have to open the Enterprise Global for editing in Microsoft Project, and then create the custom view and table in the Enterprise Global. To
    open the Enterprise Global for editing, click File > Info > Manage Enterprise Global.  When you finish creating the custom view and table, then save, close, and check in the Enterprise Global file, and then exit Microsoft Project completely.
    The next time you or any of your PMs launch Microsoft Project and connect to Project Server, the custom view and table will be visible for every current and future project.  Hope this helps.
    Dale A. Howard [MVP]

  • Delete Enterprise Custom Fields in Project Server 2010

    Hello,
    We have Project Server 2010, SP2, in SEM mode. We recently removed some legacy unused Project Level enterprize custom fields from system, and observed that, the fields are not visible via PWA System Settings, but still see them in Project Pro, Project Information
    dialog and also available as a field that I can add it to a view.
    I have already tried following:
    - Clear the roaming profile (global.mpt) and exit out of Project Pro, and reconnect to Project Server... but still see those fields.
    Any ideas, why we see it, and is there any additional steps we need to perfome to remove from Project Pro?
    Please suggest.
    Regards,
    Kishore Dodda
    Kishore Dodda

    Hello,
    They should have removed automatically. I have seen this before and carried out these steps:
    http://pwmather.wordpress.com/2012/02/22/projectserver-2010-msproject-enterprise-global-custom-fields-out-of-synch-ps2010-ps2007/
    Fully backup the system before doing this and test on a DEV / Test system first.
    Paul
    Paul Mather | Twitter |
    http://pwmather.wordpress.com | CPS

  • Project Server 2010: PWA Removing Default Project Site Security Groups When Creating a New Project

    I looked for this specific issue with Project Server 2010/PWA/SharePoint and could not find an exact answer... hopefully someone can help.
    We are currently using Project Server 2010 and have a number of project site templates that are used dependent upon the enterprise project type selected. Each of these project site templates have unique permissions which should create the default security
    groups on the project site upon publishing/syncing:
    <Project Name> Members
    <Project Name> Owners
    <Project Name> Visitors
    <Project Name> Project Managers (Project Web App Synchronized)
    <Project Name> Team Members (Project Web App Synchronized)
    Web Administrators (Project Web App Synchronized)
    Whether a user creates a project through PWA or Project Pro 2010 and imports the project into PWA, we get a weird result in the Site Permissions of the newly created project site. PWA will remove all default security groups from the project site template
    and add a whole list of users in the Site Permissions list without groups. 
    Once the project is published and the project site is created, we can then go back and add those default security groups back in the project Site Permissions and even add a couple of custom groups without them being removed on all subsequent project syncs
    or publishing. 
    How do we get PWA to not overwrite the project site templates' security groups and place each user in the proper default security groups? At the same time, how is PWA adding a number of users into the Project Site Permissions?
    Thanks in advance.

    Paul,
    Thanks for that information. Right now we are using the Test environment to turn the Auto-sync feature back on. I suspect that the reason this is happening is due to PWA groups/categories/security templates. There may be more than one PWA group that is "overwriting"
    the default project site groups upon initial creation of the project. We will look further into the security settings to tighten up the policies. 

  • Project Server 2010 - Active Directory Enterprise Resource Pool Synchronization limitations

    Greetings again.
    I have a quick question about the limitations of Active Directory Enterprise Resource Pool Synchronization.  Specifically, what has your experience
    been with extremely large numbers of users (10k plus).  Is anyone aware of a
    practical limit of users in your AD group you would recommend when using the
    Schedule Synchronization feature on a nightly or weekly basis?
    There is a caveat to this question however.  The client has decided (perhaps for some misinformed reasons) to allow access for every user, to every
    project site, within their PWA environment.  They’ve selected the View Project Site option within the
    Categories for the Team Members PWA Group for which 90% of their intended users reside.  So when we ran a couple test syncs in DEV with a smaller AD group of about 8,000 users, the sync understandably
    lasted upwards of 18 hours.  Obviously unacceptable for a PROD environment on a nightly basis and not necessarily ideal for a weekly sync either.
    Experience in addition to documents like these, “Best
    practices for managing a large number of resources in Project Server 2010” tell me that we are way over the practical limit of a scheduled resource pool synchronization...IF
    the client really desires that all users access all their sites.  But before I submit my recommendations, I wanted to check with the community just in case others may have found a way to synchronize large numbers of users (10k plus) on a nightly or weekly
    basis, within a reasonable time frame AND allowed all users to access all sites within PWA.
    What do you think?
    As always, thanks for your help.
    Chris Addis - MCTS

    Hello Hrishi.
    My delayed response has been due to a large amount of testing we have been performing on this particular topic.  Here is an update, please feel free to provide feedback.
    We went back to testing and spent more time reviewing the documents: 
    Best practices for managing a large number of resources in Project Server 2010 and
    SharePoint Server 2010 capacity management: Software boundaries and limits.  Our team interpreted those documents as saying, 1,000 security
    scopes per site is a recommended limit.  It does not say it’s a hard limit, just a recommended limit.  “When the recommended unique security scope boundaries are exceeded, performance issue can occur.”
    So we decided to perform some tests (31 in total) to try and get a gage of what we are seeing.
    We needed to establish a baseline first.  So we performed a series of 23 Active Directory Resource Pool Synchronizations with various settings in a clean, Out of the Box, environment in order to see some consistent numbers.  Here is it’s summary:
    Our AD group of 8,000 users took about 32 minutes, on average, every time to sync.  The difference between the first sync and last sync differed only by 1-3 minutes.
    Adding 40 project sites increased the average sync time from 32 to 120 minutes.
    Adding 100 users to each of those 40 project sites, did not increase the sync times.
    One setting (identified at this time) reduced the synchronization time.  It was the
    Project Site Permissions check box found within the Project Web App > Server Settings > Project Site Provisioning Settings area.  By deselecting this check box we reduced or synchronization time back to the 32 minute
    average.
    The View Project Site check box within the Project Web App > Server Settings > Manage Groups > Team Members group had no apparent effect on the sync times besides what we had gleaned from the Microsoft documentation.
    Naturally, this left us with a problem.  As I’m sure you know, by deselecting the check box (Project Site Permissions), our project sites are now (figuratively speaking) orphans with no connection to the parent site.  This generates
    a new set of issues.  For example:
    Newly created project sites cannot be accessed by the owner and team members.  They will require someone like the farm admin to come in behind them and add the intended users to the project site along with their required permissions.
    All current and futures sites will no longer have users added via the standard method of building a team and publishing the project, but will have to be added manually.
    You can use the Synchronize option found within Project Web App > Server Settings > Project Sites page, but that kinda defeats the purpose.  It would require constant updating on a per site basis to keep up with
    PM changes.  Not very sensible, but it does work.
    With this baseline information, we moved our tests into our DEV environment which somewhat mimics our PROD environment.  This environment has 352 project sites and we performed 8 tests.  This is where we had some large sync time numbers. 
    Here is the DEV test summary:
    With the Project Site Permissions check box cleared, our AD group of 8,000 users took on average 30 minutes to sync.  This was in line with our baseline times.  With the exception of one test sync that took 99 minutes to complete. 
    That anomaly is acquiescent with what I’ve seen over the years.  Sometimes syncs do some unusual things.
    With the Project Site Permissions check box selected, our AD group of 8,000 users took on average 690 minutes (11.5 hours) to sync.  Unacceptable of course.
    So here’s what we’ve learned when dealing with extremely large numbers of active directory users in your Resource Pool sync:
    We did not see a decrease in subsequent sync times after the initial Active Directory Resource Pool Synchronization as some might expect.
    Our attempt to decrease sync time via the option of removing the View Project Sites was not successful.  (Unless we interpreted Microsoft's document incorrectly.)
    However, our interpretation of the recommended software boundaries and limits of SharePoint Server 2010 as it pertains to security scopes per site at 1,000, appears to be correct.
    Using the option of clearing the Project Site Permissions does produce a reduction in AD sync time, but at a cost segregating your project sites and thus the creation of new processes of maintaining them.
    I’ll remind others that these results are particular to our environments, there may still be exceptions yet to discover.  Others may see numbers contrary to ours.
    The biggest surprise to some members on our team (myself excluded) was that we did not see a reduced sync time after any of our initial syncs.  Some are under the impression that after your initial sync, you should see reduced sync times.  I haven’t
    found that to be the absolute case in all situations, just in some situations.  The reason for this still eludes me.  Any thoughts would be appreciated.
    I’ll let this sit a bit longer, but if no one disagrees with the results, I think we have our answer:
    The number of project sites directly affects your Active Directory Resource Pool Synchronizations if you are using the
    Project Site Permissions option.  If you plan on synchronizing over 1,000 users
    and you have a large number of project sites, proceed with the knowledge that you may have performance issues and long sync times.
    As always, I’d love to hear from you or others just in case I’m missing something.
    Chris Addis - MCTS

  • Create a defaut view for the MS Project Server 2010 client

    Dear Forum,
    how can I create a defaut view for the MS Project Server 2010 client?
    I saved a template and set a default view under File -> Options ->Project View. I also did the same in the checked-out enterprise global. If I then close the client and re-open it my default view changes back again to the previous one (not the view
    I set as a default view).
    What explains this behaviour and what can I do? Any hints?
    Thank you very much for your help!

    Scheduler007 --
    The view you selected by clicking File > Options > Project View is the default view for every new project you create from a blank project template.  This is a global option, so setting it from the checked out Enterprise Global file serves no purpose. 
    When you select a view as your default view, you will see that view applied to the blank project that is opened when you launch Microsoft Project 2010, and you will see it applied if you create new blank projects.  If you create enterprise templates for
    people to use in your organization, you should simply apply the view to the template that you want as the default so that users will see this view immediately when they create a new project from the template.  In addition, if you apply a view to an open
    project, close and check in the project, and then reopen the project, you will see the last view applied in that project (as Guillaume correctly points out).
    Beyond this, there is no method possible for the Project Server administrator to specify a default view for the Microsoft Project application used by the project managers in your organization.  This is an option each PM must set.  Hope this helps.
    Dale A. Howard [MVP]

  • How to find Project Level Text Custom Fields in Project Server 2010 databases?

    Hello,
    We are using Project Server 2010 SP2 in SEM Mode. We are planning to use Project Level Local Custom fields and we want to pull them in reports using SSRS, so I am wondering which table these "Local" (non enterprise) custom fields are stored in
    database.
    Any suggestions?
    Regards,
    Kishore Dodda
    Kishore Dodda

    Hi,
    Please see this
    similar thread about reading local custom fields though the PSI.
    Hope this helps,
    Guillaume Rouyre, MBA, MVP, P-Seller |

  • Issue in Custom Filter in PWA of Ms Project Server 2010

    Hi,
    i am facing an issue on setting a cutom filter in the Project Center view of PWA. I am setting a custom filter and it works fine.
    Projects are filtered as per the filter. However, on selecting the filter for editing, I get a message viz. "Failure. There was an error processing the request".
    I am looking for pointers and guidance to resolve this issue. Any helpin this regard will be appreciated.

    Hi,
    Evenif you already checked this out, it is likely to be a security issue. This functionality is managed by permissions in PWA server settings and not in the Central Admin.
    Check this article :
    http://msprojectnow.com/Blog/tabid/142/entryid/556/Enabling-Task-Sheet-functionality-to-Add-Yourself-to-a-Task-in-Project-Server-2010-PWA.aspx
    Check if you're not belonging to multiple categories that might have the given permission disabled.
    Hope this helps,
    Guillaume Rouyre, MBA, MCP, MCTS |

  • I want to break inheritence and create unique permissions in a Project Server 2010 project site list/library.

    Some Project Managers want to restrict permissions on certain lists or libraries in their Project Server 2010 project site. However, when I have done this for them, by breaking inheritence to the parent site and then removing/adding users with unique
    sharepoint permissions, it seems that when the project schedule is published, some of the newly created permissions are lost.
    I have tried creating a SharePoint group at the project site level and then applied it with specific permissions (eg. Contribute) to the list/library and this seems to work better but I haven't been able to confirm yet if this will work in the
    longer term.
    Does anyone know what is the best method to break inheritence and set up unique permissions on a list in a Project Server 2010 project site that will not be lost when the project schedule is published?
    Thanks
    Peter

    Thanks Lynda
    I am aware that I can disengage the entire permissions sychronisation using that setting but that is not what I want to do.  I just want to be able to break the inherited permissions on individual document libraries or lists on specific Project Sites
    so that I can restrict access to nominated people.
    My issue is that when I do this, I find that some of the amended permissions disappear from time to time.  It seems to be related to when the schedule is published.  They
    don't revert to the inherited permissions, just some of the people who I have given direct access to no longer have access.
    Im just trying to find out the best way to manage setting non-automated permissions on a single list or library in a Project Server project sites so the changes stick.
    Peter

  • Is it possible to create a formula that converts a resource hours into full time units in project server 2010

    Hi
    Is it possible to create a formula that converts a resource available hours into full time equivalent units in project server 2010? Say a resource has 160 available hours for any given month this will translate into 1 FTE for this month. If it is 80 hours
    for that month then it will be 0.5 FTE and so on and so forth.
    Thanks,
    -Maurizio

    Maurizio,
    It's a bit late, but there are two OLAP cubes that can provide you with this information in a pivot table in Project Server 2010.
    "MSP_Portfolio_Analyzer" and "Resource Timephased" contains capacity measures that be used to provide calculated measures when the cube database is generated. You change OLAP cube configuration in "Server Settings -> Database Administration -> OLAP
    Database Management". In either of the aforementioned cubes, use "Calculated Measures" to create two measures:
    Member Name
    MDX Expression
    Available (FTE)
    ([capacity]-[work])/[capacity]
    Work (FTE)
    [Work]/[Capacity]
    These two fields will appear in the pivot table field list as "Values", and when combined with a "Time" column, can give you a picture of FTE usage and availability.
    I prefer the portfolio version since it contains project/assignment data and resource data, letting you see just  how resources are being utilized.
    One thing I have not been able to get around is getting ""Maximum Units" for a resource factored into the measure. A common practice is to allocate more that "100%" to generic resources to represent teams for planning purposes. The OLAP measures will show
    only 0.0 to 1.0 FTE for any resource, even if a resource represents more than one body.
    If you have an SSRS query you could share, I would appreciated it!
    Hope this helps!
    JTC
    JAckson T. Cole, PMP, MCITP

Maybe you are looking for

  • Error while editing an automaticlly populated record of  a custom infotype

    hi, a query in HR ABAP. i have created a custom Infotype to store the CTC details of an employee. this custom IT needs to get the records auto populated, when they are created in Infotype 0008. i have used the exit. EXIT_SAPFP50M_002  inside which  a

  • Reducing the Text height in Adobe Forms

    I have a text field which I have included for the long text of me22n transaction in the context node of Adobe forms. In the form I want to adjust the maximum height of the text field using java script or any other way, as in I do not want to print th

  • Some software are not working properly,don't know why?

    I can't convert video files to mp3. I tried with different software;real player, format factory, etc. But every time pop up msg shows "RealConverter or format factory has stopped working. A problem caused the program to stop working correctly. Window

  • Startup Drive Permissions

    Can I use 'chmod 777' command on my startup drive? I noticed it fixed some access problems on my external drives. Now I'm having some trouble with applications being able to access certain files that normally work without me knowing. I also get some

  • Using Adobe CS4 on Windows side of new Imac: It keeps crashing..Help!!!

    Hello, I just bought a new 2009 Imac G5, 24in screen, desktop version, 3.06 GHZ Processor, 4 GB ram, 1TB of Storage. I used Boot Camp to split the hard drive down the middle (500 GB for each side) and I installed Windows XP service pack 3. My company