Proposed source of supply price showing  expired price in the cockpit

Hi All
I created a material contract .
Mat Master no - 34567  Condition 198 USD - 31.03.2010  TO 08.04.2010 and  208 USD  09.04.2010  TO 31.12.99999
on 9 th April 2010 . i go to cockpit and
when i propse a source of supply contract shows 198 usd instead of 208 USD in the sourcing cockpit. why ?
Proposed source of supply showing expired material price why ? it mislead the buyers to select the best vendor
Any thoughts
Muthu

Price(Contract/Bid)  4.50    USD    Per   1   each  2010.04.08  2010.04.09   
Price(Contract/Bid)  5.60    USD   Per   1   each  2010.04.10  2010.04.11   
Price(Contract/Bid)  5.67    USD   Per   1   each  2010.04.12  9999.12.31 
4.5  USD is showing as price - proposed sos FOR EX. IT IS EXPIRED PRICE FOR ME
but backend contract 5.67 showing and SRM showing as 5.67 .
SHOCKED . i follow your method.
i DELETED This item too..
Price(Contract/Bid) 4.50 USD Per 1 each 2010.04.08 2010.04.09
Price(Contract/Bid)  5.60    USD   Per   1   each  2010.04.10  2010.04.11   
Price(Contract/Bid)  5.67    USD   Per   1   each  2010.04.12  9999.12.31
cheapest price is 9.0 and contract wa sshowing 4.5 usd.  there is a problem and bad data was there still .
or still it points to old data only...i keep update you sap notes to you all
but indeed mislead the buyers.
still some thing wrong.
MIUTHU

Similar Messages

  • No valid source of supply could be found - while running the cost estimate

    Hi all,
    We are running the material cost estimate for a subcontracting material. The costing is giving an error saying "No valid source of supply could be found".
    We have checked
    1. Purchase info record
    2. Source list
    3. Valid dates are maintained for the condition records for the info record.
    Still we are getting the error.
    Can somebody help on this ?
    Thanks in advance
    Regards
    Karpagam Srinivasan

    Dear Karpagam,
    Please check these points,
    Are you sure you have created a Purchase Info Record in ME11 for a Sub-contratcing process?
    Sometimes you would have crated a standard Purchase Info Record.
    Maintain procurement type as F and special procurement value 30 in the MRP2 view of the material
    master for that material.
    As you have mentioned PIR,Source list already exists,please check this and come back.
    Regards
    Mangalraj.S

  • Proposed vs. assigned source of supply

    Hello Experts,
    I have the following scenario:
    We are using SRM 5.0, extended classic scenario and have a requirement in which a material without an SAP number is selected from a catalog (something similar to a 3rd party catalog).
    However, each material in this catalog have all the information needed such as price, vendor, description, etc.
    However, when this is sent to the shopping cart, the vendor is assigned as a proposed source of supply, instead of an assigned source of supply. Because of this, this requirement is sent to the Sourcing Cockpit, which we don't want to to, since all information needed is already there, and is should automatically create a Purchase Order.
    Is it possible to do this?
    If so, which BADI's should we use?
    Regards,
    Gilberto Gallardo

    Hi
    Using BBPDOC_CHANGE_BADI, we have done this several times._
    Also, we can go for BBPCATALOG_TRANSFER BADI..._
    Please go through the links below for more details ->
    Re: Automatic PO with preferred vendor
    Re: Convert preferred vendor to fixed vendor
    Missing Name in BBP_PD_SC_GETDETAIL
    Re: I cannot access "Supplier Catalogue no" in BBP_DOC_CHANGE_BADI
    Re: partner functions  for vendor master in SRM
    Re: Partner functions OA and IP missing for Vendor in Extended classic PO
    How to select Vendor information as per the line item of the shopping cart
    Hope this will defiinitely help. Do let me know.
    Regards
    -Atul

  • SRM 7 automatically assign source of supply in SOCO

    Hi guru,
    I'm working with SRM 7.0 extended classic scenario and i have to transfer external requirements from backend SAP into SRM Sourcing Cockpit. In the SOCO I have to determine automatically the source of supply and the price.
    I read that in the SOCo the sources relevant are:
    1. contract
    2. interlinkage
    3. vendor list ( there isn't information of price)
    Could you please explain me how it works this functionality, and the priority in the determination of supply and price?
    Have you documentation about ?
    Thank in advance
    L.

    Hello,
    If there is only one source of supply available (it does not matter if it is contract or info record), system will assign it automatically.
    If there is more than one, you can press "proposed sources of supply" button and SRM will show all available sources of supply.
    Price will be taken from sources of supply in any case.
    Regards,
    Ricardo

  • Addition of New column to Vendor Overview on Shopping cart Source of supply

    Hi All,
    I have a requirement where I need to display Contract description,price in Vendor overview table of Shopping cart Source of Supply.
    Currently I can see the  Name ,Vendor , Contract  Item,  Pur.Info Record, In Vendor List  , but I also have to show the Contract Description and Price..
    Can anyone suggest how to handle this.
    Thanks in Advance.
    Neelima

    Hi Neelima,
    Please investigate the use of customer fields for meeting this requirement.
    Regards
    Azad

  • What is the significance of Interlinkage as Source of Supply in SRM ?

    Dear all,
    When we send across a external requirement to SRM, then  during the creation of shopping cart, it tries to determine a unique source of supply. It searches for available contracts , interlinkages and vendor lists.
    My question is what is meaning of interlinakge? This has the details of Vendor + Product + Price.
    Is this same as Purchasing Info record?
    How is an interlinkage created in SRM?
    Please provide links or clarification on significance of interlinakge.
    Useful note for reference is 521458.
    Many thanks in advance.
    Best regards,
    Srivatsa

    Yes. you are correct
    An interlinkage is a relationship in SAP SRM between a vendor and a product
    used to specify a price. but note is very pld ..
    It is also one of the source of supplies  in SRM like contract , vendor list , inforecord.
    in sc cockpit propose source of supply and you may get interlinkage if you maintained.
    br
    muthu

  • Sources of supply giving wrong results.

    Dear experts,
    We are using SRM 4.0 ,server 500.
    When creating a shopping cart, and checking the proposed sources of supply for a particular product, we get a list of more than 20 contracts. (correct)
    When we directly want to create a PO we only get 6 contracts for the same product? Does anybody know what can be the reason for this behavior?
    Kind Regards,
    Tom

    Tom,
    A few things to check:
    1. Is the config setting to control the source list via AVL maintained?
    2. If not then all the contracts for that material or product category will show up in the shopping cart as the source list.
    3. Have all the contracts (GOA ) created in SRM exists in R/3 or you do not have any contarcts in SRM at all.
    4. In this case have you mainatined any AVLs with backend contracts.
    Hope this helps.
    Regards
    Satish Bengeri

  • PO - contract as source of supply

    Hi,
    I am facing a problem while assigning a contract as source of supply to a PO item.
    The contract is released and is available as source of supply. Once I enter the contract id and the contract item id in the PO item, the details like price, tax code etc get copied but the vendor does not get copied. I seems weird to me.
    Could someone please help with this?
    Thanks & Regards
    Saravanan.

    Hello,
    Please check and apply  SAP Note No. 710129.
    Also if some other informaiton is missing please use BBP_DOC_CHANGE_BADI.
    I hope this will help.
    Kind regards,
    Gaurav
    PLEASE REWARD FULL POINTS FOR USEFUL REPLIES

  • Proposed souce of supply not picked up in SRM

    Hi All,
    My requirement is I Created GOA in SRM. In R/3 I created PR wrt GOA. I transferred PR to SRM.  While doing carry out sourcing, it is not showing the proposed source of supply.
    What settings do I need to check?
    Best Regards
    Lovkesh

    Hi Lovkesh,
    Please see the link below
    http://help.sap.com/saphelp_srm50/helpdata/en/43/15a4e228b62d23e10000000a1553f7/frameset.htm
    Sourcing Criteria
    During the Sourcing operation, the system checks the requirement for the validity of specific sourcing criteria.
    ·        Primary criteria
    The system checks automatically whether the criteria in the contract match those in the requirement. Sources of supply without matching primary criteria are not proposed for assignment. In the standard the following criteria are relevant.
    ¡        The product must be identical in the requirement and the contract.
    ¡        The product category must be identical in the requirement and the contract.
    ¡        The vendor must be identical in the requirement and the contract.
    ¡        Procurement takes place for the same company with which the contract exists.
    ¡        The purchasing organization responsible for the requirement is authorized to use the contract.
    ¡        The location specified in the requirement is release-authorized for the contract.
    ¡        The goods recipient has not been deleted and has not been excluded from a goods delivery for this contract.
    For more information on excluding goods recipients in contracts, see Processing Contracts.
    ·        Secondary sourcing criteria
    These are additional customer-specific criteria that you can define for your company. You can only apply secondary criteria to contracts that fulfill the primary criteria. However, you can manually select sources of supply that do not fulfill all the secondary criteria. You can display to what extent the source of supply does not match the criteria.
    regards,nishant
    please reward if this helps

  • Assigning a source of supply in sourcing cockpit not working.

    Good day Gurus,
    When we assign a source of supply in sourcing cockpit we get the following error : Invalid combination of sources of
    supply for item 1200012571/1
    This is how we got the error.
    Create a shopping cart and approve it.
    Go to sourcing cockpit and in the comntract column enter the contract number and in the contract item enter the contracts item number,when click enter we get the error as indicated below.
    Please assist,Your help is very much appreciated.
    kind regards,
    Lethabo Kgatla

    HI Anamika,
    I created a free text shopping cart and wanted to propose the source of supply without using the propose source of supply button and got the error.The functionality did work previously and does not work anymore.I am trying to find how can be resolved.
    Regards,
    Lethabo

  • Report to redetermine SNP Source of supply

    We configured Planned Order integration model to show up R/3 planned orders as SNP Planned orders in APO. However when the planners on R/3 side intervene the orders in terms of some of the fields, it passes on to APO as a planned order without source of supply. This is due to the design, the PPM information is manually maintained in APO and is out of sync with the information in R/3 side. The system thus chooses to keep a blank source of supply for the orders rather than redetermining the source of supply in APO. From some of my recollections, I understand that there are ways to run a report in APO that redetermines source of supply for planned orders with blank source. Can someone pass on this report information to me ? (We do not want to run user exits/BADIs to do this determination, and rather would prefer a standard report)

    It is by design that PPM is not synced. There are tens of resources in R/3 side which we have summarized and kept as a "aggregate" resource data in APO manually. So there is no point in deleting APO orders and re-CIFing. It is by design that the orders come into APO without source of supply. Some of these orders are NOT solver dependent and is manully managed by planners in R/3 side. So we do not want to run the solver to change that data. We just want the PPM to be picked up in APO so that we can correctly load the resources.
    If anyone has a Z program for this, it will be great if it can shared.

  • Source of supply doesnu2019t work for SC items ordered as direct material.

    Hi there.
    We are working in SRM 5.0 with classic scenario.
    We are doing a SC with material code.
    We create a SC with two identical items. The only difference between items is: one item is order as direct material and the other one not.
    The problem is that for our item order as direct material, the system doesnu2019t propose any ECC contract or any ECC info record. But for our item not order as direct material, the system propose us ECC contract and ECC info record.
    So for SC items orders as direct material, the system never proposes any source of supply.
    However, in transaction BBPSOCO01 (Carry of sourcing) the systems propose source of supply OK for SC items with and without direct material.
    Any suggest?
    Thanks and regards.
    Raúl.

    Hi,
    The issue might be because when you choose, 'order as direct', the scenario changes from classic to extended classic, hence only local contracts are proposed in this case. Since you don't have anything local, you will not see any source of supply. Try using bbp_sos_badi instead and call all backend contracts using fm meta_sourcedeter_getsos_multi.
    Regards,
    Sanjeev

  • Source of Supply Error?

    Hi,
    I am currently experiencing the following problem: (We are running SRM 5)
    I replicate vendors from the R/3 system to SRM via BBPGETVD trans code.
    I select the correct Object ID (for the Vendor Org structure I created in PPOCV_BBP)
    I check that the Vendors have been replicated (They appear in Vendor Org structure – PPOMV_BBP)
    BUT these newly replicated Vendors do not appear in the Source of Supplier when I try to assign them when creating a Shopping Cart?? It’s strange cos the previous batch of vendors I replicated worked fine and appear in the Source of Supply??
    I’ve also run the business partner check transaction: BBP_BP_OM_INTEGRATE and checked that the Org units are synchronized. I have green lights for everything.
    I’ve checked that the replicated vendor is mapped to the correct Purchasing Org, Manually in the Frontend (with Admin user via “Manage Business Partners”) and
    via the Backend with trans code BBP_UPDATE PORG. The vendor is assigned to the correct Purch Org.
    What am I missing here? Any help would be appreciated.
    Regards,
    Shayne

    Hi
    Note 901497 Industry-specific fields not changeable in the quotation 
    Note 902719 Implementation of interface method in Novation Class 
    Note 833098 Tabular customer fields in quotation increased entries
    Note 822424 CUF. Customer fields cannot be changed in the bid
    Note 809630 - Customer field in bid invitation and bid - How does it work?
    Hope this will definitely help.
    Do let me know, incase you need any other details.
    Regards
    - Atul
    Hi
    <u>Please go through the following SAP OSS Notes, which will help -></u>
    Note 1030627 - Source of supply not found for service items
    Note 1051985 - Proposed source of supply new vendor address doesn't update
    Note 1062273 - Source of supply not listed completely in classic scenario
    Note 1024423 - Source of supply not found for service items in shopping cart
    Note 1039542 - Source of supply from catalog reset on change of location
    Note 1039945 - Source of supply list is not refreshed
    Note 1043176 - Source of Supply Selection not shown from Purchaser inbox
    Note 1003666 - Determining the source of supply takes a long time
    Note  988252
    <b>Other Related Notes</b>
    Note 1006929 - Performance improvement while fetching source of supply
    Note 927077 - Error during the automatic assignment of a source of supply
    Note 905894 - Performance improvement in Sourcing
    Note 991898 - Source of supply not reset when product type changes
    Note 931757 - Source of Supply not copied correctly
    Note 881695 - Source of supply with item changes
    <u>Some other related SAP links -></u>
    Re: Vendor exists in R3 but BBPGETVD could not find it ?
    Create SC using >BBPSC03 in SAP GUI
    Source of supply problem
    Source of Supply
    Re: Source of Supply problem
    SC does not determine source of supply if Source List maintianed in R/3
    Source of supply in shopping cart
    Re: Source of Supply problem
    Sources of supply in SC not visible
    Contract Source of Supply Not Populating in SC
    Do let me know.
    Regards
    - Atul

  • Backend system used to fetch sources of supply in classic scenario?

    Dear Experts,
    In sourcing for shopping cart in classic scenaro, the proposing sources of supply fetches possibles sources like contract, info record from local system as well as backend systems. If there are number of backend systems, which system is used to fetch the probable contracts and info-record as source of supply?
    Is it the source system for the product category used in the shopping cart? or is there any settings defined in the org structres of the user attributes?
    Thanks and regards,
    Ranjan

    You could try to set a Breakpoint at FM BBP_PDC_SRC_DETERMINE  or inside META_sOS_determine.
    as KGP said you will get inforecord and contract are valid source of supply
    We call the backend system in the plugin function B46B_SOURCEDETER_GETSOS_MULTI at the line:
    Get sources of supply from backend system for all items
      CALL FUNCTION 'BBP_SOURCEDETER_GETSOS_MULTI'
        DESTINATION lv_destination
        EXPORTING
          iv_find_contract      = iv_find_contract
          iv_find_inforecord    = iv_find_inforecord
          iv_read_price         = iv_read_price
        TABLES
          it_search_criteria    = lt_sos_find_be
          et_found_contracts    = lt_found_contracts
          et_found_inforecords  = lt_found_inforecords
          et_return             = ct_return
        EXCEPTIONS
          communication_failure = 1  MESSAGE lv_msg_text
          system_failure        = 2  MESSAGE lv_msg_text
          OTHERS                = 3.
    Muthu

  • Assign Source of Supply - Inforecord

    Hello guys!
    Do you know if can be possible to assign a source of supply at a Purchase Requisition but where the inforecord isn´t brought too?
    Is there any IMG activity where i can customize this?
    Now, if an inforecord exists for a certain vendor-material and i press "Assign Source of Supply" button, this inforecord is always showed.
    Thank you very much for your help.
    Regards,
    cecil

    Hello,
    Please maintain source list .
    You define source list requirements at plant level. If a source list requirement exists, you must maintain the source list for each material before you can order it.
    The source list serves:
    To define a source of supply as "fixed". Such sources count as preferred sources over a certain period of time. For example, the fixed vendor XXXX for material 100XX is ASA Company for the first quarter and BSB Co. for the second quarter of the year.
    Select the plants for which you wish to specify a source list requirement
    You use the source list to determine the valid source of supply at a certain point in time.
    The source list contains all the sources of supply defined for a material and the periods during which procurement from these sources is possible
    Following T/Code activities in Material Management module.
    Maintain source list  -  ME01
    Display source list  -  ME03
    Display changes to source list -  ME04
    Analyze source list  -  ME06
    Reorganize source list  -  ME07
    Generate source list  -  ME05
    Display source list for material-  ME0M
    you make the system settings that are necessary for purchasing operations carried out using source lists.
    Source list requirement for materials, It may be necessary to include possible vendors of a material in the source list before the material can be ordered.
    The Source list requirement field in the purchasing data of the material master record indicates whether a source list requirement exists for a material.
    You can define the Source list requirement at plant level in IMG.  Logistics -->Materials management --> Purchasing --> Source list.
    Here you can see the plants for which a source list requirement exists.
    Reward if useful
    Kedar Kulkarni