PS for Milestone Billing

Our company supply materials to construction company. The periodic billing is configured as of now. If a new project starts the material is dispatched in phases.
In order to distribute the cost over project, the Milestone billing feature would help.
But slightly confused regarding linkage of  milestone biling with Prohject system module. Do each and every project is to be created in PS for using this functionality. Or have to configure only mile stone billing in SD.
Kindly help.
thanks

Hi Anya,
Please refer the link below
http://help.sap.com/saphelp_47x200/helpdata/en/dd/5606b5545a11d1a7020000e829fd11/frameset.htm
Regards
Tushar

Similar Messages

  • What settings are required for Milestone Billing ?

    Please explain in detail what all settings are required in order to do milestone billing ?
    Regards,
    Gobind.

    Hi
    Milestone Billing.
    1. Create New Sales Order Type, say ZOR (Copy of OR) through T.Code: VOV8
    Maintain Delivery Type as LF & Billing Type As 'F1' - Order Related / 'F2' Delivery Related.
    IMG > Sales and Distribution > Sales > Sales Documents > Sales Document Header > Define Sales Documents Types
    2. Assign New Sales Document Type to Sales Area, For Eg:
    1000 (S.Org) / 10 (D.Channel) / 10 (Division) / ZOR (S.O Type)
    IMG > Sales and Distribution > Sales > Sales Documents > Sales Document Header > Assign Sales Area to Sales Document Type
    3. Create New Item Category, say ZTAN - Copy of TAN (For delivery Related) / ZTAD - Copy of TAD (For Order realted) / ZTAS - copy of TAS (For Third Party)
    Maintain as under (others remaining same)
    Billing Relevance: I
    Billing Plan Type: 01
    IMG > Sales and Distribution > Sales > Sales Documents > Sales Document Item > Define Item Category
    4. Assign Item Category, for ex (assuming Usage & higher level item category as blank):
    Sales Document Type | Item Category Group | Default Item Category
    ZOR | NORM | ZTAN
    ZOR | DEIN | ZTAD
    ZOR | BANS | ZTAS
    IMG > Sales and Distribution > Sales > Sales Documents > Sales Document Item > Assign Item Category
    Note: In the above Billing Type '01' plays the main controller for milestone billing. In Sales order, at item level, we require to maintain the billing plan.
    Follow the Sales cycle as normal sales cycle for particular Scenarios
    Also Refer:
    https://www.sdn.sap.com/irj/scn/wiki?path=/display/erplo/milestone+billing.

  • Error while creating Credit Memo Request for Milestone billing invoice

    Hi All,
    I have a scenario where i have Milestone billing(% based) at header level in Contracts. I create Invoice for that and then try to create Credit Memo Request with reference to the Invoice.
    Problem comes when we try to change the qty in the credit memo request. we are able to change the qty but the value is not changing. It remains the same constant value of that milestone.
    In my copy control from Invoice to Credit memo request for the item category i have maintained the pricing type as "C" because i want to copy and manual conditions.
    So kindly let me know which config setting should be done so that whenever i change the qty the value should also be changed.
    Please Note : This is happening only when my billing plan is at header level. For Billing plan at Item level its working fine.....
    Thanks.....

    Hiiii.....
    Can anyone please advise on the below issue of mine.....
    Thanks alot for the help.......in advance

  • WBS element field in SO for milestone billing

    Hi,
    I am using Milestone billing. When I am trying to create the Sales order the WBS element field is greyed out. Pleae advise.
    Regards,
    Santanu

    Hi Shantanu,
    I think you need to remove the assignment of the requirement type KE from your item category. I gues you are using TAO as the item category for Milestone.
    You go to Sales and DistributionBasic FunctionsAvailability Check and Transfer of RequirementsTransfer of RequirementsDetermination Of Requirement Types Using Transaction.
    Hope it helps.
    Shivaji.
    Edited by: Shivaji  Paul  Choudhury on Mar 2, 2009 4:21 PM

  • WBS assigment for Milestone Billing

    Hi,
    I am assigning milestones to the activities in my project.
    I need a particular WBS to be assigned to only one Sales Order. The system is allowing me to assign the same WBS to another Sales Order also. Therefore copies all the milestones to the new sales order and allows me to do the milestone billing for same WBS again. [Twice]
    Is there any way to restrict the same WBS being assigned to several Sales Orders and avoid billing for the same WBS again and again.
    Please suggest.
    Thanks & Regards,
    Kabir

    U check with SD consultant as suggested by Mrinal.....It is also possible to restrict the assignment using user status...but this has to be done manually...once the user assign the WBS to sales order, he can select an user status manually which restricts the business transaction "Create Sales document"...this will not allow you to assign WBS to new sales order...but this is manual process.

  • Excise Invoice for Milestone billing

    We have configured mile stone billing.
    30% - Downpayment
    40% - Delivery
    30%- Closing invoice.
    Currently system is calculating excise and taxes at each step (CST & VAT)
    Our problem is how to creat single excise invoice at delivery time ( excise should be calculated on PR00 basic price in sales order at delivery against billing)
    Regards
    Sachin Kadam

    Our MTO Process is as below
    VA21 -  Quotation
    VA01 - Sales order wrt to quotation
    VF04 - Create invoice, print down payment request and send to customer
    F-29 -Post customer down payment
    Production process ---> Sales order stock is available.
    VL01N - Delivery
    VA02 - Delete billing blocks
    VF04 - Create invoice, print payment request and send to customer
    F-28 - Post milestone invoice
    Billing plan deatails as below
    19.01.2010     0009          Down payment     30.00     573.89      INR
    18.02.2010     YB01          Delivery                          40.00     765.18      INR     02
    20.03.2010     0008          Closing Invoi                                   1,147.77      INR     02
    Regards
    Sachin

  • Milestone Billing  for third party order process

    hai Gurus
                 Pls help me in understanding of milestone billing with example.
                 Is it possible to link the milestone billing for Thirdparty order process?
                 pls send me documents to my Id [email protected]
    I will reward points for the helpfull answers
    Regards
    SaravananS
    Message was edited by:
            Saravanan Sevuga perumal

    Hello Saravanan,
    Milestone billing means distributing the total amount to be billed over multiple billing
    dates in the billing plan.
    As each milestone is successfully reached, the customer is billed either a percentage of
    the entire project cost or simply a pre-defined amount.
    During sales order processing, the system determines from the item category whether a
    billing plan is required and, if so, which type of plan
    The type of billing plan that is determined at this point is set up in Customizing and
    cannot be changed in the sales document.
    Billing plans for periodic billing and milestone billing plans for project-related milestone
    billing have different overview screens so that you can enter data relevant to your
    processing.
    For example, for milestone billing, you must be able to enter data to identify the
    individual milestones.
    IMG configuration requires :-
    1.  Maintain billing plan types for milestone billing in OVBO.
    2.  Define date description in SM30 - V_TVTB.
    3.  Maintain Date Category for Billing Plan Type IN OVBJ.
    4.  Allocate date category in SM30 - V_TFPLA_TY.
    5.  Maintain date proposal for Billing Plan Type in OVBM.
    6.  Assign Billing Plan Type to Sales Documents Type in OVBP.
    7.  Assign Billing Plan Type to Item Categories in OVBR.
    8.  Define rules for determining the date in OVBS.
    Milestone billing is typically used for billing projects, such as plant engineering and
    construction projects. Such projects often include a series of milestones that mark the
    completion of different stages of the work. In the SAP R/3 System, milestones are defined
    in a network along with planned and actual dates for the completion of work. The milestones
    are also assigned to the billing dates in the billing plan.
    Each milestone-related billing date is blocked for processing until the Project System
    confirms that the milestone is completed.
    Delivery-relevant order items for which a milestone billing plan applies are billed on the
    basis of the requested delivery quantity and not on the total of the confirmed quantities.
    The connection between the project and the sales document item is made in the individual
    schedule lines of the item. Each schedule item can be assigned to a network in a project.
    To display the project-related data for a schedule line, proceed as follows:
    In one of the overview screens of the sales document, select
    1.  Item -> Schedule lines.
    2.  Mark the schedule line and select Procurement details.
    The following figure shows an example of milestone billing where only the Contract have
    been billed :
    Order  Item  Turbine    100,000
    Billing Plan
    Billing date Description    %  Value  Billing Block   Milestone   Billing Status
    01-10-94     Contract      10  10,000      -             x           x 
    01-03-95     Assembly      30  30,000      x             x          
    01-04-95     Maintenance   30  30,000      x             x
    01-05-95     Acceptance    30  30,000      x             x
    01-06-95     Final invoice ..    ..        x
    Network/Activities
    Milestone    Estimate      Actual
    Assembly     01-03-95      01-03-95
    Maintenance  01-04-95     
    Acceptance   01-05-95
    For each billing date in a milestone billing plan, you can specify whether the billing
    date is:
    1.  fixed
    2.  always updated with the actual date of the milestone
    3.  updated with the actual date of the milestone, if the date is earlier than the
        planned billing date for the date
    <b>**REWARD IF THIS HELPS**</b>
    Regards
    AK

  • Updation of Milestone Billing % in Sales Order

    Hi All,
    I am using Assembly Processing scenario and having milestone billing. I am able to create a sales order which creating project automatically and milestone are coping in sales order billing plan.
    My query is : after creating sales order and automatic creation of project, client changes % amount in billing milestone which is not updating in sales order. Its showing the same amount which has been put in standard milestone.
    Let me know how I can update this change in Sales Order billing plan when ever I change billing % in milestone.
    Regards,
    Atul R. Rajmane

    Hi,
    After Maintaining billing plan types for milestone billing,Please check the following,
    In CJ20N , Create milstone under the activity of WBS,Fill the invoicing percentage in Billing plan section, be sure to tick on sales document date field, then go to the sales order it will copy the data automatically from the milstone .

  • Milestone billing not splitting the invoice

    Hi,
    i specified Milestone Billing during a Sales Order but when i try to bill the customer using transaction VF01,
    it bills the whole amount of the Sales Order even though i specified only 25% to be billed.
    For example, i created a Sales Order with net amount $100, and specified in the Billing Plan for it
    to invoice the customer 25%  today.  But when i do simulate the billing using transaction VF04, it
    shows the invoiced amount as $100 instead of $25. 
    Can anyone help?
    Thanks in advance.

    Hi SHAMBHU SARKAR,
    I got milestone billing to work by specifying billing type F2 under the 'Billing plan'  tab in transaction VA02.
    Also make sure that your 'Date Category' in the 'Billing plan' tab is set to 01 for milestone billing.
    Otherwise,  go to SPRO -> Sales and Distribution -> Billing -> Billing Plan ->....  to check that your settings are correct and that
    you have assigned a Billing Plan to either your Sales Document Type or your Item Category depending
    on whether you want to use milestone billing at header level or line item level.
    Hope this helps.
    Good luck!

  • Milestone billing & Periodic Billing

    Can anybody give me the complete configurationpart of Milestone billing & Periodic Billing.If with screen shots I will be highly obliged.

    Milestone Billing.
    1. Create New Sales Order Type, say ZOR (Copy of OR) through T.Code: VOV8
    Maintain Delivery Type as LF & Billing Type As 'F1' - Order Related / 'F2' Delivery Related.
    IMG > Sales and Distribution > Sales > Sales Documents > Sales Document Header > Define Sales Documents Types
    2. Assign New Sales Document Type to Sales Area, For Eg:
    1000 (S.Org) / 10 (D.Channel) / 10 (Division) / ZOR (S.O Type)
    IMG > Sales and Distribution > Sales > Sales Documents > Sales Document Header > Assign Sales Area to Sales Document Type
    3. Create New Item Category, say ZTAN - Copy of TAN (For delivery Related) / ZTAD - Copy of TAD (For Order realted) / ZTAS - copy of TAS (For Third Party)
    Maintain as under (others remaining same)
    Billing Relevance: I
    Billing Plan Type: 01
    IMG > Sales and Distribution > Sales > Sales Documents > Sales Document Item > Define Item Category
    4. Assign Item Category, for ex (assuming Usage & higher level item category as blank):
    Sales Document Type | Item Category Group | Default Item Category
    ZOR | NORM | ZTAN
    ZOR | DEIN | ZTAD
    ZOR | BANS | ZTAS
    IMG > Sales and Distribution > Sales > Sales Documents > Sales Document Item > Assign Item Category
    Note: In the above Billing Type '01' plays the main controller for milestone billing. In Sales order, at item level, we require to maintain the billing plan.
    Follow the Sales cycle as normal sales cycle for particular Scenarios
    Periodic Billing.
    1. Create New Sales Order Type, say ZOR (Copy of OR) through T.Code: VOV8
    Maintain Delivery Type as LF & Billing Type As 'F1' - Order Related / 'F2' Delivery Related.
    IMG > Sales and Distribution > Sales > Sales Documents > Sales Document Header > Define Sales Documents Types
    2. Assign New Sales Document Type to Sales Area, For Eg:
    1000 (S.Org) / 10 (D.Channel) / 10 (Division) / ZOR (S.O Type)
    IMG > Sales and Distribution > Sales > Sales Documents > Sales Document Header > Assign Sales Area to Sales Document Type
    3. Create New Item Category, say ZTAN - Copy of TAN (For delivery Related) / ZTAD - Copy of TAD (For Order realted) / ZTAS - copy of TAS (For Third Party)
    Maintain as under (others remaining same)
    Billing Relevance: I
    Billing Plan Type: 02
    IMG > Sales and Distribution > Sales > Sales Documents > Sales Document Item > Define Item Category
    4. Assign Item Category, for ex (assuming Usage & higher level item category as blank):
    Sales Document Type | Item Category Group | Default Item Category
    ZOR | NORM | ZTAN
    ZOR | DEIN | ZTAD
    ZOR | BANS | ZTAS
    IMG > Sales and Distribution > Sales > Sales Documents > Sales Document Item > Assign Item Category
    Note: In the above Billing Type '02' plays the main controller for periodic billing. In Sales order, at item level, we require to maintain the billing plan.
    Follow the Sales cycle as normal sales cycle for particular Scenarios
    Regards,
    Rajesh Banka

  • Configuration of Milestone billing / Periodic Billing

    Dear Gurus,
    I am now on the verge of completing study of SD module.
    Request to please explain the configuration of Milestone and Periodic billing.
    I am referring book (SAP - SCM 615). I think many topices are metioned with very limited / no explanation.
    Thank you very much in advance.
    Regards,
    Ashish

    Hi Ashish
    All the best for your certification exam
    https://www.sdn.sap.com/irj/scn/wiki?path=/display/erplo/milestone+billing.
    Milestone Billing.
    1. Create New Sales Order Type, say ZOR (Copy of OR) through T.Code: VOV8
    Maintain Delivery Type as LF & Billing Type As 'F1' - Order Related / 'F2' Delivery Related.
    IMG > Sales and Distribution > Sales > Sales Documents > Sales Document Header > Define Sales Documents Types
    2. Assign New Sales Document Type to Sales Area, For Eg:
    1000 (S.Org) / 10 (D.Channel) / 10 (Division) / ZOR (S.O Type)
    IMG > Sales and Distribution > Sales > Sales Documents > Sales Document Header > Assign Sales Area to Sales Document Type
    3. Create New Item Category, say ZTAN - Copy of TAN (For delivery Related) / ZTAD - Copy of TAD (For Order realted) / ZTAS - copy of TAS (For Third Party)
    Maintain as under (others remaining same)
    Billing Relevance: I
    Billing Plan Type: 01
    IMG > Sales and Distribution > Sales > Sales Documents > Sales Document Item > Define Item Category
    4. Assign Item Category, for ex (assuming Usage & higher level item category as blank):
    Sales Document Type | Item Category Group | Default Item Category
    ZOR | NORM | ZTAN
    ZOR | DEIN | ZTAD
    ZOR | BANS | ZTAS
    IMG > Sales and Distribution > Sales > Sales Documents > Sales Document Item > Assign Item Category
    Note: In the above Billing Type '01' plays the main controller for milestone billing. In Sales order, at item level, we require to maintain the billing plan.
    Follow the Sales cycle as normal sales cycle for particular Scenarios
    https://www.sdn.sap.com/irj/scn/wiki?path=/display/erplo/periodicBillingConfiguration
    Periodic Billing Configuration:
    1. Create New Sales Order Type, say ZOR (Copy of OR) through T.Code: VOV8
    Maintain Delivery Type as LF & Billing Type As 'F1' - Order Related / 'F2' Delivery Related.
    IMG > Sales and Distribution > Sales > Sales Documents > Sales Document Header > Define Sales Documents Types
    2. Assign New Sales Document Type to Sales Area, For Eg:
    1000 (S.Org) / 10 (D.Channel) / 10 (Division) / ZOR (S.O Type)
    IMG > Sales and Distribution > Sales > Sales Documents > Sales Document Header > Assign Sales Area to Sales Document Type
    3. Create New Item Category, say ZTAN - Copy of TAN (For delivery Related) / ZTAD - Copy of TAD (For Order realted) / ZTAS - copy of TAS (For Third Party)
    Maintain as under (others remaining same)
    Billing Relevance: I
    Billing Plan Type: 02
    IMG > Sales and Distribution > Sales > Sales Documents > Sales Document Item > Define Item Category
    4. Assign Item Category, for ex (assuming Usage & higher level item category as blank):
    Sales Document Type | Item Category Group | Default Item Category
    ZOR | NORM | ZTAN
    ZOR | DEIN | ZTAD
    ZOR | BANS | ZTAS
    IMG > Sales and Distribution > Sales > Sales Documents > Sales Document Item > Assign Item Category
    Note: In the above Billing Type '02' plays the main controller for periodic billing. In Sales order, at item level, we require to maintain the billing plan.
    Follow the Sales cycle as normal sales cycle for particular Scenarios
    Regards
    Raja

  • Milestone Billing based on POC(Percentage of completion) and Sales Order

    Dear Experts,
                      With reference to following link
    SD Cycle in PS
    i would like to add one more doubt.
    My client want to copy milestone only when milestone POC is completed.
    Like After Completion of 30% of work,Billing must be copied from it.
    System does not allow you to exit untill u complete 100% billing in sales order.
    Kindly put some valuable inputs.
    Regards

    >
    astosh wrote:
    > 2.Milestonewise Billing for completion of each floor, Like for 0% completion of work 10% billing can be done, for 100% Completion of first floor 20% billing to be done.
    > Regards
    You can create activities for each task and attach milestone on it. when you complete the task confirm the activity so system will automatically confirm milestone as well, which will remove the billing block.
    >
    astosh wrote:
    > 3.Is there any way to know whether the completion of floor is occured or not.
    > Regards
    System wont know automatically, your project engineer should confirm the activity based on the completion of tasks.
    >
    astosh wrote:
    > 4.Please elaborate process to be incorporated while making Sales order.
    >
    > Regards
    Search the forum there are many posts available and also refer sap help for milestone billing.
    Tnx.
    Abdul

  • Milestone billing, the system only allows pricing types D, G and K

    Hi,
    I would like to use pricing type as C Copy manual pricing elements and redetermine the others for Mile stone billing item catagory.(VTFA copy control setup)
    While changing pricing type from G to C in copy control VTFA - ITEM LEVEL, i am getting this beow warning message.
    Milestone billing, the system only allows pricing types D, G and K
    Could you tell what is impact of this warning message?
    Best Regards,
    Chandramohan

    Read OSS Note 102961 - New pricing type for milestone billing plans.
    It looks it used to be error message, until version 4.5A.
    This is just to make sure that the cost conditions are adjusted to the billing percentage rate. By keeping value K you can achieve this.
    Regards,

  • Periodic billing and Milestone billing

    Dear SD gurus,
    Can anybody explain what is Periodic billing and Milestone billing?
    If you have the configuration guide for the above, please send the same to my email id : [email protected]
    Thanks in advance
    Regards
    Manivannan R

    Hi,
    Milestone billing means distributing the total amount to be billed over multiple billing
    dates in the billing plan.
    As each milestone is successfully reached, the customer is billed either a percentage of
    the entire project cost or simply a pre-defined amount.
    During sales order processing, the system determines from the item category whether a
    billing plan is required and, if so, which type of plan
    The type of billing plan that is determined at this point is set up in Customizing and
    cannot be changed in the sales document.
    Billing plans for periodic billing and milestone billing plans for project-related milestone
    billing have different overview screens so that you can enter data relevant to your
    processing.
    For example, for milestone billing, you must be able to enter data to identify the
    individual milestones.
    IMG configuration requires :-
    1. Maintain billing plan types for milestone billing in OVBO.
    2. Define date description in SM30 - V_TVTB.
    3. Maintain Date Category for Billing Plan Type IN OVBJ.
    4. Allocate date category in SM30 - V_TFPLA_TY.
    5. Maintain date proposal for Billing Plan Type in OVBM.
    6. Assign Billing Plan Type to Sales Documents Type in OVBP.
    7. Assign Billing Plan Type to Item Categories in OVBR.
    8. Define rules for determining the date in OVBS.
    Milestone billing is typically used for billing projects, such as plant engineering and
    construction projects. Such projects often include a series of milestones that mark the
    completion of different stages of the work. In the SAP R/3 System, milestones are defined
    in a network along with planned and actual dates for the completion of work. The milestones
    are also assigned to the billing dates in the billing plan.
    Each milestone-related billing date is blocked for processing until the Project System
    confirms that the milestone is completed.
    Delivery-relevant order items for which a milestone billing plan applies are billed on the
    basis of the requested delivery quantity and not on the total of the confirmed quantities.
    The connection between the project and the sales document item is made in the individual
    schedule lines of the item. Each schedule item can be assigned to a network in a project.
    To display the project-related data for a schedule line, proceed as follows:
    In one of the overview screens of the sales document, select
    1. Item -> Schedule lines.
    2. Mark the schedule line and select Procurement details.
    The following figure shows an example of milestone billing where only the Contract have
    been billed :
    Order Item Turbine 100,000
    Billing Plan
    Billing date Description % Value Billing Block Milestone Billing Status
    01-10-94 Contract 10 10,000 - x x
    01-03-95 Assembly 30 30,000 x x
    01-04-95 Maintenance 30 30,000 x x
    01-05-95 Acceptance 30 30,000 x x
    01-06-95 Final invoice .. .. x
    Network/Activities
    Milestone Estimate Actual
    Assembly 01-03-95 01-03-95
    Maintenance 01-04-95
    Acceptance 01-05-95
    For each billing date in a milestone billing plan, you can specify whether the billing
    date is:
    1. fixed
    2. always updated with the actual date of the milestone
    3. updated with the actual date of the milestone, if the date is earlier than the
    planned billing date for the date
    reward points if it helps
    Regards
    Govind.

  • Standard Report for Down Payment Requests of Milestone Billing

    Hi Experts,
    Is there any Standard SAP Report for Downpayment Requests of Milestone Billing. Where I can view all the downpayment requests for the customers in Milestone Billing Scenario.
    I have searched but I'm getting report for Vendors downpayment requests in transaction code FBL1N.
    Kindly help to get me this report.
    Thanks in Advance.
    Regards,
    Avinash

    Hello,
    you can use transaction VF04 to get the list of the downpayment requests to be made, and VF05N for the list of downpayment requests already made (using the proper SD invoice document as selection criteria): this is from an SD point of view.
    From an FI point of view transaction FBL5N could help you. Also F-29, as already mentioned, since it provides the list of downpayments to be cleared for a customer.
    Best regards,
    Andrea

Maybe you are looking for

  • Sql query taking 2 much time to execute

    hi every body I am trying to JOIN two tables using the following criteria GL_JE_LINES.GL_SL_LINK_ID = CST_AE_LINES.GL_SL_LINK_ID but it takes too much time .. like (1 hr r more) which mens that something is wrong with my logic... any guidance will be

  • Read a dynamic table in form

    Dear all, I have a dynamic table with 3 columns : first column which contains a subform with button Add and Remove (to add and remove current row) second column with a dropdownlist (first field  to fill in by the user) third column with a dropdownlis

  • The method 'rollback' cant be called when a global transaction is active

    I receive the following error stack while dequeuing a message (aq adapter outbound) and forward the message to a database (database adapter inbound) within Oracle ESB 10.1.3.4. The database connection is dynamic using additional variables in the xlst

  • Pro*C with Visual C++ - leaks memory with EXEC SQL CONTEXT FREE

    Hello, I am making an aplication with threads, using Visual C++ with Pro*C... and I have a problem when the aplication execute EXEC SQL CONTEXT FREE the memory reserved is not free. this is my code: #include <sqlca.h> EXEC SQL BEGIN DECLARE SECTION;

  • Can Receive Mails but cannot Send

    Hello, I've been using Mail without hassle for the past week, but suddenly one day it stopped working. I can receive Mails from all my accounts (Gmail,.Mac, etc) but when I try to send one, It wont let me. I've tried sending mails with my .mac accoun