Quota arrangement - winning contract is not auto assign in SC

My Problem: Winning contract is not auto assign to Shopping cart
I created a Quota Arrangement (QA). It contains 2
contracts, for example in line item 1, contain Contract with Supplier
'A', with target percentage of 60%. In line item 2, contain Contract with
Supplier 'B', with target percentage of 40%. I did not specify any quotabase quantity.
For your info, the contract for Supplier 'A" is a Purchasing Contract,
with target value of 80 (currency Malaysian Ringgit). Contract for
Supplier 'B' has target value of 20 (currency Malaysian Ringgit). When Icreate a Shopping Cart, with quantity 5 (each-EA) and price per unit is
2
(Malaysian Ringgit), total is MYR10. When I go to Source of Supply tab,
the system showed 2 suppliers from the 2 contracts. It did not
automatically assigned to the winning contract. We still have to choose
which contract to be assigned. I created another SC after that until theContract exceeded quantity, but the system does not proposed winning
contract automatically. Please help.
Cheers
AIN

yes, the contract have company code

Similar Messages

  • Profit center is not auto assigned to B/S account

    Hi all,
    I actived document splitting function. When I post in FB50, Profit center is assigned to P/L account by me but it is not automatic assigned to B/S account. Follow our solution, I want the system auto enter same Profit center for P/L and B/S account.
    How to the system auto fill Profit center which was assigned to P/L account by me for B/S account?
    Thanks a lot

    hi
    Is the profit center field checked as mandatory in document splitting characterstics for general ledgers, and please check once the general ledger view
    krishna
    Edited by: achantakrishna on Sep 9, 2011 12:03 PM

  • Assign Source of Supply User Exit with Quota Arrangements in ME57 and ME56

    Hi there,
    We are using Quota Arrangements to define Vendor rebate levels and we have enabled User Exit EXIT_SAPLMEQR_001 to provide a more informative popup to replace standard Source of Supply popup as need to display current allocation quantities and % allocation fulfiled.
    This User Exit is invoked during Assign Source of Supply during PReq processing (More precisely during Assign Source of Supply in ME51n and Automatic Source of Supply in ME57 and ME56) which all works fine.
    When used in ME51n and Source of Supply Assigned and PReq saved, the allocated quantity against the valid Quota Arrangement (EQUK-QUMNG) is successfully updated with the relevant amount
    When using ME56 or ME57 to Automatically Assign source of Supply via the PReq list, the User Exit is invoked correctly and on selecting Vendor and saving the PReq is update correctly, however the allocated quantity against the valid Quota Arrangement (EQUK-QUMNG) is NOT updated with the relevant amount
    I have searched SAP Notes and debuged with limited success but cannot find evidence as to why this difference is happening - I assume that it has something to do with User Exit but any advice gratefully received if anyone else has experienced this issue?
    Ben

    Hello Jerry,
    source will be determine based on the following points:
    Outline Agreement
    Info record
    Quota Arrangement
    Source List
    For more information, <a href="http://help.sap.com/saphelp_47x200/helpdata/en/75/ee11b255c811d189900000e8322d00/content.htm">Click here</a>
    Hope this helps.
    Regards
    Arif Mansuri

  • Contract With Quota Arrangement

    Hi
    I am using Contract to procure a material from a Vendor.
    Incase if have more than 1 vendor can I use the Quota arrangement ?
    If the PR is created (By MRP) does it consider the Contract ?
    What are the steps involved to work with Quota for Contract.
    Regards
    MM
    Edited by: SAP-MM1 on Sep 18, 2011 2:55 PM

    Dear,
    Contract cannot be used as a source in Quota Arrangemnets.
    Quota arrangements and Contract both are different which you already know and maintained in the system to service different purposes.
    What about - Why can't maintain quota arrangements for all vendors who have contracts [when vendors are different] ?
    Regards,
    Syed Hussain.

  • Source determination,Quota Arrangement Process

    Hi,
    Plz tell me how to maintain Source determination,Quota Arrangement.step by step

    Dear,
    QUOTA ARRANGEMENTS
    If a quota arrangement exists for a material, it has the highest priority during source determination. Like source list, the quota arrangement facilitates the administration of sources of supply at plant level.
    If you procure a material from different suppliers, you can assign a quota to each individual supplier. A quota arrangement applies to a certain period and specifies how the receipts should be distributed among each source of supply.
    If a quota arrangement exists, this does not mean that the quantity of a single manually created purchase requisition is automatically apportioned among different sources. In such case, the entire quantity of the requisition is assigned to one source u2013 the source that is next in line receive the relevant order.
    Before you can maintain a quota arrangement item with the procurement type external procurement, a source of supply (info record and / or outline agreement) must exists.
    Create quota arrangement:
    LOGISTICS u2013MATERIAL MANAGEMENT u2013 PURCHASING u2013 MASTER DATA u2013 QUOTA ARRANGEMNET u2013 MAINTAIN.
    Specify number ranges for quota arrangement:
    SAP IMG u2013 MATERIAL MANAGEMENT u2013 PURCHASING u2013 QUOTA ARRANGEMENT u2013 DEFINE NUMBER RANGES.
    You must specify the business application for which quotation arrangement will be used, for example: in material planning or in purchase requisitions. You make this specification in QUOTA ARRANGEMENT USAGE filed, which is to be found in the plant-specific purchasing/materials planning data of the material master record.
    Set quota arrangement usage indicator:
    SAP IMG u2013 MATERIALS MANAGEMENT u2013 PURCHASING u2013 QUOTA ARRANGEMENT u2013 DEFINE QUOTA ARRANGEMENT USAGE.
    System assign quota rating to each source by calculation as u2013 Quota rating = (quota allocated quantity + quota base quantity / quota).
    ADDITIONAL ASPECTS OF SUPPLY SOURCE DETERMINATION
    Quota arrangements also can be source of supply.
    Quota arrangements for material requirements arising over a certain period divided up among different sources on basis of quota. Quota arrangements determine which source of supply is automatically assigned to a purchase requisition.
    SOURCE DETERMINATION
    The purpose of the source determination process is to automatically assign a source of supply to a purchase requisition, if source determination indicator set in the requisition header, the system searches for possible sources of supply for all the items of the requisition. Quota arrangements also can be source of supply.
    In source list specify a preferred source as fixed for a certain period, the system suggest just only this source, even if other potential sources exists.
    Quota arrangements for material requirements arising over a certain period divided up among different sources on basis of quota. Quota arrangements determine which source of supply is automatically assigned to a purchase requisition.
    Source list record consists of the following:
    1.Validity period u2013 Period of validity
    2.Key source data u2013 Number of vendor and responsible purchasing organization or number and item of outline agreement.
    3.Fixed source u2013 Within a validity period not more than one source should be flagged as fixed.
    4.Procurement plant u2013 if the materials can be procured from a plant or another point within your firm, enter the plant number in PPl field and leave the field for the vendor number empty.
    5.Blocked source u2013 To block a source. If you set Blocked indicator and enter only one validity period, the material is excluded from external procurement; that is, it cannot be ordered during this period.
    6.Material requirements planning  - You use MRP indicator to determine whether an automatic source determination process is carried out during the requirements planning run. The appropriate source is then automatically assigned to a purchase requisition, or scheduling agreement delivery schedule lines can be generated directly via planning run.
    If an attempt is made to order a material subject to a source list requirement from a source that is not included in the source list, the standard system issues an error message with the text: Source not included in list despite source list requirement. You can change this to warning message.
    If source list requirement defined for a plant, all materials in the plant level must be maintained with source list before procurement.
    Analyze source list:
    LOGISTICS u2013 MATERIAL MANAGEMNET u2013 PURCHASING u2013 MASTER DATA u2013 SOURCE LIST u2013 FOLLOW ON FUNCTIONS u2013 ANALYSE.
    Define source list requirement at plant level:
    SAP IMG u2013 MM u2013 PURCHSING u2013 SOURCE LIST u2013 DEFINE SOURCE LIST AT PLANT LEVEL.
    Source lists can be created:
    -Manually.
    -Create from within an outline agreement u2013 on outline agreement overview screen, select an item for which you wish to enter source list record and choose ITEM u2013 MAINTAIN SOURCE LIST.
    -Creation from with an info record u2013 you can enter vendor in the source list when creating or changing a purchasing info record. Choose EXTRAS u2013 SOURCE LIST. If the info record valid for entire purchase organization, you can create the source list for all plants of the organization in question. Choose the plant via GOTO u2013 PLANT.
    -Automatic u2013 can generate by system automatically.
    Create source list manually:
    LOGISTICS u2013 MATERIAL MANAGEMENT u2013 PURCHASING u2013 MASTER DATA u2013 SOURCE LIST u2013 MAINTAIN/DISPLAY.
    Generate source list automatically:
    LOGISTICS u2013 MATERIAL MANAGEMENT u2013 PURCHASING u2013 MASTER DATA u2013 SOURCE LIST u2013 FOLOW ON FUNCTIONS u2013 GENERATE.
    Regards,
    Syed Hussain

  • Reg : Quota Arrangement

    Hi Gurus,
    I have made the settings for Quota arrangement.
    I have used 3 Vendors and made the settings in Quota arrangement.
    When i am creating the Purchase requisition, the system is suggesting 3 Vendor names.The particular vendor name is not getting selected Automatically. I have to select that Manually.
    Please advice what setting needs to be done for making them getting picked up automatically as per the Quota settings.
    With Regards,
    Saakithyan

    Quota arrangement is used for PRs created during MRP. System considers the quota arrangement while creating PR during MRP & assigns the source to the vendor from quota arrangement as per the quota calculation. If the lot size allows splitting of quantity then the PRs with split are generated on the sources as per quota arrangement.
    The Quota Arrangement is not at all considered for Manually Generated PRs

  • What are the config steps for contract mass change and quota arrangement?

    Hi friends
    what are the config steps for contract mass change and quota arrangement?
    Regards
    Raj Kumar

    Process Flow
    The mass change process consists of four steps. You navigate between these steps by choosing the Next and Back buttons located at the bottom right-hand corner of the screens.
           1.      Search for contracts
    You search for and select the contracts or the contract hierarchy that you want to change.
    Contracts that have the status Closed cannot be changed.
           2.      Define mass changes
    You specify the changes you want to make.
    You make changes at header data level and at item data level by choosing the relevant change methods. A green tick appears next to each change parameter so that you can see where changes are already active.
    Once you enter this step, the documents you have selected to be changed are locked so that other users cannot make changes to them until you are finished with this process.
           3.      Simulate mass changes
    Here you can perform a trial run of your mass changes. This simulation step is optional.
    We recommend that you perform this step so that you can check how the change methods you have chosen will be processed by the system.
    You receive status messages about the change methods for each contract and can quickly see whether any errors arise in connection with the proposed changes at this stage. From this step, it is easier for you to go back and correct the error than after applying the changes.
    Background processing
    The system processes the changes in the background.
    If there are a large number of contracts to be processed, this step could take some time to complete. In this case, you can leave the transaction so that you can, for example, carry out other tasks in the meantime.
    The system sends you an e-mail once the simulation step is complete. The e-mail contains a link to the relevant screen in the application so that you can return to it when it is convenient for you to do so. If you have left the SRM application, you can only return via this link.
    Here you can see the status of the changes and, if necessary, you can correct any errors by going back to the Define mass changes step.
    The messages that you receive in the simulation step are not confirmation that a change has been performed. They simulate the messages you get after you apply the changes. You must complete the final step of the mass change process and apply the changes before they take effect.
           4.      Carry out mass changes
    Here you apply the changes to the contracts.
    You cannot reverse this step, which is why we advise you to perform the simulation step beforehand.

  • While Creating PO with Quota Arrangement Quantity is not picking by % given

    HI ALL.
    created Quota arrangement with 2 vendors.
    And assigined Percentages like 30 and 70 for this.
    Created Purcahse requisition and purchase order.
    But quanity with vendor percentages is not executing.
    Regards.
    Paramesh.
    Advance Thanks.

    Hi
    Can you give more information. How you create the PR & PO manually or via MRP.
    Quota arrangement works for automatic source determination and it has the highest priority.
    Also Splitting quota is only possible with MRP.
    [http://help.sap.com/saphelp_erp60_sp/helpdata/en/75/ee116c55c811d189900000e8322d00/content.htm]
    Hope it helps
    Karthik

  • I have LastPass running on a desktop PC. I just bought a new Laptop, Win 7, I can open the Vault on the laptop, but it will not auto fill the site logins Firefox is running on both computers.both

    I have LastPass running on a desktop PC. I just bought a new Laptop, Win 7, I can open the Vault on the laptop, but it will not auto fill the site logins Firefox is running on both computers

    Hi,
    Please try this: Firefox '''Tools''' ('''Alt''' + '''T''') > '''Add-ons''' > '''Extensions''' (on the left), click '''Options''' for LastPass > '''General''', enable '''Automatically Fill Login Information'''. If a site has more than one entries, you can set the preferred login in the vault by right-clicking the preferred entry > '''Edit''' and enable '''AutoLogin'''.
    [https://lastpass.com/support.php LastPass support]

  • Source list & quota arrangement

    At which level the source list is maintained:
    Client Level
    Plant Level
    Purchasing Org. level
    When source determination takes place, does the quota arrangement takes precedence over a fixed vendor?

    Hi Vishal,
    At which level the source list is maintained?
    Plant level.
    When source determination takes place, does the quota arrangement takes precedence over a fixed vendor?
    Yes, it does.
    The system determines the source of supply of a requested material on the basis of the following factors (in the order shown):
    1. Quota arrangement
    The system first determines whether a quota arrangement within whose validity period the delivery date in the requisition falls exists for the material.
    If a quota arrangement exists, the system determines the vendor from whom the material is to be procured according to the quotas assigned to the vendors and then suggests the source.
    If no source can be determined this way, the system checks the source list.
    2. Source list
    The system determines whether an entry in the source list within whose validity period the delivery date of the requisition falls exists for the material. The source in question may be a fixed vendor or an outline agreement (contract or scheduling agreement).
    If the source list contains a unique source, the requisition is assigned to that source.
    If several sources are found, a box appears for selection purposes.
    If no source could be determined, the existing outline agreements and info records are examined.
    3. Outline agreement and info record
    The system searches for contracts, scheduling agreements, and info records for the material and suggests these.
    (If info records with more than one purchasing organization exist, all info records of the purchasing organization(s) that is/are responsible for procurement for the requesting plant are also suggested.)
    If several outline agreements and perhaps info records exist, all possible sources are offered for selection in a box.
    When an info record is found, the following two additional checks are carried out:
    - Check of supply region
    The system checks whether a certain supply region is specified in the associated vendor master record. If so, the system checks whether the plant in the purchase requisition belongs to this region. If not, the info record is discarded as a possible source.
    - Check of regular vendor
    The system checks whether a regular vendor has been specified for the material (that is, a vendor valid for the entire corporate group, or client). If this is the case, and it has been specified in Customizing that the regular vendor takes precedence, the info record for this vendor will be preferred as the source.
    Hope this will help.
    Regards,
    Ferry Lianto
    Please reward points if helpful.

  • How to calculate the quota base quantity in quota arrangement?

    Hi all,
    As we all know, when a new supplier is added in the quota arrangment, we take the help of quota base qunatity so that the new supplier does not get any unfair advantage over the existing suppliers. Would you please help me on how to calculate the quota base quantity or on what basis the quota base quantity is calculated?*
    Regards,
    Ranjan

    Dear,
    Quota arrangement divides the total requirements generated over a period of time among the sources of supplied by assigning a quota.
    Quota u2013 quota is equal to a number and its represents the proportionate of requirements. Total quota of all the vendors is equal to 100% of requirements.
    This quota arrangement is also specific to material and plant level.
    Quota rating = quota allocate quantity + quota base quantity / quota.
    Quota based quantity used only when a new vendor introduced.
    In the as on date situation, the minimum quota ratings will considered as preferred vendor.
    The 2 vendors has 2 same quota rating, the vendor who is having the highest quota will considered first.
    In the running quota, a new source of supply is included. (In situation of short supply) including a new source not means to reduce the quota for existing.
    Regards,
    Syed Hussain.

  • Regarding Quota Arrangment

    Dear Gurus,
    I have to activate quota arrangement in our organization. I have done the following steps to active the quota arrangement, 1)Activated the Quota arrange usage in material master.
    2).Activated the Source list in material master. 3)Created the product requirement
    4).Maintained the quota arrangement for Vendor X and Vendor Y 50 percent accordingly
    5).Material requirement planning - MRP run for particular product
    As per the quota arrangement in this stage PR should create for Vndr X and Vndr Y. But it is not happing.
    Your answer will be highly appreciated.
    Reg/ Shankar G.

    Dear All,
    Thanks for your valuable replies; I have done the quota arrangement successfully.
    The following functions are done to achieve the goal.
    u2022     I have created the info record for both vendors.
    u2022     Activated the Quota arrange (3) usage in Material Master (Purchasing)
    u2022     Activated the source list-purchasing
    u2022     Maintained the quota arrangement thru MEQ1 for particular material
    u2022     I have assigned 50% for 2 vendors
    u2022     We have to maintain Lot size data as a u201CFSu201D, fixed lot size field enter sum Value and also enter the rounding
                         value.   Eg- if you enter the fixed lot size 5000, you can enter the rounding value 2500. Then 2 PRu2019s will as per our
                          quota arrangement.
    u2022     Material requirement planning(MRP) run for the product thru MD02
    Reg/ Shankar G.

  • Multiple Requisition  line itme for Quota arrangement

    Hello
    We are maintaining the quota arrangement master data .
    The Purchase requisition is splitting in to two line items based on the demand and assigning the Vendor on it .
    Is it the right way or some thing missing in the configuration
    Please advice me
    Thanks
    Nick

    Hi,
    1) The creation of PR depends upon the lot size you have maintained in the material master record.
    a) If you have maintained lot size as FX (Fixing & Splitting) & the splitting indicator is maintained for the lot size in customizing, then seperate PR will be generated for each vendor maintained in quota, with quantity alloted to the respective vendor as per quota arrangement & delivery date being as per requirement of the material (probably being same for all PRs).
    b) If you are using other lot size (which does not have the splitting indicator) then one PR will be generated for each demand, which will be assigned to the first vendor in line as per quota arrangement. Next PR (probably after next MRP run) will be assigned to another vendor which will be next vendor as per the quota arrangement.
    2) Regarding firming, these PRs will not be firmed automatically. If required, you will have to firm the same manually.
    Regards,
    Prashant
    - Pl. reward points if the answer is helpful to you

  • Can someone pl explain Quota arrangement process in MM?

    Hi Folks,
    I am new to MM, could someone pl explain the quota arrangement steps step by step anything with screen would be very helpful
    for beginners like me with examples. 
    Also could some also pl tell me the Source priority in terms of Source of supply?
    Thanks.
    Steve

    Dear,
    Quota Arrangements :
    In simple words: Distributing the requirements quantity between potential source of suppliers (Vendors) - basing on their order fulfillment capacity.
    In business terminology:
    Quota arrangements allow you to define target percentages and distribute them between two or more purchasing contracts. A quota arrangement ensures that a contract is guaranteed both a minimum sales volume and a percentage of the total purchasing volume of the product category or product. A quota arrangement has the highest priority in the sourcing process.
    Quota Arrangements
    Quota Arrangements means a mechanism enabling the system to compute which source of supply to assign to a requirement for a material.
    If a material can be obtained from various sources of supply, each individual source of supply can be allocated a quota arrangement. The quota arrangement is valid for a certain period of time and specifies exactly how the receipts are to be distributed amongst each source of supply.
    We can set the quota arrangement for in-house production as well as for external procurement. Setting quotas permits the automatic apportionment of a total material requirement over a period to different sources.
    Sources of supply can be:
    - an individual vendor or outline agreement
    - another plant, from which material should be procured
    - a production version
    Quota Arrangement Usage
    The quota arrangement facilitates the determination of the applicable sources of supply for the following at a certain time.
    Purchase orders
    Scheduling agreement delivery schedules
    Planned orders
    Purchase requisitions
    Materials planning and control
    In customizing activity, we specify for each material master record which quota arrangement rule is allowed. We group the usage combinations you have chosen under different keys.
    We have to assign quota arrangement usage key to material master record in purchasing or MRP2 view (Maintaining Material Master Record T.Code MM01)
    The quota arrangement usage determines whether a material is included in a quota arrangement and which operations lead to a quota arrangement.
    We have to maintain the quota file for the material. Here we define the sequence of the sources of supply, the quotas per source of supply and numerous other parameters in the quota file.
    Maintaining the Quota File
    A quota arrangement file consists of quota arrangement records identifying the source (such as a vendor or an internal plant), the validity period, and the quota allocated to each source.
    We can maintain the quota file. Following are the steps for maintaining this file.
    T. Code: MEQ1
    The initial screen for maintaining quota appears.
    Enter the material number and the plant for the material that you want to use to maintain the quota file and choose. The header screen for maintaining quotas appears.
    Enter the Valid to date for the quota arrangement item.
    We can only define continuous validity periods for one material. In the first interval, the system sets the current date in the Valid from field. The Valid from dates of the other intervals are set continuously so that the day after the end date of the last quota item is set as the start date for the next item.
    If we want to work with splitting quota arrangements, we will enter a minimum quantity here.
    Double-click on the item to process.
    The item screen now appears.
    Here we will define the source of supply and other control parameters per item.
    Allocating the source of supply to the quota item determines the procurement type that the procurement proposal receives. Therefore, we can specify via the quota arrangement that, for example, 75% of a material is produced in-house and the other 25% is procured externally.
    Save entries.
    Regards,
    Syed Hussain.

  • Quota Arrangement || Allocated Quantity

    Hi All,
    I am currently dealing with two issues related to Quota Arrangement which are as follows:
    I have a product in APO on which inbound quota arrangement is set. The product is procured from a vendor and purchase requisitions are created on it. The validity of the quota is from 01.01.2000 to 31.12.2014. Now as per the business requirement we need to extend the validity till 31.12.2015. In APO we can't extend the validity of the quota. The other option is to delete this quota and create the new quota arrangement  of desired validity. But the challenge is 32,654 quantity is already allocated to it( in Allocated quantity field, which is as per my understanding the sum quantity of purchase requisitions and purchase orders). If I delete the quota what will be the affects of it ???. How should I proceed with this issue ???
    I have integrated a new product in APO and I am trying to arrange a quota for the same. I created it successfully. There are purchase requisitions and purchase orders created on it. However, I can see 0 in the allocated quantity field. Can anyone help me in understanding the reason behind 0 Allocated Quantity ???
    Thanks,
    Swapnil

    Dear Sethuraman,
    P - Type of procurement (Internal manufacturing, External Procurement).
    S - Special procurement type. For example consignment / sub-contracting.
    Vendor - Number of Vendor Master
    PPI - Your internal plant from which you will be manufacturing the material.
    Ver. - Production version.
    Quota - The quota percentage in which the required quantity is to be splitt.
    Allocated Qty - Total quantity from all purchase requisitions, purchase orders, release orders, and scheduling agreement schedules allocated to a given source of supply. (The quantities of quota-allocated planned orders are also taken into account.)
    Maximum Quantity - Max qty which is to be assigned to this vendor.
    Quota Base quantity - If you get a new vendor in the quota arrangement, the quota base quantity is to be entered here to avoid all requirements being assigned to the new vendor.
    Max & Min Lot Size - The lot size related to this vendor.
    Rounding Profile -
    1X - Mark tick here of the vendor is to be assigned only one lot during a MRP run. (may be due to capacity restriction).
    Maximum Release quantity - Max qty the vendor should be assigned per MRP period.
    No. - Number of periods for which the Max release qty relates.
    P - Period to which this qty relates.
    Pr - Priority determination sequence
    Determining the Quota Base Quantity
    The quota base quantity is used only when you include a new source in an existing quota arrangement.
    Read SAP Help for more details Determining the Source Under a Quota Arrangement - Purchasing (MM-PUR) - SAP Library
    Split Quota issue
    Thanks & Regards,
    Ramagiri

Maybe you are looking for