Hi All,
How to read/track the order bom changes (CU51)?
I want to track all changes made using CU51 for perticular sales order, like component deletion, change in quantity etc. I checked the tables CDHDR and CDPOS but did not get any information.
Please help

Sachin,
How did you solve this issue ? I have same req in my prj.....any help in this would help us...
Please let us know how did you solve this ? Is it by CDHDR or User exit tracking changes and passing it to Ztable ? any other method ?
pls let us know ...thanks in advance....
Gayathri

Similar Messages

  • Production Order BOM change

    Dear Expers,
    How can i restrict the Production order BOM Change. Please tell me with the steps.
    Other than screen variant.
    Regards
    Raghu

    Hi,
    To do this you can use below mentioned processed.
    1. create a user status and give approval to the order at creation and the user will not be able to change any thing in the process order.
    2. You can use user exits to restrict changes changes at "materials" screen.
    Hope this will help.
    regards,
    kaushik

  • Order BOM change type - CC03

    Hi,
    I'm building a custom report for Order BOM changes like CC03.
    Now, I'm stuck with defining the change type. I did debug into CC03 but the logic to build change type is manual and quite complex.
    Please let me know how to define the change type.
    Thanks,
    Khanh

    Hi Rav,
    That's not what I need.
    Please run the Tcode CC03 for a specific change number, then you will see many items inside that change number.
    Each item may have a different change type for e.g. NEW, DEL, OLD, Ind, ...
    I want to know that kind of change type.
    Thanks,
    Khanh

  • Planned order BOM change - PO already created. How to keep the 2 in sync?

    Hi Everyone,
    I have a question regarding planned order BOM changes AFTER a vendor PO was already created and sent.
    How can we restrict the re-explosion of a planned order (from re-ATP of item in VA02) if the PO has already been created?
    This causes problems for us when we backflush the PO components as there is a mismatch between the updated planned order BOM and the PO component list...
    Any thoughts/ideas?
    Thanks!
    Tony

    You can freely arrange the order of the photos in the contact sheet by dragging and rearranging the thumbnails of the photos on the sheet, if you set the sorting to "Manually" in the "View" menu, while viewing the Contact sheet:
    Regards
    Léonie

  • Express document "Update was terminated" in CS62 order BOM change

    Hi All,
    I am creating one sales order BOM with reference to Material BOM. While creating BOM, we have setup BOM creation in such a way that while creation BOM status will be inactive.
    While changing status to active using CS62 transaction, I am getting error Express document "Update was terminated" from author. And after BOM created in CS61 is getting deleted automatically.
    Regards,
    Sachin

    Hi,
    There could be a database related problem. Contact your Basis Pople.
    Regards,
    Siva

  • How do I change the PDF reading order without changing the image color or Lists?

    When I change the reading order in a PDF (created using InDesign), some images are getting darker. Any idea how to change this back (no, CTRL+Z doesn't work) or prevent it from happening?
    On a related topic, my PDF passes the 508 compliance check before I change the reading order, but afterwards the Lists have errors. I cannot figure out how to fix these errors manually.
    Thanks!
    (Topic originally posted in InDesign forum: http://forums.adobe.com/thread/1351206).

    You may have more luck getting a response in the Standards & Accessibility Acrobat forum:
    Standards & Accessibility (tagged PDF)
    Accessibility questions come up only rarely in the InDesign forum and its outside the knowledge of most of our users.

  • Sales Order BOM changes flow to Production

    Hi...
    I am lookign for help  in below scenario.
    We are useing the Slaes Order Boms for our Engineered to Order Material Production.
    But it s aconstant problem that if later on Sales Order BOM is changed some time later its not getting auto
    matically transfered to Production Order change BOM and its literrally a manual process to pass the communication
    from sales to production order and then do the changes in Production Order.which carries a risk always..
    Can some one propose the solution to automate this process..thanks

    Hi,
    It is not possible in STD SAP. Once the planned order is converted in to production order, the link between the production order & the master data will be removed. Then any changes in the master will not reflected in the production order.
    You need to think for some developments.
    Regards,
    V. Suresh

  • Logical Reading order options changed?

    I had to re-install Adobe Acrobat Pro XI on my computer and some options appear to have changed. Previously after running a full accessibility check I could manually adjust the logical reading order. However, the tool bar no loner has the "accessbility" tab or the option to mannualy adjust reading order. Am I missing something?

    Some of the Acrobat Tool Panes are hidden by default. You can make them visible using the little drop list near the upper right corner of the screen, or from the View menu. Then, you can add the tools you use frequently to the Quick Tools bar. Hope this helps.
    a 'C' student

  • Transfer of changed order BOM from quotation to sales order

    Good morning!
    Please consider the following scenario involving variant configuration:
    A quotation is raised in the system, and the values of the characteristics are assigned. Therefore a order BOM is generated (for the quotation), and that order BOM is changed manually using tcode CU51 (for cost estimates purposes). When it is saved, the system updates the BOM in the quotation automatically (ok, this is a desired behavior).
    Although when we create an sales order with reference to that quotation, the newly chnaged order BOM is not copied to this new order, the order BOM is redetermined instead.
    How can I make the system to copy it from the quotation properly?
    Thanks in advance!
    Adriano Cardoso

    Thanks for the reply. I have verified this note and it seems more toward the BOM explosion in the sales documents themselves than for the modifications made afterwards (CU51 changes in BOM, for example).
    After realizing that, I´ve made a little research and found the Order Engineering Workbench possibility, which seems to fulfill all our requirements regarding this point. I looked all over SDN and haven't found too much input about it. In the SAP VC book, says it is not part of the SAP ERP, but a add-on.
    So, you don't happen to have any idea of how can we check if it is activated / installed  in our system or not? We are on version 5.0.
    Thanks!
    Adriano Cardoso

  • BOM changes reflecting in sales order BOM of delievery completed materials.

    Hello gurus
    i am explaining my requrement. My scenario is like this.
    1.creating sales order
    2.reating sales order BOM
    Next production peole will create production order and will do confirmation of order and Goods reciept.
    3. after this sales people will do delivery of the materail.
    For example yesterday i have delivered one material X.
    Today if i change the super BOM of the material X, these changes are reflecting in the sales order BOM of yesterday delivery done material X also. My client want to restrict thise changes. Pl help me how to resolve this ?
    regards
    srao

    Hi Brahmankar
      we checked for User exits we didnt find. Can u help me out on this regard.
    Can we lock the sales order BOM ? means if we do any changes to super BOM assly level also, these should not reflect to sales order BOM . pl guide me
    regards
    srao

  • Plant change in Sales Order not possible due to Sales Order BOM

    Hi all,
    we are trying to change the Delivery Plant in a Sales Order after the creation of a Sales Order BOM, but it gives a V1773 message first, then a blocking error V1810. The same happens with a Production Order.
    How can we change the Delivery Plant after the creation of one of these objects?
    Our scenario:
    - Make To Order
    - Sales Order BOM created with transaction CS61
    - Sales Order Routing created with transaction CA01
    We need to create the Sales Order BOM on the Production Plant (which doesn't change), but we need to be able to change the Delivery Plant in any time.
    Should you have further questions, feel free to ask.
    Thanks in advance,
    Giuseppe

    Hello Caselli,
    For V1773, please check the solution provided by note 588884, which is a modification. With this note it turns possible to delete all multi-level sales order BOM using transaction CSKB, which may be useful.
    The behavior mentioned by you is the standard behavior of the system. The scenario works as designed, a plant change is only possible as long as there is no other document assigned to the sales order.
    Longtext of V1 810 says:
    The plant can no longer be changed in the following situations:
        2. There is a production order for the order item but it is not a static assembly order.
    Your scenario seems to be point 2 as mentioned above. You can check the requirement type (VBAP-BEDAE) and requirement class in OVZH and assembly type (MNTGA) in OVZG.
    If you change the plant for the items with existing production orders, it will cause the incorrect values in the COPA. An order item is assigned to plant A and the corresponding production order exits. This
    means that the costs are assigned to plant A (this is the place where the costs accrue). Order and production order will be balanced at plant A.
    If you now, after the process has already started, should allow to change the order to plant B the following examples of problems will come up:
    - The costs accrued in plant A (see production order)
    - The SD order is now assigned to plant B, this means billing will be with plant B
    This leads to the fact the costs are on plant A, plant B has a benefit. Plant A cannot settle the costs and plant B has unexpected earnings. Inconsistencies in all involved process steps, SD, CO, COPA are the results.
    If you want to change the plant in the sales order you'll have to perform these steps:
    = Delete the production order.
    = Change the plant of the sales order item from A to C.
      This should be possible unless there are other documents which are already assigned to this sales    order item. Save.
    = Create a new production order and assign it to the sales order item again.
    I hope I am able to help you with this information.
    Best Regards,
    Bhavin Joshi

  • Acrobat Pro 9 & 10 crash when changing read order

    I have a calendar I have been making in Indesign for years with no changes other than the entries.  After I export to PDF, I use the read order tools to arrange the read order for a blind client and calendars cant be read normally without giving it the order.  As of several months ago, when I go to rearrange the readorder, it will crash.  It doesnt do it to every change to the order I make, just certain ones, and those certain ones change on me each month.  Im clueless why this is and because of it, I havent been able to properly make a PDF for this blind client without the calendar reading completely out of order.  What could be causing this????

    Your issue may not be related to a difference between v8 and 9.
    I have not had this problem on my computers, but a coworker had this issue. For many documents that others were able to open and scroll through without issue, his computer was freezing and unfreezing.  IT determined his graphics capabilities were not able to keep up with the requirements of working with larger documents and gave his computer a RAM upgrade and a new graphics card. Particularly during scrolling, higher demands are made on the computer to graphically render and re-render page content. Documents giving him problems before became a non-issue.
    A new graphics card is obviously a $$$ solution, but you might want to check to see if your RAM meets the minimum requirements and check to see if there are any program updates (Help > Check for Updates).
    I have had an issue of pdfs freezing, but not specifically in the table of contents areas. If your document has pages with images that have an unusually high number of layers, it may affect the ability to work effectively in the document.

  • BOM change after Purchase order creation

    Dear all
    My client requirement is an error message should appear when the end users are trying to change the BOM after the purchase order creation for the BOM items and the system should allow the BOM change only after the PO cancellation.
    Please throw some light
    regards
    Kumar

    Dear Kumar,
    Do you mean to say user's should not be allowed to change hte BOM items in a purchase order?or should not be allowed to change a
    BOM,if there are some purchase orders for the same material?
    If your requirement is to restrict the BOM change of a material using T code CS02,after purchase order creation,I dont think its
    possible.
    Please explain your problem little more in detail.
    Regards
    Mangalraj.S

  • Automaticaly change keyboard language depending on item reading order

    Hi
    I have a form with items both in english and arabic. I would like to change language keyboard automaticaly depending on item. I mean when I focus on arabic item (Reading order : Right to left) the keyboard should be arabic automaticaly whithout doing ALT+SHIFT.
    is it possible on Dev 10g ?
    Thanks

    I am also interested in the same if any one has an idea.
    Thanks
    Haytham

  • Sales order costing after changes on configuration or sales order BOM

    Hi all
    Our sales order items requruire an sales order costing. This is done automatically, when saving the sales order item:
    Settings in requirement class:
    - costing: X (costing required)
    - costing-ID: B (automatic costing and marking)
    This works perfect, means the sales order receives a caluculation that is marked.
    Now, something is changed on the sales order BOM with transaction CU51
    It seems, that each time you change the BOM you have to ensure yourself, that the costing of the sales order items (via VA02 -> extras -> costing) has to be performed manually.
    There is no SAP standard process, that does this automatically.
    Thanks for your feedback.
    Pius

    Dear Pius,
    System cannot take the changes from the BOM and execute the cost estimate automatically.
    Need to refresh system when the changes are happened i..e need to execute the Cost Estimate once again.
    Kind Regards
    Umapathi G