Resource Plan in Project Server 2013 : where is the remaining availability ?

Hi,
I created a new project  with not any task but with a Resource Plan.
I selected the Calculate from: Resource Plan option and clicked
Publish and then Close
I checked the availability of resources : it is still the same. The resource plan has no impact !
What did I miss?
Thanks

Robert,
Is your resource's booking type set to Proposed, by any chance in the resource plan? If yes, are you selecting the Include proposed bookings option in the resource availability graph?
Cheers,
Prasanna Adavi, Project MVP
Blog:
  Podcast:
   Twitter:   
LinkedIn:
  

Similar Messages

  • How to configure Time-sheet in Project server 2013 please share the doc with screen shot

    How to configure Time-sheet in Project server 2013 please share the doc with screen shot
    Thanks and Regards, Rangnath Mali

    Hi,
    Please refer to the following Youtube video and article.
    https://www.youtube.com/watch?v=lZWvg4q17JE
    https://support.office.com/en-sg/article/Set-up-timesheets-and-task-status-672fa06f-8c4b-4e43-bfbc-4c355d681605
    Please don't forget to mark it answered, if your problem resolved or helpful.

  • Getting error while publishing the new Plan in Project server 2013

    Dear Team , 
    Please help me below error
    Queue:
    GeneralQueueJobFailed (26000) - CreateWssSite.CreateWssSiteMessage. Details: id='26000' name='GeneralQueueJobFailed' uid='ba6a6244-4d50-e311-bf14-ac162d773454' JobUID='5151573c-4d50-e311-bf14-ac162d773454' ComputerName='7717b7cb-9926-477e-9e7a-3d9f072b7c6b'
    GroupType='CreateWssSite' MessageType='CreateWssSiteMessage' MessageId='1' Stage='' CorrelationUID='ddd5579c-fb3c-70d0-b7c6-b85aaff1162c'. For more details, check the ULS logs on machine 7717b7cb-9926-477e-9e7a-3d9f072b7c6b for entries
    with JobUID 5151573c-4d50-e311-bf14-ac162d773454
    I am not able to understand . Please help us as soon as possible. 
    Regards, 
    Jitendra Kumar 
    +91-7483123328

    Hi Tony,
    Did you check for the ULS log error message? It will be more detailed and make your issue easier to resolve.
    Also is it happening with the out-of-the-box project site template or with a custom template? If it is a custom template, what kind of customizations did you do (column renaming...)?
    Hope this helps,
    Guillaume Rouyre, MBA, MCP, MCTS |

  • Is there a Project Server 2013 JSOM typescript definition file available?

    Hi, is there a typescript definition file (.d.ts) file available for PS.js? If not, are there any plans to come up with the definition file in the future?

    Hi, is there a typescript definition file (.d.ts) file available for PS.js? If not, are there any plans to come up with the definition file in the future?
    +1 to that - Might be a handy idea for someone to go through the documentation and write one.  I am tempted to do it myself.
    James Boman IPMO http://www.ipmo.com.au @JBoman32768

  • Baseline timephased data disappeared in MS Project 2013 with Project Server 2013!!!

    Hi,
    I am facing a very strange problem within a custom "task usage" view that I' 
    ve created. In the right pane I have three timephased fields (work, baseline 
    work and actual work). When I first add resources to tasks and save baseline 
    everything works great and the baseline work data are distributed normally in 
    the respective line next to the resource name and also in the summary tasks 
    lines. A few days after saving and publishing the project to the Project 
    Server 2013, I opened the project from the PrjProfessional and the timephased 
    baseline data had disappeared. However, the total values of baseline work 
    (shown in the respective column at the left pane) were all still there. In 
    other words, I cannot see the distribution of baseline work into the timephased 
    schedule. When I check the database the data is also gone (MSP_EpmAssignmentBaselineByDay table).
    This has a huge impact for the customer!
    If found a similar issue reported with Project 2007 --> http://www.44342.com/Microsoft-Project-f1227-t2482-p1.htm
    Regards,
    Philip
    Verlinden Philip

    Hi Philip,
    Please refer to thjis thread: 
    https://social.technet.microsoft.com/Forums/projectserver/en-US/5f721eaf-6424-4b32-9c96-fed646e94f88/cumulative-timephased-data-in-ps-2013-db-wrong-or-just-misunderstood?forum=projserv2010setup
    I think it is a known bug that Elli identified a few weeks ago. I don't know if there is a fix planned soon by MS.
    Hope this helps,
    Guillaume Rouyre, MBA, MVP, MCP |

  • Project Server 2013 - Out of Office Sync - Only two months in future?!?

    Hello there guys,
    after Long Long search for the problem, I've found out that our Project Server 2013 only syncs the out of Office time from our Exchange Calendar for the next two months.
    But for our Project planning we Need of course a more longtime synchronization, at least 6 or better 12 months.
    I didnt find any Option where I could set it to sync more then 2 months of the out of Office times in the calendars.
    I've spent already so much time on this Problem... When I set the Project Server time 2 weeks(!) in the future, then the sync will also sync two more weeks in the future, but not more.
    The timesheet periods are also set for the next 12 month.
    Does anybody have an Information/help regarding this Problem for me?
    How can I set the Out of Office sync to synchronize more then just 2 months?
    THANK YOU VERY MUCh!!
    Regards
    Lukas Meyer
    PS: Using the current October 2013 CU.

    I've searched the Verbose Log and found the following:
    12/17/2013 14:38:16.32 Microsoft.Office.Project.Server (0x0928) 0x1A6C Project Server Exchange Sync aaubf Verbose PWA:https://servername/PWA, ServiceApp:Project Server-Dienstanwendung, User:PROJECTSERVER\system,
    PSI: Calling service.GetUserAvailability() for user:2c3909bc-d6fb-e211-b239-000c296be823 for period:12/17/2013 00:00:00-02/17/2014 00:00:00, LogLevelManager Warning-ulsID:0x00014045 has no entities explicitly specified. 3a2f619c-f4a0-f018-b62b-b2d1299a489f 
    So the Project Server is only asking for two months of User Availability on the Exchange. Where can I Change this Setting so that the Project Server syncs more then 2 months?
    Otherwise this functionality is quite useless in my view as we are planning our Projects longer then only 2 months...
    Thank you!

  • Project Server 2013 - Adding Enterprise Resouce additonal Assignemt attributes with AD sync programatically

    I Have a project server 2013 environment (Sandbox right now but on its way to a production system.) and we have AD sync set up for our enterprise resource pool.
    We have 2 situations:
    1. AD only brings certain information over (Name, email etc) and leaves other information out: Which calendar to use, base cost rate, Resource departments, Time sheet approver (their manager)
    2. IN AD we store the employee number and would like to map it to the External ID field. (And several other things need to happen - outlook out of office sync, resource can be leveled etc)
    I have not seen a way "add" this  information programmatically. Everything I see says open the resource in Project pro and update.  when you have 10,000 resources manual updates and changes are not really practical. Ideally we would
    be able to have some logic that looks at a table and as resources are added/updated the various fields are filled in as part of the "ad Sync job"
    Question: Is this possible an has anyone done it? If so how?
    Thanks
    Tasks

    Hi Bob,
    Yes, you are right.  Any extention will have to be custom code.  PS operates the same in regards to what can be accessed via AD sync over the various versions.  That part has not changed, how MS processes what it reads has changed over the
    years.
    However, another point for you, be very careful if you are really planning to add 10K users to your ERP via AD.  This will be a very taxing endeavor for your systems.
    I'm not aware of any technical limits, but you will run into practical limits with more than about 5K users in your ERP.  You had better have a very large SQL server and lots of RAM in your SharePoint web and Project App servers.  You had better
    have more than 1 Project App server, etc...  You will want to consider the impact to users when various parts of the system are loaded up with 10K resources.  Design your Farm and PWA configuration accordingly or expect to wait a lot!
    Don't expect to do this during business hours or you will kill all your users processing.  AD sync jobs go in the project server Q and can take hours to process in large numbers like that, at least initially.  Don't make any security changes of
    any kind during business hours as these will trigger a "re-sync".  Etc...
    Please read everything here:  Active Directory Resource Pool Synchronization (Project Server 2013)
    http://technet.microsoft.com/en-us/library/jj819320(v=office.15).aspx
    Other postings (Hey Stowe!) have referenced this as a starter:
    http://ps2007adressync.codeplex.com/  I know this says 2007, but perhaps you can use this as a basis for understanding what's possible or how to approach.  As I mentioned, the underlying mechanics on this point are the same.
    Clearly you will want to use the PSI - which will give you access to almost everything you need.  You may need to hook into the Event handlers after the AD sync runs or just run a batch process of your own.
    Specifically, Outlook out of office can be accomplished by sync'ing with Exchange Server 2013.  See the TechNet on that topic (near the other articles).
    Resource can be leveled sounds like your custom job along with the EMP ID mapping.
    Hope this helps,
    Thanks, Eric S. Pcubed

  • Which sharepoint service applications & services are required for Project server 2013 to work fine.

    HI,
    Can any one help me,
    I am planning to install project server 2013,  what are the service applications and Services ( Manage services on server in central admin ) in sharepoint  are required for project server 2013 to work fine, so that i will run only  service
    application and services to increase server performance..i don't want to configure all service applications  when i  am configuring.
    Thanks in Advance..
    vijay kommireddi

    Hi Vijay,
    If you are installing Project Server on SharePoint farm, You need to start the service Project Application Service which would be available after you install project Server 2013.
    For Project Server Reporting you need to start Excel service and Secure Store service.
    http://technet.microsoft.com/en-us/library/ee662106(v=office.15).aspx
    Thanks,
    Phani

  • Project Server 2013 - Workflow Execution " Submit button is grayed out. "

    Dear All,
    As i was in progress to making workflows in sharepoint designer this is my first project of implementing project server 2013 and executing the workflows,in the continuation of this i followed below mentioned link to go through the process of WORKFLOWS but
    got some issue
    LINK: http://msdn.microsoft.com/en-us/library/office/jj163494(v=office.15)
    ISSUE: Is that the SUBMIT Button is grayed out after saving initial proposal plan. Snapshot is attached.
    I have checked in/out process along with this gone through re-executed the whole process same result occurred.
    Suggestion/Help needed... 
    REGARDS DANISH DANIE

    Hi Danish, 
    Its a common thing which users are experiencing.
    When you create project from workflow click on Submit it take time for transition before transition it check all the condition which you have set for workflow stage. As per your screenshot it is waiting for details in PDP (Provide details of the proposed project) 
    when you click on submit it push data into the database,sometimes it send e mails to stakeholder then it use exchange and take times to send e-mails and for transition too.
    When you/user face this issue ask them to wait for some time or close the file then reopen. 
    In the screen workflow is waiting for Project detail information in PDP that is why it is still in process and not going to next stage.
    kirtesh

  • Configure Workflow Manager 1.0 in Project Server 2013 with FBA

    Hi,
    Please suggest the ways to configure Workflow manger in Project server 2013 where PWA using FBA
    we have tried for below situation, but no luck!!
    The workflow manager configured using windows login account, we are associating a FBA site with workflow manager which is 
    Register-SPWorkflowService -SPSite 'http://FBAsite' -WorkflowHostUri 'http://workflowmanagerapplication:12291'
    Following steps are taken care while creating workflow.
    We have added users to the user service profile services
    User profile synchronization is started
    The user by whom we are logged is available in User Profile list
    we are not running workflow with share point system account
    Final step full synchronization of User Profile Application
    Below the error we are getting when workflow run
    Resume this workflow  
     RequestorId: 879e36f9-9db0-3c16-0000-000000000000. Details: An unhandled exception occurred during the execution of the workflow instance. Exception details: System.ApplicationException: HTTP 401 {"Transfer-Encoding":["chunked"],"X-SharePointHealthScore":["0"],"SPClientServiceRequestDuration":["440"],"SPRequestGuid":["879e36f9-9db0-3c16-a91c-356d29becb34"],"request-id":["879e36f9-9db0-3c16-a91c-356d29becb34"],"X-FRAME-OPTIONS":["SAMEORIGIN"],"MicrosoftSharePointTeamServices":["15.0.0.4605"],"X-Content-Type-Options":["nosniff"],"X-MS-InvokeApp":["1;
    RequireReadOnly"],"Cache-Control":["max-age=0, private"],"Date":["Sun, 15 Jun 2014 12:44:03 GMT"],"Server":["Microsoft-IIS\/7.5"],"WWW-Authenticate":["NTLM"],"X-AspNet-Version":["4.0.30319"],"X-Powered-By":["ASP.NET"]}
    at Microsoft.Activities.Hosting.Runtime.Subroutine.SubroutineChild.Execute(CodeActivityContext context) at System.Activities.CodeActivity.InternalExecute(ActivityInstance instance, ActivityExecutor executor, BookmarkManager bookmarkManager) at System.Activities.Runtime.ActivityExecutor.ExecuteActivityWorkItem.ExecuteBody(ActivityExecutor
    executor, BookmarkManager bookmarkManager, Location resultLocation)

    Hi Mafeer,
    Since this issue is related to Project Server, I would like to recommend you to post there for more effective support:
    Project Server General Questions and Answers
    Thanks for your understanding.

  • Excel 2010 reporting with Project Server 2013

    Our company purchased SharePoint Server 2013 and Project Server 2013, mainly for the reporting/BI attributes. I read that the report templates, etc. that can be used by Project Server web app can only be accessed with Excel 2013?? Does that mean that our
    group/customers have to upgrade to Excel 2013 to take advantage of the Excel Services? This is a huge deal. Can you please let me know as soon as possible? Yikes!! :-O

    Hi,
    As far as I know, Excel 2010 is still supported by Project Server 2013.
    See here:
    https://technet.microsoft.com/en-us/library/ee683978.aspx
    Hope this helps,
    Guillaume Rouyre, MBA, MVP, P-Seller |

  • Approvals on Project Server 2013 - An unknown error has occurred

    Migrated Project server 2010 to Project server 2013.  All the quick launch pages were working after I completed the migration. Started the process of publishing projects and statusing/timesheets to update project. 
    Now I see "An Unknown Error has occurred".   Tried all my solutions for Project Server 2010 without success.
    Event log looks clean.
    Has anybody seen and resolved this issue?
    Cheers!
    Michael Wharton, MBA, PMP, MCT, MCSD, MCSE+I, MCDBA, MCC 2011, MCC2012
    Website http://www.WhartonComputer.com
    Blog http://MyProjectExpert.com contains my field notes and SQL queries

    We are having the same error with an on-premise install of Project Server 2013. This is the error from the ULS logs.
    04/24/2013 06:50:58.90    w3wp.exe (0x18C0)    0x1D0C    Project Server    Task Statusing and Updates    c3bn    High    PWA:https://projects.geocent.com/commsec,
    ServiceApp:Project Server Application Service, User:i:0#.w|geocent\john, PSI: System.NullReferenceException: Object reference not set to an instance of an object.     at Microsoft.Office.Project.Server.BusinessLayer.Statusing.StatusApprovalsQueryInfo.AddAllTimesheets(DataTable&
    dt, Dictionary`2& timephased, List`1& actualDates)     at Microsoft.Office.Project.Server.BusinessLayer.Statusing.StatusApprovalsQueryInfo.TryLoad(LoadApprovalType method, DataTable& dt, Dictionary`2& timephased, List`1&
    actualDates), LogLevelManager Warning-ulsID:0x6333626E has no entities explicitly specified.    c9e7149c-070d-5035-0dca-bda3580b7d07
    Not very helpful. Any ideas?

  • Project Server 2013 Project Site Permission

    Hi All,
    Q1: We are using project server 2013, most of the time the projects are created by the PMO coordinators and it will be assigned to the project manager. Project coordinator and Project Manager belongs to "Project Manager" group. After assigning
    the project when the project manager tries to access Project Site, he is getting "why you want to access this site". When I checked project site permission only project coordinator name is added to the Owners group. Normally the project owner should
    have the permission to the project site, how to fix it.
    Q2: We have different enterprise project type with different site templates. When the project type is changed from one type to another, is it possible to delete and recreate the respective project sites automatically.
    Thanks in advance, Taj

    Taj,
    Q1) this is a question related to how your security is set up. If you are using Project Server Permission mode, people in Project managers groups, who have edit ability on your project will get added to the Project manager Synchronized group on the project
    site upon publish. You just need to make sure your secueiry ctegories and groups are set up as such.
    Alternatively, you could set the owner of the project to be the project manager once they take ownership.
    Q2) This will be a manual activity. You need to disconnect the site under server settings, then delete site. Then you can create the site, which will pickup the new EPT set project site template automatically.
    Cheers,
    Prasanna Adavi, Project MVP
    Blog:
      Podcast:
       Twitter:   
    LinkedIn:
      

  • Project Server 2013 for Resource Planning & Project Portfolio Management

    We are looking to  use project server 2013 for resource and project portfolio management.  We are an IT department of approximately 600 growing to 1,000 within the next several years.
    We would like to us PS2013 to do the following :
    Manage Portfolio of Projects
    Manage Resources against this Portfolio
    Calculate Project Finances using resource roles and rates
    I would be grateful to have both comments on experience , both positive and negative.
    Thank You

    Many teams within organizations are turning to Project Server to help them control resources, deliverables and costs better.    It does resource management very well with work & cost resources, baseline costs, material costs, budget costs and
    out of the box earned value analysis (EV).  The Strategy (portfolio) component is very powerful and it will help you identify project that align to your objects then do what if analysis to find the right mix of projects.
    Here are a couple of things you should think about when moving to PS2013:
    1) Who will be using the tool?  If it is a mix of onsite staff, remote staff, vendors, contractors etc. you may want to think about a hosted solution.
    2) Training.  Don't assume everyone will just magically 'know' how to use the tool.  Train everyone (team members, PMs, Executives) then train them again.  It's the only way to truly get the value out of the tool.
    3) Who will manage the system?  This is not a typical application.  The right administrator needs SharePoint, Project Server, SQL Server,  MS Project, Analysis Services and SQL Report writing skills.  Please note that much of this can
    be learned by the right person but DEFINITELY find the right person.
    4) Don't start customizing right out of the box.  You will get frustrated.  Adjust your organization to the tool early on.  I know that is easier said than done but you need a realistic approach to get tool acceptance moving early.  
    5) Use workflows but don't use them right out of the gate.  Workflows are great but I suggest you wait until phase 2 or 3 to start aligning them to your business processes.  
    6) Lastly and most importantly, you must first establish your own business processes THEN  align them to the tool.  DO NOT assume the tool will create business process for you.  You must think about how you are going to initiate a project,
    how are you going to track deliverables, how will time sheets be managed, etc.  Get to a whiteboard, crack open Visio and start building and establishing your processes now.  PS 2013 is pretty flexible and usually will align well with existing business
    processes.
    And don't forget to hire a good consultant.  They can be brought in during key phases of your roll-out to add value, help you avoid risks, and provide you with best practice advice.
    Good luck.

  • Resource time phased data in project server 2013/project 2013

    Hi all,
    I am using project server 2013 .
    one resource availability percentage is set as 80% ie 6.4 hrs per day. But when we are doin task assignment, only 5.6 is taken for a day and rest is pushed to next day ( i have noticed this in the timephased data in the task usage screen).
    for eg. if 6.4 work is assigned to the resources for a task with start date 1/1/2014 and end date 1/1/2014.  5.6hrs is taken for first day and 0.8 hr is moved to next day. Also the duration still shows as 1 eventhough task finish date is changed to 1/2/2014.
    Please help to understand is there any settings where 5.6 is taken for a day though the resource capacity is set as 80% ie, 6.4hrs.
    Thanks, Rose

    Hi Rose,
    is there any chance you have auto leveling turned on?  Menu Resource > Leveling Options > Automatic.

Maybe you are looking for

  • Can you do document compare in pages, can you do document compare in pages

    In that "other" word processing program, you can do a document compare to see how the documents differ. I have not found how to do that in Pages. Is it possible?

  • Probably a stupid question

    just got a macbook pro and want to be able to use the webcam to chat with my hubby on his PC when he is out of town on business. he does NOT have a webcam so we need to know what kind he can get that will allow us to talk and see each other. i know t

  • File reading at run time

    hi all, i have a problem that i want to read a file which is continously update(mean data is inserting in it) i want that my programme continously read the file and show the newly inserted data at runtime. thx in adavance for help

  • QoS application for Lync for Mac 2011 clients

    Hi guys, I'm deploying Lync 2013 at a customer site. We'll be applying QoS by enforcing static port ranges within Lync (CsConferencingConfiguration), and applying ACLs on the network equipment and dropping the various Lync modalities into the relevan

  • How can i make a simple app?

    Hi,  i just became an apple develiper,  Im wondering how to make a simple app like a "flashlight" like app,  Can anybody help me out?  would i have to start from scratch or could i use someone else's start??