Resourse related billing general query

Hi SD's,
I am PS consultant
Scenareo:
  In contract or sales order some pricing will be done and then net value will be arrived (if I am not wrong), suppose that net value is 500 USD.
According to the actual cost in project resourse related billing done billing request for 600 USD.
What will happen. I want to ask Net value is planned value and what is the effect of above scenareo.
Regards,

Dear,
Kindly put your question to PS Forum for fast answer as it is related to PS Module.
Regards
AJIT K SINGH

Similar Messages

  • Contract Management, Resourse Related Billing and Revenue Recongnisation

    Dear SAP Experts,
    Can someone help to provide me in  details such as configuration step by steps, Billing types, Billing plan with T. Codes  about the below.
    Contract - Service/Maintainace Contract, Quantity and Value contract configuration and billing document type with Transaction codes.
    Configuration steps for Resourse related billing
    Configuration steps for Revenue Recongnisation and Billing plan. This is urgent.
    best regards
    Nain Chand

    hi,
    The Price of a Customer-specific services are not determined by Standard Prices .
    For example
    Make to order production
    Plant maintenace
    Resource related Billing is used in the CUSTOMER SERVICE and PROJECT SYSTEMS
    We use the RRB process to bill the customer for the Material consumed and the Costs incurred in the customer project.
    The flow is
    Create the Sales order in VA01 which has the DIP profile assigned
    Now Using the Sales order create the BILLING REQUEST in DP91
    now create the Billing document in VF01 using hte Billing request in DP91
    VA01DP91VF01
    this is the flow
    Please check and revet.
    regards,
    santosh

  • General Query for CO related to PS

    Hi CO's
      WBS has reciever PSG in settlement rule, after settlement where the effect will shown for PSG.
    If using Resourse related billing if we do settlement first cost will be picked up in billing?
    Regards,

    If the PSG is the settlement rule, It will be updated in COPA.
    As far as resource related billing, it depends on scenario we are doing.. Some times we can capture revenue alone or costs alone..
    Please expalin your scenario in detailed.. i can answer you..

  • For third-party order related billing based on GR

    Hi Gurus,
    I have special requirement.
    In third party Processing we want to do statistical goods Goods Receipt.
    generally we do billing based on the setting in Item category TAS billing relevance "F" So system will allow billing once we do MIRO.
    Now i want to Do billing based on GRN.. is there any way for that????
    I tried with the option "G" . but it is not working. Is there any Settings i need to in Copy controls.?????
         Not relevant for billing
    A     Delivery-related billing document
    B     Relevant for order-related billing - status acc.to order qty
    C     Relevant for ord.-related billing - status acc.to target qty
    D     Relevant for pro forma
    *F     Order-related billing doc. - status according to invoice qty*
    G     Order-related billing of the delivery quantity
    H     Delivery-related billing - no zero quantities
    I     Order-relevant billing - billing plan
    J     Relevant for deliveries across EU countries
    K     Delivery-related invoices for partial quantity
    L     Pro forma - no zero quantities
    M     Delivery-related invoices-no zero qtys (incl main batch itm)
    N     Pro forma - no zero quantities (including main batch items)
    P     Delivery-related invoices for CSFG - No batch split items
    Q     Delivery-related invoices for CRM
    R     Delivery-related invoices for CRM - No zero quantities
    S     IBS-DI: Order-Related Bill. Doc. with DP w/o Billing Plan
    T     Delivery-related CRM billing with IC billing in CRM
    U     Deliv.-rel. CRM billing w. IC billing in CRM - no zero qties
    your immediate Reply will be highly appreciated .
    Thanks
    Pradeep

    Hi
    You can make the control setting as to whether the invoice receipt quantity or the goods receipt quantity should be relevant for billing in the copy control for billing on the item level in the billing quantity field.
    In Customizing, choose Sales and Distribution -> Billing -> Billing documents -> Maintain Copying Control for Billing Documents -> Copying Control: Delivery to Billing Document -> Item, then select an item category.
    Thanks & Regards
    Kishore

  • Order Related Billing - Overall Status B after billing

    We have changed billing relevance of our order related billing item category to B (Relevant for order-related billing - status acc.to order qty) and the copy control to the billing document to E (Goods receipt quantity less invoiced quantity).
    This now allows us to bill these sales orders based on the GR and not wait on the IR.
    However, how can we control the overall status of the sales order item billed? When billed partially, the overall status is set to B (Being Processed).
    I see no process, except changing order quantity which will set this overall status to C.
    I see COMPLETION RULE but after setting this and completing billing, the overall status is still BEING PROCESSED. I assume this is because the copy control from sales document to billing document does not have an 'update document flow' option.
    Is the solution a custom routine in the copy control?
    Thanks

    hello, jim.
    the system behavior is correct. in a purely order-billing scenario, the status remains as "being processed" because you have not completely billed the item, and there are quantities that are still to be invoiced.
    if the open balance is no longer to be billed, in general we "reject" the open items.  this action completes the line item status.  if there are no other line items in the order, the entire document will also be completed.
    i think you have a third party transaction.  when you say "partially billed", are you referring to quantities invoiced based on GR, which may be less than the order quantity?  if so, rejecting open quantities in the sales order should complete the order. 
    regards.

  • How to determine prices in Resource Related Billing(RRB)

    Dear Experts,
    I am working for service related client.in this SD,PS,HR and CO are integrated.
    from SD i have to create resource related billing.here while running DP91 how the system determines the resources related pricing.
    My doubts are:
    1.Whether prices are determined automatically or we will maintain manually?
    2.If prices are automatically:how and where we maintain?
    3.If prices are manually:how and when to maintain?
    I heard that to determine prices automatically by system i have to create Z table.
    Z table because,prices are differ from projects,and position of the employee.
    Thanks for helping,
    Ravikumar.R

    Yes, price determination is automatic
    If you have worked on DIP profile, there you might have come across term called Source.
    Based on the source system determines the pricing data.
    And SAP provide 9 different sources for different process like:
    1.
    Actual costs - Line items (most popular)
    2.
    Actual costs - Totals records
    3.
    Statistical indicators - Line items
    4.
    Statistical indicators - Totals record
    5.
    Funds - Line items
    6.
    Funds - Totals records
    7.
    Planned Statistical indicators - Totals records
    8.
    Planned costs - Totals records
    9.
    Easy Cost Planning (Generally used with PS Project)
    Details of source each can be learnt from SAP Help.
    Regards
    JP

  • Order related Billing-Excise duties

    Dear All,
    Excise duties are not flowing to RG1 print (J2I6) for u201CCash saleu201D Excise Invoice.
    For this I have done the cash sale process as below:
    1.Created an order (BV), here along with order no. Delivery no also got generated
    2.change mode of delivery (VL02N) done the PG1 (PICKING is grayed out)
    3.Created order related billing (BV), here I could see the Excise duties
    4.Created Excise Invoice (J1IIN) here also I could see the Excise duties
    5. Done J1I5 (with 601 move. type and IDH classification)
    6.Done J2I5 (RG1)
    7.Done J2I6 (RG1) here the Excise duties are not there.
    What is the procedure to get the Excise duties in RG1 print (J2I6) for Order related billing document?
    I have done the setting for Assign Billing doc types to Delivery doc types (CIN-SPRO) BV-BV
    Using TAXINN procedure
    Please suggest me.
    Regards,
    Ram

    Hi Swamy,
    I found the solution for my query.
    1.I have copied the BV(cash sale doc type) and created as ZBV in that(VOV8) I have changed, from order related billing to Delivery related billing.
    2.Done the copy controles for BV-BV (Delivery to billing at both header and item level-VTFL)
    3.Copied the Item cat (BVN) to ZBVN and changed the billing relavance from "B" to "A"
    4.In I tem cat assignment VOV4 assigned ZBVN (in place of BVN)= OR+NORM=ZBVN
    5.Done the process, and now I am able to see the Excise duties in RG1 print out (J2I6)
    Hope the process is correct.
    Regards,
    Ram

  • Order Related Billing for In-House Repair

    Has anyone figured out how to get order-related billing to work in the In-House Repair order when used with ERP billing?
    Your responses are greatly appreciated.

    Hi Peter,
    What I understand from your query is you want to do Billing in ECC of the in-house repair order. Kindly Confirm.
    If yes, follow these steps:
    In standard scenario external billing works with
    u2022     Service contracts
    u2022     Service orders
    u2022     Service confirmations
    Prerequisites
    1.     Synchronization of Master Data
    2.     Synchronization of Pricing Conditions
    3.     Customizing of Controlling Objects in SAP ERP
    4.     Customizing of service transactions in SAP CRM
    5.     Customizing of sales orders in SAP ERP
    6.     Mapping of transaction data between SAP CRM and SAP ERP
    Customizing
    In order to perform external billing of the service order materials, following configurations are to be done:
    1.     Create a Service order Transaction
    2.     Create an Item category - Putting Billing reference External Billing
    3.     Maintain Item Category Determination
    4.     Replicate the controlling relevant characteristics
    5.     Create the ERP Order Type- Tcode VOV8- SD Doc Category should be L.
    6.     Create the ERP Item category- Tcode VOV7 - Billing reference C
    7.     Maintain Item category Determination (ERP)
    8.     Maintain Mapping of transactions and item categories
    Settings for Service Processing  Billing Integration  Map Transaction Types and Item Categories
    When you set the status to complete, it triggers a debit memo request in ECC, with which ECC Billing can be performed.
    Regards,
    Shalini Chauhan

  • Order related Billing : Performance enhancement

    Hi Billing experts,
    We use order related standard CRM Billing (Periodic) and we have the below scenario.
    100 Customer share 1000 contracts with 0.5 Million Sales orders, undergo billing every month. currently it is taking 30 hours to finish the billing. our objective is to finish the billing in 15 hours.
    Please advise on how we can enhance the  performance of the billing.
    Regards
    Satish kumar

    Hi Ashis,
    Please follow below steps for your query:
    1. You will have to set two different billing types {one type for order related billing & one for delivery related billing} in sales document type configuration .
    2. The set up the relevant item category determination as per this sales document type, so that the proper item category will be picked up in the sales order level.
    3. Then set up the copy control fro the sales document type-billing document type at Header as well as Item level.
    I hope this will work out for your query.
    Reward points if you are satisfied.
    Regards,
    Hrishi

  • Order related billing for partial payment and inconsistent amounts

    Hi,
    We are using billing plans with payment cards to capture payments before goods are delivered.  SAP doesn't seem to support credit cards for down payments, so we are entering the payment in the payment card and billing plan lines, then generating the F1 order-related billing.
    Sometimes, the dollar amount is prorated proportionately, sometimes, it is disproportionately.  For example, if we have 5 line items for $100, $200, $300, $400, $500 a total net value of $1500, and the customer makes a credit card payment of $500, we are seeing that sometimes this explodes to $33, 66, 99, 122, 155.  Sometimes, it explodes to $0, $0, $0, $0, $500 in the billing document.
    Where does SAP control the way the amounts are derived in the billing document?  This is milestone billing.
    Ideally, we would like this evenly applied across all conditions.  I really need to understand how SAP handles this.  The configuration indicates that the pricing is copied straight from the order.  I don't see anything custom in the document copy procedure here.
    I have had a difficult time finding anything in forums or on the internet in general, I've tried search terms such as "order related billing amount distribution" and "payment card amount allocation" as well as a few other terms but haven't found anything helpful.
    Thanks for any suggestions you may have.

    Hi,
    Have you check in copy control order to invoice
    At item level Pricing type  it should be - G
    Kapil

  • Resource related  billing -reg

    hi
    My bunsiness process is like
    1.Quotation Creation,
    2.Sales Order creation with ref to Quotation,
    3. Resource related billing( A Debit memo request is creating with ref to Sales Order)
    4.Debit Memo creation with ref to debit memeo request.
    In above process customer's final billing happening from Debit memo request, From Sales ORder billing is not generating, So always that slaes order will be in open status na?
    In Resorse related billling is Sales Order is mandotory?
    Can you plz guide me
    regards
    Rajendra

    Hi Rajendra,
    I am not able to understand why you want to create debit memo request first then debit memo.
    Why are you not creating billing document with reference to sales order only??????
    As per your scenario solution is as follows
    Your first query is regarding status of sales order.
    Go to VTAA and select your combination of debit memo request and sales order.
    Go to the item level and select your item category and click on detail.
    Now in that put Pos/neg. quantity as + and save it.
    Now it will show complete status after you make debit memo request with respect to order.
    Second query is about mandatory reference.
    Go to VOV8 and select your resource related billing document or debit memo request.
    In that you will find reference mandatory which you can maintain or can remove it.
    Hope so this will help you to solve your query.
    Regards
    Raj.

  • Sales order status after resource related billing

    Hi All,
    When I am creating a resorce related billing debit memo request from DP90 with reference to a sales order, the status of my sales order item is not getting updated.
    Since i am referencing my SO items in DP90, ideally the 'Referencing status' for the order items should get as 'Fully referenced'
    Kindly help
    Aribis

    Hi Aribis
    IN IMG, in Sales and Distribution->Sales->Sales Document->Sales Document Item-> Item category, check the item configuration - one of the first fields should be completion rule, check tht it has the right completion rule, e.g. completed after full quantity has been referenced.
    hope this helps
    Kikas41

  • How to capture Ord-related bill.st. in a sales document item

    Hi Experts,
    Just want to know how will i able to capture the value of the Ord-related bill.st. in a sales document item.
    Here's to give you example.
    - Go to VA03 and type in a credit memo req.
    - Double click on first item material.
    - Go to "Status" tab and you will see the "Ord-related bill.st. under Processing status.
    I want to capture the value found to this and display it in my report but I have no idea what table maintain this.
    Hope you can help me with this ASAP... Sorry for the rush..
    Regards,
    Yu

    Hi Both,
    Thanks for this! I already saw this one but I'm doubting at first if this is correct.
    Nevertheless, thanks for all your answer. =)
    Appreciate your help! =)
    Regards,
    Yu
    Edited by: Aura Yu on Sep 16, 2010 12:37 PM

  • Invoice is not getting created in Order related billing

    Dear all,
    I am trying to do a Order related billing. After creating the order i am going to VF01 and selecting the billing type i have created and trying to create the invoice. I am getting the error "No billing documents were generated. See log" when i am checking the Log its showing now errors.
    In case if my account determination procedure is wrong, system should allow me to create a Sales invoice and accounting document will not be generated. But in this case even the sales invoice is also not getting created.
    Please suggest me if there are any configuration changes i need to do to overcome this problem.

    Apart from the suggestion already given, also ensure that
    the order is not showing in incomplete log
    the order is not blocked for credit limit
    You can also cross check in VF04 whether system is fetching that sale order.  For information, once you execute VF04, by default, system will check only "Delivery related" check box.  You have to manually select "Order related" check box.
    G. Lakshmipathi

  • How to Create Excise Invoice (J1IIN) with order related billing document

    Dear Experts,
    Is it possible  to Create Excise Invoice (J1IIN) with order related billing document? How? please guide
    Regards
    BK GAIKWAD

    Sir,
    We have make the supplementary Invoice (Debit Note) as per below process
    1) Create sales order_VA01
    2) Create billing document_VF01_with reference to sales order
    3) Create Excise Invoice With J1IS (Other Movement) It is manually job & due to heavy work load (create 200 invoice  per day) it is not possible to do manually.
    Hence we want to create excise Invoice with J1IIN instead of J1IS, any alternative solution for that?
    Regards
    BK GAIKWAD