Hi All,
With standard SAP the RA completed contracts (09) method doesnt create reserves for imminent loss.
We would like to calculate imminent loss. using RA -completed contracts (09) method and any one customized RA method "09" and calculated imminent loss. ?
Any help is appreciated.
Thanks,
Anusha

Hi Sudhir,
We are using CCM method (09) and we can't calculate imminent loss with this method.
In SAP-Standard the RA method for completed contracts (09) creates no reserves for imminent loss (sap-note 602707).
I'm looking for some solution to calculate imminent loss using RA method 09.
If planned costs are greater than planned revenues (= Imminent Loss) and the WBS-element status is REL  the system will automatically create a posting for imminent loss in FI and CO-PA. The amount of this posting will be planned costs u2013 planned revenues.If the WBS-element status changes to TECO those postings for IL will be automatically reversed.this what i would like to do.
could you please explain me RA configuration steps for above issue.
Thanks,
Anusha

Similar Messages

  • Results Analysis for Contracts

    Dear Experts,
    My Client requires to do Results Analysis for Contracts.  Please share your thoughts.
    Regards,
    Shareeq

    Dear Ahemad,
    In what would be the output of the result analysis ?I mean from sales point of view if u see then u will have to develop the report accordingly.
    If you are talking abt the MM contract then there are some std reports available.
    If ur talking abt the customer service point of view then we this std transaction IP51.
    thanks and regards
    raghav

  • Results Analysis on Contract

    Fellow developers,
    When we are creating a Service Contract VA41, we are experiencing something that I cannot figure out.
    When a plant is added to the line item and I go to the item detail screen, a results analysis key populates on the account assignment tab. Can anyone tell me why or where this key is coming from?
    Thanks,
    Justin

    Dear srikusap,
    When u carry the RA  through KKAX, then u can able to see the WIP for the WBS.  That is the reason we have to run RA.
    Raj

  • Results Analysis - Cost based POC method without margin

    Hello Experts,
    I would like to use the standard method - 03 , Cost based POC method but without margin. That means,
    1. System will calculate POC based on the actual costs and planned costs.
    2. Calulated revenue is created by multiplying the POC and the planned revenue.
    Here, Till the actual revenue is more than the planned costs, calculated revenue should be made equal to the actual costs.
    I have created standard method -03 and in the expert mode i have changed the profit indicator to " E - Profit Realization if actual revenue greater than planned costs"
    This works for first period when there is no actual revenue. After the actual revenue which is less than the planned cost,
    this does not work.
    Please let me know if you have any suggestion
    Thanks
    Regards
    Srinivasan Desingh

    in our projects I used to sit with CO consultant and do a lot of RA testing by changing different fields and finally reach the required result. Hit and Trial method (so it is hard to remember exactly what happen while changing a single field as there are many fields in expert mode). May be you can also try the same.

  • Automatic Reversal of Result Analysis Posting

    Dear Experts,
    I would like to ask for suggestions in solving below case in my current project:
    1. Project is created for sales of power solutions. Most of them are long-term, thus cost-based revenue recognition method is applied.
    2. Result analysis with cost-based method (03) is periodically executed for project. Therefore, every month there are some revenue deferral/ accrual posting calculated based on actual cost - before the project is completely billed.
    3. It is expected for revenue deferral/ accrual posting resulted from result analysis to be automatically reversed immediately in the next period (e.g. if RA is executed for July 2014, reversal posting needs to be immediately posted with posting date Aug 1st, 2014).
    At first we were thinking to define new document type specifically for the result analysis posting, and perform mass reversal using F.80 transaction. But then we came to realize that result analysis entries are posted after settlement is executed -and accounting document generated from settlement transaction cannot be directly reversed in finance.
    Anyone has encountered the same issue? How do we reverse result analysis posting without reversing the whole settlement transaction?
    Thank you,
    Regards,
    Analistia

    Hello,
    First you need to configure the functionality from the bellow path
    SPRO Financial AccountingGeneral Ledger Accounting Business Transaction  Manual Accruals  Basic Settings
    Once Engine configured Accrual document can be created through the easy access menu.
    AccountingFinancial AccountingGeneral LedgerPeriodic Processing   Manual Accruals  Create Accrual Objects
    Execution of Accrual documents
    AccountingFinancial AccountingGeneral LedgerPeriodic Processing   Manual Accruals  Start Periodic Run
    Regards,
    Venkat

  • Results Analysis Message KJ436

    While setting up Results Analysis for the POC method (03) and executing transaction KKA2, we got the following message. Both the CO version and the RA version are set to the same valuation (Group valuation). Any help would be appriciated.
    Basic RA version must have valuation category "0" (operational valuation)
    Message no. KJ436
    Diagnosis
    If a version has actual data (see basic version setting), it must be relevant to settlement in results analysis (see maintenance of version of results analysis).
    If a version does not have actual data (see basic version setting), it cannot be relevant to settlement in results analysis (see maintenance of the version of results analysis).
    Procedure
    1. Check the basic version setting in the maintenance of the general versions.
    2. Modify the results analysis version to conform to the basic version setting.
    3. Turn the indicator Version relevant to settlement on or off, whichever is appropriate.We are using CO plan version 0 (see below) and it is set for actual and plan. The RA version (0) (also below) is marked as being relevant to settlement. These settings seems to address the error message but I guess we are missing something.

    Hai Mikhail
    As u mentioned u set the RA method for POC3 in OKG3.
    Assuming maintained in OKG3 - the status control ,profit Basis,Valuation Level and its Minimum Values.
    Is the RA version been maintained in  OKG2 ?
    In OKG2 - need to maintain the RA version with respect to the Controlling Area like 0 or 1.
    Is OKG8 has been maintained on the Posting Rules - means where the RA version should have the corrsponding Profit & loss account number and Balance sheet account number.
    Kindly check and verify according to the relevant RA used/picked using OKG1 in Config - OKG2(maintain RA versions), OKG3(valuation methods for RA), Define Line ID's , OKG5 ( Assignment of Cost elements for WIP and RA) , OKG4( update of WIP calculation and RA) , OKG8 ( Posting rules in WIP and RA) .
    If all these maintained u will definetelu get the KKA2 result.
    ENJOY SAP PS
    Regards
    PP

  • No entered status set. No results analysis will be performed

    Hi Guys,
    I keep on getting this error message beloe and the valuation is on RELEASE status
    No entered status set. No results analysis will be performed
    Message no. KJ210
    Diagnosis
    The valuation of the order or project in results analysis depends on the status of the object.
    In this case, the object does not have an active status entered in the valuation methods in Customizing for WIP calculation and results analysis. Consequently, WIP calculation and results analysis cannot find a method with which the object can be processed.
    Procedure
    Decide whether the object should be processed in its current state (indicated by its active status in status management) by WIP calculation and results analysis.
    If you want to process the object:
    In Customizing for results analysis, choose Period-End Closing -> Results Analysis -> Define Valuation Methods for Results Analysis, add an entry for this status, and specify how objects with this status should be processed.
    If you do not want to process the object:
    This message is inconsequential for you. No follow-up actions are necessary.
    In Customizing for results analysis, choose Period-End Closing -> Results Analysis -> Define Valuation Methods for Results Analysis and select the No valuation indicator. This message is then no longer issued by the system.
    Example:
    In the standard system, there is normally no entry in the valuation method for the status CRTD (Created). You will therefore receive this message for objects that only have the status CRTD.

    Hi Guys,
    I manage to run the RA. The problem why I could'nt get it right was because I did not run transaction MMPV to close period for material master
    Thanks for your help.

  • Projects KKA2_ Results Analysis (Int. Orders/Projects)

    Hi,
    I have put the results analysis key under the control tab of a WBS element. When doint the KKA2 I am receiving the follwoing message.
    I want to post WIP and have done all account settings. could anybody explain the process for this periodic processing of projects how to identify WIP.
    I have posted via KB15 costs on this project and now I would expect the a WIP would be identified at this amount???
    Thanks Ulrike
    No entered status set. No results analysis will be performed                                                                               
    Message no. KJ210                                                                               
    Diagnosis                                                                               
    The valuation of the order or project in results analysis depends on the  
        status of the object.                                                                               
    In this case, the object does not have an active status entered in the    
        valuation methods in Customizing for WIP calculation and results          
        analysis. Consequently, WIP calculation and results analysis cannot find  
        a method with which the object can be processed.                                                                               
    Procedure                                                                               
    Decide whether the object should be processed in its current state        
        (indicated by its active status in status management) by WIP calculation  
        and results analysis.

    RA  is specific to the period you run for... this is standard behaviour.
    Regards

  • Result Analysis Valuation Method 3

    Hi PS Experts,
    The building block document on Profit Realization 'I58_BB_ConfigGuide_EN_DE' says that as per IAS 11 and 18, we need to configure Result Analysis Valuation Method 3 only which is cost based. Is it right and whether you are all having this valuation method in your SAP system where IFRS standards are applicable.
    Then, in addition to this cost based Revenue Recognition through this valuation method 3, we would like to input realistic POC(Engineer's certificate) into the system. Whether it is possible and if so, how and what other valuation method we need to use with or with changes to a particular valuation method. Appreciate your valuable inputs on this.
    Regards!

    Hello,
    Cost based POC i.e Method 3 is compliant with IFRS requirements. Other methods also are so.
    The choice of RA method depends on value/risk/duration/revenue plan of the project. We use this method for high value projects running for a long time where there is a need to recognise revenue before actual billing.
    Completed contract method is also used and very much in accordance with accouning principles.
    For POC calculated through progress determination- say Engineer's certificate- you can use method 7.
    Thanks,

  • Differance amoung the Valuation Methods for Result Analysis

    Dear All,
    In SAP Product Cost Controlling ther are 3 types of Cosings
    1. Production Cost by Order
    Path:- Production Cost by Order ---> Period end Closing ->WIP->Defind Valuation Method for( Actual Cost)
    2. Production Cost By Period
    Path:- Production Cost by Period ---> Period end Closing ->WIP->Defind Valuation Method for ( Target Cost )
    3. Production Cost by Sales Order
    Path :- Production Cost by Sales Order ---> Period end Closing --->Defind Valuation Method for Result Analysis.
    Note:  Here the point is Valuation Methods ( 1 to 17 ) availabel in Production Cost by Sales Order only.  The Valution Method is very important to Calculate WIP.  Different Countries follows different methods, but in the By Order and By Period we can get these Valuation Methods.  What would be the reasno behind this.  
    Regards

    Dear All,
    Any one have any ieda

  • Quantity base POC method of result analysis

    hello all,
    We are trying to create the result analysis key with quantity based POC method for Projects. we are choosing the Profit basis as E,K,M but we are getting the error ' Profit basis is only used for sales order.
    Can anybody help resolving the issue?
    Regards,
    sudhir

    RamSiva,
    I see that you've got the calculated COGS equal to the actual cost.  I would have thought that for quantity based POC the calculated cost should be equal to POC x C(p).  So if that's the case, I think the postings should be as follows:
    Debit Revenue for 36,000
    Credit Reserve for Revenue surplus for 36,000
    Since I don't know what the planned cost were I don't know what the correct signs are for COGS adjustment;
    Debit / Credit (Expense)
    Debit / Credit (Capitalized cost or reserve for unrealized cost, depending on the sign)
    If R(a) less than R(c) then:
    Credit Revenue
    Debit Revenue in excessive of billings
    thanks,

  • Which Results Analysis Method is good for LOSS Projects?

    Dear Experts,
    Our client have Loss projects scenario.
    for Eg. Plan Revenue_: 100,
    Plan Cost__________: 120
    Loss______________: = -20
    Loss 20 should post in accounts at first period end closing time itself for that which Results Analysis Method can help me for it. Plz give me your valuable solution soon.
    Thanks
    Bhagirath

    Hi,
    which RA Method you are using.
    If you are using method 01 then  in OKG8,Choose RA Cat RIML(Reserves for Imminent loss) or if you are using 03 method then use POCL .Assign the GL accounts againt these RA cat one B/S Account and one P&L (not a Cost element).
    Muzamil

  • Result Analysis method 03 Cost Proportional POC

    Hi,
    I am going to use Result analysi 03 Cost Proportional POC. Please guide me how the accounting entries will
    flow in  this method and formulas for this method.
    Thanks & Regards,
    Srilakshmi

    Hi,
    In your RA key definition, in column, Valuation...
    change valuation basis to J - Cumulative Actual Costs, Cumulative Actual Revenues

  • Result analysis method

    hi dear,the expert mode is active for one RA key,then how can i know the original result analysis method used in this key?because i can not display view of "simplified maintenance of valuation method" after expert mode used

    Hi,
    In your RA key definition, in column, Valuation...
    change valuation basis to J - Cumulative Actual Costs, Cumulative Actual Revenues

  • Results analysis for POC method with statistical cost element

    Hi,
    We are testing ETO (engineering-to-order) scenario With valuated
    project stock and cost based POC RA method.
    Inventory is updated during external procurement and we have used
    statistical cost elements (Cost element category - 90) for inventory G/L.We want to use a
    Result analysis method which considers this statistical cost elements
    for calculating POC.For this purpose we have implemented SAP Notes
    616960, 616869 and 78420.
    In short, as per SAP note 616869, we created a customer enhancement
    project for customer enhancement 5 of the results analysis (see Note
    H78420). We copied the source code for customer enhancement 5 of the
    correction instructions of note 616869 and then implemented SAP note
    616960 to read the statistical actual costs.
    Then we included the statistical cost as actual costs - Category K in
    OKG4.
    The system is doing POC and revenue in excess of billing calculation
    correctly after taking into consideration the posted statistical cost.
    During settlement of RA (CJ88), system is not giving effect to
    inventory value. On settlement of RA, revenue should be recognized but
    at the sametime the inventory represented by statistical posting should
    be consumed(COS). The system should post a P&L posting which reduces
    the inventory (representing statistical cost) and updates the actual
    costs on settlement.
    In our example, Statistical actual
    posting is of USD 57150, planned revenue USD 100000 and POC is 70.27%.
    Revenue in excess of billing comes to USD 70265.60. Recognisation of
    revenue of USD 70265.60 is not correct as actual consumption is yet to
    happen. The correct posting in FI should be revenue of USD 70265.60
    along with COS of USD 57150.
    Please suggest why on settlement the system is not posting the COS
    along with revenue recognised?
    Thanks,
    BK

    Hi Bijay,
    We are in a similar situation in one project.  Did you get any solution to the problem you posted here? If you can share it, please.
    Regards,
    Gireesh

Maybe you are looking for

  • Program that run a cron job in EP?

    Hi All, My requirement is : if a user upload a file to the specified folder in EP repository. (file will be .txt format), b'z they are the big customers to our client, so that they can just upload the order file.txt in a specified folder. after uploa

  • Inserting a Mac command symbol into a document

    Ok, this should be so simple but it's doing my head in. Basically, I'm preparing an indesign document - specifically a clue card sheet for call centre workers who use a Mac platform. I cannot for the life of me figure out how to insert the various sy

  • Volume adjustment

    when you have multiple audio tracks, how can you adjust the volume? - not just the entire volume for the track - not the volume for all tracks (master track) --> in master track you can fade in and out as you want by creating points. Is there a way t

  • Automatic conversion of purchase requisition to purchase orders.

    Hi I normally convert purchase requisition to purchase order automatically through ME59N. Now I want only firmed requisition to be converted to Purchase order when I run ME59N. Is there any way to do this. Other than ME59N is there any way to convert

  • Standard XML schema for Vendor data exchange between SAP and other system

    Is there a SAP standard way of XML schema that we exchange between SAP and other system? Please let me know. Thanks.