Rework Operation Quantity

Hi Guys,
I have a production order with operation 10,20 and 30 with quantity 10.
Triggr point is attached to operation 20 which would insert operation 25 If operation staus becomes PCNF.
lets say if a report 8 as confirmed quanity and 2 as rework quantity, new operation 25 is inserted in prod order with operation qty as 2.
Operation 20 has status PCNF now.
Now processing is carried further at 25 and rework quanity 2 is confirmed.
Operation 30 would be confirmed with quantity 30.
How operation 20 would achieve final confirmation CNF status if it has rework qty. After rework operation is inserted should we enter a final confirmation for 0020 with yeild as 0.
let me know.

Hi,
Follow the same procedure.
But is it necessary to have the status CNF?
SmanS

Similar Messages

  • Rework operation

    Hi gurus
    In production in any industry there will be rework generated at any stage of production operation.
    For this i have tried with rework activity explained in SDN and SAP Help.
    I am not able to get a proper result result like
    1) When tried with rework operation with a trigger point after result recording with required settings rework operations are getting created but the inspection charecteristics of the operation are not copied into the rework inspection
    2) Order is created with a trigger point to the inspection lot is not getting generated with out which we cannot record results.
    Can anybody clarify my doubt that why rework operation is addressed properly in SAP or is my assumption is wrong and there is a way out to address this problem.
    If there is solution in SAP to resolve this problem it will be of lot of help for the consultants like me.
    Awaiting a reply with a solution from the experts !
    Venkata Varanasi

    Generally in the Shop floor, rework happen frequently, In SAP rework is done by different ways
    1.     Automatic triggering of rework order when we enter rework qty in confirmation screen.
    2.     If rework has to be done immediately after entering in to rework qty in the confirmation screen before proceeding next operation, by done by control key with rework option and enter the time in operational detail and operation quantity.
    3.     Create a reference operation set and create a rework order with rework order type and settle the rework order into main production order.
                             If the order quantity is 100, and have 5 oprn, in the second operation rework happened means confirm the operation with partial confirmation with entering yield and rework quantity, and create a rework order, in the rework order confirm the quantity with Final operation. Again in main production order, in the 2 nd operation confirm the rework quantity with out entering any activity in the confirmation with final confirmation.
    Regards,
    SUNDARESAN.E.V

  • Fixed operation Quantity- Execution factor

    Dear All
    SAP NOTE:
    Use of Execution Factor
    Use the execution factor to indicate how many times an operation or sub-operation is to be carried out during processing of an order.
    The execution factor refers to the work, the operation duration, the operation quantity and the material quantity.
    If the indicator fixed operation quantity was set, the execution factor has no effect. If the indicator fixed lot was set, the material quantity remains unchanged.
    Where i can find Fixed operation quantity and fixed lot indicator field in project builder.
    Thanks
    Shobana

    Please refer this SAP link:
    http://help.sap.com/saphelp_erp2005/helpdata/en/0f/28b904c3e511d194f900a0c93033d8/frameset.htm
    i.e.
    If the indicator Fixed lot quantity is set (in the component item under General data), the execution factor of the components is not taken into account for the component quantity.
    If the indicator Fixed op.quantity is set (on the external processing screen of the operation), the execution factor is not taken into account.
    Hope this will help you.
    Regards,

  • Selection Of Alternative Sequence Automatically By Operation Quantity

    Dear All,
    We are Using Discrete Manufacturing Scenario, In That Scenario Routing Contains Six Operation and One or Two Operations having alternative Sequence , My client required during production Order Creation , If Operation quantity is more than 250
    system should select std sequence else system should select alternative sequence, But i am not getting to mantain lot size for std sequence for operation even I maintaining lot size for alternative sequence , system should not considering alternative sequence. Pls Suggest me how to Resolve Issue
    Thanks

    Vipin,
    It is not possible to control the  routing sequence selection based on lot size.
    As suggested by forum experts, create mulitple group counters for the same material routing group and you can use them based on lot size.
    You can also create production versions for different lot sizes.
    Check and revert,
    Santosh Sarda

  • In-process  inspection for rework operation

    Hi all,
    i have a production order to which the in-process inspection characteristics are assigned in routing. when a production order is released, an in-process inspection lot is created. Inspection is carried after the end of an operation.  During which rework will be carried out if the product is rejected.   Rework operations are trigged through trigger points assigned to the production order. A reference operations set indicating the rework operations is assigned to the trigger point. rework operation in the reference opeation set is also assigned with inspection characteristics.  But during the results recording, the rework inspection characteristics are not displayed for results recording.....
    pls explain the possible solution.
    regards,
    sravan kumar v

    Hello
    I think that the process can be mapped in one of these ways:
    - according to what you describe this is closer to a good receipt inspection and not to in-process inspection, as the trigger for the inspection is the GR and not the release of the order. So, why dont you give a chance to a 04 inspection type, with inspection lot creation for every GR ? Check the indictor in MM02, QM view for "04" inspection, and uncheck the "Stock in quality", so you dont get caught by the stock in quality and resembles in process "Non-stock relevant" inspection
    - alternatively you can define the use of inspection points ? So you are adding new results as new confirmations are made. Disadvantage: you can only give one usage decision to the inspection Lot, irrespective of the number of samples you have analyzed.
    Regards

  • Rework operation in the routing

    Hi All,
    We are in the REM process,  We plan to change the existing Routing so that need to include the rework as the operation in the routing.
    we are not going to do rework for finished product (i.e after the confirmation). if any problem , we make it as the scrab.
    we need to do the rework for the product before final stage of inspection itself  . ie. we have a inprocess inspection .
    i.e we have a operation called soldering, if this is not done properly, we remove the soldering and do it again as a rework.
    1.how to mapp this operation as rework in the routing
    2. whether  we need to create the separate routing for rework or we can add this rework operation in the same existing routing itself ?
    3. if we do rework for the assembly, we can do create the rework, but in the component stage itself
    we need to do the rework.
    Edited by: raj on Jun 5, 2009 7:37 AM

    Hi Ramaling,
    my scenario is like , we have 10 operation, after the 3rd operation, we have the inspection as the 4th one.
    if any qty have rework , we have done the rework manually .
    so client need us to create the WC for rework and they need to find the cost inoccur for the rework
    after rework was done ,all the other operation will continue  for the reworked materials.
    how to include this rework WC in the routing what we used.
    is it advisable or not
    if it is not how to mapp my scenario ?
    Edited by: raj on Jun 5, 2009 12:52 PM

  • New operation for production order - change operation quantity not possible

    Hello all,
    we want to create a new operation for a production order.
    So we go to CO02 and to the operation order overview screen.
    But when we add a new operation, the system will not let us determine the operation quantity for the new operation, the system will just take the quantity from the operation before.
    How can I determine the qty by myself?
    Thanks
    Anne

    You can do another way also.   You change your routing with new operation quantity and save it in CA02.    NOw you go to CO02 and read master data in funtions,  then the new operation quantity will definetly come in to the production order.
    KrishnamurtyDSS

  • Difference between "base quantity" and "operation quantity" in an operation

    Hello
    what is the difference between "base quantity" and "operation quantity" in a production order ?
    thank you for your answers

    Base Quantity - Quantity of the material to be produced to which the standard values of the operation refer.
    Operation Quantity - Quantity planned for this operation.
    Base quantity and operation quantity may not always be the same, if we have partial lots delivered during the sequence of operations, the operation quantity will be equal to the lot delivered during the operation.
    Base quantity is dependent on the BOM, where it signifies the total quantity of output after using the components of certain quantity.
    Hope this may help you.

  • Rework operation in REM

    hi,
    how can i confirm  rework operation in rem manufacturing.
    already backflush happened.

    Dear Prakash,
    Do you want to post the activities that have been used for the extra operation of a HALB or FERT material?
    Then enter the material Part no and the radio button for activity backflush and by the options fetch Planned activites from routing or No
    Planned activities from routing.
    This extra amount spent can be checked in KKF6N in Product Cost collector of that material.
    Regards
    Mangalraj.S

  • IPC control for added rework operations

    Dear Experts,
    Can you please, help me with the following case:
    I have a production order and IPC control for certain operations.
    The system has created an inspection lot (03).
    During the results recording (with operation confirmation) one piece is reported to be for rework.
    The trigger point was activated and a new operation for rework was added to the production order.
    The new operation for rework also has an inspection point (the same as in the production order - freely defined, no quantity or time dependency) and also has a quality characteristic.
    My expectation was that after the new operation has appeared in the production order either the created inspection lot should be updated for the new operation and its characteristic or a new inspection lot should be created for the new operation.
    However nothing happened - where did I go wrong or what is missing?
    I will gladly supply additional information on demand.
    Looking forward to hearing from you,
    Rumi

    either the created inspection lot should be updated for the new operation
    This is not possible in std SAP ,As Once lot is created it will not updated automatically after changes made in the task list or routing etc.
    new inspection lot should be created for the new operation.
    This will also not possible because lot is already created for the said Qty in Production order.
    Now what remains is if you have not taken UD of the existing lot & status of the Inspection lot is REL then,
    go to QA02>enter lot number->click on Reset sample--->save
    Now status of lot will become CRTD.
    Now again go to QA02>enter lot number->click on inspection specification>click on sample>save
    check the status .It should be REL & here you can see the new operation attached to the task list.

  • Rework for quantity in sales order stock

    Hi Gurus,
    The following is the scenario of my client.
    My client is a paint manufacturing Industry. T
    They Will create a sale order for 100 Gallons of paint.
    Will convert the sale order to process order and bring the stock to quality inspection (batch managed)
    After inspection quantity will be moved to sale order unrestricted use stock.(321 mvt type)
    Now i have to send  only 1 Gallon to the customer and based on the approval from customer, we will dispatch the remaining quantity.
    In case the customer rejects the sample, i want to carry out rework for the remaining batch (balance 99). Now the stock will be in sale order unrestricted use.
    How to carry out the rework for the unrestricted use quantities in sale order stock.
    Please let me know how to address this scenario
    Please give your views it will be helpful for me.
    Thanks and Regards
    Hari

    Hi,
    For mapping this requirement you have create a rework process order type and when ever you create rework process order for rest 99 you have to delete all component from component overview tab and add that stock of 99 pcs which is lying in sales order stock.
    Note :- This can only happen if this is not the dispatch location. If this is the dispatch location you also have to create a separate storage location before this sales order location.
    Regards
    Vivek

  • Create Rework Operation in Production Order

    Hi,
    I am looking for a function module that will create/insert an operation in a Production Order when a rework is done.
    Do you know any? Please help. Thanks.
    Regards
    Ryan

    Hello Frank,
    Please inform us the follwing details:
    Whether you are getting the Status: PRT after Shop papers printing?
    Immediately after the operation insertion (Because of Trigger Points) what is the Print Status?
    Please refer the OSS Note for fuether details: 755992, 568883
    Regards,
    Siva

  • Operation quantity

    PP Gurus,
    In CO15 order quantity reflected, but for the same order in CO11N order quantity is not reflecting. What will be the reason?
    Thanks in advance

    Dear ,
    U have to goto OPK4-Confirmation Parametrs set up.Selcet the Order Type and click on the change mode.Here u will find  the Tab " Operation Individaul Entry using initial screen " .U have to mark  Display Confirmed Quanitites /Display Default in Quanity tab page .U have to do the same in Date  as well as HR data if wish to fetch all those information from Production Order .
    Hope this will solve the problem .
    Regards
    JH

  • To split an operation quantity in a single production order into different work centers.

    Detailed Process:
       Our client have 17 factories. Inside each factory there are 15-20 Sewing lines (Work Centers). In each line 15-20 machines (individual capacities) are there. The standard manufacturing scenario practiced here is MTO. Merchandisers create sales order and allot it to a particular plant. Now line level planning happens inside the factory. Based on the order delivery date to meet the requirements they split the production order and allot it to several sewing lines (work centers).  In SAP we can have work around solution to partially convert planned order to production order and allot it to particular line. The challenge here is to have same production order number which can be allotted to several sewing lines with a mandatory option to enter the quantity for each sewing line
    We have proposed alternative and multiple routing for converting planned order into number of production orders but the solution was not meeting their requirements.
    Please provide your valuable opinions on this issue.

    Hi,
    Please explore the option of using the concept called Parallel sequence in routing...
    Check the below thread...
    parallel sequence in Routing
    Routing - Parallel Sequence
    Hope this helps
    Thanks
    Kumar

  • Rework operation in configurable products

    Dear Experts ,
    I need your expertise knowledge in Re-work scenario for configurable product.
    I have a scenario where i have produced one configurable product which is lying in stock against specific customer.
    Now at some point of time , i came to know that this product can be sold to some other customer with just change in the few variants like color and
    Cylinder capacity. In this kind of scenario , to carry our re-work process my business wants to consume the stock lying against different customer in
    stock ( hopefully customer delaying to get it delivered)  Is this the right approach..? Can i consume the configuarablke material stock and make few
    changes and deliver to the customer..? Is this the right approah.
    Need you expertise knowledge on impact of both Finance. Production.
    Note : i have tested the scenario , system is allowing me to consume Stock of configuarable product ( For testing purpose i did transfer posting from customer stock to own stock by 411 E.
    regards,
    Daya

    Hi Daya,
    To understand myself the above scenario, I used the
    example of Tined drinks/beers. The product beer is going to be the same for the
    brands UB and Kingfisher, only the difference is brand sticker pasted over the
    tin.
    Now, the retailer of UB had placed some order and the
    stock for them is produced as well and available at UB sales order stock. In
    business perspective it is required to remove the UB sticker from tin and paste
    the kingfisher stickers over it.
    In the above structure, I hope there is no standard SAP transaction available for links in colour red(For dis-mantle and re-assembling). All the links in Green are available in standard SAP. If the scenario is often occuring, then it is good to have a custom program for this in the below mentioned way.
    Step 1
    The final product (UB Beer), to dismantled to beer and UB sticker (may be 132 and 262 - Consumption reversal), here it is possible to custom single level or multi level as well - The cost of dismantling also to be capture in a seperate cost center (may be a re-work cost center).
    Step 2
    Assemble the Beer and KF sticker (131 and 262) - Assembling cot needs to be captured in seperate cost center if required. Or for ex, if this stickering operation is defined as a seperate level of process, then this can be handled by cretaing a regular production order.
    This dis-mantling custom program can be used for scrapping as well, for ex, the final product is rejected and needs to be scrapped for some reason, But some of its components are re-usable.
    This dismantling and re-assembling is very often in breweries as there would be lot of promotions and discount sales will be going on and to push the produce stock it is required to go with the brands which is selling high in a particular season.
    But it is good to go for custom program only if the dis-mantling and assembling is often in the business process. Other wise it is better to split the configured product into two process like
    Process 1 - Until the configuration come into place, produce the product at this level in MTS scenario
    Process 2 - Pick the MTS product and go either for ATO or STO scenario.
    Let the community know any further inputs are required.   
    Regards,
    Chinna.