HI,
I have created,
tigger point, assigned to operation (before this created reference operation set assigned in trigger point).
While confirming (CO11n) operation (with PCNF, where tigger point is assigned), a pop-up is coming for creation of rework order and also CO01 seen, but in MD04 I am not seeing this order. why?
what is problem can any one help on this.
Thanks
Raj

Hi,
Then what sould be setting?
can pl tell me to over come to create 2 orders (means 2 times pop-up coming while I am doing confirmation as yield as 2 and rework as 2 entry for the total order quantity =4 PC).
Santosh,
New order is created with material and it can be seen COOIS as said by you and others, but you said there is way in the same order to create, pl tell me what procedure for this?
Thanks to all
Regards,
Raj

Similar Messages

  • Purchase Order is not created once in a while

    Hi All,
    I have peculiar problem that, when we are creating purchase orders some of the purchase orders are not existing even it gives message "Purchase Order created with purchase order number" is displayed.
    But if I try to create the purchase ordrer with same data it is creating, this problem is coming once in a while.
    points will be rewarded
    Regards,
    Venkat.

    customizing problem.
    or
    field mapping not correct.

  • CRM service order does not create purchase requisition

    Dear experts,
    CRM 5.0
    We have a scenario where saving a released service order should create a purchase requisition in ECC and update the document flow. I have performed the following steps and still the PR isn't getting created.
    1. Configuration in CRM and ECC for integration of service processes with logistics and maintaining the purchasing document types.
    2. Maintaining standard pruchase groups in ECC table V_TMW01
    3. Assigning standard purchase org to the plant
    4. Making sure correct RFC destination is assigned to the logical system.
    Am I by any chance missing some middleware steps as saving the service order does not even trigger anything in the system?
    Thanks
    Ritwik

    Hi Ritwik,
    Just check the following activities  are maintained or not
    1) You have created the subscription in SMOEAC with Site , Replication object  and Service Order
         Process type in the criteria value.
    2) You have maintained the customizing entry in CRM in spro for the following combination in logiistics      
        Integration for  Trans.Type  Item Cat.  Service Organization Org Unit (Service)  Log. Scen.
    Regards
    Pavan.A

  • How to block the sales order for not creating requirement

    Dear All,
    My client want that whenever a sales order is raise, that should not go create requirement for production unless until account department check whether the prices etc are correctly put or not
    how can i do this
    thanks

    I suggest you can try to use the functionality of Status Profile.
    Create one Status Profile  with 2 line items-
    1: First line : Pricing Approval or PR and check what all you want to block if this status is assigned to the order type.
    2: Second line : Released and check what all you want to be released once the Approval is done.
    So by default the status profile - Pricing Approval will be assigned to the Sales Order during order creation. Then after your accounts department check the pricing and approves , they can change the status to Released and the order can be processed further.
    Regards
    Sai

  • In-House Cash - Internal Payment Order is NOT created.

    Hi.
    I already finished all customize needed to post the internal payment order.
    But I couldn't post the internal payment order using Transaction-code: IHC1IP.
    The message below is remaining. (Other messages were cleared.)
    Error message - Payment order IHC/0100000002/2011 was not posted(Message no. IHC298)
    In addition to the above,
    Inboude IDoc: PAYEXT also doesn't post
    with Status: 51/Message: Bank JP 9990009 is assigned either to no bank area or to more than one.
    In Customize, even though Bank key 9990009 is assigned to Bank Area: IHC ONLY.
    I think these errors are caused by same reason.
    What customize should I check?
    I know this question is really abstract though,
    I'm a MM consaltant not FI specialist, so I need your helps...
    Thanks.
    Naomi Hirose

    Thanks for your reply, Ravi.
    My target is the Internal Payment Scenario with IDoc.
    After processing of Automatic Payment Transaction (T-code: F110) on the subsidiary's server,
    inbound IDoc (Message type: PAYEXT) doesn't process on the IHC server,
    and I got the IDoc Status 51(Application document not posted) with a message below.
    Bank JP 9990009 is assigned either to no bank area or to more than one
    I already checked all customize corresponding the BANK AREA,
    but I didn't found the reason...
    Since IDoc doesn't process,
    I tried to post the internal payment order manually to find the reason of above error though,
    only one error message appeared on detail log screen,
    other messages are green.
    #on the detail log screen
    red signal)......Payment order IHC/0100000005/2011 was not posted
    green signal)...Account currency amount 1050 JPY to be posted for items - OffsetAcct
    green signal)..Source transaction currency amount: 1050 JPY
    green signal)..Posting JPY made to original account OffsetAcct 2
    green signal)..Account currency amount 1050 JPY to be posted for items - Payer
    green signal)..Source transaction currency amount: 1050 JPY
    green signal)..Posting JPY made to original account Payer Account 1
    green signal)..*--- Final Posting: Internal payment order
    green signal)..Transaction type INTPAY was transferred with posting attribute FINP
    green signal)..IHC payment order IHC/0100000005/2011 was created
    Thanks.

  • My sales order is not created and showing erroe

    dear sir,
    i ve already created the customer with internal no
    and wen i m raising the sales order one erroe is comming" no costomer master record exist for the sold to party" error no 199
    but the customer master is still there and i ve  also created the custome in same sales area wer i m raising the sales order
    before some dayz i ve done a blonder that i ve deleted the partner functions from strandard but again i ve created as standard .then i used it for my account group.
    so why the error is comming please help
    its really urgent....
    with regards
    subrat

    Subrat,
    since you deleted the cusomer master and since your number assignment is internal , once you delete the customer master you would not be able to create the customer master with same OLD Number range , it will take a new number this time for the sold to party which is created.....
    and that is why the old one will not work , use the customer master and it should work fine ...
    Cheers

  • Sales Order is not creating with reference to Quantity Contract.

    Dear SAP Experts,
    I am creating a Sales Order with reference to quantity contract but system showing an error *"""Material SUG10051 does not exist in RG1 Table for Excise Group 42 - Message no. ZCOMM002"""* i am not getting y system showing this error because all the necessary configuration for series group is maintained already.
    Please advise me what should i do.
    Looking forward for your quick response on the same.
    Regards
    Parul Deshwal

    Hi
    As per STD SAP, all billing items will be updated in RG1 register.
    The control is in J1ID where you have to select "Material and Chapter ID combination" and choose the tab "Material type".
    There against the billing material code, maintain "F"
    Also check setting
    IMG --> Logistics General --> Taxes on Goods movements --> India Check Basic Settings, Master Data, A/c deteremination, Business transactions and Tools.

  • Sales order do not create after SAP upgradation to package EHP7

    Dear Experts,
    SAP client is recently upgraded to EHP7. Since then we are observing difficulty in Sales order creation [VA01] manually [with or without order reference].
    When click on SAVE button, entire screen display get freezed, without any message [Error/Information/Warning] pop-up. it seems as if system was trying to display message; caused due to any kind of event occurrence; but unable to show up.
    Moreover, when we click on "BACK" or "EXIT" button, then it prompts choices to save the data. Yet again we receive the same freeze response whenever chose "Yes" option.
    Please note:- before up-gradation, we were able to create orders with the same data, what we are using to create now.
    Any help or clue on this subject would be highly appreciated.
    Thank you for all your help.
    Best regards,
    Rahul Agarwal

    Hi,
    did you check what are the sales orders Enhancements that are activated with EHP7 under T.code-SFW5

  • Purchase order Acknowledgement not create in SRM?

    Hi there,
    We are able to create Purchase order in SRM, but we don't see PO Ack generated. How do we set up PO Ack in SRM? Are we missing some configurations?
    Any help is appreciated.
    Thanks,
    Karma

    Hi there,
    We have a scenario where we trigger,from portal, in R/3 to send Orders02 to XI,XI maps Orders02 to Purchase Order to XML, and  sends to a SRM system. We see a Purchase Order being created in SRM system, and ALE AUDIT Idoc is sent to the sender R/3 system sucessfully. Now, when we "confirm" the purchase order in the SRM system, this should automatically trigger a Purchase Order Response from SRM to XI and then from XI to the R/3. This part isn't working for us. Are we missing some configurations the SRM side?
    Does anyone know how to fix this problem?
    Any help is appreciated.
    Thanks.
    Karma

  • Purchase order in not created in classic scenario

    hi everybody,
    we are using classic scenario.System is unable to create a PO direcetly in the backend .it created a pr when the shopping cart is created in R3.i have done complete settings like define backend objects ,and in shopping cart i have entered price as well as vendor.kindly let me know the solution.
    thanks
    chakradhar

    Hi. Muthu is probably right, are you entering a fixed vendor from a contract or are you keying in a desired vendor?
    If you key the vendor in you will get a req, as it is not a fixed source of supply.
    To make it fixed you have to use the BBP_DOC_CHANGE_BADI to change the partner type from preffered to fixed.
    Regards,
    Dave.

  • Auto-release Planned Orders is not creating WIP job after zero on-hand (i.e. Level Below  safety stock)

    Hi
    The time release fence in defined at item level as 1 day also safety stock level is defined in inventory safety stock form.
    Once MRP launch it should create the discrete job against item as zero onhand for that item but MRP workbench is showing planned order for the item instead of creating item.

    Hi
    The time release fence in defined at item level as 1 day also safety stock level is defined in inventory safety stock form.
    Once MRP launch it should create the discrete job against item as zero onhand for that item but MRP workbench is showing planned order for the item instead of creating item.

  • Planned order is not creating for a phantom assembly

    Dear experts
    My fert having two semi finished components
    first semifinished is assigned with a raw material
    And second semifinished is assigned with two different raw material
    in material master of second semifinished mrp2 view Special procurement=50
    and after running mrp, second semifinished is not getting any planned order or dep requirement all the raw material under this getting planned order
    But in my understanding of phantom second semifinished in should not get any planned order?
    Am  i correct?
    Pls advise me where i need to check
    Abu Fathiam

    Hi,
    Phantom assembly will generate planned order for its component when you will maintain:
    Procurement type: E
    Special procurement type: 50
    Also in SPRO: OPPQ BOM explosion
    Also check in BOM In basic data tab
    In MRP Data screen, check explosion type- are you maintained phantom assembly off? Check it if you want planned order.
    If you don't want system generated planned order for your phantom assembly component you should not maintain this indicator.
    Regards,
    Alok Tiwari
    Edited by: Alok Kumar Tiwari on Feb 29, 2012 11:38 AM
    Edited by: Alok Kumar Tiwari on Feb 29, 2012 11:39 AM

  • Error when creating rework order

    Hi
      When I am creatng a rework order for a material it is showing an error message that referance doesnt exist why is that error coming

    Dear Pradeep,
    Cofiguration Settings For Rework order
    1) just copy std re-work order type & give new name as u required in OPJH
    2) in OPL8, copy existing rework order type & give ur re-work order type & plant & save
    Master data for rework order
    1) CA11 - Creating reference operation set
    1) after Executing CA11, just enter without giving data in initial screen
    2) usage - 1, status - 4. from lot -1, then click on operations
    3) then give work center & descrption
    4) Double click on Description, then give timings for setup, machine & labour & save
    Rework order Creation
    1) Normally rework order is created by t-code CO07
    2) while doing confirmation of header material in CO11N or CO15, we give re-work quantity
    3) then creat re-work order in CO07
    4) in CO07, give plant then order type (rework order type) then enter
    5) materail description, quantity to be reworked then date enter
    6) system will ask u refernece opeartion set (it should be created before only in CA11)
    7) then give the referce operation set Number then system will take u to settelment Rule
    8) here for CAT, give as ord, then in settelment receiver give ur header order number then percentage as 100 %
    9) then clcik on component overview icon, then give ur BOM componets (which to re-worked & assign an opeartion to it)
    10) then save the order
    11) then do the confirmation to re-work order
    12) then do GR to header order & settelment will take place to header order only not to re-work order
    Note : For rework work, GR will not take place
    Regards
    Madhu

  • Restrict Product Allocation if Planned order is not getting created

    Hello All,
    We have a scenario that when ever a Sales Order is getting created, Product allocation assignment will be done automatically and planned orders will be created for that requirement in APO.
    There are some cases where in because of wrong Variant Configuration, Planned orders wont be created. Our requirement is to delete the Product Allocation automatically or to stop the product allocation assignment if the planned orders are not created.
    Do we have any standard setting for doing so or Kindly suggest me some BADI's which can be used for it.
    Thanks in advance.
    Best Regards,
    Srinivas.D

    Srinivas,
    A rather odd requirement.
    Have you tried in SCM APO 'Maintain check instructions' to perform the product check first, then allocation?  I would think that if the product check failed, then allocation would not be consulted, and no allocation therefore assigned.
    IMG > APO > GATP > General Settings > Maintain check instructions
    Best Regards,
    DB49

  • SRM Purchase Order not Created Automatically

    SRM 7.0 Extended Classic Scenario:
    Issue:  When creating a standard shopping cart in SRM the Purchase Order is not created in SRM (or in R3).  Eventhough the shopping cart is fully approved and has a vendor assigned.  The overall shopping cart status remains approved,the line items status shows 'item in transfer process'.  Otherwise there are no errors in the application monitor.  Nothing appears in table BBP_DOCUMENT_TAB
    Considerations:  Everything is working fine for limit shopping cart, the PO gets created automatically and the SC has status follow-on document created.
    Also, this was working fine for standard orders, it seems that support pack 7 or 8 broke this functionality, yet I do not see any notes regarding the issue.  Any ideas on what controls the automatic PO generation or how it could work for limits but not standard SC's would be greatly appreciated.
    Thanks,
    Matt
    Edited by: Matt Joseph on Nov 17, 2010 10:27 AM

    First of all PO should be created then you can see entry in doc table.
    u Note 1480994 - How to process a shopping cart with status I1111?
    see SAP treatment and some work around..
    Symptom
    Shopping Cart is stuck in status I1111 (Item in transfer process).
    Other terms
    Application Monitor, I1112, I1111, Monitor Shopping Cart
    Reason and Prerequisites
    This is a FAQ note, which shows how to treat such Shopping Carts.
    Solution
    Shopping Cart status I1111 (Item in transfer process) is a temporary status, which means that shopping cart is being processed in order to generate a follow-on document.
    However, it is possible that status I1111 becomes permanent and, in this case, shopping cart status is inconsistent.
    There are some procedures to be considered when shopping cart is stuck in status I1111.
    Report BBP_ALERT_SB_NOTTRANSFERED is available to change the status of the shopping cart item from I1111 to 'Error in transmission' (I1112) and later on, it is possible to retransfer this shopping cart from Application Monitor/Monitor Shopping Cart transactions.
    Note 441768 provides more information about this report.
    However, BBP_ALERT_SB_NOTTRANSFERED works in a time stamp. BBP_ALERT_SB_NOTTRANSFERED will check shopping carts created after date specified in table BBP_CONTROL.
    To check this information, go to SE16 -> BBP_CONTROL and as input parameter provide the report name. Here you will see the last date that report has been run.
    If you have a shopping cart in status I1111 which is older than date specified in table BBP_CONTROL, you have to change manually the time stamp specified in such table. You have to specify an older date (before shopping cart creation).
    Doing this, you can run report BBP_ALERT_SB_NOTTRANSFERED and cart in question will have status I1112 assigned.
    Once status I1112 is assigned to shopping cart, you can retransfer it from Application Monitor (BBPWEBMONITOR transaction in SAP_GUI) or Monitor Shopping Cart in the web.
    To transfer Shopping Carts from BBPWEBMONITOR, some settings need to be done.
    Following notes should be considered:
    550044
    FAQ Alert monitor RZ20 does not show any alerts
    396102
    BBP Alert monitor RZ20 does not work
    387701
    The Shopping Card are not transfered after "resubmit"
    According note 387701, workflows WS10000214 and WS10000215 have to be activated. One of them is to delete shopping cart item using Application Monitor and the other one is to resubmit the cart. Then, once this settings are done, you can retransfer I1112 carts from Application Monitor.
    If all settings are done and you have a cart with status I1112 that it is not appearing in Application Monitor, report BBP_ALERT_SC_STATUS_ERROR is available, which checks the carts in status I1112 and put them in the Application Monitor, in order to allow you to transfer them again. Note 631513 explains about this report.
    Additional notes to be considered in this scenario:
    1159609
    Transfer function does not create local purchase orders
    1233037
    BBP_MON_SC: Shopping cart transfer ends in status I1111
    1040878
    Cannot transfer shopping carts with status I1112
    Header Data
    Release Status: Released for Customer
    Released on: 09.08.2010  16:04:09
    Master Language: English
    Priority: Recommendations/additional info
    Category: Consulting
    Primary Component: SRM-EBP-SHP Shopping Cart
    Secondary Components: SRM-EBP-APM Application Monitors
    Affected Releases
    Release-Independent
    Related Notes
    1233037 - BBP_MON_SC: Shopping cart transfer ends in status I1111
    1159609 - Transfer function does not create local purchase orders
    1040878 - Cannot transfer shopping carts with status I1112

Maybe you are looking for

  • How to register custom report under Custom Development Application

    Hi 2 all How to register custom report under the Custom Development application in R12 vision DB, and also confirm location/folder of Custom Development application in R12. Thanks Zulqarnain

  • TestStand 4.0 Slow Startup

    Hi, I've just recently updated the TestStand from v3.5 to v4.0. I found it's significant slower than v3.5. It took around 1 min to load the TestStand sequence editor with a blank sequence. My computer is a P4 3GHz HT w/ 1G of memory. I checked task m

  • Ipad locked - please help

    Hi all, my iPad got locked after the soft update, it now asks  me for the passcode and when I tried to restore from the computer it tells me to go on my ipad and disable ipad find first, but I dont even have it installed. so I am stuck. anyone can he

  • How to import cd into existing playlist?

    In the new (12.0.1) iTunes, how can I import the contents of a CD into an existing playlist? It appears I have to import the contents into my general library, then drag the imported titles into an existing playlist. Two steps, where before there was

  • Black printing as grey . . .

    This suddenly ocurred, changed black cartridge and only printed grey. Did all the test as Doctor said, still not joy. Changed all colours and new black . . . still no joy, have done so many printer head cleans is now getting rediculous. I think the p