Sales quotation for project through DP80 or Manual ?

Dear All ,
We are facing a some problem in sales quotation for project , business case is as below ,
"One of our client is into "Supply , Instalation and service kind of project with material"  , Here they do with  with BOQ based billing and service releted billing . We are unable to come to conculsion that whether we had to create sales quotation with reference to DIP profile or we have to create manual quotation because each time their project vary on material and serice point of view and most of them are government project with BOQ and service type  . Each time createing manual quotation will take time because around 500item in most of the project . What is the best method we can adopt for this process
1. Whether we have to adopt DP80 for quotation ?
2. Manual quotation with unit costing ?
3. Is it DIP is must for easy costing ?
What kind of process will follow above said kind of industry ? Is is DIP is meant for only fixed kind of project or RRB project ?
RB

Hi,
Since you mentioned each project needs to be delt case on case basis , you can explore following
1) DP81 - Sales Qutotation w.r.t Project costing. For this Sales Inquiry is mandatory.
2) Easy Cost Planning (E.C.P). Sales Inquiry not Mandatory.
For DP81 it is you must default DIP profile in Project Definition.
Thanks
Saikishore.Ganga

Similar Messages

  • Sales quotation for project through DP80 or Manual for varying kind of pro?

    Dear All ,
    We are facing a some problem in sales quotation for project , business case is as below ,
    "One of our client is into "Supply , Instalation and service kind of project with material" , Here they do with with BOQ based billing and service releted billing . We are unable to come to conculsion that whether we had to create sales quotation with reference to DIP profile or we have to create manual quotation because each time their project vary on material and serice point of view and most of them are government project with BOQ and service type . Each time createing manual quotation will take time because around 500item in most of the project . What is the best method we can adopt for this process
    1. Whether we have to adopt DP80 for quotation ?
    2. Manual quotation with unit costing ?
    3. Is it DIP is must for easy costing ?
    What kind of process will follow above said kind of industry ? Is is DIP is meant for only fixed kind of project or RRB project ?

    Hi
    Resource billing is based on the resource consumption for the particular activities. Dynamic Item Processor (DIP) profile is used for the resource related billing. on viewing your scenario, its apt to go for RRb with dip profile, since its dynamic in nature
    here Steps to be followed:
    1) Configure DIP Profile (T.code ODP1)
    2) Specify the usage - 
    Billing & Result Analysis (RRB)
    (ii) Request Quotation (Sales Pricing)
    3) Specify - 
    Sales Document Type (PS2)
    (ii) SD Doc Type CMR 
    4) In Sales Order Type --> Sales Order Category - "L" (Debit Memo Request)
    5) Document Pricing Procedure --> PS (Customer Project)
    6) Select the billing usage and click on characteristics. eg--> Activity Type
    7) Then define sources. Select "Actual Cost" as we use actual cost for RRB. Define%
    8) Sources --> Selection Criteria: This would display all characteristics. Now in Activity Type --> Mention the activity type
    9) If more activity type are being used then create set of activity type using T.code GS01
    10) Material Determination --> Initially create material with "Material Type = Service"
    11) The service material should be mentioned in the material determination
    12) Criteria -- In criteria allocate the activity type for the specific material. (We can also use cost element, cost center, which we have defined in characteristics)
    13) Create Project (T.code CJ20N)
    14) Create Sales Order (T.code VA01)
    15) Book CATS 
    16) Execute DP91 to view Sales Pricing
    Hope you find it useful.
    With Regards
    baala

  • How to create Sales Quotation from project through DP81

    Dear Guru's,
          How to create Sales Quotation(VA22) from project through DP81, what all the customization settings are required for this functionality; please explain me all the step those are required for this process.
    Regards,
    Sai

    Hi,
    You can use DP81 and DP82 to create Quotations .
    If you want to use DP81 then you need to link Sales Inquiry with Project by entering the WBS Element in Account Assignment Tab of Inquiry and also enter the DIP Profile in Sales B View.
    Else you can carry sales pricing without the creation of Inquiry.Enter the DIP Profile ,Dist Channel,Division in control data tab of project and also enter Sold to party in Partner tab.
    See SAP help for customisation of DIP Profile .
    Muzamil

  • Sales Orders for Projects

    I have some strange situation with reports:
    CN54N - shows no data
    CN55N - shows data
    CNS54 - no data
    CNS55 - no data
    Same time there are Sales orders created with WBS account assignment.
    Any ideas?

    I think your slaes orders are line item account assigned. That is why CN55N shows sales order line items. CN54N is for sales order headers. You assign a WBS to the sales order header under account assignment tab  and you would get output for CN54N.
    With regard to CNS54 & CNS55 also the same holds good. Better check the db profile in this particular selection you have made.
    regards
    Muraleedharan.R

  • Sales Quote and Sales Order for Service Module.

    Hi All,
    I have a scenario with one of the customer where they have a Service Department. The customer is into installation and servicing of Air conditioning systems.
    The scenario is as mentioned below:
    Customer does the installation of Air Conditioning work and then provides service to the same, if contract mentioned that service is also to be provided by same team. There are also times when the customer quotes only for Servicing of the Air Conditioning in the Projects where the installation is not done by them, but a third party. In such case the customer sends his Sales Quotation for taking up the Servicing of the Air Conditioning (AMC for a year), to be provided to the principle client. If he wins the opportunity then the same will be transferred to Sales Order.
    Now in SAP Business One the Service Module starts only with Service Contract and Service Warranty Templates. This is considering that the equipments are delivered by the Contractor him self. This scenario is fine.
    But for equipments which are not delivered by the customer, then manual Customer Equipment Card can be prepared and then service contract created to it. But here there is a disconnect between the Quotation that they send to principle and attaching the Sales Order, if the Service Bid is won by Customer. If i need to keep a reference as to which Sales Order was received by Customer from Principle in Service Contract, there is no provision for same.
    Is there any way i can do it other than creating a UDF and linking the sales order number to Service Contract and not developing any screens for same?
    Require all your valuable inputs..
    Regards
    Rohan S. Kamble

    Hi Rohan........
    There is no such standard field in Service Contract to attach Sales Order. You can create UDF else you can have FMS and map it to remark field.
    And when you copy it to service call you can attach the same SO at Activity level or it will be attached automatically as yiu are defining it into the service contract.........
    Regards,
    Rahul

  • Generating sales order for semifinished product

    Hello every one. I am finding difficulty in creating a particular planning scenario. I require to sell a semi finished material which is assigned to a finished material. Finished product strategy is 50. Semi finished has strategy group with main strategy 70 and another strategy 50. While running mrp for finished material everything is running perfectly. But if i generate sales order for semi finished it is generating without errors, but requirements are not generated for the semi finished in MD04. Please provide solution.

    Hi Sayak,
    MRP can not generate sales order. It is an element which is being created manually after the customer is giving us PO. Against a sales order planned/production/Purchase order can be created.MRP will create production/procurement element. Not the sales order.
    If you want to create sales order for semi material, create it manually(Or create CIR). The availability check should be 2 for the semi. Then it should appear in MD04 screen after putting the semi material in input screen.
    Your concept is the semi should be consumed for finished product as well can be sold also.
    In that case you have to create sales order separately. If some requirement is generated (PIR etc) internally, then MRP can take care of those requirement. But not the sales order.
    If you are talking with sales BOM, that is a different concept.
    Hope I made it clear.
    Regards,
    Krishnendu.

  • Sales order for service should create project and link equipments.

    Hi,
    I'm trying to create a sales order for a service material through VA01. The problem is that this sales order should create a proyect, but at the same time i should be able to associate several equipments to the item position.
    The problem is that if I want to create a project, option " Sched.Line Allowed" should be marked for the item category, But if do it, when i create a sales order, if i want to associate 1 o more equipments to my item position, (Extras-->Technical Objects), i get this message "Serial number profile is missing for material..." instead of the table where i would introduce my equipments.
    Is there any solution to this problem or should i proceed in a different way?
    Thanks in advance.
    Luis.

    Hi Luis,
    We both are working on the same vertical, I am also working now in elevators and escalators.
    We have enabled similar (not same) scenario like this.
    When order is created (sales order) using serial number profile, serial no and equipment number are generated. I think even during service order, this can be enabled. The only thing you have to do is to create a profile and link that to material master. Please explore in SD and MM. This is easy to do. This will create equpment no for every item in the service order.
    We have also enabled the creation of whole project for the order and one WBS element  and network for each of the line items adn this happens automatically.  This is done as explained earlier. Creation of standard project, std WBS, std network adn then linking the material codes to these objects in CN08. To my knowledge, this is the only way.  If there is one standard project, which is linked to all related standard WBS, then during order creation, a WBS element is created after the creation of a standard project. When project is created, service order is linked to the project. So for other items, this project is taken and the WBS and network are created using this project.
    Now your assembly processing, production order, Purchase requisition are taken care of by the usage of components overview for activities in the network and object dependencies. For Production orders, you also have standard BOM, which can be linked to activities in the NW. You can control the materials of the standard BOM using selection condition dependencies. You can also initiate variant configuration in service order to maintain the nature of service and then use dependencies to trigger respective assembling, PR etc.
    If you want to do this for multiple eqpmts, you can also use functional location, which links multiple equipments to one place.
    The only thing you have to do is to configure this and see. Only then you will get ideas.
    Pls let me know if you need more information.

  • Standard smartform name and standard print program name for Sales Quotation

    Hi,
    I would like to know the standard smartform name and standard print program name which can be used for sales quotation through transaction VA23.
    For eg: The standard output type for billing document (For T code VF03) is RD00 and it' smartform name is LB_BIL_INVOICE. It's print program name is RLB_INVOICE.
    Similarly, I would like to know the standard smartform name and standard print program name for AN00 output type which is used for sales quotation. .
    Regards,
    Zahid

    Hello
    std driver prgram is /SMB40/RVADOR01
    form entry is ENTRY
    std smartforms is /SMB40/SDQUO_A an du can check this the in NACE tcode.
    Output Type     AN00          Quotation
    Application     V1            Sales
       Program                   /SMB40/RVADOR01
       Form Routine              ENTRY
       Form                      RVORDER01
       PDF/Smartform Form        /SMB40/SDQUO_A                 
    Thank u,
    santhosh

  • Report for Billing Document/sales order against project/WBS/Network

    Hi Experts,
    I want to see the Billing Document/Sales Order for Network/WBS in the projects.
    Also want to see the cost transaction against the WBS and Network.
    Suggest report which can show the details of the Sales Order/Billing Document against the WBS/Network.
    Thanks and Regards
    Ram Kalel

    Hi Ram,
    Please check standard TCODE like
    CN45N for Order list
    CN54N for sales n Distribution documents
    CN55N for sales document items
    Thanks
    Sunil

  • Storeprocedure for sale order without sale quotation

    hi,
    i want sp where without creating SQ, SO WILL NOT ADD

    Hi ,
    Please try this ,
    create TRIGGER [dbo].[BaseEntry] ON [dbo].[RDR1]
    for Insert
    AS DECLARE
        @BaseEntry nvarchar(max) 
    BEGIN
         SET NOCOUNT ON;
        SELECT @BaseEntry =isnull(BaseEntry,'') FROM INSERTED
        if isnull(@BaseEntry,'') =''   begin
           RaisError('Please Raise Sales Quotation First.',16,10)
           Rollback transaction
        end
    END
    Thanks
    Lloyd

  • Moving Average Price for Sales stock and Project stock of a material

    Hiya Gurus,
                     I am developing a report to display inventory details. My requirement is that I have to display the Moving average price of a material for all Valuation type. I also need to display the Moving average price if a material has got Project stock or Sales stock.
                     In MBEW table I can get the Valuation type and its Moving average price, but how can I find the moving average price for the same material if it has got Sales stock and project stock. Please let me know the table and field where I could get the relevant data.
                    Kindly help me on this, it would be deeply appreciated.
    Cheers,
    ZIa

    Hi
    can you look at tables
    EBEW                             Sales Order Stock Valuation
    QBEW                             Project Stock Valuation
    Nat

  • Manual reservation for Project Stock / wbs element

    Dear Gueus,
    In Project base Industry,
    For Production order confirmation I want to transfer Project stock of raw Materials from Main Storage stock  to Production WIP stock,  from this WIP Stock,  I will consume raw mtl at the time of Order confirmation.
    Now at the time of Manual Reservation in MB21 system is not allowing  311 Q  Mvt type  for Project stock reservation.
    Is there any other procedure / t- code to reserve project stock.
    Pl guide me for the same.
    Thanks
    Umesh

    Hi,
    A word of caution, before processing any mass transactions such as COHV etc, its always better to double check the data. Reason is because the program performs mass update & any reversal would be a time consuming process.
    Now for mass confirmations of orders via COHV
    1. Execute COHV, in the first screen, select Order Headers, specify the order numbers in the field. If you have saved the list as a text file, then click on multiple selection & click the green icon at the bottom right corner, specify the file & the orders will be read.
    2. In the tab - Mass Processing, select confirmation for the field Function & if you want to execute immediately, then select the same in execute function. Depending on your rqmt, you can have the log & also output the logs.
    3. Click execute or F8, then select all the orders & then click on the mass processing drop down icon & click execute. The processing begins in foreground. Once the processing is done, system puts out a log showing the once which were confirmed & the once which were not able to be processed & the reason for the same. (For background processing, select the same in mass processing tab in the selection screen).
    Please note, for order confirmation to take place the status has to be REL, also if any user status is active, check if the same allows confirmation.
    I would strongly suggest, first try in your sandbox server & once you're familiar with its processing, then proceed to use in production system.
    Hope the above helps.
    Regards,
    Vivek

  • Billing for Project Systems without using Sales Orders

    Hello All,
    We are using project systems in our project and we are not creating any sales orders for the same, however I am creating delivery using t-code CNSO and hence the outbound delivery is getting created, my question is can I create a billing document for this delivery and if yes how can I create the same.
    Kind Regards
    Atul

    Hi,
    Yes you can create billing document for this delivery
    Make sure following pre requsites
    In VOFA for your billing type assign document pricing procedure under account assignment/pricing tab
    In XD02 for customer under sales area data >> Billing assign customer pricing procedure
    And last in OVKK in combination of
    sales organization + distribution channel + division + document pricing procedure + customer pricing procedure = Price procedure
    kapil

  • Req:validtion query for sales quotation

    Hi,
    I would like to put validation for sales quotation when Freight1 Tax Code at line level is not empty
    My query is:
    if @object_type ='23' and @transaction_type in ('A','U')
    begin
    if exists(SELECT *  FROM [dbo].[OQUT]  T0 INNER JOIN QUT2 T1 ON T0.DocEntry = T1.DocEntry
    INNER JOIN QUT1 T2 ON T0.DocEntry = T2.DocEntry
    WHERE T1.TaxCode is not null and T0 .DocEntry = @list_of_cols_val_tab_del and
    T2 .DocEntry =@list_of_cols_val_tab_del )
    select @error=N'001'
    select @error_message =N'Freight1 Tax code should be empty.'
    end
    but didnot get the result.Plz give the solution.

    Hi Md Zak,
    Try dis..
    IF (@object_type = '23' and (@transaction_type IN ('A','U')))
    BEGIN
    If Exists (SELECT T0.DocEntry  FROM OQUT T0 INNER JOIN QUT2 T1 ON T0.DocEntry = T1.DocEntry
    INNER JOIN QUT1 T2 ON T0.DocEntry = T2.DocEntry
    WHERE T1.TaxCode is not null and T0 .DocEntry = @list_of_cols_val_tab_del)
      Begin
      set @error = N'001'
      set @error_message = N'Freight1 Tax code should be empty.'
      End
    END
    Hope Helpfull
    Regards::::
    Atul Chakraborty

  • RA for sales order and RA for project

    Hi,
    What is the technical difference between these two RA methods, while sales order is linked to project.
    Can any one brief some detail .
    Zinni

    RA is a methodology and can be used for any cost collector - you can see various posts or go to SAP help to understand what RA is.
    When Sales Order is a cost collector then you can use RA on sales order
    When Project is a cost collector then you use RA on WBS element
    By cost collector I mean the object that is being used to collect all costs (and revenue)
    When project is linked to sales order then the project object is used as a cost collector, hence RA on sale sorder is not required